Professional Documents
Culture Documents
MINISTRY OF ROADS
October, 2012
in association with
FOREWORD
(One page for foreword)
‐ 1 ‐
Supervision and Contract Evaluation Manual for Road Works
Table of Contents
2. Supervision 8
2.1 Supervisors 8
2.2 Supervision stages 8
2.3 Works execution programme 10
2.3.1 Purpose 10
2.3.2 Contents 11
2.3.3 Authorization procedures 14
2.4 Supervision Check List 14
2.4.1 Purpose 14
2.4.2 List Composition 14
2.4.3 Procedures 18
2.5 Check Points 20
3. Contract Evaluation 52
3.1 Application 52
3.1.1 Purpose 52
3.1.2 Evaluators 52
3.1.3 Evaluation timing 53
3.2 Evaluation procedures 54
3.3.1 Overall procedures 54
3.3.2 Grading 57
3.3 Evaluation items 59
3.4 Evaluation by Resident Engineer 60
3.4.1 Evaluation items 60
3.4.2 Grading criteria 60
3.4.3 Grading sheet 61
3.5 Evaluation by Engineer’s Representative 63
3.5.1 Evaluation items 63
3.5.2 Grading criteria 63
3.5.3 Bonus/Penalty 67
3.5.4 Grading sheet 68
‐ 2 ‐
Supervision and Contract Evaluation Manual for Road Works
Appendix 86
A. Incorporating in Tender and Contract Document for Application of the Manual 87
B. Work execution programme template 88
C. Daily report sample 102
D. Monthly Progress Report templates 103
(Supervision check list) 112
E. Report for Substantial Completion Meeting 121
F. Contract evaluation tally sheet 122
F.1 Contract Evaluation Grading Sheet for Resident Engineer 123
F.2 Contract Evaluation Grading Sheet for the Engineer's Representative 122
F.3 Contract Evaluation Grading Sheet for QAO/IAC 124
F.4 Contract Evaluation Tally Sheet (Large scale work) 127
F.5 Contract Evaluation Tally Sheet (Small scale work) 128
F.6 Contract Evaluation Tally Sheet (Labour-based work) 129
G. Notification of scoring of contract evaluation 130
H. Taking Over Certificate 133
I. Database Format 134
I.1 Contract Evaluation Database Format in Authority 134
I.2 Integrated Contract Evaluation Database Format 135
‐ 3 ‐
Supervision and Contract Evaluation Manual for Road Works
ER Engineer’s Representative
RE Resident Engineer
‐ 4 ‐
Supervision and Contract Evaluation Manual for Road Works
1. Introduction
The concept of supervision and contract evaluation system is to streamline the cyclic
management process as shown in Fig.1.1 for contracted road works. Through continuous exercise
of this cycle, the system will help Road Authorities supervise and manage road works effectively
and also give Contractors incentive to improve their performance.
This can be achieved by providing transparent and objective “check and record” methods. The
methods cover the key performance and technical requirements for road works and matters such
as safety, environmental and social impacts of the work execution. The latter are becoming more
significant in Kenya and needs careful mitigation actions to avoid any negative consequences
that may arise.
Database
Management Stages
Quality/Quantity
Scheduling
Check List
Safety
Environmental/Social
Issues
‐ 5 ‐
Supervision and Contract Evaluation Manual for Road Works
Next
Procure Launching Conclusion
ment Stage Execution Stage Stage
Procure
ment
Authority
Supervision Check List Contract
Evaluation Score
Score Check & Record Grading/Scoring
Finished
Work Product
(1) Application
This Manual which is administrated by the Ministry of Roads shall be applied to all road
works contracted by Roads Authorities in the Republic of KENYA. Target groups of the manual
are officers in the regional office and headquarters of the Authority who are in charge of the
management of contracted road works. The manual shall be applied to road maintenance,
construction, improvement, and rehabilitation of works.
‐ 6 ‐
Supervision and Contract Evaluation Manual for Road Works
(4) Documentation
The following documents are prepared and exchanged between the contractor and the
Authority during the contract period. These documents are all proof material to conduct
supervision and contract evaluation procedures. Fig. 1.3 illustrates the usage of the documents in
the process. The templates of these documents are shown in Appendix B-H.
1) Works Execution Programme (WEP)
2) Site diary (daily report)
3) Monthly progress reports
4) Substantial Completion Certificate (Taking-over Certificate)
5) Notification of Scoring of Contract Evaluation
At supervision stage, the actual work proceedings are compared to the planned one written in
WEP. The comparison is recorded on the site diary confirming whether the works are in
accordance with WEP. The contents in site diary are used to mark and update SCL. That
information on SCL becomes a basis of grading and scoring in contract evaluation. Scores of
contract evaluation are reported to the contractor by the official notification letter and input and
stored in database through RMMS.
Comparison
Works Execution
Work Appraisal
Programme
Compliance
with Corrective Site Diary
Order (Daily Report)
Contract Evaluation
‐ 7 ‐
Supervision and Contract Evaluation Manual for Road Works
2. Supervision
2.1 Supervisors
ii. Submission of performance guarantee shall be within the period stated in the Appendix to
contract for the date from the award of the Authority (the same applied to performance
guarantee guarantees where applicable).
‐ 8 ‐
Supervision and Contract Evaluation Manual for Road Works
Order to Commence
Submission of WEP
No
Approval
Yes
Commencement of Works
Daily Inspection
Yes
Issuance of
Corrective Order
No
Yes No
Substantial Completion Meeting Management Meeting
No
Compliance with WEP
and Specifications
Yes
Contract Evaluation
‐ 9 ‐
Supervision and Contract Evaluation Manual for Road Works
Resident Engineer and contractor carry out monthly inspection in order to determine the overall
monthly progress and update SCL based on the cumulative daily inspection reports. This is the
basis of monthly progress reports discussed and confirmed in the monthly progress meeting.
(Reference)
2.1) Clause 14.1, FIDIC “Conditions of Contract for Works of Civil Engineering Construction,
Forth Edition”, 1987 (FIDIC)
When WEP is submitted and approved by the Authority, it becomes the official document and
the benchmark of supervision with which the Authority checks whether works are proceeding as
planned.
The Authority should carefully examine the contents of WEP and confirm the adequacy of
WEP through comparisons with standard/special specifications and relevant documents before
approval. Likewise contractor should prepare WEP carefully with no unclear, false or flawed
description or it is disapproved and incompliance is pointed out during the execution.
Note that WEP as referred to in this document is different from the programme of works
described in FIDIC and SSRBC. Therefore it can be said that the programme of works forms part
of WEP.
‐ 10 ‐
Supervision and Contract Evaluation Manual for Road Works
2.3.2 Contents
The contents to be included in WEP are shown in Table 2.1. A sample format of WEP is shown
in Appendix A.1. The definition for the “Scale of Works” in the table is as follows:
Scale of Works
Item Large Scale Work Small Scale Work
Labour-based Work
(Class A – D) (Class E and under)
‐ 11 ‐
Supervision and Contract Evaluation Manual for Road Works
‐ 12 ‐
Supervision and Contract Evaluation Manual for Road Works
The Contractor shall provide a photograph plan to record the progress and proof of quality
control, measurement and any event that may arise. The type of works, filming item description,
filming frequency and filming location mapping are incorporated in the plan.
(Reference)
2.2) Road Maintenance Manual, pp.11-7 to 11-88 (Table 11.2 to 11.57) “Performance and
scheduling Considerations”
2.3) Road Maintenance Manual, pp.10-1 to 10-2 Chapter 10, “REPORTING OF EXECUTION
PLAN”
2.4) Standard Specification for Road and Bridge Construction, pp.1.14, 130 “Progress
Photographs”
‐ 13 ‐
Supervision and Contract Evaluation Manual for Road Works
(1) Submission
The Contractor submits to the Authority within the prescribed period after receipt of the order
to commence.
(2) Approval
The Authority thoroughly examines the submitted WEP and, if its contents are satisfactory,
gives approval in writing. Works commence after the approval. However, approval by the
Authority shall not relieve the Contractor of any of his responsibilities under the contract.
(3) Revision
When WEP needs to be modified during execution due to change(s) in the work circumstance
and staff/equipment mobilization plans, contractor submits the modified WEP and obtains a
written approval by the Authority.
The Authority may require contractor to revise WEP to address the short comings identified in
the submission. The Contractor shall discuss and agree on the required revisions with the
Authority, and then submit the modified WEP for approval.
(Reference)
2.5) 104 Programme, General, Standard Specification for Road and Bridge Construction, pp1.1
2.6) Clause7.3, FIDIC1987
The followings are components of SCL. Its format is shown in Appendix D.5.2. Table 2.2 is an
example.
‐ 14 ‐
Supervision and Contract Evaluation Manual for Road Works
(2) Checking
The date of confirmation needs to be recorded first. Then whether the Contractor’s
performance with each check point is satisfactory or not is recorded in the box. Checking
procedure is written in 2.4.3.
(3) Remarks
Remarks shall be recorded as detailed descriptions of checking results, such as reasons of
dissatisfaction, reference number/date of site diary, record of corrective order (are written as
remarks). Positive remarks about outstanding performance and explanation in case of “Not
Applicable (N/A)” are recommended to be written as a remark.
‐ 15 ‐
Table-2.2(a) Supervision Check List
Supervision Check List (1/2)
Date Name Signature
Project Title: Repair and Resealing of N ‐ G Road (C##) The Engineer's
Representative 21‐May‐12 AAAA BBBB AAAA BBBB
Contractor: @@@@@ Construction Co. Ltd. (Project Engineer)
1. This check list is for Resident Engineer to check contractor's work execution process.
2. Fill in date of checking as (day/month), mark as indicated in Filling Example, and state remarks. Resident Engineer 17‐May‐12 CCCC DDDD CCCC DDDD
3. Put this check list in the Monthly Progress Report.
1 Execution system Works Execution Programme (including its revised version if any) is Contractor could not submit WEP before the commencement date (Corrective Order 16/10/2011)
1-1 submitted before the date specified in contract document ■ ✓ WEP was submitted on 01/11/2011 and approved on 04/11/2011.
in general
Works Execution Programme properly reflects the given specifications Modification is needed for WEP because of flood in February (Site Diary 16/02/2012)
1-2 and site conditions ■ ✓ ■ ✓ The Contractor could not modify it by 08 March.
Modified WEP was approved on 05/04/2012.
Execution procedures are in accordance with Works Execution The Contractor started making the second stock yard which is not planned in WEP (Corrective Order
1-3 Programme ✓ ✓ ✓ ■ ✓ ✓ 18/02/2012)
2 Equipment All equipment used are properly mobilized in accordance with Works Asphalt Cutters were not mobilised in Site (Corrective Order on 02/12/2012).
2-1 Execution Programme ✓ ■ ■ ✓ ✓ ✓ Enough numbers of Asphalt cutters are not mobilised in Site (C.O. on 18/01/2012).
holding
All equipment used is well maintained during the execution of works Contractor's broke down backhoe is left out of Site without repairing (Corrective Order on 12/03/2012).
2-2 ✓ ✓ ✓ ✓ ✓ ■
3 Contractor's in- Qualified technical staff of contractor are properly assigned as specified in The Site Agent quitted the job on 16/04 and Successor has not been assigned yet (Corrective Order
‐ 16 ‐
3-1 Works Execution Programme ✓ ✓ ✓ ✓ ✓ ■ 10/05/2012).
house staff
Contractor's in-house key staff understand work process and schedule
3-2 properly ✓ ✓ ✓ ✓ ✓ ✓
Supervision and Contract Evaluation Manual for Road Works
Contractor's in-house staff give technical guidance and direction to The Contractor have a short meeting between in-house staffs and workers/operators in every morning
3-3 workers and operators properly and timely ✓ ✓ ✓ ✓ ✓ ✓ so that they can share the day's programme (Site Diary 01/11/2011, Confirmed 17/05/2012).
