You are on page 1of 7

SITE REPORT

WE’RE NOT BIG...


...but we are clever. Challenging traditional wisdom that says existing
tunnels must be internally propped before connecting into them,
Taylor Woodrow BAM Nuttall JV has come up with new solutions at
London Underground’s Victoria Station Upgrade which are already
attracting attention. Kristina Smith visited site to find out why.

Figure 1: The schematic layout of the Victoria Station scheme

PAL 22 PAL 10
connection (PAL 16/18
directly beneath)

PAL 7
connection

IN A WORLD WHERE TBMS just keep getting grade for London Underground. “Here, the high though. Because, by the time those 306m
bigger, and in a City where Crossrail will soon scheme is more like a Rubik’s cube: every time have been constructed, TWBN will have several
have completed 42km of tunnel, the team at you need to move something, you have to very useful lessons to share with the industry.
the Victoria Station Upgrade sometimes feel a move something else to accommodate it. That One such lesson, which is already attracting
little inadequate. Their project to increase ca- is the constant theme.” interest, is the innovative prop-free solutions
pacity and improve journey times for people TWBN’s works include a new ticket hall and that TWBN has developed with its designer
using the underground station can boast only entrance to the North of the station, doubling Mott MacDonald, for the connections into ex-
306m of 6m-diameter tunnel; and four years the size of the existing southern ticket hall, isting tunnels. No less impressive is Keller’s un-
in, they’ve completed just 198m. nine new escalators and eight lifts and pedes- precedented jet grouting programme involving
“We find ourselves regularly compared with trian tunnels to connect the two stations and over 2000 columns. Finally, creating the under-
adjacent sites, such as Land Securities’ £2.2bn various other passages. The tunnelling, includ- pass beneath the existing District and Circle
Nova development,” says Ian Heath, tunnel ing £37M-worth of jet grouting, accounts for Line, which will see the rails literally sitting on
manager for the Taylor Woodrow BAM Nuttall around £64M top of the new tunnel, will be a technical feat
(TWBN) JV which is delivering the £300M up- Heath and his team can hold their heads worth hearing about.

10 TUNNELLING JOURNAL
SITE REPORT

Far left: The


method of
propping as
used at King’s
Cross, and (left)
the much less
intrusive
propless
method as
seen at Victoria

“We are not big, but it is clever,” says Glen TWBN and Motts have developed – essentially existing platform tunnel, thick with props,
Keelan, London Underground’s programme – three different solutions. alongside a shot of one of the platforms at
manager. Working side-by-side with Heath to break Victoria where the only sign of an impending
Heath’s desire to do away with props comes with the ‘doing things the way we’ve always break through is a hoarding which protrudes
from his time spent on the upgrade of Kings done them’ tradition is Anmol Bedi, senior SCL just 450mm onto the walkway.
Cross underground station, where he was engineer for Motts who is on site all the time. Heath reckons TWBN has made substantial
working for Morgan Sindall, his employer of Wielding his 3D model, he is ready to revisit savings by avoiding the use of props. It has also
13 years before he joined BAM Nuttall to the design to find the best solutions as the saved several logistics headaches: much of the
tackle this project. tunnels advance, while maintaining a watchful plant and equipment for propping would have
“I just started asking the question,” he says. eye on the installed ‘real time’ instrumentation had to come in by train or escalator. And there
“At Kings Cross, we propped all the cross pas- and monitoring to ensure the works are per- have been savings on the time and paperwork
sages. There was massive disruption and it cost forming as expected. involved in gaining approvals from London Un-
a fortune.” The differences the prop-free solutions have derground operational staff, technical staff and
On the Victoria Station Upgrade pro- made are significant. To illustrate his point, the emergency services.
gramme, there are six points at which tunnels Heath shows a photo from the Kings Cross Up- The most important thing for London Under-
must break into existing ones. To tackle these grade with a possession work site within the ground is that the station’s staff and the travel-

fermacell AESTUVER
Tailor-made solutions specifically for underground and overground transport systems.
Q Reliable protection for concrete against effects of fire loads of up to 1 350 °C
Download our
Q Frost and water resistant PDF brochure.
Q Painting and coating options for customized finishes

www.aestuver.de Fermacell GmbH | fermacell AESTUVER | Düsseldorfer Landstr. 395 | 47259 Duisburg | E-Mail: info@aestuver.de | fermacell® is a registered trademark and a company of the XELLA Group.
SITE REPORT

