1) The document provides a cost estimate for road work above 60 feet, listing 7 items needed and their individual costs.
2) The total cost for a 60 foot road as per the estimate is Rs. 35018.11, which includes all material, equipment, labor, overhead, and operational costs.
3) The major cost items are providing and laying wet mix macadam base at Rs. 573 per cubic meter and providing and applying 37.50 mm thick compacted bituminous macadam at Rs. 1920 per metric tonne.
1) The document provides a cost estimate for road work above 60 feet, listing 7 items needed and their individual costs.
2) The total cost for a 60 foot road as per the estimate is Rs. 35018.11, which includes all material, equipment, labor, overhead, and operational costs.
3) The major cost items are providing and laying wet mix macadam base at Rs. 573 per cubic meter and providing and applying 37.50 mm thick compacted bituminous macadam at Rs. 1920 per metric tonne.
1) The document provides a cost estimate for road work above 60 feet, listing 7 items needed and their individual costs.
2) The total cost for a 60 foot road as per the estimate is Rs. 35018.11, which includes all material, equipment, labor, overhead, and operational costs.
3) The major cost items are providing and laying wet mix macadam base at Rs. 573 per cubic meter and providing and applying 37.50 mm thick compacted bituminous macadam at Rs. 1920 per metric tonne.
Sr Item Description Rate Per Rate of For 60 FT road
no. REFERENCE S.O.R I. Cost Code 1 Clearing and grubbing road land grass 31739 hec R AND 26117 31739 bushes vegetation saplings girth till 300 B c mm, removal of stamps of tress by mechanical means in area of light jungle 2 Earthwork in cutting in all sort of soil and 80.50 CM R AND 26005 80.50 soft morrom including conveying and T B spreading stuff, embakement as and where directed within 200 MT from the end of the cutting with all reired lead and left 3 Scarifying graveled macadam or bitumen 25.60 smt R AND 26063 25.60 macadam surface 6cm to 10 cm depth B including stacking materials on road sides and disposing off remaining stuff
4 Granular Sub-Base with Coarse Graded 558.00 CM RA 558.00
Material (Table:- 400- 2) 150mm T (Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotator at OMC, and compacting with vibratory roller to achieve the desired density, complete for Grade - III Material. 5 Providing and laying geonet above sub base 70 smt 70 of approved brand and quality in sb base of pavement confirming to MORTH and H specification table 700-7 6 Providing and laying wet mix macadam 573 CM RA 573 base coarse 150mm thick T 5 Providing and applying primer coat with 27.00 CM RA 27 cationic bitumen emulsion SS1 grade T conforming to IS:8887 on prepared surface of wet mix macadam including clearing of Wet mix macadam surface with air compressor to remove all loose material other Foreign material. The primer shall be sprayed uniformly at the rate of 7.5 kg/ 10sqm. It shall be applied by a self- propelled or towed bitumen pressure sprayer, equipped for spraying the material uniformly at a specified rate. No dilution or heating at site of RS1 bitumen emulsion shall be permitted. 6 Providing and applying 37.50 mm thick 1920 MT RA 1920 compacted B.M with B.T aggregate with tack coat with VG-30 at the rate of 34 kg/mt Grade bitumen using bitumen pressure distributor on the existing bituminous surface cleaned with Air Compressor. 7 Providing and laying Asphalt painting on 25.01 SMT RA 25.01 B.T. surface with bitumen grade 60/70 (VG- 30) @ rate of 5 kg/10 smt by Mechanical sprayer and spreading the stone dust on prepared surface at the rate of 0.03 cum/10 smt. and rolling with smooth wheeled and pneumatic roller and brushing etc. comp.
TOTAL COST FOR 60 FT ROAD 35018.11
NOTE: THE COST INCLUDES ALL TYPES OF MATERIAL COST, EQUIPMENT COST, MANPOWER COST, OVERHEAD, LAYING AND OTHER OPERATIONAL COST