Professional Documents
Culture Documents
BHOPAL-462036
PROJECT REPORT ON
“DESIGN OF SUMP WELL CAPACITY 200 KL AT NRI CAMPUS RAISEN ROAD
BHOPAL”
NIIST, Bhopal
1
DECLARATION
I hereby declare that the work which is being presented in the major project
report entitled “DESIGN OF SUMP WELL CAPACITY 200 KL AT NRI
CAMPUS BHOPAL ”in the partialfulfillment of Bachelor of Engineering in
Civil Engineering is an authentic record of our own work carried out under the
guidance of Prof. Sandeep K. Shrivastava.The work has been carried out at NIIST,
Bhopal.
The matter embodied in the report has not been submitted for the award of any
other degree or diploma.
2
NRI INSTITUTE OF INFORMATION SCIENCE &
TECHNOLOGY
(AFFL. BY RAJIV GANDHI PRODYOGIKI VISHWAVIDYALAYA)
BHOPAL
CERTIFICATE
This is to certify Syed Mohd. Mashood student of Fourth year (VIII semester)
Bachelor of Civil Engineering, NIIST have successfully completed their Major
Project Report on “DESIGN OF SUMP WELL CAPACITY OF 200 K.L.
AT NRI CAMPUS BHOPAL.” We approve the project for the submission for
the partial fulfillment of the requirement for the award of degree in Civil
Engineering.
3
NRI INSTITUTE OF INFORMATION SCIENCE
&TECHNOLOGY
(AFFL. BY RAJIV GANDHI PRODYOGIKI VISHWAVIDYALAYA)
BHOPAL
APPROVAL CERTIFICATE
--------------------------- --------------------------
--------------------------- ---------------------------
4
ACKNOWLEDGEMENT
We would like to express our deep sense of gratitude to our respected and
learned guideProf. Sandeep k. Shrivastavafor his valuable guidance. We are
also thankful for his timely encouragement given in completing the project.
We are also grateful to respected Mr. J.P. Nanda, HOD (Department of Civil
Engineering) NIIST, Bhopal for permitting us to utilize all the necessary
facilities of the institution.
We would like to thank Dr. S.C.Kapoor, Director NIISTfor his valuable
encouragement and approval for the project.
We are also thankful to all other staff members of our department for their kind
co-operation and help.
Lastly, we would like to express our deep appreciation towards our classmates
and family members for providing us the much needed kind support and
encouragement.
Thank You
5
TABLE OF CONTENTS
1. Introduction 8
1.2 About the campus 9
1.3. Mission of NRI 10
1.4 Vision of NRI 11
1.5 Potable water 12
1.6 Properties of potable water 13
1.7 Improving availability 14
1.8 Safety indicators for potable water 15
1.9 Requirement of water 16
1.10 Institution requirement of water 17
1.11 Requirement for domestic purpose 18
1.12 Water requirement for NRI campus 19
2 Total cost of the project 20
3 Key plane 21
4 Abstract of cost of water supply line at NRI campus 22
5 Estimation of water supply line main gate to sump well 23
6 Abstract of cost of Sump well capacity 200 kl 24-25
7 Estimation of Sump well capacity 200 kl 26-28
8 Drawing of Sump well 29
9 Design of Sump well 30-33
10 Abstract of cost of pump house 34-35
11 Estimation of Pump hose 36-38
12 Drawing of Pump house 39
13 Design of Pump house
13.1 Design of slab (pump house) 40-43
13.2 Drawing of Slab 44
13.3 Design of beam 45-49
13.4 Drawing of beam 50
13.5 Design of column 51-53
13.6 Drawing of column 54
13.7 Design of plinth beam 55-59
13.8 Drawing of plinth beam 60
6
14 Nominal dimension of pile foundation. 61
15 Conclusion 62
16 Site Photo 63
17 References 64
7
INTRODUCTION
A sump well is used to store water to cater the daily requirement. A sump is low
space that collects any often undesirable liquids such as water or chemicals. A
sump can also be an infiltration basin used to manage surface runoff water and
recharge underground aquifers .