4 Personnel Workers and operators are deployed in accordance with Works Execution
4-1 Programme ✓ ✓ ✓ ✓ ✓ ✓
employment
Wage payment is properly made on time Wage payment for the subcontractor had been stopped since February. Workers made demonstration in
4-2 ✓ ✓ ✓ ■ ■ ■ front of the Regional Office (Site Diary 06/04/2012, Corrective Order on 16/03, 14/04, 13/05/2012)
5 Site base Office and stockyard are prepared in accordance with Works Execution The Contractor started making the second stock yard which is not planned in WEP (Corrective Order
5-1 Programme ✓ ✓ ✓ ■ ✓ ✓ 18/02/2012)
facilities
Site is well maintained during the work execution and cleared on Borrow pits have not been reinstated (Corrective Order on 10/05/2012).
5-2 completion ✓ ✓ ✓ ✓ ✓ ■
Material stored on site is properly managed during the work execution Stock yard has not been made while material is brought to Site (Corrective Order on
5-3 ■ ✓ ✓ ✓ ✓ ✓ 01/11/2011).
6 Quality and Material testing, structural examination, and measurements are properly
quantity 6-1 and routinely conducted based on specifications and Works Execution ✓ ✓ ✓ ✓ ✓ ✓
management Programme
Filling Example : ✓Check point is satisfactory ■ Check point is unsatisfactory N/A Not applicable
Table-2.2(b) Supervision Check List
7 Work scheduling Understanding of critical path and its reflection on scheduling are proper The Contractor divided the site into five segments. Works in each segment are conducted in optimised
7-1 ✓ ✓ ✓ ✓ ✓ ✓ order by sophisticated method (Site Diary on 25/01, 04/04/2012).
Changes caused by site conditions are properly handled to keep Works Changes on site terrain caused by Flood in March brought delays on the work scheduling (Site Diary ).
7-3 on schedule ✓ ✓ ✓ ■ ■ ✓
All works are completed within the contract term or within the extended
7-4 term as allowed
‐ 17 ‐
8 Work safety No accident occurs to workers, operators, or third-parties.
8-1 ✓ ✓ ✓ ✓ ✓ ✓
management
Supervision and Contract Evaluation Manual for Road Works
Safety of workers and operators is considered Safety Gears are not supplied to the workers/operators (Corrective Order on
8-2 ■ ■ ■ ■ ■ ■ 30/10/2011).
Enough numbers of safety gears are not yet supplied (C.O. on 28/11/2011)
Accident prevention efforts for third-parties are proper The Contractor erects signs and barricade which caution people on the work areas in
8-3 ✓ ✓ ✓ ✓ ✓ ✓ order to avoid accidents.
Traffic and site safety devices are properly installed and managed The Contractor's purchase for safety devices is not made properly (Site diary 01/11/2012. Corrective
8-4 ■ ■ ✓ ✓ ✓ ✓ Order 16/12/2011)
Temporary facilities (e.g. scaffolding) are constantly checked N/A during November and December because there is no temporary facilities until
8-5 N/A N/A ✓ ✓ ✓ ✓ structural works start in January 2012
9 Environmental Environmental and social mitigation efforts (e.g. against noise, vibration, Backfilling has not been done for a pit hole that currently appear like a pond. It is a
9-1 emission, and dust ) are conducted ✓ ✓ ✓ ✓ ✓ ■ potential risk for the community to draw and mosquito bites (Corrective order
and social
28/04/2012)
management Waste material from site is properly disposed Bituminous waste was left on road side for a month (Corrective Order 22/11/2012)
9-2 ✓ ■ ✓ ✓ ✓ ✓
Damage to existing roads, works and services is avoided or are repaired Damage on pavement vicinity of the stock yard shall be repaired (Corrective Order
9-3 when it occurs ✓ ✓ ■ ✓ ✓ ✓ 22/01/2012).
Transportation by vehicles is properly done with no overloading, and Dump Track hauling gravel was overloaded and ticketed on weighbridge (Site Diary
9-4 neither material falling, leakage, nor spillage. ✓ ✓ ✓ ■ ✓ ■ 02/02, 04/05/2012)
Filling Example : ✓Check point is satisfactory ■ Check point is unsatisfactory N/A Not applicable
Supervision and Contract Evaluation Manual for Road Works
2.4.3 Procedures
(1) Check Procedure
Except check points that are checked before the commencement or after the completion,
checking using SCL is conducted as below;
(2) Recording
✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓
‐ 18 ‐
Supervision and Contract Evaluation Manual for Road Works
New Worksheet
Worksheet of
Previous Check
Latest Remarks can be added
All check results
are shown
Old Remarks are kept
‐ 19 ‐
Supervision and Contract Evaluation Manual for Road Works
If RE finds an unsatisfactory situation against check points, he/she points out the issue to
contractor. Although corrective order itself can be issued in various forms (e.g. oral, telephone,
text message, facsimile, email and written format), it is required to be recorded on site diary as
shown in Appendix A.2 or attached to it as a reference. Every time corrective order is issued, RE
puts the sequence number of daily record on SCL as a remark.
In the following pages, the check points in the Supervision Check List (SCL) are explained in
tables. The tables include the following contents.
(1) Description
It defines what performance is required by the check point.
(3) Reference
It indicates reference materials which dictate the validity of items to be checked. It basically
comes from existing contractual documents, but also it includes a part of contract documents
which is unique to the maintenance works.
‐ 20 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.1.1
Check Point Works Execution Programme (including its revised version if any) is
1-1
submitted before the date specified in contract document
Description:
Works Execution Programme (WEP) shall not only be adequate but also submitted before the
date. This check point requires punctuality exclusively. It is the next check point 1-2 that
examines adequacy of WEP.
Reference
Clause14.1 in FIDIC1987
SSRBC Section1-106 “Submissions to the engineer”
Section 1-108 “Method of construction”
Case examples
(The case of giving corrective order)
‐ 21 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.1.2
Check Point Works Execution Programme properly reflects the given specifications and site
1-2
conditions
Description:
In order to achieve the required performances of road works, the Works Execution Programme
(WEP) shall conform to both the standard/special specifications and site conditions. Site
conditions are land terrain, climate, transportation, land use, and so on.
Reference
SSRBC Section1-105 “Order of Work”
Case examples
(The case of giving corrective order in supervision check)
‐ 22 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.1.3
Reference
SSRBC Section1-104 “Programme”
Case examples
1. Although a major change of the site condition brought revision of execution procedure on
WEP, works are executed in accordance with revised WEP.
Mobilization
Survey ・ Plant ・ Office
Signs ・ Marking ・ Guard-post ・ Street Lighting
‐ 23 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.2.1
Check Point All equipments used are properly mobilized in accordance with Works
2-1
Execution Programme.
Description:
In the Works Execution Programme, types and numbers of equipment are designated so that
the required performance of road works can be achieved by using those equipments. Supervisor
shall check whether the contractor mobilises equipments in accordance with the WEP or not in
execution stage.
Reference
Schedule of supplementary information in tender document (Schedule and measure item of
construction and equipment)
Case examples
1. Types and number of equipment on site are not same as designated in WEP
1. The contractor has provided extra equipment which is not specified or whose capacity is
more than specified in contract document. And that equipment brought the more efficient
execution of the works.
‐ 24 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.2.2
Check Point 2-2 All equipment used is well maintained during the execution of works.
Description:
It is preferable that all equipments are always serviceable, but it is unavoidable for
equipments to have a problem, therefore it is also important for the contractor to have system
to handle the problems of equipment e.g. providing spare equipment and spare parts.
Check timing and frequency
Monthly during execution of works.
Reference
Case examples
1. Extra spare parts are available on site for all major key equipment.
2. The contractor has qualified mechanics (at least diploma level) on site.
‐ 25 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.3.1
Reference
Case examples
1. The Contractor has provided staff with more relevant experience than specified in the
contract document.
‐ 26 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.3.2
Check Point Contractor’s in-house key staffs understand work progress and schedule
3-2
properly.
Description:
In-house key staffs shall understand work progress in site and its schedule. This is very
important to manage the work’s progress and also to deal with any adverse situation properly.
Reference
Case examples
1. Contractor’s in-house key staffs do not understand work process and schedule properly.
1. Contractor’s supervisors understand the nature of the works well so that best practices can
be applied to the works in terms of engineering and management.
2. Contractor’s in-house key staff is able to adapt quickly to unforeseen change in execution of
work.
‐ 27 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.3.3
Check Point Contractor’s in-house staffs give technical guidance and direction to
3-3
workers and operators properly and timely.
Description:
In the course of works, many changes in the activities at site are bound to occur. It is the
responsibility of the Contractor’s in-house staff to tell workers and operators what activities
are going to be implemented in the site with appropriate technical guidance. It is good to have
daily briefing in the morning with workers and operators to inform them of the day’s activities
for this purpose.
Reference
Case examples
1. Contractor’s in-house staff fails to give technical guidance and direction to workers and
operators.
1. There is a close communication and coordination between teams of workers and operators
on the same site to execute different tasks simultaneously without any conflict.
‐ 28 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.3.4
Check Point 3-4 Communications with Authority in writing is proper and timely.
Description:
Communication between the Contractor and Authority shall be adequate so that it facilitates
work progress in accordance with Works Execution Programme and adaptation to any changes
in site conditions. This check point uses written format as an indicator to judge whether or not
communication is adequate because it is always dated and can be used as evidence. Although
this check point uses communication in writing as the indicator, any kinds of communication
(e.g., verbal, phone, email, and so on) shall be conducted properly and timely.
Reference
Case examples
‐ 29 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.4.1
Check Point Workers and operators are deployed in accordance with Works
4-1
Execution Programme.
Description:
The list of workers and operators shall be submitted as part of Works Execution Programme
(WEP). Supervisor shall check whether or not the contractor assigns workers/operators in
accordance with WEP. If the contractor employs subcontractors, this check item has to be
applied to workers/operators of subcontractors also.
Reference
Case examples
1. Workers or operators who are not in the list of Work Execution Programme are assigned.
1. The Contractor engages local sub-contractors for part of the works to develop their capacity
2. The Contractor employs people who reflect the face of Kenyan (from different communities)
3. For unskilled works, the Contractor employs majority of the local community.
4. The Contractor endeavours to have gender balance in employment as per the constitution.
‐ 30 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.4.2
Check Point Wage payment is properly made in accordance with Works Execution
4-2
Programme.
Description:
In order to check the contractor’s personnel management, wage payments to workers,
operators, and subcontractors shall be checked as part of cash flow.
Reference
Case examples
2. The Contractor has provided social activities and welfare for his workers.
‐ 31 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.5.1
Check Point Office and stockyard are prepared in accordance with Works Execution
5-1
Programme.
Description:
Planning for site base facilities’ in Works execution programme should be organised to
satisfy the followings; 1) Location, 2) Capacity, 3) Efficiency, 4) Safety, 5) Environment.
Reference
Case examples
1. Site base facilities are arranged in order to facilitate efficient work execution.
‐ 32 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.5.2
Check Point Site is well maintained during the work execution and cleared on
5-2
completion.