Figure 2: Top - PAL 7: Providing a link between the new main pedestrian tunnel and an existing interchange concourse,
props in the existing pedestrian area were considered unfeasible as they would have reduced circulation space and
impinged on the area for an escalator’s upper machine chamber. Constructed in a mixed face of London Clay and water
bearing River Terrace Gravels, the designers increased the jet grouting in this area to form a hood over the cross passage
location. This reduced the ground loading and distortional tendency of the lining. TWBN constructed the SCL shell right up
to the connection point, using multiple benches while installing a sectional opening frame, bolted to the back of the
existing liner. Temporary props within the new tunnel reduced deformation as the lower SCL benches were excavated.
Bottom - PAL 22 - Linking from the main tunnel into an existing passage, the approach for this connection was similar [to
the one above], with internal propping and additional jet grout over the existing passageway.

Permanent support Temporary support


Existing Zone of ground Zone of ground
concrete improvement improvement
headwall Existing passage 4202 250 SFR B 263 x 293 x 109 UC 250 SFR
to Westbound D & C line primary lining temporary prop primary lining
610 x 229 x 140 UB
temporary beam

Top
Timber packing Top
A lintel
lintel
PAL #7 PAL #7 F.F.L. 5026
Top 91318
Existing 32´ 6˝ LD
lintel interchange
Area of primary 610 x 229 x 140 UB
concourse tunnel temporary beam
lining thickening
200 x 203 x 100 UC for the temporary
B
A temporary prop Area of primary prop and beam
lining thickening 600
for the temporary
Timber Existing concrete prop and beam
packing collar (to be cut 610 x 229 x 140 UB Existing 32´ 6˝ LD
out locally) temporary beam interchange
concourse tunnel
PLAN Section A-A Section B-B
(Scale 1:100) (scale 1:50) (scale 1:50)

Permanent support Temporary support Existing 4500 Zone of ground


LD SGI lining improvement

Jamb SFR primary lining B 250 SFR Top


Top
lintel primary lining lintel

Top PAL #22 PAL #22


lintel Existing
passageway
Jamb 3203 Jamb
Lower F.F.L. 91318
A A
lintel
Existing
passageway
3203
Lower Lower
Existing 4500 B lintel lintel
LD SGI lining
PLAN Section A-A Section B-B
(Scale 1:100) (scale 1:50) (scale 1:50)

ling public can go about their business unhin- flows which interest London Underground. Its cent mainline rail station, meeting a similar
dered. “From our perspective, minimising dis- modellers look at a measure called Fruin levels flow heading in. And carrying them in and
ruption was the priority,” says Keelan. which run from A to E, with E being the most out are just three escalators.
“Victoria is so busy, that any disruption could congested. “Our origin and destination surveys showed
have meant that there was a genuine risk that “When we looked at Victoria Station to de- that a large proportion of people wanted to
we might have to alter the Victoria Line serv- velop the planning of the solution, Fruin levels be to the North and North East of the station,
ice... which we would never want to do.” tended to be around D and E in peak hours,” to carry on their journey towards Westmin-
says Keelan. “The station staff frequently have ster,” says Keelan. Hence the new Northern
Busier than Heathrow to apply control measures; they have to hold ticket hall and the new entrance in
A journey through Victoria underground sta- peoples’ journey through station because of Bressenden Place.
tion at rush hour will explain why this station the sheer number of people moving in and TWBN beat off competition from JVs of Bal-
is in need of an upgrade. It is close to burst- out. That was a key element of the business four Beatty/ Morgan Est and Costain Laing
ing. One of the busiest stations in London, case for doing something at Victoria.” O’Rourke to be awarded the contract in May
84.6 million people passed through it last With an exit point to the South of the sta- 2010. This was the second success for the
year. That’s more than Heathrow Airport tion – a common feature of most stations on newly-formed joint venture which had se-
which saw a mere 72.3m people in 2013. the Victoria line – busy periods see huge flows cured the Tottenham Court Road upgrade
But it’s not so much numbers as space and of people trying to head out through the adja- project in late 2009.

