Professional Documents
Culture Documents
PAL 22 PAL 10
connection (PAL 16/18
directly beneath)
PAL 7
connection
IN A WORLD WHERE TBMS just keep getting grade for London Underground. “Here, the high though. Because, by the time those 306m
bigger, and in a City where Crossrail will soon scheme is more like a Rubik’s cube: every time have been constructed, TWBN will have several
have completed 42km of tunnel, the team at you need to move something, you have to very useful lessons to share with the industry.
the Victoria Station Upgrade sometimes feel a move something else to accommodate it. That One such lesson, which is already attracting
little inadequate. Their project to increase ca- is the constant theme.” interest, is the innovative prop-free solutions
pacity and improve journey times for people TWBN’s works include a new ticket hall and that TWBN has developed with its designer
using the underground station can boast only entrance to the North of the station, doubling Mott MacDonald, for the connections into ex-
306m of 6m-diameter tunnel; and four years the size of the existing southern ticket hall, isting tunnels. No less impressive is Keller’s un-
in, they’ve completed just 198m. nine new escalators and eight lifts and pedes- precedented jet grouting programme involving
“We find ourselves regularly compared with trian tunnels to connect the two stations and over 2000 columns. Finally, creating the under-
adjacent sites, such as Land Securities’ £2.2bn various other passages. The tunnelling, includ- pass beneath the existing District and Circle
Nova development,” says Ian Heath, tunnel ing £37M-worth of jet grouting, accounts for Line, which will see the rails literally sitting on
manager for the Taylor Woodrow BAM Nuttall around £64M top of the new tunnel, will be a technical feat
(TWBN) JV which is delivering the £300M up- Heath and his team can hold their heads worth hearing about.
10 TUNNELLING JOURNAL
SITE REPORT
“We are not big, but it is clever,” says Glen TWBN and Motts have developed – essentially existing platform tunnel, thick with props,
Keelan, London Underground’s programme – three different solutions. alongside a shot of one of the platforms at
manager. Working side-by-side with Heath to break Victoria where the only sign of an impending
Heath’s desire to do away with props comes with the ‘doing things the way we’ve always break through is a hoarding which protrudes
from his time spent on the upgrade of Kings done them’ tradition is Anmol Bedi, senior SCL just 450mm onto the walkway.
Cross underground station, where he was engineer for Motts who is on site all the time. Heath reckons TWBN has made substantial
working for Morgan Sindall, his employer of Wielding his 3D model, he is ready to revisit savings by avoiding the use of props. It has also
13 years before he joined BAM Nuttall to the design to find the best solutions as the saved several logistics headaches: much of the
tackle this project. tunnels advance, while maintaining a watchful plant and equipment for propping would have
“I just started asking the question,” he says. eye on the installed ‘real time’ instrumentation had to come in by train or escalator. And there
“At Kings Cross, we propped all the cross pas- and monitoring to ensure the works are per- have been savings on the time and paperwork
sages. There was massive disruption and it cost forming as expected. involved in gaining approvals from London Un-
a fortune.” The differences the prop-free solutions have derground operational staff, technical staff and
On the Victoria Station Upgrade pro- made are significant. To illustrate his point, the emergency services.
gramme, there are six points at which tunnels Heath shows a photo from the Kings Cross Up- The most important thing for London Under-
must break into existing ones. To tackle these grade with a possession work site within the ground is that the station’s staff and the travel-
fermacell AESTUVER
Tailor-made solutions specifically for underground and overground transport systems.
Q Reliable protection for concrete against effects of fire loads of up to 1 350 °C
Download our
Q Frost and water resistant PDF brochure.
Q Painting and coating options for customized finishes
www.aestuver.de Fermacell GmbH | fermacell AESTUVER | Düsseldorfer Landstr. 395 | 47259 Duisburg | E-Mail: info@aestuver.de | fermacell® is a registered trademark and a company of the XELLA Group.
SITE REPORT
Figure 2: Top - PAL 7: Providing a link between the new main pedestrian tunnel and an existing interchange concourse,
props in the existing pedestrian area were considered unfeasible as they would have reduced circulation space and
impinged on the area for an escalator’s upper machine chamber. Constructed in a mixed face of London Clay and water
bearing River Terrace Gravels, the designers increased the jet grouting in this area to form a hood over the cross passage
location. This reduced the ground loading and distortional tendency of the lining. TWBN constructed the SCL shell right up
to the connection point, using multiple benches while installing a sectional opening frame, bolted to the back of the
existing liner. Temporary props within the new tunnel reduced deformation as the lower SCL benches were excavated.
