CHAPTER: 5 DATA COLLECTION

5.1 Cost of Road Work above 60ft

Sr Item Description Rate Per Rate of For 60 FT road


no. REFERENCE
S.O.R I. Cost
Code
1 Clearing and grubbing road land grass 31739 hec R AND 26117 31739
bushes vegetation saplings girth till 300 B c
mm, removal of stamps of tress by
mechanical means in area of light jungle
2 Earthwork in cutting in all sort of soil and 80.50 CM R AND 26005 80.50
soft morrom including conveying and T B
spreading stuff, embakement as and where
directed within 200 MT from the end of the
cutting with all reired lead and left
3 Scarifying graveled macadam or bitumen 25.60 smt R AND 26063 25.60
macadam surface 6cm to 10 cm depth B
including stacking materials on road sides
and disposing off remaining stuff

4 Granular Sub-Base with Coarse Graded 558.00 CM RA 558.00


Material (Table:- 400- 2) 150mm T
(Construction of granular sub-base by
providing coarse graded material, spreading
in uniform layers with motor grader on
prepared surface, mixing by mix in place
method with rotator at OMC, and
compacting with vibratory
roller to achieve the desired density,
complete for
Grade - III Material.
5 Providing and laying geonet above sub base 70 smt 70
of approved brand and quality in sb base of
pavement confirming to MORTH and H
specification table 700-7
6 Providing and laying wet mix macadam 573 CM RA 573
base coarse 150mm thick T
5 Providing and applying primer coat with 27.00 CM RA 27
cationic bitumen emulsion SS1 grade T
conforming to IS:8887 on prepared surface
of wet mix macadam including clearing of
Wet mix macadam surface with air
compressor to remove all loose material
other
Foreign material. The primer shall be
sprayed uniformly at the rate of 7.5 kg/
10sqm. It shall be applied by a self-
propelled or towed bitumen pressure
sprayer, equipped for spraying the
material uniformly at a specified rate. No
dilution or heating at site of RS1 bitumen
emulsion shall be permitted.
6 Providing and applying 37.50 mm thick 1920 MT RA 1920
compacted B.M with B.T aggregate with
tack coat with VG-30 at the rate of 34 kg/mt
Grade bitumen using bitumen pressure
distributor on the existing bituminous
surface cleaned with Air Compressor.
7 Providing and laying Asphalt painting on 25.01 SMT RA 25.01
B.T. surface with bitumen grade 60/70 (VG-
30) @ rate of 5 kg/10 smt by Mechanical
sprayer and spreading the stone dust on
prepared surface at the rate of 0.03 cum/10
smt. and rolling with smooth wheeled and
pneumatic roller and brushing etc. comp.

TOTAL COST FOR 60 FT ROAD 35018.11

NOTE: THE COST INCLUDES ALL TYPES OF MATERIAL COST, EQUIPMENT COST, MANPOWER COST,
OVERHEAD, LAYING AND OTHER OPERATIONAL COST