Description:
Any facilities on site shall be maintained properly during the execution. And temporary
facilities shall be removed after the completion.
Reference
Case examples
2. Site base facilities are damaged by lack of maintenance during the work execution.
1. There is neither work related accident nor damage inside and outside the work site because
all facilities are kept in good order and well managed.
Photo 2.6 Stones used for traffic control were left after completion of work
‐ 33 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.5.3
Check Point 5-3 Material stored on site is properly managed during the work execution
Description:
Material stored on site shall be stored according to specified procedure during the execution
so that it will neither deteriorate (e.g., corrosion of reinforcing bar) nor cause any safety
problems (e.g., collapsing of material piled up).
Reference
SSRBC Section 1-128 “Storage of materials and manufactured articles”
Case examples
2. Materials are left out in the open and deteriorated (e.g. corrosion of reinforcement, decaying
of backfilling materials)
1. Management of material storage is excellent (e.g. protection and sign for materials on site,
consideration of proper timing to bring materials on site).
Photo 2.7 Materials are scattered around the site interfering the passage
‐ 34 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.6.1
Reference
SSRBC Section 2 “Materials and testing of materials”
Case examples
1. Material testing, structural examination and measurements are not conducted based on
specifications and WEP.
2. Same materials qualified by the test are not used in the site.
‐ 35 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.6.2
Reference
SSRBC Section 2 “Materials and testing of materials”
SSRBC Section 3-302 “Tolerances“
Case examples
1. Measurement results of quality and quantity are not within the tolerances.
1. Not only that the results are within the specified values, but the contractor has a
management system in which statistical data of the result gives feedback to rationalise
management for quality and quantity control.
‐ 36 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.6.3
Reference
SSRBC Section 1-126 “Materials and manufactured articles”, 1-127 “Information from
exploratory boring and test pits” , 1-128 “Materials and testing of materials” , 1-129 “Test
certificates”
Case examples
1. Results are organised as statistical data in conjunction with target values and limitation
values in the reports.
2. The Contractor has a database of all test results for reference purpose.
3. The Contractor properly compiles photograph records for quality and quantity management
‐ 37 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.7.1
Check Point 7-1 Understanding of critical path and its reflection on scheduling is proper.
Description:
The contractor shall make work schedule within the time frame in order to complete the
works within the contract term. It is important to understand critical paths in the work process
and consider it in work schedule.
This check point asks both the whole scheduling in Works Execution Programme (WEP) and
short term scheduling (e.g., daily/weekly) to be made with understanding the critical path and
reflection of it.
Reference
WEP
Case examples
‐ 38 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.7.2
Check Point Actual proceedings are periodically compared to the planned schedule
7-2
described in Works Execution Programme.
Description:
It is very important for the contractor to compare the actual work progress with work
schedule by recording the work accomplished. This helps in progress management and in
determining whether works are within schedule. Preparation of accumulation curve gives
indication of progress and expected date of completion. The below figure shows an example of
schedule management by bar chart for each work items and accumulation curve for the entire
work.
Check timing and frequency
Monthly during execution of works
Reference
Case examples
1. Contractor organizes the schedule and executes it for the early completion of the entire
project through predictions of each work through comparison between actual and planned work
progress.
‐ 39 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.7.3
Check Point Changes caused by site conditions are properly handled to keep the
7-3
works on schedule.
Description:
Changes shall be handled properly so that impact on the schedule is minimized. Even the site
condition is considered in the drafting of Works Execution Programme (WEP), occasionally an
adverse event occurs. Such adverse events shall be adequately dealt with through consultation
with the Authority, and also reflected in WEP.
Reference
Case examples
1. Contractor does not try to compensate delay of schedule caused by foreseen change of site
condition (e.g. climate, environment, and procurement of materials).
‐ 40 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.7.4
Check Point All works are completed within the contract term or within the
7-4
extended term as allowed.
Description:
This check point requires that all works are completed within the contract term or within the
extended time. It should be noted that most of check points other than this is for checking
contractor’s execution system and process, however this check points requires the result of
timely completion because in itself can be a proof of good scheduling.
Reference
Case examples
1. Contractor couldn’t complete works within the due date without any reasonable cause.
1. Regardless of unforeseen site conditions, contractor completes the work within the due date.
‐ 41 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.8.1
Description:
It should be noted that most of check points other than this is for checking contractor’s
execution system and process, considering the importance of safety, however, this check points
requires the result that no accident occurs to workers, operator, or third-parties. Not only
damage on human, but if damage on property might have caused damage on human, such
incident shall also be regarded as an accident to be recorded for this check point.
Reference
SSRBC Section 1-117 “Health, Safety and Accidents”
Case examples
‐ 42 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.8.2
Description:
Supervisor shall check if the contractor takes necessary actions to prevent an accident. If there
is a cliff or a hole that people may fall down, barricade shall be set up, or at least indicated by
rope or tape. It is also important to prevent things from falling down onto people and/or
properties. A net shall be set to prevent such fallings.
1) Safety Gears
The workers and operators shall be well equipped for the safety. Wear helmets at least.
Wearing reflective vest is necessary when the work is done on the road.
Fall accident is major in the civil works; the supervisor shall check how the workers are doing
their jobs if the works includes one in higher place. The worker shall wear safety belt and use
it properly. Scaffolding shall be strong enough for loads, equipped well to prevent fall accidents,
and firmly supported on the ground.
Operators of machinery shall make a clear sign to people around the machine for the safety.
When a crane is used, outrigger should be stretched fully to avoid overturn.
It is also important for the site agent to instruct safety skills to workers with less experience.
Supervisor shall check if the contractor is conducting necessary safety education to its workers.
Reference
SSRBC Section 1-117 “Health, Safety and Accidents”
‐ 43 ‐
Supervision and Contract Evaluation Manual for Road Works
Case examples
1. Effort for keeping site safety is excellent (e.g. conducting ‘toolbox meeting’, safety
instruction for workers)
2. Not only the contractor provides workers safety gears but also it gives workers and
operators the instruction to how to use it through continuous safety awareness efforts.
3. The contractor not only makes effort for accident prevention, but also takes measures for
preparedness against accident and natural disaster
4. The contractor manages to minimise damage on the site when a severe natural disaster hit
the area.
Photo 2.11 Example Photo: Application of Do-nou (Sand bag) for safe passage for workers
‐ 44 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.8.3
Check Point 8-3 Accident prevention efforts for third-parties are proper.
Description:
The site agent shall take necessary action to prevent any accidents on third party. The
supervisor shall check on how the contractor is managing the site, especially at places where
third party come closer or even come into.
Reference
SSRBC Section 1-118 “Preservation and maintenance of fence and gates”
Case examples
1. Designation of work area is not clear so that the third party is able to get in.
‐ 45 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.8.4
Check Point 8-4 Traffic and site safety devices are properly installed and managed.
Description:
When works are conducted on or close to the carriageway, adequate measures should be
taken to warn and protect road users and workers. Details of safety measures are proposed in
Chapter12 of RMM.
Reference
RMM Chapter12 “Safety methods for execution works”
Case examples
1. Distinct signs are well arranged and visible so that road users can get an extra cautious.
‐ 46 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.8.5
Check Point 8-5 Temporary facilities (e.g. scaffolding) are constantly checked.
Description:
Temporary facilities affect safety very much during the execution period. The Contractor
shall check whether or not the facilities themselves are strong, they are fixed firmly on the
ground, and the ground has enough bearing capacity. This check point requires periodic and
as-need basis checking of these features of temporary facilities.
Reference
SSRBC Section 1-117 “Health, Safety and Accidents”
SSRBC Section 1-115(k) “Construction Generally”
Case examples
Photo is an example of form supports on a river. Several supports on the left are scoured and
hanging because of river flow. The area got much rain in the day before. Therefore, check
should be done not only periodically but also after major events such as collision, heavy rain,
and so on,
1. The contractor checks safety of temporary facilities daily based on its own safety code.
‐ 47 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.9.1
Check Point Environmental and social mitigation efforts (e.g. against noise,
9-1
vibration, emission, and dust ) are conducted
Description:
The contractor shall try to minimise pollutions and affections of those pollution on
environment. If noise and/or vibration would be a problem by the works near residential area,
it is preferable to choose low-noise/vibration machines for the work. If damage by dust is
predictable, the contractor shall consider water-spraying.
Reference
SSRBC Section 1-115 (c) (d) “Construction Generally”
Case examples
2. The contractor takes a voluntary measure to mitigate social inconvenience during the work
execution.
‐ 48 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.9.2
Check Point 9-2 Waste material generated from the site is properly disposed
Description:
The contractor shall properly dispose any waste that is generated in the site. This is to
prevent any environmental problems such as air pollution and water pollution. Also the issue
shall be checked whether or not the Contractor is committing illegal dumping.
Reference
SSRBC Section 1-115 (c) (d) “Construction Generally”
SSRBC Section 1-120 “Protection of existing works and services”
Case examples
1. The contractor disposes waste material in an eco-friendly manner, or put it into recycle
process.
‐ 49 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.9.3
Check Point Damage to existing roads, works and services are avoided or are
9-3
repaired
Description:
Damages on existing roads, works, and services shall be avoided as long as possible. In case of
giving damage, it should be restored as soon as possible.
Reference
Case examples
1. The contractor takes measures to prevent damage on existing facilities prior to the
commencement of the works, or repairs any damage that may occur.
‐ 50 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 2.5.9.4
Reference
Case examples
2. The contractor instructs and periodically check transporters to obey the traffic regulations.
‐ 51 ‐
Supervision and Contract Evaluation Manual for Road Works
3. Contract Evaluation
3.1 Application
3.1.1 Purpose
3.1.2 Evaluators
(3) Quality Assurance Office (QAO) or Inspection and Acceptance Committee (IAC)
QAO/IAC evaluates the works as third evaluator with independent point of view.
Composition of members of IAC is regulated in clause No.17 of the public procurement and
disposal regulations 2006. In that case IAC chairperson checks and endorses the evaluation done
by IAC. If the authority does not have Quality assurance office, third party evaluation is
conducted solely by IAC.
‐ 52 ‐
Supervision and Contract Evaluation Manual for Road Works
Evaluators
Contract is
Case audited by Contact Sum
Resident QAO/IAC
QAO* The Engineer
Engineer (The third Evaluator)
Resident Engineer’s
1 Yes N/A QAO
Engineer Representative
Contract is audited by QAO
YES NO
YES NO
Resident Engineer
QAO evaluates IAC evaluates
evaluates
‐ 53 ‐
Supervision and Contract Evaluation Manual for Road Works
can observe the site for close checks. However, IAC shall ask the Contractor to get out of the
meeting venue during the evaluation in order to avoid the influence by the Contractor.
1) The contractor submits Works execution programme (WEP) before the commencement of the
work.
2) Resident Engineer (RE) checks the contractor’s execution system using Supervision Check List
(SCL) in terms of compliance with WEP.
3) RE checks quality and finished works dimension based on reports from the Contractor.
4) RE evaluates nine items and puts the results on Grading Sheet for the Resident Engineer
whose example is shown in Table 3.7.
6) ER evaluates five items and two items for bonus and penalty. ER puts the results on Grading
Sheet for the Engineer’s Representative whose example is shown in Table 3.7.
7) Quality Assurance Office (QAO) or Inspection and Acceptance Committee (IAC) evaluates two
items in CETS. Evaluations are done using Grading Sheet for Quality Assurance Office / Inspection
and Acceptance Committee whose example is shown in Table 3.9(a) – (c).