12 TUNNELLING JOURNAL
SITE REPORT

Figure 3: PAL10 - This inclined shaft for escalators 10-12 runs directly above the Though every tunnelling project conducted
hand-dug tunnel and envelopes the concourse tunnel. It cuts through two existing in a busy city area has the challenge of multi-
cross passages which will no longer be used, with two new cross passages towards ple stakeholders, the variety and vicinity of
its end to provide access to platform tunnels on either side. Had the inclined SCL those for the Victoria Station Upgrade is quite
tunnel been constructed, followed by the cross passages, the deformation would mind-boggling. A major transport hub, with
have been too great. In order to limit deformation, TWBN constructed the cross the inner circle ring road linking the North and
passages first from the existing concourse tunnel. This provided rigidity, locking the South of the city running through it, Victoria is
platform tunnels against further deformation while the main tunnel was built. also on multiple bus routes and has a national
coach station, as well as the underground
lines and mainline station.
Neighbours include government depart-
ments, businesses, shops, restaurants and two
theatres – the Grade II* listed Victoria Palace
Theatre and the Grade II* listed Apollo with
the Victoria Palace Theatre so close to the tun-
nelling works that some operations must stop
when a performance is on. Add into the pic-
ture the construction of the 897,000 sq ft
(83,300 sq m) mixed-use development that is
Nova, and you begin to see the constraints
under which TWBN is working.
“The main challenges for us at Victoria con-
cern customers and stakeholders,” says David
Waboso, London Underground’s head of capi-
tal projects. “We have to do this incredibly
complicated job in the middle of all this.
“We have to communicate with our surface
transport colleagues, communications and
stakeholder relations people and attend meet-
ings with local stakeholders. Glen is the mid-
field general in all of that.”

Tackling buildability
Several designers have been involved in this
scheme, as is often the case. Projects such as
these can be on the drawing board for years
or decades. Victoria Station was delayed due

Figure 4: PAL16/PAL 18 - traditional hand dug tunnel - This access tunnel connects the new emergency services shaft to
the existing Victoria Line platform tunnels via two cross passages. It runs between and parallel to the existing platform
tunnels which would have normally have required extensive propping. TWBN built the tunnel within a large-scale
traditional timber and steel square works opening, exposing the platform tunnel lining on both sides with large steel
frames spanning between the linings, bracing the rings against each other to reduce deformation. At the cross passages,
timber adits were driven in stages with large frames installed around the opening along with a series of temporary
props. Once the concrete around the openings was complete, the props and tunnel rings were removed and the cross
passage completed.

