Practice - Working with Enforce Demand Due Date Plans

Distribution
Oracle Advanced Supply Chain Planning

Job Title*

Ownership
The Job Title [list@YourCompany.com?Subject=LAB3EB7Y] is responsible for ensuring that
this document is necessary and that it reflects actual practice.

Copyright © Oracle Corporation, 2003. All rights reserved.

Practice - Working with Enforce Demand Due Date Plans 439925741.doc


Effective 07/04/02 Page 1 of 5 Rev 1
Practice - Working with Enforce Demand Due Date Plans
Please mention lab identifier 3EB7 in course evaluation comments.

Overview
This practice covers working with enforce demand due date plans.

Tasks
Responsibility: Advanced Supply Chain Planner

Instance:Organization = TST:M1

Make a Copy of the EDD Plan

1. Navigate to the Supply Chain Plan Names form.

2. Select plan 00_EDD.

3. Navigate to the Copy Plan form.

4. Enter the information to copy the plan in the Destination region:

Work With the EDD Plan

5. Navigate to Planner Workbench Navigator.

6. In the Navigator, select the Plans tabbed region.

7. View By = Actions

8. Expand directory Plans

9. Multi-select plans XX_ECC and XX_EDD.

10. Navigate to the right-click menu and select Exceptions > Summary. Note the columns Plan
and Version.

11. Look at the exception messages in exception groups Late Sales Orders and Forecasts and
Material and Resource Capacity Exceptions. How might they differ by plan?

12. View Constrained - Enforce demand due dates exception message Sales order/forecast at
risk.

13. View one Resource overloaded exception message.

Copyright © Oracle Corporation, 2003. All rights reserved.

Practice - Working with Enforce Demand Due Date Plans 439925741.doc


Effective 07/04/02 Page 2 of 5 Rev 1
Solution – Working with Enforce Demand Due Date Plans
Responsibility: Advanced Supply Chain Planner

Instance:Organization = TST:M1

Make a Copy of the EDD Plan

1. Navigate to the Supply Chain Plan Names form.


 (N) Supply Chain Plan > Names

2. Select plan 00_EDD.

3. Navigate to the Copy Plan form.


 (B) Copy Plan

4. Enter the information to copy the plan in the Destination region:


 Name = XX_EDD
 Description = Enforce demand due dates plan
 Plan Type = Manufacturing Plan

Work With the EDD Plan

5. Navigate to Planner Workbench Navigator.

6. In the Navigator, select the Plans tabbed region.

7. View By = Actions

8. Expand directory Plans

9. Hold down the shift key, and multi-select plans XX_ECC and XX_EDD.

10. Navigate to the right-click menu, and then select Exceptions > Summary.

 The Actions window appears.

Copyright © Oracle Corporation, 2003. All rights reserved.

Practice - Working with Enforce Demand Due Date Plans 439925741.doc


Effective 07/04/02 Page 3 of 5 Rev 1
Notes:

 Note the columns Plan and Version.

11. Look at the exception messages in exception groups Late Sales Orders and Forecasts and
Material and Resource Capacity Exceptions. How might they differ by plan?
 The EDD plan has Sales order/forecast at risk exception messages (with resource
and supplier capacity overloaded, end demands are at risk of being late if you can’t
resolve the constraints); the ECC plan has Late replenishment for sales order and
Late replenishment for forecast exception messages (with resource and supplier
capacity respected, end demand fulfillment is scheduled late).
 The EDD plan has Resource overloaded and Supplier capacity overloaded exception
messages (by respecting demand due dates, it overloads resource and supplier
capacity); the ECC plan has Resource constraint and Material constraint exception
messages (the planning engine reaches the limits on the resource and supplier
capacities, it begins to push out end demand due dates).

Copyright © Oracle Corporation, 2003. All rights reserved.

Practice - Working with Enforce Demand Due Date Plans 439925741.doc


Effective 07/04/02 Page 4 of 5 Rev 1
12. View Constrained - Enforce demand due dates (Plan Name: XX_EDD) exception message
Sales order/forecast at risk.
 (N) Supply Chain Plan > Workbench
 Navigate to the Navigator
 Select tab Plans
 View By = Actions
 Expand directory Plans
 Select plan XX_EDD
 Expand version Current
 Expand exception group Late Sales Orders and Forecasts
 Expand exception message Sales order/forecast at risk
 Expand an organization
 Right-click an item and click icon Exceptions

13. View one Resource overloaded exception message.


 (N) Supply Chain Plan > Workbench
 Navigate to the Navigator
 Select tab Plans
 View By = Actions
 Expand directory Plans
 Expand plan XX_EDD through the directories to exception message Resource
overloaded, right-click it, and select Exceptions > Summary
 Double-click Resource overloaded
 Select an exception message (not the first one) and note its Start Constraint Date and
End Constraint Date
 Right-click the same exception message and select Horizontal Plan
 Scroll to the constrained dates referenced in the exception message
 Note the overload (Net hours available)

Copyright © Oracle Corporation, 2003. All rights reserved.

Practice - Working with Enforce Demand Due Date Plans 439925741.doc


Effective 07/04/02 Page 5 of 5 Rev 1