This document provides a quotation and schedule for finishing work on the 16th and 17th floors of a building. It includes a list of work items, quantities, unit prices, and totals for each floor. The total for floor 16 is IDR 46,381,300 and for floor 17 is IDR 53,607,330. It also includes a 68 day schedule showing the sequence of work items like installing door frames and completing each unit over the two floors.
This document provides a quotation and schedule for finishing work on the 16th and 17th floors of a building. It includes a list of work items, quantities, unit prices, and totals for each floor. The total for floor 16 is IDR 46,381,300 and for floor 17 is IDR 53,607,330. It also includes a 68 day schedule showing the sequence of work items like installing door frames and completing each unit over the two floors.
This document provides a quotation and schedule for finishing work on the 16th and 17th floors of a building. It includes a list of work items, quantities, unit prices, and totals for each floor. The total for floor 16 is IDR 46,381,300 and for floor 17 is IDR 53,607,330. It also includes a 68 day schedule showing the sequence of work items like installing door frames and completing each unit over the two floors.
I Lantai 16 (26 Unit) 1 Langsir Material 26 unit 70.000 1.820.000 2 Ceklist 26 unit 1.350.000 35.100.000 - Plester 1 m² 38.500 0 - Acian 1 m² 22.500 0 - Pengecatan 1 m² 15.000 0 - Tali air 1 m¹ 20.000 0 - Tuch-up 1 ls 55.000 0 - Cleaning 1 ls 85.000 0 3 STR Pantry 1 unit 200.000 200.000 4 Fin Pantry 1 unit 200.000 200.000 5 Opening P1 3 unit 100.000 300.000 7 Opening P2 3 unit 125.000 375.000 8 Koridor 1 ls 7.000.000 7.000.000 9 Dinding KM 24,78 m² 45.000 1.115.100 10 Lantai KM 6,78 m² 40.000 271.200 TOTAL : 46.381.300
No Description Qty Sat Harga Satuan Jumlah
II Lantai 17 (28 Unit) 1 Langsir Material 28 unit 70.000 1.960.000 2 Ceklist 28 unit 1.450.000 40.600.000 - Plester Aci 1 m² 38.500 0 - Acian 1 m 22.500 0 - Pengecatan 1 m² 15.000 0 - Tali air 1 m¹ 20.000 0 - Tuch-up 1 ls 55.000 0 - Cleaning 1 ls 85.000 0 4 STR Pantry 1 unit 200.000 200.000 5 Fin Pantry 1 unit 200.000 200.000 6 Habel Perubahan+Op 1 unit 410.500 410.500 7 Eks Balok 17,58 m² 25.000 439.500 8 Eks Kolom 22,77 m² 29.000 660.330 9 Eks Plat 86,85 m² 20.000 1.737.000 10 Opening PJ 1A 2 unit 200.000 400.000 11 Koridor 1 ls 7.000.000 7.000.000 TOTAL : 53.607.330
Not : Harga belum termasuk PPH
Estimasi pengerjaan 68 hari JADAWAL PELAKSANAAN PEKERJAAN
No Deskirption Hari Kerja
M.Pwr Lantai 16 (26Unit) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 Langsir Material 2 Org Unit 1 3 Org Unit 2 3 Org Unit 3 3 Org Unit 4 3 Org Langsir Material 2 Org Unit 5 3 Org Unit 6 3 Org Unit 7 3 Org Unit 8 3 Org Langsir Material 2 Org Unit 9 3 Org Unit 10 3 Org Unit 11 3 Org Unit 12 3 Org Langsir Material 2 Org Unit 13 3 Org Unit 14 3 Org Unit 15 3 Org Unit 16 3 Org Langsir Material 2 Org Unit 17 3 Org Unit 18 3 Org Unit 19 3 Org Unit 20 3 Org Langsir Material 2 Org Unit 21 3 Org Unit 22 3 Org Unit 23 3 Org Unit 24 3 Org Langsir Material 2 Org Unit 25 3 Org Unit 26 3 Org
No Deskirption Hari Kerja
M.Pwr Lantai 17 (28 Unit) 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 Langsir Material 2 Org Unit 1 3 Org Unit 2 3 Org Unit 3 3 Org Unit 4 3 Org Langsir Material 2 Org Unit 5 3 Org Unit 6 3 Org Unit 7 3 Org Unit 8 3 Org Langsir Material 2 Org Unit 9 3 Org Unit 10 3 Org Unit 11 3 Org Unit 12 3 Org Langsir Material 2 Org Unit 13 3 Org Unit 14 3 Org Unit 15 3 Org Unit 16 3 Org Langsir Material 2 Org Unit 17 3 Org Unit 18 3 Org Unit 19 3 Org Unit 20 3 Org Langsir Material 2 Org Unit 21 3 Org Unit 22 3 Org Unit 23 3 Org Unit 24 3 Org Langsir Material 2 Org Unit 25 3 Org Unit 26 3 Org Unit 27 3 Org Unit 28 3 Org