TUNNELLING JOURNAL 13
SITE REPORT

to funding issues, as the downturn started bit-


ing in 2008.
Arup was the first practice to work on the
upgrade, back at the feasibility phases in
2004. Scott Wilson took it further in 2005
and 2006, before the design package had to
be retendered due to a significant increase in
scope and Mott MacDonald won and took
over the baton.
When TWBN inherited the design, it was
reasonably advanced: at RIBA stage E (now
known as RIBA Stage 3 or 4), having been ad-
vanced to that level in order to gain planning
approval through the Transport Works Act
Order (TWAO). In moving the design forward
for construction, TWBN was able to bring in a
number of changes which improved its build-
ability.
The most dramatic change was the method
of constructing the tunnels which connect the
new ticket hall to a new escalator shaft down
to the Victoria Line platforms, the main tunnel
taking passengers from
North to South and a shaft than in most London projects due to the
which will provide access for water bearing nature of the ground.
the emergency services. “This is also a self-assuring design and build
Rather than tunnel these contract so we want to use materials which
sections using SCL, TWBN we know will work.”
elected to build the whole The SCL here, in contrast to Crossrail, is
structure in open cut . classed as temporary works only, so that it is
“We wanted to do top not assumed to take any of the permanent
down but pile embedment loads. TWBN is using the inclined face method
issues due to the Victoria of SCL, designed to keep men away from the
Line meant we had to prop dangers of green concrete falling from over-
and build bottom up,” says head.
Heath. “In reality it was a lot Waterproofing is sheet membrane from
easier to build.” Flag Soprema installed by Austrian firm IAT,
This was a good solution, topped by a reinforced permanent concrete
too, for minimising the risk lining. The permanent lining reinforcement
of disruption to the Kings was originally designed as traditional rebar,
Scholar Pond Sewer, a storm but the team are now looking at steel fibres.
sewer for several areas of “We are now in the
London. The open cut solu- process of switching from
tion meant that the sewer Above: The rebar to steel fibre rein-
could be diverted safely into PAL 4 and PAL forced concrete,” says
pipes. The downside was 22 Junction Heath. “We have been
that the excavation took up able to take advantage of
all of TWBN’s site compound Left: Pal 7 some of the innovations
area. excavation on Crossrail and this is
Another change came at complete one of them.” TWBN has
the junction between the commissioned a series of
main North–South passen- pre-production lab and
ger tunnel and a tunnel which branches off North and South apart from where we go field tests to verify the fibre reinforced second-
towards a passage running to the District and under the District and Circle line.” ary lining will perform acceptability over its de-
Circle Line eastbound platform. Motts’ origi- Curves, too, have been eliminated where sign life in terms of both strength and
nal design called for a trouser-leg or ‘Y’ possible, replaced by kinks. This allows for serviceability.
shaped junction, TWBN wanted a 90 degree standardisation of the formwork, a travelling One technique which helps with both qual-
junction. shutter supplied by CIFA, for the secondary ity and congestion issues for traffic around
TWBN has also brought construction effi- lining. Victoria is the use of pre-blended sprayed con-
ciencies to the design by standardising the di- Though determined to innovate in his tem- crete from CPI. This is delivered to site, blown
ameter of the main tunnels, which in the porary works, Heath has taken the opposite into a silo and produced to order from the
original design varied many times, with the approach with the materials being used for screw mixer which is part of the silo system.
thickness of the SCL and the secondary lining the permanent works. It’s ‘tried and tested’ all “It’s more expensive per cubic metre but
changing too. the way. you have a lot less wastage,” says Heath. “All
“It’s all about trying to make it simple,” says “We did not want to do anything revolu- the specs say you have to have shotcrete on
Heath. “Now the secondary lining is roughly tionary here,” he says. “There is a much site before you break ground but it can’t be
the same shape and size all the way between higher long-term risk of water ingress here used once it’s over three hours old. Here we