8) Grading results by three evaluators are input on Contract Evaluation Tally Sheet so that the score is
calculated.
‐ 54 ‐
Supervision and Contract Evaluation Manual for Road Works
Contractor Road Authority
Works Execution Resident Engineer
Programme 1)
Supervision 4) Grading
Supervision Check List (Chapter 3.4)
✓ Execution System in
General
Execution System Check the
Quality and Quantity ✓ Equipment Holding
2) Check Compliance ✓ In‐house Staff
Works on site with WEP ✓ Personnel Employment
✓ Site Base Facilities
✓ Quality and Quantity
3) Management
Report Quality/Quantity ✓ Work Scheduling
Testing & Measurement Check & Confirm ✓ Work Safety Management
✓ Environmental and Social
Management
Quality Assurance Office / The Engineer's 5)
Contractor’s self Inspection and Acceptance Representative
management Committee
6) Grading
7) Grading (Chapter 3.5)
Supervision
✓Equipment Holiding
(Chapter 3.6)
✓ In‐house Staff
✓Execution System in General
✓ Personnel Employment
✓Quality and Quantity
✓ Work Scheduling
management
Contract Evaluation ✓ Work Safety Management
✓ Environmental and Social
Management
✓ Innovation Effort
Evaluator ✓ Compliance with Statutory
Requirement
Documentation
8) Scoring on Contract Evaluation Tally Sheet
‐ 55 ‐
Supervision and Contract Evaluation Manual for Road Works
Supervsion
Substantial Completion
Meeting
(Signing on Contract
The Engineer's approval Evaluation Tally Sheet and
Notification)
14 days
No
Template : I. Database
Score Database (3.8.3)
Format
Datbase in MoR/KRB
‐ 56 ‐
Supervision and Contract Evaluation Manual for Road Works
3.2.2 Grading
Evaluation results are expressed in five grades as shown in Table 3.2. Basic score is given for
each grade; the scores cannot be intermediate values between basic scores. Hereafter in this
manual, the word “grade” is used for determination of grades “a”, “b”, “c”, “d”, or “e” in a part of
evaluation process.
It should be noted that grading is to be conducted strictly in accordance with Table 3.3 and
Section 3.4 to 3.6. This means that grading shall be done by neither intuition by the words like
“Very good”, “Good”, or “Very poor” nor any percentages implied from Basic Scores of 10.0, 7.5,
5.0, 2.5, or 0.0.
a b c d e
Grade
(Very good) (Good) (Fair) (Poor) (Very poor)
Determining grade which corresponds to the level of contractor’s performance is the core part
of the evaluation process. Table 3.3 summarizes the grading criteria. Detailed procedures are
described in Chapter 3.4 to 3.6 by type of evaluator.
‐ 57 ‐
Table 3.3 Grading Criteria on Contract Evaluation
‐ 58 ‐
The Engineer's and ER does not find any
Representative OR - remarkable efforts by the - Fig.3.4
(ER) 2. RE evaluates "b, c, or Contractor
Supervision and Contract Evaluation Manual for Road Works
There are 11 items for evaluation. Note that evaluation items 1 to 9 are identical to the items
in Supervision Check List (SCL). Each evaluation item contains one or two sub-items. Not all
sub-items are to be evaluated by each evaluator; sub-items to be evaluated are varied by scales of
the works as shown in Table 3.4.
The definition of scales of the works is the same as in 2.3.2; Large scale work is a project by
Class A, B, C, and D company, Small scale work is a project by Class E and under company, and
Labour-based work is a project under the Roads 2000 scheme.
*RE ER QAO/IAC
Item Description Note
**L S Lb L S Lb L S Lb
3. Contractor's In-house The qualified technical engineers and in-house staffs are
○ ○ ○ ○ --- --- --- --- ---
staff assigned
7. Work scheduling Work has been progressed and completed as planned ○ ○ ○ ○ --- --- --- --- ---
11. Compliance with statutory requirements --- --- --- ○ ○ ○ --- --- --- Penalty
*RE;Resident Engineer, ER;Engineer's Represenmtative, QAO;Quality Assurance Office, and IAC;Inspection and Acceptance Committee (IAC)
**L;Large Scale Work (Class A - D), S;Small Scale Work(Class E and Under), and Lb;Labour Based Work
‐ 59 ‐
Supervision and Contract Evaluation Manual for Road Works
The Resident Engineer (RE) shall evaluate all items that are identical to the items on
Supervision Check List (SCL) since he/she inspects all aspects of work on a daily basis through
site inspectors.
1. Execution System in General
“Work procedures are in accordance with Works Execution Programme that properly
reflects given conditions.”
2. Equipment holding
3. In-house staff
4. Personnel employment
5. Site base facilities
6. Quality and quantity management
“Material testing, structural examination, and measurements are properly and
routinely conducted. Results are within the specifications and compiled for checking.”
7. Work scheduling
8. Work safety management
9. Environmental and social management
Note that “2. Equipment holding” and “5. Site base facilities” are not evaluated in the contract
of labour based works (See Table 3.4).
‐ 60 ‐
Supervision and Contract Evaluation Manual for Road Works
Issuance of corrective order
NO YES
Excellent performance is The Contractor complies the
presented? order?
YES NO
YES NO
Correction made is fair or “e”
“a” “b”
good?
YES NO
“c” “d”
Fig. 3.3 Grading Flow Chart for Resident Engineer
‐ 61 ‐
Supervision and Contract Evaluation Manual for Road Works
Contract Evaluation Grading Sheet for Resident Engineer
Project Title: Repair and Resealing of N - G Road (C##) Date: 21/08/2012
Resident Engineer : AAAA BBBB Signature: AAAA BBBB
Comment :
Scale of Work
Items Descriptions Grade Note
(Record on Supervision Check List)
*L S Lb
Work procedures are in accordance with Works
1. Execution System
in General
Execution Programme that properly reflects given ○ ○ ○ a b c d e
conditions.
2. Equipment All equipments used in the works are mobilised
holding properly and well-maintained
○ ○ -- a b c d e
3. Contractor's In- The qualified technical engineers and in-house
house staff staffs are assigned
○ ○ ○ a b c d e
4. Personnel Reasonable number of skilled workers/operators is
employment properly employed by the contractor
○ ○ ○ a b c d e
5. Site base Site facilities are properly prepared, maintained
facilities during execution, and cleared on completion.
○ ○ -- a b c d e
Material testing, structural examination, and
6. Quality and
measurements are properly and routinely
quantity
conducted. Results are within the specifications
○ ○ ○ a b c d e
management
and compiled for checking.
9. Environmental
Environmental and social issues caused by the
and social
works are minimized and mitigated properly
○ ○ ○ a b c d e overloading twice
management
*L;Large Scale Work (Class A - D), S;Small Scale Work(Class E and Under), and Lb;Labour Based Work
Grading Criteria
a b c d e
No corrective order is made Corrective order is made
Excellent performance is The work executed is The Contractor complies The Contractor complies The Contractor does not
presented for the satisfactory, but no with the order within the with the order within the comply with it during the
evaluation items specified excellent peformance is contract period. contract period. However contract period
in 3.4.1. presented for the corrections are poor.
Examples of excellent evaluation items specified
performance are indecated in 3.4.1.
in Table 2.5.1.1 ‐ 2.5.9.4
Issuance of corrective order
NO YES
Excellent performance is The Contractor complies the
presented? order?
YES NO
YES NO
Correction made is fair or “e”
“a” “b”
good?
YES NO
“c” “d”
‐ 62 ‐
Supervision and Contract Evaluation Manual for Road Works
(1) Grading
2. Equipment holding
3. In-house staff
4. Personnel employment
7. Work scheduling
8. Work safety management
9. Environmental and social management
(2) Bonus/Penalty
10. Innovation effort
11. Compliance with statutory requirement
(3) Variation of items by scale of the works
Set of evaluation items varies by scales of the works as shown in Table-3.4. The definition of
the scale of works is written in 3.3. Grading items 2, 3, 4 and 7 are evaluated or not evaluated
depending on scale of a work. Grading items 8 and 9 are evaluated in either scale of works. Item
10 for bonus is evaluated for large scale works only, while Item11 for penalty are evaluated in
either scale of works.
‐ 63 ‐
Supervision and Contract Evaluation Manual for Road Works
Grading by Resident Engineer
Overcoming unforeseen
difficulties or achieving
outstanding outcomes?
YES
NO
‐ 64 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 3.6 Case examples for upgrading “c” to “a” by the Engineer’s Representative
Scale of the
Item* Work** Case Examples of "Remarkable Efforts"
L S Lb
‐ 65 ‐
Supervision and Contract Evaluation Manual for Road Works
‐ 66 ‐
Supervision and Contract Evaluation Manual for Road Works
3.5.3 Bonus/Penalty
The following two items are evaluated as bonus or penalty, respectively. For the moment, those
score levels are at the discretion of the evaluator. And they are neither subject to inter-items
weightings nor evaluator weightings.
‐ 67 ‐
Supervision and Contract Evaluation Manual for Road Works
‐ 68 ‐
Supervision and Contract Evaluation Manual for Road Works
Contract Evaluation Grading Sheet for the Engineer's Representative
Project Title: Repair and Resealing of N - G Road (C##) Date: 24/08/2012
Engineer's Representative : CCCC DDDD Signature: CCCC DDDD
Comment :
9. Environmental
Environmental and social issues caused by the
and social
works are minimized and mitigated properly
○ ○ ○ a b,c,d
e a c e
management
Grading Criteria
a b c d e
Remarkable effort is Effort is made in Effort is insufficient
made for the average sense for for the evaluation
evaluation items the evaluation items items specified in
specified in 3.5.1. specified in 3.5.1. 3.5.1.
Grading by Resident Engineer
Overcoming unforeseen
difficulties or achieving
outstanding outcomes?
YES
NO
‐ 69 ‐
Supervision and Contract Evaluation Manual for Road Works
As the independent evaluator, QAO/IAC deals with the two key items which indicate the
contractor’s capacity to deliver;
1. Execution system in general
“Overall system of execution is confirmed to be proper during audit or at
substantial completion meeting”
6. Quality and quantity management
“Measured parameters are within the specified allowable ranges with proper
workmanship”
Evaluator determined in Table 3.1 and Fig.3.1
Resident Engineer
QAO evaluates IAC evaluates
evaluates
Grading based on scorings for Supervision Check list
Grading based on Rate of the followings
compliance with Quantity Management
requirements in Table 3.9 Quality Management
(b) Workmanship
in Table 3.9 (c) “a”, “b”, “c”, “d”, “e”
“a”, “b”, “c”, “d”, “e” “a”, “b”, “c”, “d”, “e”
‐ 70 ‐
Supervision and Contract Evaluation Manual for Road Works
Table3.6 shows an example of grading for “Execution system in General”. The blank format is
in Appendix A5.4. If the Contractor does not comply with the corrective order issued on status of
the system, grade “e” is given. If the correction is poor, grade “d” is given. In other cases, Grading
“a” to “c” is determined according to the number of checks in the sub-table.
