Professional Documents
Culture Documents
Method Statement For Air Leak Test For HVAC Duct System Light Test
Method Statement For Air Leak Test For HVAC Duct System Light Test
RENCO-KAT
PROJECT: KE01-A1-000-RK-M-TT-0002-000
KASHAGAN DEVELOPMENT EXPERIMENTAL PROGRAM
CONTRACT DESCRIPTION:
SIS BUILDING CONSTRUCTION PROJECT
ABSTRACT:
This method statement is the document detailing how HVAC
Ducting system are tested (Light Test) for KEP SIS (Kashagan
Experimental Program – Satellite Instrument Station) Building
(Oil, Gas & Sulphur) Construction Project
Page 2 of 24
Hold
Para. Description of Hold
No.
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct system (Light Test)
Rev. C01, November 2008
Page 3 of 24
AGIPKCO
KASHAGAN DEVELOPMENT EXPERIMENTAL PROGRAM
November 2008
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct system (Light Test)
Rev. C01, November 2008
Page 4 of 24
LIST OF CONTENTS
1.0 PURPOSE.........................................................................................................................................................................5
2.0 SCOPE.............................................................................................................................................................................5
6.0 HSE..................................................................................................................................................................................7
7.0 METHODOLOGY.........................................................................................................................................................7
9.0 ATTACHMENTS............................................................................................................................................................8
1 REQUEST FOR INSPECTION...................................................................................................................................... 8
2 RISK ASSESSMENT................................................................................................................................................... 8
3 Attachment from SMACNA (HVAC DUCT CONSTRUCTION STANDARDS)..........................................................8
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct system (Light Test)
Rev. C01, November 2008
Page 5 of 24
1.0 PURPOSE
The purpose of the method statement is to describe the method of testing HVAC Duct
system for air leak (by light test) that will be performed in the scope of SIS buildings at
Kashagan Field Development Project Finishing of Satellite Instrument Shelter Buildings (Oil,
Gas & Sulphur). This statements made shall be followed by Supervisors and Foremen
without omissions.
2.0 SCOPE
The Method Statement defines the methodology of carrying out air leak test by light in HVAC
Duct system related to Satellite Instrument Shelter Buildings (Oil, Gas, Sulphur).
3.0 REFERENCES :
Functional Specification for HVAC and Building Utility
KE01.A0.690.KD.C.SF.0001.000
Industrial Building Areas
KE01-A1-690-KD-C-SP-0012-000 Ductwork Specification
Page 6 of 24
QA/QC Manager : Responsible for controlling and directing the activities complying with
the quality requirements given in the references. He reports to the Project Manager.
HSE Manager: Responsible for the maintaining of the HSE Plan and management system. He
reports to the Project Manager.
Construction Manager: Shall plan the work schedule and coordinate with project manager for
the methodology and resources required to conduct the work. And he ensures that Project
safety Procedures are being implemented.
Site QC Inspector: Shall perform first line inspections and follow it with developing and
implementing Inspection Requests in accordance with Construction priorities. Accompany Agip
KCO Inspectors to carry out routine Inspections when requested.
Supervisor: shall be responsible for Inspection of the HVAC system to ensure quality and
confirm compliance with project documents and specifications. Timely delivery of the material to
site and ensure the work is progressing according to the schedule. Provide technical directions
and monitor "checkout test" associated with pre-commissioning. Evaluate shipping damage to
HVAC materials and recommend corrective action. He reports to construction manager. Shall
ensure that the work crew under his supervision shall work according to safety standards.
Foreman: He is directly in charge of the crew, equipments and material being used to conduct
the work. He shall ensure that all work performed under his supervision shall be performed
according to approved project HSE procedures.
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct system (Light Test)
Rev. C01, November 2008
Page 7 of 24
6.0 HSE
All work shall be carried out in accordance to AGIP KCO and Renco-KAT safety regulations
& policies.
Team coordination shall be implemented by the work supervisor.
All personnel related to work shall wear PPE.
Valid certification of all lifting equipment will be verified prior to operation.
All personnel involved in HVAC installation shall be competent enough and well conversant
with the works to be carried out.
When working at height, safety harness with double lanyard shall be fixed with approved
safety life line, and man lift/scaffolding shall be used.
Scaffolding shall be erected/approved/dismantled under supervision of scaffolding
supervisor.
If lifelines are used, it will be designed to withstand a load of 2275 Kg per person attached
to the line.
Only two persons may be attached to a lifeline at any time. After implementation, a lifeline
needs to be inspected on a regular basis.
AKCO HSE must be notified if a lifeline is going to be used.
All man lifts / trucks / cranes to be inspected & approved for use on site.
All lifting equipments /tackle to be inspected & certified prior to use and shall adhere to
AKCO color coding procedure
TRIC & TBT to be conducted prior to start of work.
Continuous HSE coverage to be available.
7.0 METHODOLOGY
To verify whether duct is free of the air leak - smoke test, light test or leakage test as per
code ASHRAE can be used.
By SMACNA “HVAC Duct Construction Standards” - testing of low pressure ducts for
leakage is untested (see attachment 3). Because ducts are low pressure can be used
light test to verify connection of the elements duct, prior start insulation. The points of
leakage if found any shall be sealed with approved sealing material.