WELL LOCATION
The location of well is mainly determined by well’s purpose. For drinking and
irrigation water- production well, ground water quality and long term ground
water supply are the most important considerations . Hydrogeological
assessment to determine whether and where to locate a well should always be
done by a knowledgeable driller or professional consultant.
SUMP PUMP
A sump pump is a pump used to remove water that has accumulated in a water
collecting sump basin, commonly found in the basement of homes. The water
may enter via the perimeter drains of a basement waterproofing system,
funnelling into the basin or because of rain or natural ground water, if the
basement is below the water table level. Sump are used where basement
flooding happens regularly and to solve dampness where the water table is
above the foundation of home. Sump pumps send water away from a house to
any place where it is no longer problematic, such as a municipal storm drain or
dry well.
PUMP HOUSE
Pump House or a Pumping stations are facilities
including pump and equipment for pumping fluids from one place to another.
They are used for a variety of infrastructures system, such as the supply of
water to canals the drainage of low-lying land, and the removal of sewageto
processing sites
8
ABOUT THE CAMPUS
• Number of Colleges - 5
• Number of Hostels - 1
• Number of Canteens - 2
• Number of Gardens - 3
9
MISSION OF NRI
NRI is the leading education group of Madhya Pradesh with over 5000+ students,
studying across 15 acres of hi-tech campus.
At NRI, our mission is to produce professionally competent Technocrats,
pharmacists & managers by providing value based and quality education to the students
and to make them adaptable to ever changing demands and requirements. The institutes
intend to infuse fresh ideas in the field of education. Some of these include Yoga,
language lab, work study program, internship program, etc. The end result is
improvement in the quality of education.
At NRI we are passionate about grooming leaders who are not only professionals but
also good human beings with values and Sanskars .
10
VISION OF NRI
The vision of the society is to develop this group of institutions as the “Centre
for Excellence” , The management team intends to infuse fresh ideas, some of
these include Work Study program, Live project, Skill development program
etc. which results in improvement of education quality.
To attain global leadership in academics by exploring new frontiers of
technology through innovative research and grooming future leaders as
well as entrepreneurs.
AWARDS
11
POTABLE WATER
Potable water is water which is fit for consumption by humans and other animals. It is
also called drinking water .This water is that has been either treated cleaned or filtered
and meets established drinking water standards or is assumed to be reasonable free of
harmful bacteria and contaminants ,and considered safe to drink or use in cooking and
baking . Examples of portable water would be that from treated municipal water system.
Over large parts of the world, humans have inadequate access to potable water and use
sources contaminated with disease vectors, pathogens or unacceptable levels of toxins or
suspended solids. Drinking or using such water in food preparation leads to widespread
acute and chronic illnesses and is a major cause of death and suffering worldwide in
many different countries. Reduction of waterborne diseases and development of safe
water resources is a major public health goal in developing countries.
Water has always been an important and life-sustaining drink to humans and is essential
to the survival of most other organisms. Excluding fat, water composes approximately
70% of the human body by mass. It is a crucial component of metabolic processes and
serves as a solvent for many bodily solutes
12
PORPERTIES OF POTABLE WATER
13
IMPROVING AVAILABILITY
WELL CONTAMINATION
Some efforts at increasing the availability of safe drinking water have been
disastrous. When the 1980s were declared the "International Decade of Water"
by the united nations the assumption was made that groundwater is inherently
safer than water from rivers, ponds, and canals. While instances of cholera,
typhoid and diarrhea were reduced, other problems emerged due to polluted
groundwater.
Sixty million people are estimated to have been poisoned by well water
contaminated by excessive fluoride, which dissolved from granite rocks. The
effects are particularly evident in the bone deformations of children. Similar or
larger problems are anticipated in other countries including China, Uzbekistan,
and Ethiopia. Although helpful for dental health in low dosage, fluoride in large
amounts interferes with bone formation.