The level of quality and quantity achievements is judged by the following sub-items. They can
be evaluated by QAO/IAC only with written reports and visual inspection of finished works.
i) Quantity measurements
ii) Quality measurements
iii) Workmanship
As shown in Table3.6, points are given for each sub-item according to the degree of satisfaction
with fixed benchmarks. The criteria of point rating are shown in Table 3.7. The points are
summed up and the total point determines the grade. Weight allotment for each sub-item is 3.0,
3.0, and 4.0 respectively..
i) Quantity measurements
Sub-grades “a’ to ”e’” are determined whether or not the all necessary size and volume
measurements are conducted and recorded as specified, and all measured figures are within
specified allowable range. And the corrective actions of failed results if any are also checked.
ii) Quality measurements
Sub-grades “a’ to ”e’” are determined whether or not the all necessary material testing and
structural checking are conducted and recorded as specified, and all measured figures are within
specified allowable range. And the corrective actions of failed results if any are also checked.
iii) Workmanship
Sub-grades “a’ to ”e’” are determined by the number of satisfactory visual check points specified
in Table 3.9(c). Table 3.8 below shows sample pictures for the check points
‐ 71 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 3.8(a) Sample pictures for check points “Good appearance of finished work”
Check Points Photographs Note
(Satisfactory)
(Satisfactory)
(Satisfactory)
4. Good top and edge Top and edge are finished with
finishing good workmanship
(Satisfactory)
(Unsatisfactory)
‐ 72 ‐
Supervision and Contract Evaluation Manual for Road Works
(Unsatisfactory)
(Unsatisfactory)
Table 3.8(b) Sample pictures for check points “No major flaws or deterioration”
Check Points Photographs Note
(Unsatisfactory)
(Unsatisfactory)
‐ 73 ‐
Supervision and Contract Evaluation Manual for Road Works
(Unsatisfactory)
(Unsatisfactory)
(Unsatisfactory)
‐ 74 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 3.8(c) Sample pictures for check points “Fitness for purpose”
Check Points Photographs Note
(Unsatisfactory)
(Satisfactory)
(Unsatisfactory)
‐ 75 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 3.9(a) Grading Sheet for Quality Assurance Office / Inspection and Acceptance Committee (Example)
Contract Evaluation Grading Sheet for QAO/IAC (1/3)
Project Title: Repair and Resealing of N - G Road (C##) Date: 04/09/2012
Quality Assurance Office/Inspection and Acceptance
EEEE FFFF Signature: EEEE FFFF
Committee Chair: (Name)
Comment :
Scale of Work
Items Descriptions Grade Note
*L S Lb
6. Quality and
Measured parameters are within the specified
quantity
allowable ranges with proper workmanship
○ ○ ○ a b c d e
management
*L;Large Scale Work (Class A - D), S;Small Scale Work(Class E and Under), and Lb;Labour Based Work
Grading Criteria
a b c d e
Rate of compliance Rate of compliance Rate of compliance Rate of compliance Rate of compliance
with requirements in with requirements in with requirements in with requirements in with requirements in
3.6.2 is very good 3.6.2 is good for the 3.6.2 is fair for the 3.6.2 is poor for the 3.6.2 is very poor
for the evaluation evaluation items in evaluation items in evaluation items in for the evaluation
items in 3.6.1. 3.6.1. 3.6.1. 3.6.1. items in 3.6.1.
‐ 76 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 3.9(b) Grading Sheet for Quality Assurance Office / Inspection and Acceptance Committee (Example)
Contract Evaluation Grading Sheet for QAO/IAC (2/3)
Item 1. Execution System
Check (✓)
Points to be checked
Satisfactory Unsatisfactory N/A
α = 6
Total Number --- β= 0
Percentage γ = α / (12-β) *100% = 6 / (12 - 0) x 100 = 50.0 %
a b c d e
‐ 77 ‐
Supervision and Contract Evaluation Manual for Road Works
Table 3.9(c) Grading Sheet for Quality Assurance Office / Inspection and Acceptance Committee (Example)
Contract Evaluation Grading Sheet for QAO/IAC (3/3)
Item 6. Quality and quantity management
Description Measured parameters are within the specified allowable ranges with proper workmanship
All necessary scale measurements Although some of the necessary scale Nevertheless a corrective order was
are conducted and recorded as measurements were not conducted as issued, the Contractor did not comply
Quantity specified, and all measured specified, the contractor complied with a with it.
Measurements parameters are within the specified corrective order
allowable range
All necessary quality measurements Although some of the necessary quality Nevertheless a corrective order were
are conducted and recorded as measurements were not conducted as issued, the Contractor did not comply
Quality specified, and all measured figures specified, the Contractor complied with a with it.
Measurements are within the specified allowable corrective order
range
Check (✓)
Sub-sub item Check Point
Satisfactory Unsatisfactory N/A
a) Good 1 Good exterior appearance ✓
appearance of
finished work
2 Good alignment and spacing ✓
3 Good overall surface alignment ✓
4 Good top and edge finishing ✓
5 Good shaping for connection to adjacent structures ✓
6 Good overall cleaning ✓
7 Good surface touch ✓
b) No major 8 No irregular shape of earth works ✓
flaws or
Workmanship
deterioration
9 No visible cracks ✓
10 No water leakage ✓
11 No excessive water pool (puddle) on the surface ✓
12 No spot of bitumen/mortar on other structure ✓
13 No visible flaws and rusts on the surface ✓
c) Fitness for 14 Good functionality of structure for its purpose ✓
purpose
15 Good visibility of road furniture from road users ✓
16 No obstacles for road users left ✓
Total Number α = 8 --- β=2
Percentage γ = α / (16 - β) * 100% = 8 / (16 - 2) x 100% = 57.1%
γ = 100 - 80.1% γ = 80.0 - 60.1% γ = 60.0% - 40.1% γ = 40.0 - 20.1% γ = 20.0 - 0.0%
Z 4.0 3.0 2.0 1.0 0.0
‐ 78 ‐
Supervision and Contract Evaluation Manual for Road Works
3.7 Weighting
3.7.1 Concept of weighting
In order to reflect relative differences of importance between evaluation items and of degree
evaluators’ responsibility, relative weights are used on tallying of scores.
Net score for an item by an evaluator score is calculated as the following equation;
p = w 1 x w2 x p 0
Set of inter-item weight is provided by scale of contract. Table 3.10 shows the weighting set for
the contract of large scale works (for Class D and above company), the contract of small scale
works (for Class E and under company), and labour based work contract.
Labour-based work
Labour-based work
Small scale work
(Class A - D)
(Class A - D)
Scale of Works
Item
Total 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
‐ 79 ‐
Supervision and Contract Evaluation Manual for Road Works
Weights specified in this section are not subject to change for the validity of unified scoring
scheme. However, when the clear changes of social, economic, environment, technological
requirements are observed, weight setting can be updated with unanimous agreement among
relevant organizations.
Based on the results on three grading sheets (Table 3.5, 3.7, and 3.9), scores are automatically
given for each item by each evaluator. Contract Evaluation Tally Sheet (CETS) is the unified
template to calculate the total score from these scores. Fig 3.6 shows part of the CETS. An
evaluator fills the blank by choosing a “Net Score” which corresponds to the grading for the item
and the evaluator. There are three formats of CETS for large scale work, small scale work, and
labour based work.
Table 3.12 shows CETS for large scale works. They also include basic contract information and
fixed weights by contract size.
After the calculation of total score, CETS shall be signed by The Engineer.
Table 3.11 is a rough standard of contract’s performance judging from the total score.
66-75 Satisfactory
56 – 65 Fair
‐ 80 ‐
Supervision and Contract Evaluation Manual for Road Works
evaluator w2
weights w1
Inter‐item
weight by
a b c d e
it
10.0 7.5 ✕ 5.0 2.5 0.0
I t
Net Score p = w1 x w2 x p0
‐ 81 ‐
Table 3.12 Contract Evaluation Tally Sheet (Example, Large Scale Work)
Contract Evaluation Score Tally Sheet (Large scale work by Class A, B, C, and D companies)
Project Title Repair and Resealing of N ‐ G Road (C##) Date of Commencement 22 ‐ OCT ‐ 2011
Contract Number KeNHA/RD/M/###/2011 Completion Date 08 ‐ AUG ‐ 2012
Contractor @@@@@ Construction Co. Ltd. Company Class A Date of Substantial Completion Meeting 21 ‐ AUG ‐ 2012
Contract Sum Ksh11,233,109.00‐ Scoring Date 24 ‐ AUG ‐ 2012
Quality Assurance Office/
Resident Engineer The Engineer's Representative
Inspection and Acceptance Committee
weight by
weight by
weight by
Inter‐item
Inter‐item
Inter‐item
weights w1
weights w1
weights w1
evaluator w2
evaluator w2
evaluator w2
Net Score p = w1 x w2 x p0 Net Score p = w1 x w2 x p0 Net Score p = w1 x w2 x p0
Work procedures are in accordance with Works Execution Programme that 6.00 4.50 3.00 1.50 0.00
1.2 0.5
1. Execution System in properly reflects given conditions. 3.00
7.00
General Overall execution system is confirmed to be proper during audit or at 8.00 6.00 4.00 2.00 0.00
4.0 0.2
Substantial completion meeting 4.00
‐ 82 ‐
employment the contractor 2.50
Material testing, structural examination, and measurements are properly
and routinely conducted. Results are within the specifications and 1.0 0.5
6. Quality and quantity 5.00
compiled for checking. 11.00
management
Measured parameters are within the specified allowable ranges with 12.00 9.00 6.00 3.00 0.00
6.0 0.2
proper workmanship 6.00
8. Work safety Necessary measures are taken for safety of workers, operators, and third 5.00 3.75 2.50 1.25 0.00 3.00 1.50 0.00
1.0 0.5 1.0 0.3 0.00
management party. No serious accident occurs during the contract period. 0.00 0.00
9. Environmental and Environmental and social issues caused by the works are minimized and 5.00 3.75 2.50 1.25 0.00 3.00 1.50 0.00
1.0 0.5 1.0 0.3 4.25
social management mitigated properly 1.25 3.00
Innovation effort is made by using new materials, new technology, process 0 ‐ +10
10. Innovation effort 5.00
rationalization, etc. 5
0 ‐ ‐10
11. Compliance with statutory requirements ‐5.00
‐5
28/08/2012 Sign
Grand Total 57.50 Date GGGG HHHH
(The Engineer)
Supervision and Contract Evaluation Manual for Road Works
The authorized total score and its breakdowns are notified to the Contractor as an official
letter from the Authority. The format is shown in Appendix G. The contractor can raise questions
on the results of scoring within a specific number of days after the issuance. The Authority
answers in writing to the Contractor.
Every score along with basic contract information and the type of work conducted are stored in
the unified database without delay. The procedure is depicted in Fig 3.7. Input data from each
Authority is rearranged to be a list of companies which contains information shown in Table 3.13
so that scores of any company can be easily extracted. Detailed example of database format is
shown in Appendix 8.1 and 8.2. Database is accessible to any authority in the next procurement
process. It is used as a reference of past experiences of similar type of works in the tender
evaluation stage.
