Determine Demand
- MTO: make to order, base on the order of customer => combine all order => plan: receive order => combine order to make plan = > produce => delivery to customer
- MTS: make to stock, base on historical data, combine with other method to make forecast: do forecast (data,…) => make plan => produce (keep) => demand comes, delivery to
customer
Plan 1: Constant workfore (không sản xuất vượt giờ, không dùng dữ trự an toàn, không hợp đồng phụ)
Plan 2: Subcontracting (Sử dụng hợp đồng phụ, không dữ trữ) - duy trì mức sản xuất thấp nhất
Plan 3: Hiring and Firing (Thuê người và sa thải theo khối lượng công việc) - sản xuất theo yêu cầu
Month Forecast Daily production Basic prod cost Extra cost of incresing Extra cost of decresing Total
(units) rate (demand*1.6h/unit*5$/h) Production (hiring) Production (layoff) cost
Jan 900 41 900 * 1.6 * 5 = 7,200$ - - 7,200$
Feb 700 39 700 * 1.6 * 5 = 5,600$ - (41 - 39) * 600 = 1,200$ 6,800$
Mar 800 38 6,400$ - (39 - 38) * 600 = 600$ 7,000$
Apr 1,200 57 9,600$ (57 - 38) * 300 = 5,700 $ - 15,300$
May 1,500 68 12,000$ (68 - 57) * 300 = 3,300$ - 15,300$
Jun 1,100 55 8,800$ - (68 - 55) * 600 = 7,800$ 16,600$
6,200 49,600$ 9,000$ 9,600$ 68,200$
Comparison of 3 plan
Cost Plan 1 Plan 2 Plan 3
Inventory carrying 9,250$ 0 0
Regular-time labor 49,600$ 39,680$ 49,600$
Plan 2 is the lowest cost option
Overtime labor 0 0 0
Hiring 0 0 9,000$
Layoff 0 0 9,600$
Subcontracting 0 14,880$ 0
Total cost 58,850$ 54,560$ 68,200$
Exercise:
Inventory:
Expected damand = 400 + 440 + 500 + 400 + 500 + 600 + 700 + 520 = 4,060 units
Number of production days = 25 + 22 + 20 + 20 + 20 + 20 + 25 + 18 = 170 days
Average requirement = 4,060/170 = 23.8824 units = 24 units
Month Production at 24 units/day Demand forecast Monthly inventory change Ending inventory
1 24 * 25 = 600 units 400 +200 200
2 24 * 22 = 528 units 440 +88 288
3 24 * 20 = 480 units 500 -20 268
4 24 * 20 = 480 units 400 +80 348
Subcontracting:
Month Expected demand Production days Demand per day
1 400 25 400/25 = 16
2 440 22 440/22 = 20
3 500 20 500/20 = 25
4 400 20 400/20 = 20
5 500 20 500/20 = 25 Minimum requirements is 16 units per day
6 600 20 600/20 = 30
7 700 25 700/25 = 28
8 520 18 520/18 = 29
• Becase labor-hours to produce a unit is 3.2h/unit and worker do 8h per day
=> 1 worker can do 8/3.2 = 2.5 units/day
=> 16 units day need 16/2.5 = 6.4 workers = 7 workers
• Expected damand = 400 + 440 + 500 + 400 + 500 + 600 + 700 + 520 = 4,060 units
Number of production days = 25 + 22 + 20 + 20 + 20 + 20 + 25 + 18 = 170 days
In-house production = 16 units/day * 170 days = 2,720 units (Tổn sản phẩm sản xuất)
Subcontract units = Total expected demand - In-house production = 4,060 - 2,720 = 1,340 units
Cost
Regular-time labor 7 * 56$/day * 170 = 66,640$
Subcontracting (10$/unit) 1,340 * 20 = 26,800$
Total cost 93,440$
MASTER PRODUCTION SCHEDULE (MPS) AND MATERIAL REQUIREMENTS PLANNING (MRP) SYSTEM
Agg plan
Net material requirement plan (Kế hoạch nhu cầu vật tư thực tế)
Lot-for-lot
EOQ = 73 units
Average weekly GR = = 27 units