14
SAFETY INDICATORS FOR POTABLE WATER
15
WATER REQUIREMENTS
• Domestic
• Institutional
• Industrial
• Public
• Agricultural
16
INSTITUTIONAL REQUIREMENT
17
REQUIREMENTS FOR DOMESTIC PURPOSE
1 Drinking 5
2 Cooking 5
3 Bathing 55
4 Washing Of Clothes 20
5 Washing Of House 10
6 Washing Of Utensils 10
7 Flushing of W.C. 30
18
WATER REQUIREMENT FOR NRI CAMPUS
No. OF
NAME STUDENT QUANTITY(LT)
COLLEGES
1) NIIST 2620 2620X35=91700
2) NIRT 1415 1415X35=49525
3) NIP 588 588X35=20580
4) NIPS 320 320X35=11200
5) NIDP 180 180X35=6300
6) NVISMT 840 8400X35=29400
19
TOTAL COST OF THE PROJECT
20
.
21
ABSTRACT OF COST OF WATER SUPPLY LINE MAIN
GATE TO SUMP WELL
S.no. Item Nos. Quantity Unit Rate/unit Cost(Rs.) Remark
1 E/W in excavation 1 208.59 mᶟ 156 32540.04
3,70,337.04
Say Total Amount = Rs.3,70,500
22
ESTIMATE OF WATER SUPPLY LINE MAIN GATE
TO SUMP WELL AT NRI CAMPUS
S.no. Item Unit Nos. L(m) B(m) D/H(m) Quantity Remark
1 E/W in excavation
a)IBD to NIIST west corner mᶟ 1 285.1 0.7 0.9 179.61
b)NIIST west corner to mᶟ 1 46 0.7 0.9 28.98
sump well
208.59
2 200mm crus dust filling for mᶟ 1 331.1 0.7 0.2 46.35
base 0f pipe
3 150 mm C.I. pipe
a)IBD to NIIST west corner each 47 47 no. of pipe=47
285.1/6.1=46.73
use 20' pipe
b)NIIST west corner to each 8 8 46/6.1=7.54
sump well
5 back filling
a)above the pipe mᶟ 1 331.1 0.7 0.5 115.88
(0.7X0.2)-
b)filling of pipe sides mᶟ 1 331.1 (π/4X.15² 40.5
156.38
NOTE - Use SOR of M.P.P.W.D. FOR BUILDING WORK IN FORCE FROM AUG 1ᶳᶵ 2014 FOR COSTING
23
ABSTRACT OF COST200KL CAPACITY SUMP WELL
(Use rate of quantity as per SOR of M.P.PW.D for building works in force from Aug. 1st 2014)
S.NO. ITEM NO. Particular / Item NO. QUANTITY UNIT RATE PER UNIT COST(RS.) REMARK
2 4.1/45 providing in laying in posiition cement concrete of specified grade excluding the 1 7.85 m³ 3808 29892.8
cost of centering and shuttering - all work up to plinth level
4.1.2.2 nominal mix 1:3:6 grade stone aggregate (M-10)
3 5.7/66 R.C.C work (with 20 mm nominal size graded stone aggregate) in well- steining 1 15.7 m³ 4953 77762.1
excluding the cost of centering shuttering finishing and r/f in M-20 grade conc.
