Post Tender Valuations & Budget Control: Better Financial Control For Your Projects Using Candy Valuations
Post Tender Valuations & Budget Control: Better Financial Control For Your Projects Using Candy Valuations
&
Budget Control
Course Notes
Chapter 1. Starting Up
1.1 Starting Candy
Start the System from the windows desktop by double clicking on the Candy shortcut.
Complete the user Login with your User Name, Initials and Company name.
This is the top level menu in the system where a maximum of 24 companies may be created.
For example, if you are tendering in a joint venture with another firm, you can create a brand new
company for that bid.
To select a company, position the cursor on the required company and use Enter or Double click.
1
Post Tender Valuations & Budget Control Company & Job Manager
Do this
Click the Company > New > Company menu.
Note: You may enter a Company Code and a Password for your company
2
Post Tender Valuations & Budget Control Company & Job Manager
The job manager generates a new header and new job automatically. You may create up to 99
jobs within a company that may be copied, renamed, deleted and backed up using the Job menu
or using the Right-click Menu.
3
Post Tender Valuations & Budget Control Company & Job Manager
Edit the job name to read “Waste Water Treatment Works” and then click
Note: You may designate a Job Code and Password for your job
4
Post Tender Valuations & Budget Control Company & Job Manager
From the Job Manager click Job > Backup/recover job > Recover into a NEW job > from file
Recover the Ventshaft and Substation Contract using the following directory on the Candy
Installation CD <CD Drive>/FSCOMMAND/Demo Jobs/Ventshaft and Substation Contract
5
Post Tender Valuations & Budget Control Company & Job Manager
Click to confirm
6
Post Tender Valuations & Budget Control User Interface
Candy Button System Toolbar Title Bar Application Tab Candy Version
General Toolbar Application Menu Application Toolbar General Menu Customise Toolbar
The Candy user interface consists of four main sections namely: Title bar, Application Tabs,
Application Menus & Toolbars.
Candy button To select the job manager, system settings and to exit the
software
System toolbar Job manager and system settings toolbar buttons
Title Bar Displays the company and job you are working in
Displays the software version installed on the computer and
Candy version
displays the system information
Application tabs To select the Various Candy applications
Application menu Displays the menus of the application selected
General menu Menu for Utilities & Help including telephone list, daily dairies,
card games, help files, licence registration, support information
& a website link to Update the Candy version
General toolbar Displays general tool buttons for use on all applications
Application toolbar Displays shortcuts specific to the application selected. This tool
bar changes when a different application tab is selected
To select the toolbar buttons displayed on the different
Customise Toolbar
toolbars
7
Post Tender Valuations & Budget Control User Interface
Column
Escape Selector
Select all
records
Record
Selector
Page Navigation
Buttons Function Buttons
8
Post Tender Valuations & Budget Control User Interface
In a cell:
Right Click
In a record selector:
Right Click
9
Post Tender Valuations & Budget Control User Interface
In a selected column:
Right Click
10
Post Tender Valuations & Budget Control User Interface
Keystrokes
This is a list of the Editing and Cursor Movement Keystrokes, with a brief explanation of the
function, and the equivalent Icon if available.
Note: Normal Windows shortcut keys can be used e.g. Ctrl C – Copy, Ctrl V – Paste etc.
Ctrl+Tab Moves the document currently on top to behind all other documents.
Ctrl+Insert Inserts a new line at the cursor position
Ctrl+Del Deletes the current line at the cursor
Tab Moves the cursor forward to the next Field. Shift+Tab moves the cursor
backwards.
Home Moves the cursor to beginning of the field
End Moves the cursor to the end of the field
Ctrl + > Move to the next page
Ctrl + < Move to the previous page
11
Post Tender Valuations & Budget Control User Interface
Ctrl+Page Up Takes you to the first line of the first page of a document
Ctrl+Page Down Takes you to the first line of the last page of a document
Ctrl+Enter Split the line at the cursor position
Backspace Deletes one character at a time
Ctrl+Backspace Deletes one word at a time
Ctrl+Left-arrow Bubble Up - move the current line up
Ctrl+Right-arrow Bubble Down - move the current line down
Ctrl+Up-arrow Collapse level headings (to hide all text under headings)
Ctrl+Down-arrow Expand level headings (to show all text under headings)
Shift+Ctrl+Down- Opens all sub headings within the cursor position heading
arrow
Shift+Ctrl+Up- Closes all sub headings within the cursor position heading
arrow
Ctrl+Space Bar Open all headings completely
Shift+Ctrl+Space Close all headings completely
Bar
Ctrl+R Pick Up the current Line
Shift+Ctrl+R Drop (insert) Lines picked up using Ctrl+R at the current line
(Ctrl+D)
Ctrl+U Turn current line to UPPERCASE letters
Ctrl+L Turn current line to lowercase letters
Ctrl+T Turn current word to Sentence case
Ctrl+K Copy the Field above
Ctrl+J Copy the Field above and moves cursor down one line
Alt+Del Close the active Document.
Shift+Alt+Del Close All Documents.
Ctrl+Z Undo.