‐ 83 ‐
Supervision and Contract Evaluation Manual for Road Works
Garding by Quality
Evaluation by Evaluation by The
Data Assurance Office /
Resident Engineer's
Aquisition Inspection and
Engineer Representative
Acceptance Committee
No
Data Submission
Road Authority A
Road Authority B
Data
Accumulation Road Authority C
and Storage
MoR/KRB
Data Integration
ID/Password Protected
Data Data Table in PDF Format
Space on Web‐site
Distribution
‐ 84 ‐
Supervision and Contract Evaluation Manual for Road Works
Appendix
‐ 85 ‐
Supervision and Contract Evaluation Manual for Road Works
Table of Contents
Appendix 86
A. Incorporating in Tender and Contract Document for Application of the Manual 87
B. Work execution programme template 88
C. Daily report sample 102
D. Monthly Progress Report templates 103
(Supervision check list) 112
E. Report for Substantial Completion Meeting 121
F. Contract evaluation tally sheet 122
F.1 Contract Evaluation Grading Sheet for Resident Engineer 122
F.2 Contract Evaluation Grading Sheet for the Engineer's Representative 123
F.3 Contract Evaluation Grading Sheet for QAO/IAC 124
F.4 Contract Evaluation Tally Sheet (Large scale work) 127
F.5 Contract Evaluation Tally Sheet (Small scale work) 128
F.6 Contract Evaluation Tally Sheet (Labour-based work) 129
G. Notification of scoring of contract evaluation 130
G.1 Large Scale Work 130
G.2 Small Scale Work 131
G.3 Labour-based Work 132
H. Taking Over Certification 133
I. Database Format 131
I.1 Contract Evaluation Database Format in Authority 134
I.2 Integrated Contract Evaluation Database Format 135
‐ 86 ‐
Supervision and Contract Evaluation Manual for Road Works
In order to specify the use of “Supervision and Contract Evaluation Manual for Road works”, the
following will be introduced
‐ 87 ‐
Supervision and Contract Evaluation Manual for Road Works
(Project Title)
CONTRACT No.: / /
DD/MM/YYYY
‐ 88 ‐
Supervision and Contract Evaluation Manual for Road Works
Table of Contents
B.7.3 Duties of the Safety OfficerB.8 Environmental and social management plan 97
‐ 89 ‐
Supervision and Contract Evaluation Manual for Road Works
A brief description of the project which includes location, nature and extent of works
(e.g. (i) contribute to improving the general service on the priority road network;(ii) promoting
economic recovery; (iii) support the Government in its policy of provision of access to learning
institutions (iv) reducing transport cost; (v) improving the living conditions of the neighboring
population and their awareness of HIV/AIDS, road safety and environmental protection; and
(vi) building the technical and operational capacity of the Authority (ix) job creation etc.)
Project Title: ,
Contract Number: ,
Financier: ,
Employer: ,
Represented by: ,
Implementing Agency:: ,
Engineer: ,
Engineer’s Representative: ,
Regional office: ,
Contractor: ,
Address: ,
Phone/Fax: / ,
Site Agent: ,
Date of Tender: ,
Date of Award: ,
Contract Sum: ,
Period of commencement: : ,
‐ 90 ‐
Supervision and Contract Evaluation Manual for Road Works
Commencement date: ,
MAP
It shall include the route of the road with emphasizing portion of the works.
Location of Contractor’s site base shall be indicated I the map.
‐ 91 ‐
Table B.2.1 Programme of Works
‐ 92 ‐
Executed 60%
Planned
Executed 50%
Supervision and Contract Evaluation Manual for Road Works
Planned
Executed 40%
Planned
Executed 30%
Planned
Executed 20%
Planned
Executed 10%
0%
Planned % % % % % % %
Finished Work Amount in the Month
Executed % % % % % % %
Planned % % % % % % %
Finished Work Amount (Accumulated)
Executed % % % % % % %
Table B.2.2 Planned Cash Flow
‐ 93 ‐
0
Supervision and Contract Evaluation Manual for Road Works
Aug‐11 Sep‐11 Oct‐11 Nov‐11 Dec‐11 Jan‐12 Feb‐12 Mar‐12 Apr‐12 May‐12 Jun‐12 Jul‐12
Month Aug‐11 Sep‐11 Oct‐11 Nov‐11 Dec‐11 Jan‐12 Feb‐12 Mar‐12 Apr‐12 May‐12 Jun‐12 Jul‐12
Original Cash Flow kshs
1st Revision kshs
2nd Revision kshs
3rd Revision kshs
Monthly Certificate kshs
Actual Certificate Cash Flow kshs
Estimated Monthly Certificate kshs
Supervision and Contract Evaluation Manual for Road Works
Project Manager
Project Engineer
Materials Engineer
Workshop Manager
Quarry Manager
Chief Surveyor
Earthworks Superintendent 1
Earthworks Superintendent 2
Fuel Manager
Field Mechanic
‐ 94 ‐
Supervision and Contract Evaluation Manual for Road Works
2011 2012
Ref Deployment
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
1 Site Agent
2 Site Engineers
3 Foreman
5 Plant Mechanic
6 Mechanic
7 Auto Electrician
8 Electrician
9 Tyreman
10 Boilerman
11 Mason
12 Carpenter
13 Pick-up Driver
14 Tipper Drivers
15 Pulvimixer
16 Excavator Operator
17 Shovel Operator
18 Broom Operator
19 Grader Operator
20 Roller Operator
21 Paver Operator
22 Milling Operator
23 Welders
24 Store Keeper
25 Office Assistant
26 Watchman
27 Causals
TOTALS
‐ 95 ‐
Table B.5.1 Equipment List and Schedule
2011 2012
Machine Capacity Qty. Unit Term-1 Term-2 Term-3 Roles and Purpose
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
‐ 96 ‐
Asphalt Distributer 3t 1 No. Pavement
Supervision and Contract Evaluation Manual for Road Works
Site Office Map
‐ 97 ‐
Supervision and Contract Evaluation Manual for Road Works
Head Quarter ‐ (Address, etc)
G.M. MTCE (E‐mail address, etc)
Authority Manager MTCE
Project Engineer
Resident Engineer
Head Office
Contractor Site Office
Site Agent
Head Office
Subcontractor 1 Site Agent
Operator
Head Office
Subcontractor 2 Site Agent
Operator
Hospital
Police
For Emergency Ambulance
Fire brigade
Electricity
‐ 98 ‐
Table B.9.1 Quality Control Plan
Work Item Test Item Test Method Standard Value Test Frequency Remark
opening up
Plasticity Index less than 50% TS-505
and each new source of aggregate
opening up
CBR AASHTO T99 not less than 8% (after a 4-day soak) TS-505
and each new source of aggregate
material
upper 300mm : once per 500m2
Maximum Dry Density AASHTO T99 TS-226( ⅰ )
backfill : each new material
Earthwork
(except the 300mm below formation) : 95% MDD
2)The 300mm below formation upper 300mm : once per 250m2
field density test TS-508
in embankments : 100% MDD backfill : twice per 10m3
Site 3)The 300mm below formation in cuttings
under the carriageway and shoulders : 100% MDD
proofrolling a loaded scraper or truck with a minimum axle load of 8 tones *Consultant Approval TS-1307
‐ 99 ‐
(ASTM C 131) Base : Max.45 and each new source of aggregate
Subbase : Max.35
Aggregate Crushing Value BS 812 ditto TS-1303(b)
Base : Max.32
Supervision and Contract Evaluation Manual for Road Works
Subbase : Max.35
Flankiness Index (FI) BS 812 once per 500m3 TS-1303(b)
Base : Max.30
Maximum Dry Density (MDD) BS 1377 - once per 400m2 of each layer TS-226( ⅶ )
Base : average not less than 98% MDD with no result less than 96% MDD
field density test AASHTO T99 once per 200m2 of each layer TS-226( ⅶ )
Subbase : average not less than 96% MDD with no result less than 94% MDD
Site
proofrolling - *Consultant Approval TS-1307
Supervision and Contract Evaluation Manual for Road Works
Wearing, Binder, Base, Sub base Thickness 98% ≦ t ≦ 125% 5 points in any length of 100m
Wearing, Binder, Base, Sub base Average thickness 100% ≦ t ≦ 120% ditto
‐ 100 ‐
Supervision and Contract Evaluation Manual for Road Works
General
Construction
Quality Control
Construction Work
Progress
Other
‐ 101 ‐
Supervision and Contract Evaluation Manual for Road Works
SECTION:
b) Plant: (Working)
Idle(reasons)
c) Materials delivered:
DAILY PROGRESS (including time lost, standing time for labour, plant,type of work completed and location):
MEETINGS:
EMERGENCY WORKS:
TESTS CARRIED OUT: (short summary indicating actual location and source of materials)
‐ 102 ‐
Supervision and Contract Evaluation Manual for Road Works
(Project Title)
CONTRACT No.: / /
DD/MM/YYYY
‐ 103 ‐
Supervision and Contract Evaluation Manual for Road Works
Table of Contents
APPENDICES 117
Appendix D1 Programme of Works
Appendix D2 Work progress chart
Appendix D3 Cash Flow
Appendix D4 Contractor’s personnel and labour
‐ 104 ‐
Supervision and Contract Evaluation Manual for Road Works
‐ 105 ‐
Supervision and Contract Evaluation Manual for Road Works
Percentage %
D.1.4 Claims
(Summary and list of claims and notices of intention to claim)
(brief statement on pending approvals, contractual claims, constraints, any significant
occurrences disrupting to the works)
MAP
It shall include the route of the road with emphasizing portion of the works.
Location of Contractor’s site base shall be indicated I the map.
‐ 106 ‐
Supervision and Contract Evaluation Manual for Road Works
Contract Number: ,
Financier: ,
Employer: ,
Represented by: ,
Implementing Agency:: ,
Engineer: ,
Engineer’s Representative: ,
Regional office: ,
Contractor: ,
Address: ,
Phone/Fax: / ,
Site Agent: ,
Date of Tender: ,
Date of Award: ,
Contract Sum: ,
Period of commencement: : ,
Commencement date: ,
‐ 107 ‐
Supervision and Contract Evaluation Manual for Road Works
‐ 108 ‐
Supervision and Contract Evaluation Manual for Road Works
Done
Bill Estimated
Description Unit Total Outstanding % Done
No. This Total Total
Previous
Month to date
Months
Overall progress km
Quantities (Numbers)
Type of Plant/
S/No. Specification Unit Remarks
Equipment Planned
Mobilized Balance
number
‐ 109 ‐
Supervision and Contract Evaluation Manual for Road Works
Numbers
S/No. Personnel Remarks
Planned
Mobilized Balance
number
‐ 110 ‐
Supervision and Contract Evaluation Manual for Road Works
Table D.4.1
Date Payment Interest Default
Amount
Cert. No. Signed by expiry period as at commence Remarks
(Kshs)
RE date (date) ment date
Total Due
A Subtotals 1
B Contingencies
C V.O.P
D Subtotals 2
E VAT
TOTAL
‐ 111 ‐
Supervision and Contract Evaluation Manual for Road Works
‐ 112 ‐
Supervision Check List (1/2)
Date Name Signature
Project Title: The Engineer's
Representative
Contractor: (Project Engineer)
1. This check list is for Resident Engineer to check contractor's work execution process.
2. Fill in date of checking as (day/month), mark as indicated in Filling Example, and state remarks. Resident Engineer
3. Put this check list in the Monthly Progress Report.
1 Execution system Works Execution Programme (including its revised version if any) is
in general 1-1 submitted before the date specified in contract document
2 Equipment All equipment used are properly mobilized in accordance with Works
holding 2-1 Execution Programme
3 Contractor's in- Qualified technical staff of contractor are properly assigned as specified in
house staff 3-1 Works Execution Programme
‐ 113 ‐
Contractor's in-house key staff understand work process and schedule
3-2 properly
Supervision and Contract Evaluation Manual for Road Works
4 Personnel Workers and operators are deployed in accordance with Works Execution
employment 4-1 Programme
5 Site base Office and stockyard are prepared in accordance with Works Execution
facilities 5-1 Programme
6 Quality and Material testing, structural examination, and measurements are properly
quantity and routinely conducted based on specifications and Works Execution
6-1
management Programme
Filling Example : ✓Check point is satisfactory ■ Check point is unsatisfactory N/A Not applicable
Supervision Check List (2/2)
Signature
Project Title: The Engineer's
Representative
Contractor: (Project Engineer)
1. This check list is for Resident Engineer to check contractor's work execution process.
2. Fill in date of checking as (day/month), mark as indicated in Filling Example, and state remarks. Resident Engineer
3. Put this check list in the Monthly Progress Report.
6 Quality and Results of material testing, structural examination and measurements are
6-2 within the specifications.