Bottom - PAL 22 - Linking from the main tunnel into an existing passage, the approach for this connection was similar [to
the one above], with internal propping and additional jet grout over the existing passageway.
Top
Timber packing Top
A lintel
lintel
PAL #7 PAL #7 F.F.L. 5026
Top 91318
Existing 32´ 6˝ LD
lintel interchange
Area of primary 610 x 229 x 140 UB
concourse tunnel temporary beam
lining thickening
200 x 203 x 100 UC for the temporary
B
A temporary prop Area of primary prop and beam
lining thickening 600
for the temporary
Timber Existing concrete prop and beam
packing collar (to be cut 610 x 229 x 140 UB Existing 32´ 6˝ LD
out locally) temporary beam interchange
concourse tunnel
PLAN Section A-A Section B-B
(Scale 1:100) (scale 1:50) (scale 1:50)
ling public can go about their business unhin- flows which interest London Underground. Its cent mainline rail station, meeting a similar
dered. “From our perspective, minimising dis- modellers look at a measure called Fruin levels flow heading in. And carrying them in and
ruption was the priority,” says Keelan. which run from A to E, with E being the most out are just three escalators.
“Victoria is so busy, that any disruption could congested. “Our origin and destination surveys showed
have meant that there was a genuine risk that “When we looked at Victoria Station to de- that a large proportion of people wanted to
we might have to alter the Victoria Line serv- velop the planning of the solution, Fruin levels be to the North and North East of the station,
ice... which we would never want to do.” tended to be around D and E in peak hours,” to carry on their journey towards Westmin-
says Keelan. “The station staff frequently have ster,” says Keelan. Hence the new Northern
Busier than Heathrow to apply control measures; they have to hold ticket hall and the new entrance in
A journey through Victoria underground sta- peoples’ journey through station because of Bressenden Place.
tion at rush hour will explain why this station the sheer number of people moving in and TWBN beat off competition from JVs of Bal-
is in need of an upgrade. It is close to burst- out. That was a key element of the business four Beatty/ Morgan Est and Costain Laing
ing. One of the busiest stations in London, case for doing something at Victoria.” O’Rourke to be awarded the contract in May
84.6 million people passed through it last With an exit point to the South of the sta- 2010. This was the second success for the
year. That’s more than Heathrow Airport tion – a common feature of most stations on newly-formed joint venture which had se-
which saw a mere 72.3m people in 2013. the Victoria line – busy periods see huge flows cured the Tottenham Court Road upgrade
But it’s not so much numbers as space and of people trying to head out through the adja- project in late 2009.
12 TUNNELLING JOURNAL
SITE REPORT
Figure 3: PAL10 - This inclined shaft for escalators 10-12 runs directly above the Though every tunnelling project conducted
hand-dug tunnel and envelopes the concourse tunnel. It cuts through two existing in a busy city area has the challenge of multi-
cross passages which will no longer be used, with two new cross passages towards ple stakeholders, the variety and vicinity of
its end to provide access to platform tunnels on either side. Had the inclined SCL those for the Victoria Station Upgrade is quite
tunnel been constructed, followed by the cross passages, the deformation would mind-boggling. A major transport hub, with
have been too great. In order to limit deformation, TWBN constructed the cross the inner circle ring road linking the North and
passages first from the existing concourse tunnel. This provided rigidity, locking the South of the city running through it, Victoria is
platform tunnels against further deformation while the main tunnel was built. also on multiple bus routes and has a national
coach station, as well as the underground
lines and mainline station.
Neighbours include government depart-
ments, businesses, shops, restaurants and two
theatres – the Grade II* listed Victoria Palace
Theatre and the Grade II* listed Apollo with
the Victoria Palace Theatre so close to the tun-
nelling works that some operations must stop
when a performance is on. Add into the pic-
ture the construction of the 897,000 sq ft
(83,300 sq m) mixed-use development that is
Nova, and you begin to see the constraints
under which TWBN is working.
“The main challenges for us at Victoria con-
cern customers and stakeholders,” says David
Waboso, London Underground’s head of capi-
tal projects. “We have to do this incredibly
complicated job in the middle of all this.
“We have to communicate with our surface
transport colleagues, communications and
stakeholder relations people and attend meet-
ings with local stakeholders. Glen is the mid-
field general in all of that.”