Note: As soon as the cursor is moved off the line, the line is stored
and the undo button will not function
12
Post Tender Valuations & Budget Control Post Tender Checks
Explanation
The estimate created by the tender department in Candy Estimating can now be used by the
Site Team. It is essential to do some post tender check to prepare the Tender for Post Tender
use.
Recover the estimate and do the following Checks. It is good practice to copy the job before
Remodelling the job for Post Tender Valuations. Eventually the Q.S will have and electronic copy
for the Job at Estimate Stage and a copy for the Remodelled Job for use at Post Tender Valuations
stage.
Do This
Go to the Job Manager Duplicate the Ventshaft & Substation Contract, rename the job to
Ventshaft & Substation Contract- Remodelled.
13
Post Tender Valuations & Budget Control Post Tender Checks
Certain useful information like the Contract Value and Job Size can be analysed.
Do this:
Choose the Valuations application tab.
The job total by trade can be displayed by clicking the (Trade Totals) icon.
14
Post Tender Valuations & Budget Control Post Tender Checks
The Gross Trade Total and Selling Trade Total can be displayed using the same icon and
selecting the appropriate rate.
15
Post Tender Valuations & Budget Control Post Tender Checks
Do this:
16
Post Tender Valuations & Budget Control Post Tender Checks
Gives an overall listing of the job and is an important indicator for the time factor allocated to the
job.
Do this:
Click Check & Review > Job Size Display
At Tender Stage the: Net Rate + Applied Mark Up = Gross Rate. The gross rate is calculated based
on the net and mark up applied therefore any changes made on the net or applied mark up will
change the gross rate. This is ideal at tender stage but not ideal for the post tender stage of the
contract.
At the Post tender stage, a Selling Rate is available in Candy. The selling rate is used as the
contractual rate for printing the Interim Payment Claim to the client. Adjusting the net or Applied
Mark Up will not affect the selling rates.
Therefore, for Post Tender Stage the: Net Rate + Calculated Mark Up = Selling Rate
The selling is a fixed contractual rate by adjusting the Net (job remodelling) the Calculated Mark
Up will change.
One of the essential checks at post tender is to ensure that the job contains a selling rate. The
confidence check shows items that do not have a selling rate therefore, the selling rate must be
entered or we can copy the Selling rate from Gross rate.
17
Post Tender Valuations & Budget Control Post Tender Checks
Do this:
Open the Document Manager by choosing Documents > Valuation Document Manager.
Note the selling rate column on the right side of the document. At Tender Stage the job was
priced and the Mark up was applied, the selling rates can now be established by copying the Gross
rate.
Right-click in the selling rate column header, select Copy > Copy Selling rates from Gross.
18
Post Tender Valuations & Budget Control Post Tender Checks
Right Click
Check the option to lock selling rates after copy and Copy zero gross rates click OK…
…and confirm the message.
Note the selling rates are displayed next to each bill item.
NB: Check the selling amount balances back to the signed contract document.
If the totals do not balance then go back to the problem bill page and check the selling rate of
each bill item on that page.
19
Post Tender Valuations & Budget Control Post Tender Checks
The indicator in the selling rate column indicates that the rate is locked. To fix the rate
we must first unlock it.
Right click on the selling rate and select Lock/Unlock > Unlock selling rate.
20
Post Tender Valuations & Budget Control Post Tender Checks
Something to consider........
The bill quantity will normally be used for the first Final Value projection and as a starting point
can be copied to the Final Quantity column.
Do this:
Click YES
21
Post Tender Valuations & Budget Control Post Tender Checks
See that the Bill qty have been copied to the Final Qty
Note: Later in the course the final qty will be re-measured using the quantity calc sheet.
22
Post Tender Valuations & Budget Control Post Tender Checks
Explanation
Now Candy can generate a number of reports to help you check for any possible problems on
the tender.
Do this:
23
Post Tender Valuations & Budget Control Post Tender Checks
Explanation
The Price code list may contain price codes not used in the bill. You should consider deleting
unused price codes which will result in having a less confusing job. The job will therefore only
contain price codes used in the bill.
To delete unused price codes go to the document 1.1 Price Code Listing ( )
24
Post Tender Valuations & Budget Control Post Tender Checks
Similarly unused resource can also be deleted directly from the resource list.
Do This
Go to the document 1.1.Resource List ( ),
click Tools > Delete ALL unused resources > Delete Key resources as well
25
Post Tender Valuations & Budget Control Post Tender Checks
Explanation
Checks for mistakes on worksheet calculation lines. If there is a space between +5%waste then
the wastage report would be incorrect. If *CONC] is used instead of *[CONC] the first
occurrence would be seen as a comment and not a variable if 1.O9 is used instead of 1.09 then
1.00 instead of 1.09 will be used on the calculation line. Ensure accuracy at all times.
Click OK.
How many errors were detected?
If errors are detected a report will be generated.
Explanation
At tender stage the estimator may mark worksheets, resources and bill items as provisional.
Locate the provisional worksheets, resources and bill items.
26
Post Tender Valuations & Budget Control Post Tender Checks
Explanation
80/20 rule of thumb, identify which items contain the value and which items should be
concentrated on at pre and post tender stage.