Page 8 of 24
To provide the light – inside the duct, access door dampers cab be used;
Source of the light inside the duct – can be simple lamp 100-200W, portable with
protection
Mechanic, flexible cable (30m-50m) and possibility to switch ON/OFF;
The lights inside the room where testing to be carried out shall be switched off at the
time of test.
Scaffolding will be provided to access the ducts
Total darkness shall be maintained at test area during the test.
Check at every joint – the light from outside shall not be visible.
If any defects found, the point shall be marked and then rectified/sealed after finishing
the test
After rectification, the test to be repeated;
Test to be done for each section of the duct (supply and return duct);
9.0 ATTACHMENTS
10.0 Request for Inspection
11.0 Risk Assessment
12.0 Attachment from SMACNA (HVAC DUCT CONSTRUCTION STANDARDS)
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct system (Light Test)
Rev. C01, November 2008
Page 9 of 24
ATTACHMENT 1
Page 10 of 24
The above mentioned work activity has been final inspected and accepted.
Вышеуказанная работа была проинспектирована и принята.
RENCO-KAT/ CONSTRUCTION RENCO-KAT/ QA/QC RENCO-KAT / OTHER
Ренко-КАТ / ОТДЕЛ КОНТРОЛЯ
Ренко-КАТ/ СТРОИТЕЛЬНЫЙ ОТДЕЛ Ренко-КАТ / ДРУГИЕ
КАЧЕСТВА
Name Name Name
Имя Имя Имя
Date Date Date
Дата Дата Дата
Signature Signature Signature
Подпись Подпись Подпись
Validated by AKCO / CONSTRUCTION
Date &
Name: Signature:
Time:
Received by AKCO / QA-QC
Date &
Name: Signature:
Time:
RFI Acceptance & Inspection Result
ACCEPTED REJECTED
Page 11 of 24
Comments:
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
………………………………………………………………………………………………………………
AKCO / QA-QC
Date &
Name Signature
Time
RENCO-KAT / QA-QC
Date &
Name Signature
Time
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct system (Light Test)
Rev. C01, November 2008
Page 12 of 24
ATTACHMENT 2
RISK ASSESMENT
Page 13 of 24
RISK
RISK ASSESSMENT
ASSESSMENT
(NO CONTROLL)
(WITH OVER
S.N JOB STEP TARGET UNDESIRABLE EVENTS CONTROL MEASURES CONTROLL) ALL
SEVE LIKELIH SEVER LIKE RISK
RITY OOD RISK ITY LIHO
OD
Proper PPE
Make sure that have a correct foot
wear to suit the ground condition
P Slips , Trips & Falls due to poor
A house keeping in work area
3 B 3B Job site must be kept clean and free 3 3B M
of obstruction in working areas
Walk slowly if there are slippery or
Preparation and
1. uneven conditions
set up
Proper PPE
P Proper Training on manual handling
Back pain and body injuries due to 1 C IC 1 IB L
A Prefer to mechanical means of
improper manual handling
manual handling
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct system (Light Test)
Rev. C01, November 2008
Page 14 of 24
RISK
RISK ASSESSMENT
ASSESSMENT
(NO CONTROLL)
(WITH OVER
S.N JOB STEP TARGET UNDESIRABLE EVENTS CONTROL MEASURES CONTROLL) ALL
SEVE LIKELIH SEVER LIKE RISK
RITY OOD RISK ITY LIHO
OD
Wear full body harness (double
lanyard with shock absorbers) and
100% tie-off on heights.
Adequate access and egress
Working at P Falling from height
2. 4 C 4C arrangements and suitable working 3 3B M
height A Falling objects
platforms at the place of work
RA/Safety training awareness
Necessary barricades and indication
at the ground level
Always follow safe work practices
Scaffolding shall be assembled by
certified worked and supervised
P Dropping tools and objects, 2 2 M according to the specific procedure
3.
Scaffolding use A dropping of the crew, Scaffolding Toe- boards need to be used 1 1 M
collapse, overturn Egress/Ingress points always need
to be assigned
Always temporary power lines
needs to be attached to scaffolding
or working platform by a certified
electrician
4. Electric Shock P Electric shock due to cable 2 2 M Illumination shall be arranged and 1 1 M
A damage, equipment and switch tested during day light
damages There shall be qualified electrician
on site with quick access to
location.
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct System (Light Test)
Rev.C01,November 2008
Page 15 of 24
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct System (Light Test)
Rev.C01,November 2008
Page 16 of 24
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct System (Light Test)
Rev.C01,November 2008
Page 17 of 24
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct System (Light Test)
Rev.C01,November 2008
Page 18 of 24
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct System (Light Test)
Rev.C01,November 2008
Page 19 of 24
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct System (Light Test)
Rev.C01,November 2008
Page 20 of 24
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct System (Light Test)
Rev.C01,November 2008
Page 21 of 24
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct System (Light Test)
Rev.C01,November 2008
Page 22 of 24
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct System (Light Test)
Rev.C01,November 2008
Page 23 of 24
RENCO-KAT CONSTRUCTION&ENGINEERING
KE01-A1-000-RK-M-TT-0002-000
KEP SIS Method Statement for Air Leak Test for HVAC Duct System (Light Test)
Rev.C01,November 2008
Page 24 of 24