quantity
management Results of material testing, structural examination, and measurements are
6-3 properly compiled as reports for confirmation
7 Work scheduling Understanding of critical path and its reflection on scheduling are proper
7-1
All works are completed within the contract term or within the extended
7-4 term as allowed
‐ 114 ‐
8 Work safety No accident occurs to workers, operators, or third-parties.
8-1
management
Supervision and Contract Evaluation Manual for Road Works
Traffic and site safety devices are properly installed and managed
8-4
9 Environmental Environmental and social mitigation efforts (e.g. against noise, vibration,
9-1 emission, and dust ) are conducted
and social
management Waste material from site is properly disposed
9-2
Filling Example : ✓Check point is satisfactory ■ Check point is unsatisfactory N/A Not applicable
Supervision and Contract Evaluation Manual for Road Works
‐ 115 ‐
Supervision and Contract Evaluation Manual for Road Works
7.1 General
‐ 116 ‐
Table D.A2.1 Works Progress Chart
MAY
TH
BILL No. DESCRIPTION OF WORKS BILL TOTAL
TODATE
% OF BOQ
PREVIOUS
END 15
% THIS MONTH
SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
ITEM % COMPLETE
TOTAL % COMPLETE
TOTAL % COMPLETE
11.40 0.28 100.00 11.14 11.42 51 53 63 68 73 78 83 88 93 98 100
1 General 340,369,905.60
0.07 63.33 7.16 7.23 63.3
12 Subbase 74,065,700.00
0.07 112.46 2.72 2.79 112.5
‐ 117 ‐
0.80 - - - -
14 Subbase 23,083,200.00
- - - -
surface dressing
0.03 21.17 1.18 1.21 21.2
‐ 118 ‐
Table DA6.1 Records of Payment
‐ 119 ‐
Supervision and Contract Evaluation Manual for Road Works
Supervision and Contract Evaluation Manual for Road Works
Total Monthly
Rainfall
‐ 120 ‐
Supervision and Contract Evaluation Manual for Road Works
1 Executive Summary
1.1 Location of the Project
1.2 Background of the Project
2 Project Descriptions
2.1 Detailed Scope of Works
2.2 Contract Details
2.3 Physical Work Progress Summary
3 Conclusions and Snag List
3.1 Appendix II: Project Location Map
3.2 Appendix III: Project Photographs
‐ 121 ‐
Supervision and Contract Evaluation Manual for Road Works
Contract Evaluation Grading Sheet for Resident Engineer
Project Title: Date:
Comment :
Scale of Work
Items Descriptions Grade Note
(Record on Supervision Check List)
*L S Lb
Work procedures are in accordance with Works
1. Execution System
in General
Execution Programme that properly reflects given ○ ○ ○ a b c d e
conditions.
2. Equipment All equipments used in the works are mobilised
holding properly and well-maintained
○ ○ -- a b c d e
3. Contractor's In- The qualified technical engineers and in-house
house staff staffs are assigned
○ ○ ○ a b c d e
4. Personnel Reasonable number of skilled workers/operators is
employment properly employed by the contractor
○ ○ ○ a b c d e
5. Site base Site facilities are properly prepared, maintained
facilities during execution, and cleared on completion.
○ ○ -- a b c d e
Material testing, structural examination, and
6. Quality and
measurements are properly and routinely
quantity
conducted. Results are within the specifications
○ ○ ○ a b c d e
management
and compiled for checking.
9. Environmental
Environmental and social issues caused by the
and social
works are minimized and mitigated properly
○ ○ ○ a b c d e
management
*L;Large Scale Work (Class A - D), S;Small Scale Work(Class E and Under), and Lb;Labour Based Work
Grading Criteria
a b c d e
No corrective order is made Corrective order is made
Excellent performance is The work executed is The Contractor complies The Contractor complies The Contractor does not
presented for the satisfactory, but no with the order within the with the order within the comply with it during the
evaluation items specified excellent peformance is contract period. contract period. However contract period
in 3.4.1. presented for the corrections are poor.
Examples of excellent evaluation items specified
performance are indecated in 3.4.1.
in Table 2.5.1.1 ‐ 2.5.9.4
Issuance of corrective order
NO YES
Excellent performance is The Contractor complies the
presented? order?
YES NO
YES NO
Correction made is fair or “e”
“a” “b”
good?
YES NO
“c” “d”
‐ 122 ‐
Supervision and Contract Evaluation Manual for Road Works
Contract Evaluation Grading Sheet for the Engineer's Representative
Project Title: Date:
Comment :
9. Environmental
Environmental and social issues caused by the
and social
works are minimized and mitigated properly
○ ○ ○ a b,c,d
e a c e
management
0 - -10
11. Compliance with statutory requirements ○ ○ ○
*L;Large Scale Work (Class A - D), S;Small Scale Work(Class E and Under), and Lb;Labour Based Work
Grading Criteria
a - c - e
Remarkable effort is Effort is made in Effort is insufficient
made for the average sense for for the evaluation
evaluation items the evaluation items items specified in
specified in 3.5.1. specified in 3.5.1. 3.5.1.
Grading by Resident Engineer
Overcoming unforeseen
difficulties or achieving
outstanding outcomes?
YES
NO
‐ 123 ‐
Supervision and Contract Evaluation Manual for Road Works
Contract Evaluation Grading Sheet for QAO/IAC (1/3)
Project Title: Date:
Quality Assurance Office/Inspection and Acceptance
Signature:
Committee Chair: (Name)
Comment :
Scale of Work
Items Descriptions Grade Note
*L S Lb
6. Quality and
Measured parameters are within the specified
quantity
allowable ranges with proper workmanship
○ ○ ○ a b c d e
management
*L;Large Scale Work (Class A - D), S;Small Scale Work(Class E and Under), and Lb;Labour Based Work
Grading Criteria
a b c d e
Rate of compliance Rate of compliance Rate of compliance Rate of compliance Rate of compliance
with requirements in with requirements in with requirements in with requirements in with requirements in
3.6.2 is very good 3.6.2 is good for the 3.6.2 is fair for the 3.6.2 is poor for the 3.6.2 is very poor
for the evaluation evaluation items in evaluation items in evaluation items in for the evaluation
items in 3.6.1. 3.6.1. 3.6.1. 3.6.1. items in 3.6.1.
Evaluator determined in Table 3.1 and Fig.3.1
Resident Engineer
QAO evaluates IAC evaluates
evaluates
Grading based on scorings for Supervision Check list
Grading based on Rate of the followings
compliance with Quantity Management
requirements in Table 3.9 Quality Management
(b) Workmanship
in Table 3.9 (c) “a”, “b”, “c”, “d”, “e”
“a”, “b”, “c”, “d”, “e” “a”, “b”, “c”, “d”, “e”
‐ 124 ‐
Supervision and Contract Evaluation Manual for Road Works
Contract Evaluation Grading Sheet for QAO/IAC (2/3)
Item 1. Execution System
Check (✓)
Points to be checked
Satisfactory Unsatisfactory N/A
12
α =
Total Number --- β=
Percentage γ = α / (12-β) *100% =
a b c d e
‐ 125 ‐
Supervision and Contract Evaluation Manual for Road Works
Contract Evaluation Grading Sheet for QAO/IAC (3/3)
Item 6. Quality and quantity management
Description Measured parameters are within the specified allowable ranges with proper workmanship
All necessary scale measurements Although some of the necessary scale Nevertheless a corrective order was
are conducted and recorded as measurements were not conducted as issued, the Contractor did not comply
Quantity specified, and all measured specified, the contractor complied with a with it.
Measurements parameters are within the specified corrective order
allowable range
All necessary quality measurements Although some of the necessary quality Nevertheless a corrective order were
are conducted and recorded as measurements were not conducted as issued, the Contractor did not comply
Quality specified, and all measured figures specified, the Contractor complied with a with it.
Measurements are within the specified allowable corrective order
range
Check (✓)
Sub-sub item Check Point
Satisfactory Unsatisfactory N/A
a) Good 1 Good exterior appearance
appearance of
2 Good alignment and spacing
finished work
3 Good overall surface alignment
γ = 100 - 80.1% γ = 80.0 - 60.1% γ = 60.0% - 40.1% γ = 40.0 - 20.1% γ = 20.0 - 0.0%
Z 4.0 3.0 2.0 1.0 0.0
Total Point : X + Y + Z =
Ranges 10.00 - 7.51 7.50 - 5.01 5.00 - 2.51 2.50 - 0.01 0.0
Grade a b c d e
‐ 126 ‐
Contract Evaluation Score Tally Sheet (Large scale work by Class A, B, C, and D companies)
Project Title Date of Commencement
Contract Number Completion Date
Quality Assurance Office/
Resident Engineer The Engineer's Representative
Inspection and Acceptance Committee
weight by
weight by
weight by
Inter‐item
Inter‐item
Inter‐item
weights w1
weights w1
weights w1
evaluator w2
evaluator w2
evaluator w2
Net Score p = w1 x w2 x p0 Net Score p = w1 x w2 x p0 Net Score p = w1 x w2 x p0
Work procedures are in accordance with Works Execution Programme that 6.00 4.50 3.00 1.50 0.00
1.2 0.5
1. Execution System in properly reflects given conditions. 6.0
14.0
General Overall execution system is confirmed to be proper during audit or at 8.00 6.00 4.00 2.00 0.00
4.0 0.2
Substantial completion meeting 8.0
‐ 127 ‐
Site facilities are properly prepared, maintained during execution, and 5.00 3.75 2.50 1.25 0.00
5. Site base facilities 1.0 0.5 5.0
F.4 Contract Evaluation Tally Sheet (Large scale work)
cleared on completion. 5.0
Material testing, structural examination, and measurements are properly
and routinely conducted. Results are within the specifications and 1.0 0.5
6. Quality and quantity 5.0
compiled for checking. 17.0
management
Measured parameters are within the specified allowable ranges with 12.00 9.00 6.00 3.00 0.00
6.0 0.2
proper workmanship 12.0
8. Work safety Necessary measures are taken for safety of workers, operators, and third 5.00 3.75 2.50 1.25 0.00 3.00 1.50 0.00
1.0 0.5 1.0 0.3 8.0
management party. No serious accident occurs during the contract period. 5.0 3.0
9. Environmental and Environmental and social issues caused by the works are minimized and 5.00 3.75 2.50 1.25 0.00 3.00 1.50 0.00
1.0 0.5 1.0 0.3 8.0
social management mitigated properly 5.0 3.0
Innovation effort is made by using new materials, new technology, process 0 ‐ +10
10. Innovation effort 0
rationalization, etc.