27
Post Tender Valuations & Budget Control Post Tender Checks
28
Post Tender Valuations & Budget Control Post Tender Checks
Resources can be checked for potential problems like provisional rates or out-dated rates.
Do this
29
Post Tender Valuations & Budget Control Post Tender Checks
Explanation
This is the column layout selector. To include column data into your document, you can move
available columns (left hand side) to the right with the green arrow; to remove them use the red
arrow.
Add the column 4.2 Date of resource rate change and confirm.
Now open your new document 1.1a Resource list with Date. Look for resources that have old
dates and check the rates.
30
Post Tender Valuations & Budget Control Post Tender Checks
When you are finished you can clear the sort with
31
Post Tender Valuations & Budget Control Post Tender Checks
Provisional resources
If you move the pointer over the red dots on the Final rate, you will notice that these are marked as
provisional, like this:
Alternatively, a fixed filter can be used to find resources that where marked as provisional.
Select the document menu View > Filter > Provisional Resources
You can now show just the resources you want with
32
Post Tender Valuations & Budget Control Post Tender Checks
33
Post Tender Valuations & Budget Control Post Tender Checks
34
Post Tender Valuations & Budget Control Pricing using Worksheets
Plug rates and split rates must also be converted to Worksheets to generate the required resource
budget.
The pricing check report printed earlier listed Price code E1133 as a Plug rate and Price code
E42111 as Split rate. To control your allowable the plug rate and split rate must be priced using
worksheets.
The list of price codes for the job can be displayed by clicking on the
35
Post Tender Valuations & Budget Control Pricing using Worksheets
Do this
36
Post Tender Valuations & Budget Control Pricing using Worksheets
About Worksheets
315 Calculation lines are available to calculate the net rate for the price code. The worksheet
header displays Price code, Pricing description and pricing qty of “8250m2”. The worksheet
header also display where the price code is used in the bill “Page 4 item A and Page 1 item A”.
Therefore the change in rate for the price code will change the rate on the items where the price
code is used.
Note: A calculation must start in the beginning of the line using a resource code. Beginning with
a space will only create a comment line.
Do This
To add the required resources to the worksheet from the Resource List, type resource codes
32511
3171
2211
…at the beginning of calculation lines 2, 3 & 4.
The worksheet fetches the resources from the Resource List.
Now multiply each resource by the required number. Type in the multipliers:
32511 JD 410 Digger loader *1off
3171 6m3 Tipper *2off
2211 Labourer *4off
37
Post Tender Valuations & Budget Control Pricing using Worksheets
Start an applied factor using“#” on calculation line 1. End the applied factor using a “=” followed
by the calculation *0.5day/710m2.
Note: The Enter key or moving off the line will automatically calculate the result and the words
“APPLIED FACTOR” will appear.
Use the shifted function on the Store & next w/s function
button to change the store mode from
Store & Next worksheet to Store & return to document.
38
Post Tender Valuations & Budget Control Pricing using Worksheets
Note
The worksheet header displays the total pricing qty of “1725m3”, 600m3 on Page 4/Item C, and
1125m3 on Page 1/Item C.
39
Post Tender Valuations & Budget Control Pricing using Worksheets
Price worksheet using the applied factor applying a production of 85m3/day and adding 10% for
battering.
40
Post Tender Valuations & Budget Control Pricing using Worksheets
41
Post Tender Valuations & Budget Control Pricing using Worksheets
42
Post Tender Valuations & Budget Control Value Engineering
Resource List
43
Post Tender Valuations & Budget Control Value Engineering
Note that the Diesel allowable decreases from 280 155.37 to 266 814.64 representing a buying
saving of 13 340.73.
The tender rate for Diesel at 6.3/Ltr calculates Material Net Amount of 2 583 388.80 and a Markup
of 757 249.87
44
Post Tender Valuations & Budget Control Value Engineering
The Diesel at 6/Ltr calculates Material Net Amount 2 570 048.08 and a markup is now higher at
770590.59. An increase in markup of 13 340.72
Now return to page one of the Bill of Quantities
Do this:
Open document 1.1 Gross to Sell Bill
Notice that the Net and Gross rates have changed as these items use the cheaper diesel in their
make-up. The Selling rates remained fixed and the calculated mark-up has increased in relation to
the Selling.
Do this:
Access document 3.1 Variation Pricing
This document is ideal for variation pricing.
45
Post Tender Valuations & Budget Control Value Engineering
Right click on the price code column header and select Explode Macro Price codes > Explode
Macros without recoding
Click Yes
46
Post Tender Valuations & Budget Control Value Engineering
Note: The additional Internal Items were added below Item F. Internal Items only have a net rate
and no Selling rate. Internal items are marked with an “I” in the attributes column and therefore will
not be printed on the Interim Payment claim to the client. Item F is the external item and
therefore only has a selling and no Net rate.
Do this
Do a filter for internal Items.
Right click in the attributes column header, select filter > Internal items.
47
Post Tender Valuations & Budget Control Value Engineering
Right click in the Final Qty Column header, Select filtered records
Yes to confirm
48
Post Tender Valuations & Budget Control Cost and Group Codes
Do this:
Open the document manager and select the resources Tab
Resource document 1.6 Resource Group and Cost code allocation is available as a template
document.