Tackling buildability
Several designers have been involved in this
scheme, as is often the case. Projects such as
these can be on the drawing board for years
or decades. Victoria Station was delayed due
Figure 4: PAL16/PAL 18 - traditional hand dug tunnel - This access tunnel connects the new emergency services shaft to
the existing Victoria Line platform tunnels via two cross passages. It runs between and parallel to the existing platform
tunnels which would have normally have required extensive propping. TWBN built the tunnel within a large-scale
traditional timber and steel square works opening, exposing the platform tunnel lining on both sides with large steel
frames spanning between the linings, bracing the rings against each other to reduce deformation. At the cross passages,
timber adits were driven in stages with large frames installed around the opening along with a series of temporary
props. Once the concrete around the openings was complete, the props and tunnel rings were removed and the cross
passage completed.
TUNNELLING JOURNAL 13
SITE REPORT
14 TUNNELLING JOURNAL
SITE REPORT
TUNNELLING JOURNAL 17
SITE REPORT
Eastbound platform of the District and Circle Muck M540 walking excavator designed spe- this year. However, the fun is not over yet. The
Lines. cially to work on slopes; a mountain-climbing main tunnel has yet to pass underneath the
The approach for making both these two Riwal cherry picker; and a Putzmeister shot- District and Circle Line.
connections was similar: a combination of crete robot adapted by Shotcrete Services to Austrian contractor Strabag AG is currently
bracing on the back of the existing tunnel, work on a downhill slope. permeation grouting underneath the tracks of
rather than inside it; installing a jet grouting Constructed in the 1960s, initial survey the District and Circle Line. A slab will then be
canopy over the top of the area to reduce the work showed that the existing cast iron plat- constructed within the existing cut and cover
ground and water loading; and digging the form tunnel rings had already experienced sig- brick arch tunnel, which will support the
last section between new tunnel and connect- nificant deformation over time. With no tracks and form the roof of the underpass.
ing point as speedily as possible. propping, driving the large escalator shafts This operation will be carried out during a six
“The traditional way would have been to and then the cross passages would have day blockade over Christmas.
hand dig the last section. We didn’t do that caused a level of deformation beyond the limit “Come January, that will all be done, and
here because it all adds to the time taken set down in the Predicted Damage Assess- we can tick off a major issue from the risk reg-
which increases the deformation,” explains ment. ister” says Heath.
Heath. “We had two principles: we are not The solution was to drive the cross passages The extension to the Southern ticket hall
going to use any props and we will go as fast first, accessing them from the existing con- was nearing structural completion in October,
as possible before the ground has time to course tunnel. The new steel and concrete with the southern sections of tunnelling due
move.” cross passages then ‘lock’ the platforms, prop- to begin. These will connect the ticket hall to
“We developed a sequence that allowed ping them against each other to prevent fur- the District and Circle underpass section.
the SCL shell to be constructed using multiple ther damage. The design of the tunnels on this side of the
benches in order to install a sectional opening TWBN built the cross passages traditionally project will benefit from knowledge gained so
frame that was bolted to the back of the ex- using opening sets, concrete and rebar, in- far. “We were able to redesign this due to our
isting lining,” says Bedi. “Temporary props stalled within a large-scale timber opening. experiences on the Northern section,” says
were installed within the new tunnel that re- The escalator tunnel will then remove the Heath. “We took out a lot of rebar from
duced deformation as the lower SCL benches temporary parts of the new cross passage as it openings and junctions and made the design
were excavated. This approach resulted in less envelopes the existing concourse. more efficient.”
deformation than the traditional ‘stop short – “Numerical modelling showed that this se- By April next year, all tunnelling bar a shaft
timber up’ method.” quence resulted in significantly less deforma- in Victoria Street for the Disrict & Circle line
The excavation of the 9m-diameter inclined tion,” says Bedi. “It’s counter-intuitive, but it should be complete. By late 2016 the new en-
escalator shaft began in November 2013 and works.” trance on Bressenden Street and the new
at the time when TJ visited site in early Octo- Northern ticket hall will be in action, with the
ber was two-thirds complete. “This is a very Fun at Christmas whole scheme expected to finish in 2018.
complicated sequence of works, some within Many of the challenges of this small but beau- At that point the station’s capacity will have
the operational station, some with SCL, some tifully complex tunnelling project have been been boosted by 110%. And if London Un-
hand work. It’s a very long process,” says conquered: the prop-free connections, the derground’s predictions on future passenger
Heath. hand-dug tunnels, the unprecedented volumes are realised, Victoria underground
TWBN is employing some specialist equip- amounts of jet-grouting, which itself took two station should be running smoothly for the
ment to create the inclined tunnel: a Menzi years to complete, finishing mid-September next 75 years.
18 TUNNELLING JOURNAL