4 4.2/45 Providing and laying cement concrete in retaining wall, return walls,walls (any
thikness) including atteched pilasters, columns , pillars, post, struts, buttresses,
string lacing coureses, parapets, copying, bed blocks, anchor blocks, plain window
sills, fillets etc.up to floor tw0 level, excluding the cost of shuttering centering
and finishing 1 19.07 m³ 6582 125518.74
4.2.1.1 M-25 grade concrete
5 4.1/45 providing in laying in posiition cement concrete of specified grade excluding the
cost of centering and shuttering - all work up to plinth level
4.1.1.1 M-25 grade concrete 1 10.96 m³ 6338 69464.5
7 10.1/178 structural steel work in singal section fixed with or without connecting plate 1 933.7 kg 65.3 60975.8
including cutting, hoisting fixing in position and applying a priming coat of
approved steel primer all complete(horizontal & vertical)
8mm Ø bar
8 10.1/178 structural steel work in singal section fixed with or without connecting plate 1 250.27 kg 65.3 16342.65
including cutting, hoisting fixing in position and applying a priming coat of
approved steel primer all complete (in base slab)
8mm Ø bar
9 10.1/178 structural steel work in singal section fixed with or without connecting plate 1 830.21 kg 65.3 54212.7
including cutting, hoisting fixing in position and applying a priming coat of
24
approved steel primer all complete (in top slab)
10mmØbar
10 5.9/66 centering & shuttering including strutting,propping etc. and removal of form for 1 190.69 m² 320.4 61097.076
5.9.15 Extra for shuttering in circular work or any other geometrical shape
(20% of respective centring and shuttering item)
5.9.3 suspended floors, roofs, landing, balconies and access platform 1 67.89 m² 264 17922
11 10.2/178 structural steel work riveted, bolted, or welded in built up section,trusses and
framed work including cutting, hoisting, fixing in position and applying a priming
coat of approved steel primer all completed
I.S.A-30X30X5 1 30 kg 68.7 2061
TOTAL
5,73,230.766
6,59,215.3726
25
ESTIMATING OF SUMP WELL 200KL CAPACITY AT NRI CAMPUS RAISEN ROAD (BPL)
H/D(
Sr.No. ITEM NO. Particular / Item Unit No.s L(m) B(m) m) Quantity Remark
1 2.8/23 Earth work in excavation by mechanical mean/manual means in foundation m³ 1 π/4x(10)² 3 235.6
tranches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including
dressing of sides and ramming of bottoms lift up to 1.5 m including getting out
the excavated soil and disposal of surplus excavated soil as directed with in a
lead 50 m (no extra lift is payable if work is done by mechanical means
2 4.1/45 providing in laying in posiition cement concrete of specified grade excluding th m³ 1 π/4 (10)² 0.1 7.85
cost of centering and shuttering - all work up to plinth leveL
4.1.2.2. nominal mix 1:3:6 grade stone aggregate (M-10)
3 5.7/66 R.C.C work (with 20 mm nominal size graded stone aggregate) in well- steining m³ 1 π/4 (10)² 0.2 15.7
excluding the cost of centering shuttering finishing and r/f in M-20 grade conc.
4 4.2/45 Providing and laying cement concrete in retaining wall, return walls,walls (any m³ 1 π/4 (9.4-9)² 3.3 19.07
thikness) including atteched pilasters, columns , pillars, post, struts, buttresses,