Add a new template document by clicking on New Document
49
Post Tender Valuations & Budget Control Cost and Group Codes
The Cost and Group must be defined before allocating them to the resources.
Do this:
Click on the to access the definitions and Enter and check the following Cost and Group Codes.
Choose 4.1 Cost codes (Ledger code)
50
Post Tender Valuations & Budget Control Cost and Group Codes
51
Post Tender Valuations & Budget Control Cost and Group Codes
Cost Code
Check that all the simple resources have a cost code and that the correct Cost code has been
allocated to the simple resources. The money is summarised into the cost codes for Cost &
Allowable control.
Return to the resource list and allocate the Cost and Group codes to the various resources. Cost
and Group codes should only be applied to Simple resources, those resources that are bought and
are defined with a letter in the resource type column i.e. M for Material, P for Plant.
Complex resource
Complex resource is a combination of simples and complexes. A complex resource is identified by
using a number in the Type column. The number represents the level of the complex from level 9
being the most basic to 1 being the most complex.
Applying a cost code to a complex resource such as JD 410 Digger Loader W&O would be
incorrect because the complex includes a combination of Plant, Fuel and Labour.
Do this:
Go to View > Filter > Blank codes> Cost codes (simples only)
Click to view only the simple resources with blank cost codes.
52
Post Tender Valuations & Budget Control Cost and Group Codes
Double click in the Cost code column for resource code 60329 – High Tensile Steel
Click Abandon
53
Post Tender Valuations & Budget Control Cost and Group Codes
Resource analysis reports can now be printed showing the resource Utilisation and Amount
including a Cost code or Group code summary.
Do this:
Open the Valuation Reports by choosing Reports > Valuation Reports Manager
54
Post Tender Valuations & Budget Control Cost and Group Codes
55
Post Tender Valuations & Budget Control Cost and Group Codes
Page 3 reflects all the simple resources. Note that all simple resources should have a Cost Code
allocated.
56
Post Tender Valuations & Budget Control Cost and Group Codes
Do this:
From the report manager select report Analysis by Group/Cost (72).
Customise the report and select Sort by Cost Code.
Entering a cost code in the sieve will print out only those resources that contribute to that
particular cost code. By leaving the sieve blank will analyse all the cost codes.
57
Post Tender Valuations & Budget Control Cost and Group Codes
Tracer report
The Tracer report will list all the bill items that contribute to a particular cost code. The tracer
report is available under the Check and Review Reports heading.
Print the Tracer report and select Cost Codes in the tracer selector.
58
Post Tender Valuations & Budget Control Cost and Group Codes
Do this:
From the report manager select report Analysis by Group/Cost (72).
Customise the report and select Sort by Group Code.
59
Post Tender Valuations & Budget Control Cost and Group Codes
Click OK
60
Post Tender Valuations & Budget Control Task Codes
61
Post Tender Valuations & Budget Control Task Codes
Do this:
Open the Definitions and enter the following Task codes.
Task codes may be summarised into Task code headings. The level column represents the heading
level from level 9 to level 1. Therefore, the Earthworks Tasks of Clear site and Excavation may be
summarised into the level 1 heading Earthworks. Note the m2 quantity of Clear site must be
factorised by 0.10 to calculate the m2 to m3.
The task code accumulates the amount of money and quantity; therefore, each task code should
have a unit.
62
Post Tender Valuations & Budget Control Task Codes
Do this:
Open the Valuations Document Manager , select Valuation Bills Tab.
63
Post Tender Valuations & Budget Control Task Codes
Customise the document and add columns 26.8 Task code description and 26.9 Task code unit.
Do this:
Open document 2.6 Task coding (Controlling labour & plant) and check to see if all the bill
items have Task code.
To filter for Bill items without Task codes Right click in the Task code column select Filter > Filter
for blanks.
Click
64
Post Tender Valuations & Budget Control Task Codes
65
Post Tender Valuations & Budget Control Task Codes
66
Post Tender Valuations & Budget Control Task Codes
Do this:
Do an on-screen task analysis, click Finalisation > Job analysis > Job analysis by Task code.
Click Yes
Click OK
67
Post Tender Valuations & Budget Control Task Codes
Note that the Total Quantity, Amount and derived rate is calculated for each Task Code. When
finalising a tender, if the derived rate is much lower or higher compared to previous tenders, then
relevant items can be investigated for possible errors in the pricing worksheets.
The total allowable for Labour is calculated for each Task Code, i.e. The Labour allowable for
placing concrete in Foundations is 1,352,959. Once progress quantities have been entered for each
bill item, the total Labour allowable amount for each Task code is calculated and should be
reconciled back to the total Labour cost for each Task code.
Clicking the Split Rates or Split Amounts toggles between displaying split rates and split amounts
for each of the Task Codes.
Note the derived Labour rate to place 1m3 of concrete in Foundations is 80.16 per m3, if the
concrete team on site has poured 10m3 then you should not have spent more than 10 x 80.16 =
801.60 on the Labour team.
Daily costing should be done against the relevant Task Codes which should be reconciled to the
Labour allowable based on the work that has been completed on site.