14 TUNNELLING JOURNAL
SITE REPORT

don’t throw away lots and lots of wagon


loads because we are out of time. And our Right: PAL 16 invert
silos take up less space than a batching plant. excavation
It is also available when you need it, not when
the batcher is open.”
Producing the concrete this way is around At the cross-passages,
twice as expensive as ready-mixed concrete. timber adits were driven in
TWBN did consider it for the secondary lining stages with much larger
concrete, some of which is now being cast, steel frames installed
but there were technical difficulties in deliver- around the opening in
ing self-compacting concrete this way – as combination with a series
well as the issue of cost to consider. of temporary props. Once
the concrete around the
Fragmented programme openings was complete,
Tunnelling work on the contract began in the props and tunnel rings
2012 with the sinking of the emergency ac- could be removed.
cess and lift shaft at the North end of the ex- TWBN’s tunnelling team
isting Victoria Line tunnels. Following a break then handed over to the
to allow the London 2012 Olympics to run civils team who con-
unhindered, TWBN began hand-digging a structed the open cut box
tunnel from the shaft, which was to connect directly above the hand
via new cross passages into the Victoria Line mined tunnel, which con-
platform tunnels, finishing with a small equip- nected the Northern ticket
ment room beyond the cross passages. This hall to the start of the main
18m of tunnel took six months to build. North-South route and the
The temporary works solution here, de- escalator.
signed by Alun Auld Engineering, sub-de- It wasn’t until October
signer to Motts, used traditional London Clay 2013 that the main North-
hand mining methods. Excavating to expose South tunnel launched.
the backs of the existing iron linings, the face This was the moment of
of the excavation was supported with timbers truth for the jet grouting.
while large steel frames with curved shoes to At this higher level, only the invert of the tun- “We had lots of mitigation in place if the
push off the linings braced the excavation nel is in the London Clay, with the majority in grouting was not as good as we hoped,”
every 700mm. The final concrete lining fol- water-bearing River Terrace Gravels. says Heath. “Keller was on hand to do re-
lowed on as the tunnel advanced. Detailed and meticulous records of the jet medial permeation grouting and we had our
The frames, all installed with winches, effec- grout column installation has been added to own grouting capability within the mining
tively braced the rings against each other, re- Bedi’s 3D model, so that the miners have in- gangs too.”
ducing deformation to acceptable levels. formation on what they can expect to en- The treated ground was better than any-
Using the usual approach, extensive propping counter each shift as they excavated. But no one could have been hoping for. “When we
along both platform tunnels would have been one knew until the ground was attacked broke the piles down, the face was rock
required. whether reality would match theoretical. solid,” says Heath. “The grouted ground
was so dense, we could not
break it.”
An excavator-mounted pecker
just produced holes, rather than
shearing the material. The solu-
tion was to put a roadheader on
the Schaeff excavator.
“We had a variety of equip-
ment because we didn’t know
exactly what would be needed,”
says Heath. “No one has grouted
to this scale in the UK before.
Because you’re mixing the exist-
ing ground with grout, you don’t
know what you have until you
try and mine through it.”
Two tunnels branch off the
North-South tunnel on the
Northern side of the District and
Circle Lines. One connects into
the interchange concourse link-
ing the Victoria Line escalators to
the District and Circle Line link
passages. The other connects
PAL 10 concourse cross passage propping into a passageway between the
Victoria Line escalators and the

TUNNELLING JOURNAL 17
SITE REPORT

More people, more tunnels


The Victoria Station Upgrade is London Underground’s director of inherited planning applications. In Tottenham Court Road and
part of London Underground’s capital projects. “They frequently others, it links into other work Victoria, where good ideas
capital works programme. With have to close the station.” that is going on. With Crossrail, emerged from the contractor
an annual budget of £1.5bn, With London’s living and for example, it made sense to do post-tender, London Underground
capital works encompasses train working populations on the rise, Tottenham Court Road at the introduced its Innovative
systems, infrastructure and Victoria is not the only station same time as Crossrail was Contractor Engagement (ICE)
stations. which needs more capacity. coming through.” process for Bank which sees a
Work on stations happen for a Similar schemes at Tottenham Though every station contractor appointed pre-
number of reasons: Court Road, Bond Street and programme is “absolutely planning to develop a design
refurbishments to ensure they are Vauxhall are all on site, with unique” in its history, structure which meets operational
fit for purpose and in a plans for similar projects at Bank and usage, says Waboso, lessons performance targets (see TJ
reasonable state of repair; and Holborn on the drawing are passed on from one to February 2014).
alterations, such as incorporating board, and an upgrade at another, often through the Sharing safety lessons is also
lifts to provide step-free access Camden possible too, depending contracting community. “There important for London
from pavement to platform; and on planning issues and the are not many contractors who Underground: “We can make sure
‘capacity schemes’, adding to the Northern Line Upgrade. can attempt this sort of work,” he that if there are safer ways of
underground space so that The order in which projects are says. “It’s a global village.” doing things, everybody knows
people can move through the delivered is not necessarily One area where London about it. That’s the main
station more efficiently. determined by the level of Underground is trying to learn advantage of having one
“Victoria is a classic capacity crowding. “Life is complex,” says lessons is in procurement. overarching capital works
scheme,” says David Waboso, Waboso. “In some cases we have Following experiences at programme,” says Waboso.