string lacing coureses, parapets, copying, bed blocks, anchor blocks, plain window
sills, fillets etc.up to floor tw0 level, excluding the cost of shuttering centering
and finishing 4.2.1.1 - M-25 grade concrete
26
7850×π/4×0.0
8²
πd=3.14x9=28.2
no- (1100/140)+1 0.395 6
lenth of bar is
8mmØ@140mm c/c 12m so
2 full & 1extra
b)inner side above 1.1 kg 14 28.86 0.395 159.59 bar so
3 over lap is
(no.-(2200/160) provide
(straigthlength
8mmØ@160mm c/c of lap
shall be greater
than
c)outer side kg 23 30.12 0.395 273.6 15d or 20cm
L=28.86
9 10.1/178 structural steel work in singal section fixed with or without connecting plate
including cutting, hoisting fixing in position and applying a priming coat of
approved steel primer all complete(VERTICAL )
a)inner side kg 143 3.45 0.395 195
(3.14x9)/.20)+1
8mmØ@200mm c/c
b)outer side 149 3.45 0.395 203
(3.14x9.4)/0.2)+1 933.78
10 10.1/178 structural steel work in singal section fixed with or without connecting plate
from center
including cutting, hoisting fixing in position and applying a priming coat of point to specify
distance & take
approved steel primer all complete(IN BASE SLAB ) avg length
8mmф@200mm c/c kg 20 9 0.395 71.1 0.2 to 1.0 = 9
,, kg 8 8.7 0.395 27.492 1.2 to 1.4 =8.7
,, kg 8 8.4 0.395 26.54 1.6 to 1.8= 8.4
,, kg 8 8 0.395 25.28 2.0 to 2.2 = 8
,, kg 8 7.5 0.395 23.7 2.4 to 2.6 = 7.5
,, kg 8 7 0.395 22.12 2.8 to 3 = 7
,, kg 8 6.2 0.395 19.6 3.2 to 3.4 =6.2
,, kg 8 5.15 0.395 16.27 3.6 to 3.8 = 5.15
,, kg 8 3.75 0.395 11.85 4 to 4.2 = 3.75
,, kg 8 2 0.395 6.32 for 4.4 =2
250.272
11 10.1/178 structural steel work in singal section fixed with or without connecting plate
including cutting, hoisting fixing in position and applying a priming coat of
approved steel primer all complete(IN TOP SLAB )
π/4x0.010²x78 0.105 to 0.840 =
10mmф@105mm c/c kg 32 9 50 178.56 9
27
0.62
0.945 to
,, kg 28 8.7 0.62 151.03 1.565=8.7
1.67 to 2.085=
,, kg 20 8.25 0.62 102.3 8.25
,, kg 12 7.8 0.62 58.03 2.19 to 2.4=7.8
2.505 to 2.715
,, kg 12 7.4 0.62 55.05 =7.4
,, kg 8 7 0.62 34.72 2.82 to 2.925=7
3.03 to
,, kg 8 6.6 0.62 32.74 3.135=6.6
3.24 to
,, kg 8 6.2 0.62 30.75 3.345=6.2
3.45 to
,, kg 8 5.6 0.62 27.78 3.555=5.6
10mmф@55mm c/c kg 12 5.3 0.62 39.43 3.61 to 3.72=5.3
3.775 to
,, kg 12 4.8 0.62 35.72 3.83=4.8
,, kg 12 4.3 0.62 32 3.94 to 4.05=4.3
4.105 to
,, kg 12 3.4 0.62 25.3 4.215=3.4
,, kg 12 2.6 0.62 19.35 4.27 to 4.38=2.6
,, kg 8 1.5 0.62 7.45 4.435to 4.49=1.5
830.21
12 5.9/66 centering & shuttering including strutting,propping etc. and removal of form for
5.9.15 Extra for shuttering in circular work or any other geometrical shape
(20% of respective centring and shuttering item)
for outside m² 1 29.51 3.3 97.4 πD=πx9.4
for inside m² 1 28.28 3.3 93.29 πD=πx9.0
190.69
two 4m and
13 structural steel work riveted, bolted, or welded in built up section,trusses and 9,0.6 m steps
are use 0f I.S.A-
framed work including cutting, hoisting, fixing in position and applying a priming 30X30X5
so use 13.4m
coat of approved steel primer all completed angle section
and its WT
I.S.A-30X30X5 kg 1 4 30 2.2kg/m
NOTE-USE STANDARD SCHEDULE OF RATE FOR BUILDING WORK (IN FORCE FROM AUG 1ᶳᵀ 2014 OF GOVT.OF M.P.P.W.D.