A similar approach should be followed to control Plant.
68
Post Tender Valuations & Budget Control Task Codes
Totals for Task code headings may be displayed by placing the cursor on the heading and pressing
Ctrl-Up and Down Arrow.
Various Task code reports are available in the Report Manager under the report heading Project
Code Reports.
The project codes report will list the bill items in Task Code order with a total for each Task Code.
69
Post Tender Valuations & Budget Control Task Codes
Select Task code as Primary and none as the secondary and click OK.
70
Post Tender Valuations & Budget Control Task Codes
The Project Codes Quantity Summary report lists the total quantity for each task.
The project code quantity summary report is available in the template reports.
Do this:
From the report manager click New report and select report 9.6 Project Codes Quantity
Summary (83).
71
Post Tender Valuations & Budget Control Task Codes
The Task code summary report displays the total Quantity per Task. Note for this job consists of a
total of 27745m3 of excavations.
Do this:
Print the Project Codes Resource Analysis.
Select Analyse complexes to level 9, Print codes separately and Summary by Cost Code.
72
Post Tender Valuations & Budget Control Task Codes
Page 1 - 50: Lists the resource analysis per Task and the Cost code summary per Task
73
Post Tender Valuations & Budget Control Task Codes
74
Post Tender Valuations & Budget Control Variation Pricing
Do This
Go to Valuation bills in the Document manager and open document 3.1 Variation pricing
Variation orders can be entered between existing bill items or entered on new page of the bill. The
practical method would be to add and price all the VO’S in a new page in the bill. Heading levels
can be used to group each VO in to headings.
75
Post Tender Valuations & Budget Control Variation Pricing
Do This
Type in the New heading, Sub headings & Variation item including final qty. Headings should
coincide with existing heading structure, Create the level 2 heading called Variation orders and
level 3 heading for variation order # 1.
Price V.O. # 1 Clear site North Boundary using Price code E1133.
Note: The bill item Clear site North boundary adopts the Price codes Net and Selling rates
effectively speeding up the pricing process. The Price Code E1133 has a red indicator block
indicating that it is used on multiple bill items. If the rate is changed then the changed rate will
apply to all the bill items. Therefore if different rate is required the bill item will require a different
Price code.
Do This
Open document 2.6 Task coding (Controlling labour & plant)
Note: The bill item already has a Task code 0100. The task code is allocated to the price code
therefore by allocating the same price code the bill item will adopt its Task code.
76
Post Tender Valuations & Budget Control Variation Pricing
8.2 VO Codes
Open document 2.5a My Variation pricing and Allocate VO Code 1 and mark it approved.
Do This
Go to Valuation bills in the Document manager and select document 3.2 Variation Orders
with BOQ allocations
77
Post Tender Valuations & Budget Control Variation Pricing
Go to Valuation bills in the Document manager and select document 3.3 Variation Orders-
Financial Summary
78
Post Tender Valuations & Budget Control Valuations
The Candy Valuations is used for the post tender stage of a project. The Bill of Quantities created in
Candy Estimating is available in Candy Valuations, the difference between Estimating and
Valuations is the extra Valuation quantity columns, Valuation layouts and the Valuation reports.
Do this:
Go to the Job manager , select Ventshaft & Substation Contract - Remodelled, click on Job in
the menu and select Duplicate job then rename it to Ventshaft & Substation Contract –
Valuation NO. 1
79
Post Tender Valuations & Budget Control Valuations
Please Note: Setup next valuation will copy all to date Quantities to previous. Therefore this step
must be done before entering any new quantities for all Valuations that follow.
80
Post Tender Valuations & Budget Control Valuations
Valuation Documents
Do this:
Click on or Open the Valuation Document Manager Documents > Valuation Document
Manager
Duplicate document 2.2 Primary Valuation Entry & rename it to 2.2a Favourite Valuation Entry
81
Post Tender Valuations & Budget Control Valuations
Select document 2.2a Favourite Valuation Entry Click on to select the columns required
in the Valuation document
Select the required columns as per the above layout and click .
Note: The valuation toolbutton will now open your Favourite valuation entry.
82
Post Tender Valuations & Budget Control Valuations
Note: Item 1/A Clear and strip site has a calcsheet for the bill qty therefore indicating a green
indicator block on the Bill Quantity and a “B” in the Qty Calcsheet indicator column.
Do this:
Using Document 2.2a Favourite Valuation Entry double click on the Final Qty for Clear and Strip
site to open a calcsheet.
Measurements from other calcsheets and bill items can be copied using .
Copy the Bill qty calcsheet into the Final Qty calcsheet. Select the Bill qty as the source selection
and type in Page “1” Item “A”.
83
Post Tender Valuations & Budget Control Valuations
Click to confirm.
On line 4 add the following calculation “20*20” and remarks “Area 4 DRW # 110 Rev1”.
Click
84
Post Tender Valuations & Budget Control Valuations
Note: The quantity calc sheet indicator now contains a “B” and “F”
85
Post Tender Valuations & Budget Control Valuations
Do this:
Progress all Earthworks, Formwork, Reinforcing, Concrete and Joints in the ventilation shaft as
100% complete by typing in 100% in Actual % Final column.