Eastbound platform of the District and Circle Muck M540 walking excavator designed spe- this year. However, the fun is not over yet. The
Lines. cially to work on slopes; a mountain-climbing main tunnel has yet to pass underneath the
The approach for making both these two Riwal cherry picker; and a Putzmeister shot- District and Circle Line.
connections was similar: a combination of crete robot adapted by Shotcrete Services to Austrian contractor Strabag AG is currently
bracing on the back of the existing tunnel, work on a downhill slope. permeation grouting underneath the tracks of
rather than inside it; installing a jet grouting Constructed in the 1960s, initial survey the District and Circle Line. A slab will then be
canopy over the top of the area to reduce the work showed that the existing cast iron plat- constructed within the existing cut and cover
ground and water loading; and digging the form tunnel rings had already experienced sig- brick arch tunnel, which will support the
last section between new tunnel and connect- nificant deformation over time. With no tracks and form the roof of the underpass.
ing point as speedily as possible. propping, driving the large escalator shafts This operation will be carried out during a six
“The traditional way would have been to and then the cross passages would have day blockade over Christmas.
hand dig the last section. We didn’t do that caused a level of deformation beyond the limit “Come January, that will all be done, and
here because it all adds to the time taken set down in the Predicted Damage Assess- we can tick off a major issue from the risk reg-
which increases the deformation,” explains ment. ister” says Heath.
Heath. “We had two principles: we are not The solution was to drive the cross passages The extension to the Southern ticket hall
going to use any props and we will go as fast first, accessing them from the existing con- was nearing structural completion in October,
as possible before the ground has time to course tunnel. The new steel and concrete with the southern sections of tunnelling due
move.” cross passages then ‘lock’ the platforms, prop- to begin. These will connect the ticket hall to
“We developed a sequence that allowed ping them against each other to prevent fur- the District and Circle underpass section.
the SCL shell to be constructed using multiple ther damage. The design of the tunnels on this side of the
benches in order to install a sectional opening TWBN built the cross passages traditionally project will benefit from knowledge gained so
frame that was bolted to the back of the ex- using opening sets, concrete and rebar, in- far. “We were able to redesign this due to our
isting lining,” says Bedi. “Temporary props stalled within a large-scale timber opening. experiences on the Northern section,” says
were installed within the new tunnel that re- The escalator tunnel will then remove the Heath. “We took out a lot of rebar from
duced deformation as the lower SCL benches temporary parts of the new cross passage as it openings and junctions and made the design
were excavated. This approach resulted in less envelopes the existing concourse. more efficient.”
deformation than the traditional ‘stop short – “Numerical modelling showed that this se- By April next year, all tunnelling bar a shaft
timber up’ method.” quence resulted in significantly less deforma- in Victoria Street for the Disrict & Circle line
The excavation of the 9m-diameter inclined tion,” says Bedi. “It’s counter-intuitive, but it should be complete. By late 2016 the new en-
escalator shaft began in November 2013 and works.” trance on Bressenden Street and the new
at the time when TJ visited site in early Octo- Northern ticket hall will be in action, with the
ber was two-thirds complete. “This is a very Fun at Christmas whole scheme expected to finish in 2018.
complicated sequence of works, some within Many of the challenges of this small but beau- At that point the station’s capacity will have
the operational station, some with SCL, some tifully complex tunnelling project have been been boosted by 110%. And if London Un-
hand work. It’s a very long process,” says conquered: the prop-free connections, the derground’s predictions on future passenger
Heath. hand-dug tunnels, the unprecedented volumes are realised, Victoria underground
TWBN is employing some specialist equip- amounts of jet-grouting, which itself took two station should be running smoothly for the
ment to create the inclined tunnel: a Menzi years to complete, finishing mid-September next 75 years.

18 TUNNELLING JOURNAL

You might also like