0 ‐ ‐10
11. Compliance with statutory requirements 0
Signature
Grand Total 100.00 Date
(The Engineer)
Contract Evaluation Score Tally Sheet (Small scale work by Class E and Under Companies)
Project Title Date of Commencement
Contract Number Completion Date
Contractor Company Class Date of Substantial Completion Meeting
Contract Sum Scoring Date
Quality Assurance Office/
Resident Engineer The Engineer's Representative
Inspection and Acceptance Committee
weight by
weight by
weight by
Inter‐item
Inter‐item
Inter‐item
weights w1
weights w1
weights w1
evaluator w2
evaluator w2
evaluator w2
Net Score p = w1 x w2 x p0 Net Score p = w1 x w2 x p0 Net Score p = w1 x w2 x p0
Work procedures are in accordance with Works Execution Programme that 5.00 3.75 2.50 1.25 0.00
1.0 0.5
1. Execution System in properly reflects given conditions. 5.0
13.0
General Overall execution system is confirmed to be proper during audit or at 8.00 6.00 4.00 2.00 0.00
4.0 0.2
Substantial completion meeting 8.0
4. Personnel Reasonable number of skilled workers/operators is properly employed by 7.00 5.25 3.50 1.75 0.00 9.00 4.50 0.00
1.4 0.5 3.0 0.3 16.0
‐ 128 ‐
employment the contractor 7.0 9.0
8. Work safety Necessary measures are taken for safety of workers, operators, and third 5.00 3.75 2.50 1.25 0.00 6.00 3.00 0.00
1.0 0.5 2.0 0.3 11.0
management party. No serious accident occurs during the contract period. 5.0 6.0
9. Environmental and Environmental and social issues caused by the works are minimized and 5.00 3.75 2.50 1.25 0.00 6.00 3.00 0.00
1.0 0.5 2.0 0.3 11.0
social management mitigated properly 5.0 6.0
Innovation effort is made by using new materials, new technology, process
10. Innovation effort
rationalization, etc.
0 ‐ ‐10
11. Compliance with statutory requirements 0
0
Signature
Grand Total 100.00 Date
(The Engineer)
Contract Evaluation Score Tally Sheet (Labour based)
Project Title Date of Commencement
Contract Number Completion Date
Contractor Company Class Date of Substantial Completion Meeting
Contract Sum Scoring Date
Quality Assurance Office/
Resident Engineer The Engineer's Representative
Inspection and Acceptance Committee
weight by
weight by
weight by
Inter‐item
Inter‐item
Inter‐item
weights w1
weights w1
weights w1
evaluator w2
evaluator w2
evaluator w2
Net Score p = w1 x w2 x p0 Net Score p = w1 x w2 x p0 Net Score p = w1 x w2 x p0
Work procedures are in accordance with Works Execution Programme that 6.00 4.50 3.00 1.50 0.00
1.2 0.5
1. Execution System in properly reflects given conditions. 6.0
14.0
General Overall execution system is confirmed to be proper during audit or at 8.00 6.00 4.00 2.00 0.00
4.0 0.2
Substantial completion meeting 8.0
All equipments used in the works are mobilised properly and well‐
2. Equipment holding
maintained
9.00 6.75 4.50 2.25 0.00
3. In‐house staff The qualified technical engineers and in‐house staffs are assigned 1.8 0.5 9.0
9.0
4. Personnel Reasonable number of skilled workers/operators is properly employed by 11.00 8.25 5.50 2.75 0.00 12.00 6.00 0.00
2.2 0.5 4.0 0.3 23.0
employment the contractor 11.0 12.0
‐ 129 ‐
Site facilities are properly prepared, maintained during execution, and
5. Site base facilities
cleared on completion.
F.6 Contract Evaluation Tally Sheet (Labour-based work)
8. Work safety Necessary measures are taken for safety of workers, operators, and third 6.00 4.50 3.00 1.50 0.00 9.00 4.50 0.00
1.2 0.5 3.0 0.3 15.0
management party. No serious accident occurs during the contract period. 6.0 9.0
9. Environmental and Environmental and social issues caused by the works are minimized and 6.00 4.50 3.00 1.50 0.00 9.00 4.50 0.00
1.2 0.5 3.0 0.3 15.0
social management mitigated properly 6.0 9.0
Innovation effort is made by using new materials, new technology, process
10. Innovation effort
rationalization, etc.
0 ‐ ‐10
11. Compliance with statutory requirements 0
0
Signature
Grand Total 100.00 Date
(The Engineer)
Supervision and Contract Evaluation Manual for Road Works
Official Letter Head
REF :
DATE :
To :
CONTRACT NAME:………………………………………………………………..
‐ 130 ‐
Supervision and Contract Evaluation Manual for Road Works
Official Letter Head
REF :
DATE :
To :
CONTRACT NAME:………………………………………………………………..
‐ 131 ‐
Supervision and Contract Evaluation Manual for Road Works
Official Letter Head
REF :
DATE :
To :
CONTRACT NAME:………………………………………………………………..
Item
Scores Allocation
Execution System in General 14.0
In‐house staff 9.0
Personnel employment 23.0
Quality and quantity management 18.0
Work scheduling 6.0
Work safety management 15.0
Environmental and social management 15.0
Subtotal 100.0
Compliance with statutory requirements ‐10 ‐ 0
Grand Total 100.0
‐ 132 ‐
Supervision and Contract Evaluation Manual for Road Works
Official Letter Head
CONTRACT NAME:………………………………………………………………..
EMPLOYER ENGINEER CONTRACTOR
(Authority Name) General Manager (Dept. Name) (Contractor)
Thro’ General Manager (Dept. Name) (Authority Name) (Company Name)
(Authority P.O. Box) (Authority P.O. Box) (Company P.O.Box)
NAIROBI. NAIROBI. (Name of Town)
Pursuant to Clause 48 of the Conditions of Contract, it is hereby certified that the Contractor has finally completed the works
detailed above to the satisfaction of the Engineer. Inspection of these works was carried out on …………… by
representatives of the Employer, the Engineer’s Representative, and the Contractor.
‐ 133 ‐
Supervision and Contract Evaluation Manual for Road Works
I Database Format
Authority KeNHA … … … …
Region Central … … … …
Routine Maintenance of
Name of the Contract … … … …
AAA BBB (C##) Road
Contract
Information
Contract Number RD### … … … …
Date of Commencement 2010/09/23 … … … …
Completion Date 2011/10/26 … … … …
Date of Sibstantial Completion Meeting 2011/12/01 … … … …
Contract Sum Ksh181,268,560‐ … … … …
Contractor's Name ABC Company … … … …
Company
Class C … … … …
Information
PIN Code ####### … … … …
1. Execution System in General 10.50 … … … …
2. Equipment holding 9.75 … … … …
3. In‐house staff 9.75 … … … …
4. Personnel employment 3.75 … … … …
5. Site base facilities 3.75 … … … …
6. Quality and quantity management 14.50 … … … …
Score
7. Work scheduling 9.75 … … … …
8. Work safety management 5.25 … … … …
9. Environmental and social management 4.00 … … … …
10. Innovation effort 4.00 … … … …
11. Compliance with statutory requirement 0.00 … … … …
Total 69.75 … … … …
4. Site clearance and Topsoil Stripping ✽ … … … …
5. Earth works ✽ … … … …
7. Excavation and Filing for Structures ✽ … … … …
8‐1. Ditch and Culvert Cleaning ✽ … … … …
8‐2. Culvert installation and construction ‐‐‐ … … … …
9. Passage of Traffic ‐‐‐ … … … …
10. Grading and Gravelling Works ‐‐‐ … … … …
13. Graded Crushed Stone Base and Subbase ✽ … … … …
14. Cement and Lime Treated Subgrade, Subbase, and Base ✽ … … … …
15. Bituminous Surface Treatment and Surface Dressing ‐‐‐ … … … …
16. Bituminous Mixes ✽ … … … …
17. Concrete Works ✽ … … … …
20. Road Furnitures and Maintenance ✽ … … … …
‐ 134 ‐
Numbers of Contracts by Work Types
Company Information Total Scores in Contract Evaluation
2012 ‐ 2016
CLASS
Name Code
Alphabet
Scores AVE. Scores AVE. Scores AVE. Scores AVE. Scores AVE.
4. Site clearance and Topsoil Stripping
5. Earth works
7. Excavation and Filing for Structures
8‐1. Ditch and Culvert Cleaning
8‐2. Culvert installation and construction
9. Passage of Traffic
10. Grading and Gravelling Works
11. Paved Roads ‐ Shoulder Maintenance and Repairs
12. Natural Material Base and Subbase
13. Graded Crushed Stone Base and Subbase
14. Cement and Lime Treated Subgrade, Subbase, and Base
15. Bituminous Surface Treatment and Surface Dressing
16. Bituminous Mixes
17. Concrete Works
20. Road Furnitures and Maintenance
A A AA1 Company Ltd. 15274 65 65 68 68 64 64 58 65 62 69 69 1 2 5 6 5 5 2 5 5 3
A A AB1 Company Ltd. 31489 71 74 73 68 68 65 73 69 75 75 71 68 70 1 1 6 4 1 3 3 6 6 2 1
A … …
A Z ZZ1 Company Ltd. 56304 76 64 71 70 66 68 72 69 69 69 71 74 73 71 72 72 1 3 5 3 1 5 6 3 5 7 5 11 4
B A AA2 Company Ltd. 73190 73 67 75 72 69 76 64 72 70 72 69 75 72 66 65 64 65 65 67 66 3 5 5 2 5 4 7 10 7 10 5 5 14 4 3
‐ 135 ‐
B A AB2 Copany Ltd. 67845 65 65 58 58 1 1 2 1 1 1 1 1 1 2 1
B … …
B Z ZZ2 Company Ltd. 34582 54 58 56 58 61 55 58 57 59 58 54 54 4 1 4 3 4 4 3 2 3 2 8 4 2
I.2 Integrated Contract Evaluation Database Format
Supervision and Contract Evaluation Manual for Road Works
C A AA3 Company Ltd. 75618 78 72 75 73 71 69 71 65 68 67 70 70 1 1 2 6 4 2 3 3 8 1
C A AB3 Company Ltd. 52356 72 72 70 70 68 68 65 65 1 2 2 2 1 4 4 2 3 1 2 4 4 1
C … …
C Z ZZ3 Company Ltd. 32659 67 78 63 69 66 66 75 71 68 71 67 66 63 65 5 7 5 3 10 3 4 4 4 7 7 5 10 8 2
D A AA4 Company Ltd. 72190 71 68 72 74 71 75 69 67 70 70 68 75 72 74 72 67 66 74 72 70 69 74 67 72 71 17 12 10 20 15 6 3 5 3 2
D A AB4 Company Ltd. 43275 65 65 67 68 68 64 68 66 3 4 4 3 3 3 1
D … …
D Z ZZ4 Company Ltd. 36486 54 54 57 57 57 57 53 53 2 4 1 2 2 1
E A AA5 Company Ltd. 63891 56 62 63 60 58 53 56 68 65 58 61 63 56 67 71 65 65 64 59 54 67 61 17 5 5 11 2 5
E A AB5 Company Ltd. 47819 68 68 65 65 63 63 67 67 4 1 4
E … …
E Z ZZ5 Company Ltd. 74278 75 64 71 70 66 68 72 69 69 69 71 74 73 71 72 72 11 3 3 1 3
F A AA5 Company 83591 56 63 68 62 57 62 60 58 71 64 68 65 73 62 65 59 65 64 58 73 69 66 17 2 1 12 3
F A AB5 Company 24057 55 55 54 54 56 56 58 58 4 1 4
F … …
F Z ZZ5 Company 58903 64 58 70 64 66 68 72 69 69 69 71 74 73 71 72 72 11 3 7