On Page1
On Page 2
86
Post Tender Valuations & Budget Control Valuations
On Page 3
On Page 7
87
Post Tender Valuations & Budget Control Area Bills
88
Post Tender Valuations & Budget Control Area Bills
Do this:
Click on Areas > Area II definitions to access area bills.
89
Post Tender Valuations & Budget Control Area Bills
90
Post Tender Valuations & Budget Control Area Bills
Click Tools > Import bill items > Import bill items by page & trade
Importing may be done using a page range. Uncheck Select all pages and Select trades. Select
page range from page 4 to 6.
91
Post Tender Valuations & Budget Control Area Bills
Do this
In the Area manager Select Sub B - Substation B
92
Post Tender Valuations & Budget Control Area Bills
Note: The area code Sub A has already been allocated to the bill items.
Filter for area code Sub A. Right click in the Area Code column > Filter > Start a new filter.
Type Sub A
93
Post Tender Valuations & Budget Control Area Bills
Right click on the selection > Code allocation > Areas > Allocate to Area
94
Post Tender Valuations & Budget Control Area Bills
95
Post Tender Valuations & Budget Control Area Bills
96
Post Tender Valuations & Budget Control Valuation Reports
Do this:
Click on to access the Valuations Job Manager , double click on Valuation Bills and select
Interim Payment Claim, click .
97
Post Tender Valuations & Budget Control Valuation Reports
Do this:
Return to the Valuation Document Manager and select Valuation Listings Report then select
and
98
Post Tender Valuations & Budget Control Valuation Reports
99
Post Tender Valuations & Budget Control Valuation Reports
Do this:
Return to the Valuation Document Manager and double click on Resource Analysis Reports and
select Valuation Resource Analysis report then select and
100
Post Tender Valuations & Budget Control Valuation Reports
Do this:
Return to the Valuation Document Manager and double click on Project Codes Reports and click
on Project Codes Analysis report then select and
101
Post Tender Valuations & Budget Control Valuation Reports
Click .
102
Post Tender Valuations & Budget Control Valuation Reports
Do this:
Click on the tool button select Actual Quantity and select Net rate.
103
Post Tender Valuations & Budget Control Cost & Allowables
104
Post Tender Valuations & Budget Control Cost & Allowables
The Cost & Allowables documents are available in the Valuation document manager.
105
Post Tender Valuations & Budget Control Cost & Allowables
The above document shows the To-date, Remaining and At completion for the current
Valuation period.
Note: The Task code column is included by default in this document. The BuildSmart® accounting
system has both the Task code (Activity code) and Cost code (Ledger code) for more
comprehensive cost control. However some other accounting systems only make use of Cost codes
for their cost control.
Do This
From the document menu select View > Column layout. Remove the Task code column and
confirm. The document is automatically re-calculated and displays only the Cost code information.
106
Post Tender Valuations & Budget Control Cost & Allowables
Note: To do a meaningful comparison with the costs from accounts it is essential to measure
the actual quantity on the day of cost close (e.g. 25th of the month). Additionally Job
remodelling is essential to price Plug rate and split rate with worksheets (Refer to Chapter 4).
Do This
Select the Cost & Allowable tab on the Valuation document manager.
Open the document 4.1 Cost import. Select Tools > Import and overwrite Cost to date > Import
cost from a file. Use explorer to find the text (Excel) file and import the file.
Column Identification is used to select column headings that match the imported information.
Identify columns for the Cost code and Real cost to date.
107
Post Tender Valuations & Budget Control Cost & Allowables
Click Continue
108
Post Tender Valuations & Budget Control Cost & Allowables
109
Post Tender Valuations & Budget Control Cost & Allowables
If the imported file is not fully compatible with Candy’s information a message will be displayed
advising which line/lines are not compatible.
These lines will also be filtered out and displayed.
Most likely it would be column headings in the import document that have not been defined as
cost codes in Candy. Use CTRL+DELETE to remove this unwanted information.
Re-check the file and you should get a Validation successful message.
110
Post Tender Valuations & Budget Control Cost & Allowables
Do This
Use the cost import document to make some reallocations and additional cost provisions as per
the screen below.
Do This
Click Tools > Release costs for Costs & Allowables
111
Post Tender Valuations & Budget Control Cost & Allowables
Something to consider........
The cost import document should form part of your Cost reporting pack.
Do This
Open doc 2.1 Cost Allowables by Period and Click Calculate to view
112
Post Tender Valuations & Budget Control Cost & Allowables
Do this
Use doc 7.2 Resource cost rates to completion
In the Cost rate column change the simple resource’s cost rate to the following resources.
4914 Diesel rate change cost rate from 6.00/Ltr to 6.20/Ltr.
53111 Stock Bricks rate change cost rate from 750.75/Thou to 800/Thou.
53411 Face Bricks rate change cost rate from 915.92 to 980/Thou.
113
Post Tender Valuations & Budget Control Cost & Allowables
Re-calculate the document 2.1 Cost & Allowables by period to see the changes in the Remaining
Cost column.