FOR COSTING OF ESTIMATE QUANTITIES OF SUMP WELL
28
DRAWING OF SUMP WELL 200KL CAPACITY AT NRI CAMPUS RAISEN ROAD (BPL)
29
DESIGN OF SUMP WELL 200KL CAPACITY AT
NRI CAMPUS RAISEN ROAD (BPL)
CAPACITY CALCULATION
Thickness 160 mm
concrete strength M-25
Self wt. = 0.160 x 2500 = 400 kg/m2
Live load = 400 kg/m2
---------------------
= 800 kg/m2
2
Moment in slab at support = ----- x w x r2
16
2
= ----- x 800 x 4.52
16
= 2025 kg.m
or
Mu = 29.80 KN.m
30
Say Mu=30KN.m
1
Moment in slab at center = ----- x w x r2
16
1
= ----- x 800 x 4.52
16
= 9.93 kg.m
or
Mu = 14.89 KN.m
Say Mu =15KN.m
DESIGN CONSTANT
m 𝜎cbc 10.98×8.5
n= -------------------- = -------------------- =0.384
m 𝜎cbc+𝜎𝑠 10.98×8.5+150
𝑛 0.384
j=1- -------- = 1- ---------=0.384
3 3
M 30×10^6
Ast at corner = --------------- = ------------------------- = 1433.48mm2
𝜎𝑠 × 𝑗 × 𝑑 150× 0.872 × 160
=1435 mm2
M 15×10^6
Ast at center = ------------------- = ----------------------
𝜎𝑠 × 𝑗 × 𝑑 150× 0.872 × 160
=716.473mm2≅718 mm2
31
Use 10mm dia bar
0.785×10²×1000
Spacing at corner bar =--------------------- =55 mm
1435
32
9549
Tesile stress = ------------------------- = 4.64 kg/cm2 < 13 kg / cm2
20 x 100 + 8 x 7.18
Moment on wall
At base
Moment = 0.0187 x 1000 x 3.3³= 203.64 kg.m / m
= 204 kg.m / m
Provide thickness 20 cm over all & 16 cm effective
620 x 100
Ast = ------------------------------ = .97 cm2 / m
0.87 x 1500 x 16
Ast≅ 𝟏𝐜𝐦𝟐 /𝐦
3672
Stress = _________ = 1.83 Kg/cm2 < 60 Kg/cm2
20 x100
The pr. is very less (Safe)
33
Abstract of Cost of Pump House at NRI
Campus,Bhopal
(Use SOR of MP PWD for Building Works in force from August 1st, 2014 )
S.No Item Nos. Quantity Unit Rate/Unit Cost(Rs.) Remark
34
15 Steel work in Plinth Beam 4 17.01 kg 65.3 4443.01
TOTAL= 1,75,490
Total 2,01,814
35
ESTIMATION OF PUMP HOUSE AT NRI
CAMPUS
H/D(m
S.no Particular/item Unit Nos L(m) B(m) ) Quantity Remark
1 boring and cast in situ of piles rm 4 3.75 15
300mm dia
eac
a)bulb provided h 4 4
36
120 mm thick
37
kg 10 0.55 0.395 2.175
Steel Work in Plinth beam 28.295
18 i) Main bar of 12mm dia
ii) Anchor Bar of 10mm dia kg 2 3.54 0.89 6.29
iii)Stirups of 8mm dia kg 2 3.54 0.62 4.38
1.25
kg 13 4 0.395 6.34
17.01
Steel work in Pile
19 i) longitudnal bar of 12mm dia
ii) ties of 8mm dia 300mm c/c kg 6 4.1 0.89 21.89
kg 20 1.23 0.395 9.76
31.65
38
DRAWING OF PUMP HOUSE
39
DESIGN OF PUMP HOUSE
d= 120 - 15 – 4 = 101mm
Effective Span
40
Design Moment & Shear
Ly/lx = 3.3/3.3 = 1
Simply supported
Lx = 0.062
Ly = 0.062
Mux = lx Wu lx²
= 0.062 x 9.0 x (3.3)²
= 6.07 kN-m
Mxy = ly Wu lx²
= 0.062 x 9.0 x 3.3²
= 6.07 kN-m
Vu = Wlx (r/2+r)
= 9x3.3 (1/2+1)
= 9.9 Kn
dreq = √Mu/Rub
Ru = 0.138 fck for M-25 cmc
Ru = 3.45
= √6.07 x 10⁶ / 3.45 x 1000