Do this:
Open the document 6.2 Bill with cost rates for cost w/s adjustment.
Open the worksheet for item 5/A – One brick wall in foundations.
Adjust the output formulae from 600 bricks per shift /day down to 500 bricks per shift and change
the wastage from 10%waste to 15%waste.
Store worksheet
Note:
Indicators on the Cost rate will indicate cost rates that use Net rate, Use Net w/s with resource
cost rate and Use Cost worksheet.
115
Post Tender Valuations & Budget Control Cost & Allowables
Re-calculate the document 2.1 Cost & Allowables by period to see the additional changes in the
Remaining Cost column.
116
Post Tender Valuations & Budget Control Cost & Allowables
Allowable at completion is calculated using the Final quantity x Net rate and the Cost at
completion is the sum of the Cost to date and Remaining costs. This information is used to
determine the at Completion performance of the project.
Do this:
Open document 2.1 Cost & Allowables by period and Calculate
117
Post Tender Valuations & Budget Control Cost & Allowables
The Cost Code provides resource-based control for managing fixed resources such as Materials.
The Cost Code will provide limited control to productive resources such as Plant and Labour but is
not ideal. The engineering site staff will require the Labour and Plant allowable in more detail
typically the allowable per Task completed on site.
Cost Code “201 General Labour” is a typical problem, we know we losing money on labour but now
we need to know what Task is the cause of the losses. The example below illustrates a loss for
labour on Vertical formwork and a gain on Excavation.
118
Post Tender Valuations & Budget Control Set up Next Valuation
Open 2.1 Valuation Input – Actuals. Note the Previous Actual qty is empty because this was the
first Valuation.
Do This
Go to the Job manager , copy Ventshaft & Substation Contract – Valuation No. 1 and
rename it to Ventshaft & Substation Contract – Valuation No. 2
119
Post Tender Valuations & Budget Control Set up Next Valuation
Note:
The option to Archive previous qty is checked. This will archive all previous quantities. The archived
quantities can be viewed using valuation document 4.3 Archive Valuation Quantities.
120
Post Tender Valuations & Budget Control Set up Next Valuation
121
Post Tender Valuations & Budget Control Subcontract Manager
122
Post Tender Valuations & Budget Control Subcontract Manager
Do this
In Valuations select Subcontract > Subcontract manager
Click New
123
Post Tender Valuations & Budget Control Subcontract Manager
Explanation
A new Subcontract can be added using the following options:
Manually: This option is used for when we need to create a new subcontract from
scratch.
Selecting a s/c package code: This option is used to select pre-defined subcontracts.
Selecting a subcontract from the adjudicator: This option is used to select subcontracts
from the Subcontract adjudicator.
124
Post Tender Valuations & Budget Control Subcontract Manager
Do This
Open the Painting subcontract by double-clicking on the subcontract, or by pressing the Select
softkey or Enter.
Any item on the BOQ (or a selection of items) can be dragged, copied or imported into a
subcontract bill - the code for that subcontract will be displayed against the BOQ item.
Alternatively, entering a subcontract code against a Main BOQ item will insert that item into the
subcontract bill.
Many subcontract codes can be entered against a BOQ item - in other words, many subcontracts
can refer to the same BOQ item.
Do This
Import the bill items by page & trade
Click on Tools> Import bill items > Import bill items by page & trade
125
Post Tender Valuations & Budget Control Subcontract Manager
Importing may be done using a page range or trade. At the tender stage trades have been and
therefore check the option Select Trades to import by trade.
126
Post Tender Valuations & Budget Control Subcontract Manager
Do This
Right click in the Awarded Quantity column, select Copy from selected Bill quantity
127
Post Tender Valuations & Budget Control Subcontract Manager
To import the bill rates into the subcontract bill, right click on the Subcontract rate column and
select Import Bill rates.
128
Post Tender Valuations & Budget Control Subcontract Manager
Select “S Subcontract”
129
Post Tender Valuations & Budget Control Subcontract Manager
Do this
On the S/C Manager click New and choose the option Select a subcontract from the Subcontract
Adjudicator
130
Post Tender Valuations & Budget Control Subcontract Manager
Click OK
131
Post Tender Valuations & Budget Control Subcontract Manager
Note: The S/C Bill Items have been imported using the rates quoted by Drainaway limited in the
S/C Adjudicator
132
Post Tender Valuations & Budget Control Subcontract Manager
Do This
For the Painting subcontract entre the code SEAGREEN and Name Seagreen Painters
For the Plumbing subcontract entre the code DRAIN010 and Name Drainaway Ltd. Then entre
the subcontractor details.
133
Post Tender Valuations & Budget Control Subcontract Manager
Note:
Subcontractors code could be the code used for the subcontractor in your company’s accounts
system. If the subcontractor is already in your Subcontractor database, the drop down list can
be used to copy the details.
134
Post Tender Valuations & Budget Control Subcontract Manager
Do this
Choose the Painting contract
To access the s/c document manager click Tools > Document manager
135
Post Tender Valuations & Budget Control Subcontract Manager
Note: the Subcontract Bill with progress update includes Due and Pay quantities.
136
Post Tender Valuations & Budget Control Subcontract Manager
137
Post Tender Valuations & Budget Control Subcontract Manager
138
Post Tender Valuations & Budget Control Subcontract Manager
139
Post Tender Valuations & Budget Control Subcontract Manager
14.6 Extras
Any additional work done by the subcontractor outside his contract can be added as an extra cost.
VO’S between the main contractor and the subcontractor are extras. VO’S that need to be claimed
to the client will not be an extra. Client VO’S must be entered as a Main bill Item and then imported
into the Subcontract bill.
Repairs charged to others will be additional work done that must be contra charged to another
subcontractor.
Do This
Seagreen Painters damaged an eaves gutter during painting. The damaged gutter must repaired by
the Plumber and contra charged to the Painter.
In the Plumbing subcontract select the Extras Tab and click New in the “Repair charged to
others” section
140
Post Tender Valuations & Budget Control Subcontract Manager
141
Post Tender Valuations & Budget Control Subcontract Manager
14.7 Charges
Any items that incurred by the subcontractor will be a charge. Charges from Main Contractor will
be some additional items supplied to the subcontractor like safety equipment.
Do This
In the Painting subcontract select the Charges tab
Note the charge from the Plumbing subcontractor automatically appears as a Charge from other
Subcontractor.
142
Post Tender Valuations & Budget Control Subcontract Manager
Materials on Site claimed by the subcontractor. Only the entries for the current period are regarded
for this period’s certificate - in other words, any lines that are displayed in grey text are ignored in
determining the current month's MOS. When the next certificate is made, the previous certificate's
entries will be displayed in grey text but cannot be changed.
Do This
Add MOS for the Plumbing Subcontractor as per the illustrated below.
Select the MOS Tab then Click New and add the rainwater pipe.
Click OK
143
Post Tender Valuations & Budget Control Subcontract Manager
Certificate record
All previous and the current certificate are recorded. All the information shown on this screen can
be edited to reflect the progress of the payment to the subcontractor. However, the Certificate
Number cannot be changed as it reflects the sequence of certificates and is in cemented
automatically when the next certificate is setup.
Do this
Click Edit
Click Ok
144
Post Tender Valuations & Budget Control Subcontract Manager
Note:
The next certificate button is used to setup next S/C certificate. When used, the to-date values
will be copied to previous. Therefore this must be done before entering the next certificate
value. The next certificate button will only apply to the current Subcontractor and must be done
for each individual subcontractor.
Lookup values
This is the accumulation of all the Subcontractor data and is used to create the subcontractors
certificate. The export button will send the data in this list to your Excel template, the information
can be mapped to your Excel Template by row and column.
145
Post Tender Valuations & Budget Control Subcontract Manager
146
Post Tender Valuations & Budget Control Subcontract Manager
A summary of all the subcontractors can be viewed in the S/C Liability document. The liability
document displays all the subcontractors’ bill values.
Do This
Note:
The Subcontract liability amount is calculated using Total due less Total Pay Amount
147
Post Tender Valuations & Budget Control Valuation using Subcontract Manager
148
Post Tender Valuations & Budget Control Valuation using Subcontract Manager
Do This
Open the valuation document Manager
Customise document 8.2 Bill with Subcontract update to add column 28.13 Subcontract total
due quantity
149
Post Tender Valuations & Budget Control Valuation using Subcontract Manager
150
Post Tender Valuations & Budget Control Valuation using Subcontract Manager
151
Post Tender Valuations & Budget Control System Registration
152
Post Tender Valuations & Budget Control System Registration
If the system has been registered the job selector will be displayed.
153
Post Tender Valuations & Budget Control System Registration
154
Post Tender Valuations & Budget Control System Settings
Fonts
Change the font, style and size for various areas of the system. You may find that the view is
limited in a document, for example the Bill of Quantities, and may need to adjust your fonts later.
155
Post Tender Valuations & Budget Control System Settings
Documents
Colours can be selected for cursors and input fields on documents and level headings.
Tool buttons
Frequently used shortcuts keys can be activated here by applying ticks or removing ticks
Do this:
156
Post Tender Valuations & Budget Control System Settings
The Candy system can be configured on the network by setting up the folders and paths. The
following paths can be set as below:-
Common backups – to set the path to the Common folder used by all the users wishing to backup
data on the organisation’s network. (The backed up data can be recovered by other users)
Archived backups - to set the path to the Archived folder for the individual user wishing to
backup data on the organisation’s network. (The backed up data can only be recovered by the
individual user)
Candy network masters – To set the path for a master network company enabling users to access
the master library job centrally
Microsoft Excel - the path pointing to Excel for exporting Candy data directly to Excel.
Tool buttons Set tool buttons to display in each toolbar button
Job start-up Set the start tool button document to open immediately when a job is
selected.
Folders and Set the folders and network path for backups and network masters. If Excel
paths is installed on the computer, the executable command can be located here
for exporting document information direct into Excel.
Number format Set number styles to use
Keyboard Set text input and Enter key direction
Languages Set the langue file to use (other than English)
Macro keys Set keyboard shortcuts to activate recorded keystrokes in sequence
Toolbar keys Set keyboard short cut commands to activate tool button functions
157