= 41.949 <101mm
dreq = 41.949 <dassumed . Hence OK
41
Ast min = (0.12/100) x 1000 x 120 = 144mm²
Ast provided = 1000x50.3/ 285 =178.24 say 180mm² > 144mm². Hence OK
42
Check for Deflection
Pt = 0.17%
Fs = 0.58fy[Astreq/Ast provided]
= 0.58x415 [175/180]
= 234.01 N/mm²
For Pt = 0.17%
Fs = 234 N/mm² from
Kt = 1.9
(l/d)max = 20x1.9 = 38
(l/d)provided = 3300/101 = 32.6
(l/d)max > (l/d)provided. Hence OK
43
DRAWING OF SLAB (PUMP HOUSE)
44
DESIGN OF BEAM
Given data
Length = 3 m
Wight = 5.6 KN
B=200
= 3 + .26 =3.26m
45
STEP-3 Load calculation
Imposed load = 5.62 kN/m
Mu =10.29 KN –M
=√10.29𝑋10ˆ6/(0.9𝑋200)
=237.77< 260
dreq< 𝑑𝑎𝑠𝑠𝑢𝑚𝑒
Eff. Depth=d=300-25-8-14/2
=260 mm
46
STEP-6 Area of steel R/F
M 10.29×10⁶
Ast = --------------- = -------------------------- = 191.93 mm2
𝝈𝒔𝒕 × 𝒋 × 𝒅 230×0.9×260
≅192
Provide φ of bar = 12 mm
Provide 2 no. of 12 mm φ
V = wl/2
Nominal shear stress =τv
(Vu = Wu leff/2)
τv = 0.024 N/mm²
47
Ʈc max = 1.8 N/mm² for M-20 concrete
Pt = 0.60 %
hence shear r/f is not required however nominal shear r/f is to be provided as
per code
Sv = 0.87 Asufy/0.46
= 273.31
≅ 280
48
STEP-10 Check for Development Length
M1= 𝜎𝑠𝑡𝐴𝑠𝑡𝐽𝑑
= 230x308x0.9X260= 16576560N
M1 = 16576560N
V=1.29
τbd = 0.8N/mm²
= 12946.04mm
DESIGN SUMMARY
50
DESIGN OF COLUMN
Given data
LO = 3.0 M = 3000 mm
= 0.65X3 = 1.95 M
= 109.5 KN
= 10.56 or 20mm
emi n = 20mm
51
Hence local formula for short column is applicable
Pu = 0.4fck AC + 0.67FY AS
AC = Area of concrete
Ac = Ag-Asc
= 200X200 – Asc
= 40000- Asc
= 320000-8XAsc+278XAsc
109.5X10³ = 320000+270Asc
Asc =779.62
=780 mm²
= 113.09
= 6.89
= 8 no of bars
52
Step- 5 Lateral ties
The pitch of the ties should not be less than the following
(c) 300 mm
Hence provide tie bar 8mmø with spacing 3000 mm c/c as double ties
53
DRAWING OF COLUMN
54
DESIGN OF PLINTH BEAM
Given data
b=200 mm
D=300mm
k=0.29
j=0.90
R=0.91N/mm²
deff = 300-40
55
Total Load =11.76 KN/m
= 3 + .26 =3.26m
M=15.05KN-m
=√15.05𝑋10ˆ6/(0.91𝑋200)
=287.5< 300
dreq< 𝑑𝑎𝑠𝑠𝑢𝑚𝑒
Eff. Depth=d=300-25-8-12/2
=261 mm
56
Taking 25mm as car cover 8 mm ∅ where stirrups and 12 mm ∅ as the main
bar
𝝈𝒔𝒕 × 𝒋 × 𝒅230×0.9×261
Provide 2 no. of 12 mm φ
V = wl/2
V=1176X3.2/2 =1882N
57
Nominal shear stress =τv
τv = 0.036 N/mm²
Pt = 0.43 %
τc=0.36 N/mm²
Sv = 0.87 Asufy/0.46
= 273.31
≅ 280
58
2) 300
Provided 8 mm ø 2 legged stirrups @ 200 mm c/c through out the
length at the beam.
M1= 𝜎𝑠𝑡𝐴𝑠𝑡𝐽𝑑
= 230x226.19x261= 13578185.7 N
M1 = 13578185.7N
V=1882
τbd = 0.8N/mm²
= 7310.76mm
59
DRAWING OF PLINTH BEAM
60
NOMIANL DIMENTION OF PILE FOUNDATION
61
CONCLUSION
62
SITE PHOTO
63
REFERENCES
Estimating by B.N.Datta
For costing MPPWD SOR for building work (from 1Aug 2014)
www.wikipidia.com
64