Rencana Anggaran Biaya (RAB)

Proyek : Rumah 1 Unit


Lokasi : Indonesia

SATUAN VOLUME HARGA SAT. JUMLAH HARGA


NO. URAIAN PEKERJAAN
[SAT.] [VOL.] [Rp.] [Rp.]
A PEKERJAAN PENDAHULUAN
1 Pek. Pengukuran / Pas. Bouwplank m1 18.00 91,760 1,651,680
2 Pek. Penyediaan Air Kerja Ls 1.00 5,000,000 5,000,000
3 Penyediaan Gudang / Direksi Keet / Pagar Proyek Ls 1.00 20,000,000 20,000,000
SUB-TOTAL [Rp.] 26,651,680
B PEKERJAAN PONDASI
1 Pek. Galian Pondasi Setempat (PS) M3 50.70 46,200 2,342,340
2 Pek. Galian Sloof S1 20/40 M3 16.72 46,200 772,464
3 Pek. Urugan Pasir dibawah PS M3 1.95 128,700 250,965
4 Pek. Cor Tapak Pondasi 30x120x130 M3 11.70 3,671,350 42,954,795
5 Pek. Stik Kolom 20/40 M3 2.00 3,671,350 7,342,700
SUB-TOTAL [Rp.] 53,663,264
C PEKERJAAN STRUKTUR
1 Pek. Sloof S1 20/40 M3 16.72 dst… dst…
2 Pek. Kolom K1 15/40 M3 6.00 dst… dst…
3 Pek. Kolom Praktis K2 15/15 M3 2.88 dst… dst…
4 Pek. Balok Gantung Pintu Depan 15/25 M3 0.23 dst… dst…
5 Pek. Plat Beton Pintu Depan, tebal 10cm M3 0.74 dst… dst…
6 Pek. Cor Rabat Lantai M3 16.80 dst… dst…
SUB-TOTAL [Rp.] dst…
D PEKERJAAN DINDING BATA
1 Pek. Pas. Dinding 1/2 Bata Camp. 1:4 M2 706.67 dst… dst…
2 Pek. Plesteran dan Aci 1:4 M2 1,413.34 dst… dst…
SUB-TOTAL [Rp.] dst…
E PEK. KUSEN, PINTU, JENDELA, DAN AKSESORIS
1 Pek. Kusen & Pintu Utama (Pintu 2 Daun) Unit 4.00 dst… dst…
2 Pek. Kusen & Pintu Belakang (Pakai Jalusi Kayu) Unit 4.00 dst… dst…
3 Pek. Kusen & Pintu K.Tidur Unit 8.00 dst… dst…
4 Pek. Pintu Fiber Sisir KM [tanpa kozen] Unit 4.00 dst… dst…
5 Pek. Kusen & Daun Jendela Kaca Depan Unit 4.00 dst… dst…
6 Pek. Kusen & Jendela Kaca Nako Belakang (Pakai Jalusi Kayu) Unit 4.00 dst… dst…
SUB-TOTAL [Rp.] dst…
F PEKERJAAN INSTALASI LISTRIK
1 Pek. Instalasi Titik Lampu & Stop Kontak Ttk 64.00 dst… dst…
2 Pek. Pas. Saklar Bh 36.00 dst… dst…
3 Pek. Pas. Stop Kontak Set 28.00 dst… dst…
4 Pek. Panel box Unt 4.00 dst… dst…
SUB-TOTAL [Rp.] dst…
G PEKERJAAN SANITAIR
1 Pek. Instalasi Air Bersih [Pipa PVC 3/4" dan 1/2"] M' 104.00 dst… dst…
2 Pek. Instalasi Air Kotor K.Mandi, Dapur, Air Hujan [Pipa PVC Ø3"] M' 154.00 dst… dst…
3 Pek. Instalasi Air Buangan Closet [Pipa PVC Ø4"] M' 48.00 dst… dst…
4 Pek. Septick tank Unt 4.00 dst… dst…
SUB-TOTAL [Rp.] dst…
H PEKERJAAN ATAP BETON
1 Pek. Balok Gantung 25/50 M3 10.00 dst… dst…
2 Pek. Balok Duduk 20/40 M3 6.00 dst… dst…
3 Pek. Cor Plat Beton (tbl. 10 cm) M3 24.00 dst… dst…
4 Pek. Kolom Praktis K2 15/15 (Pagar Keliling Atap) M3 0.56 dst… dst…
5 Pek. Pas. Dinding 1/2 Bata Camp. 1:4 M2 85.60 dst… dst…
6 Pek. Plesteran dan Aci Bata 1:4 M2 214.00 dst… dst…
7 Pek. Plesteran dan Aci Lantai Atap 1:4 M2 240.00 dst… dst…
8 Pek. Floor Drain M2 12.00 dst… dst…
SUB-TOTAL [Rp.] dst…
I PEKERJAAN FINISHING
1 Pek. Keramik Lantai (Keramik 40x40) M2 240.00 dst… dst…
2 Pek. Keramik K.Mandi Unit 4.00 dst… dst…
3 Pek. Meja Dapur dan Pas. Keramik Unit 4.00 dst… dst…
4 Pek. Plafon M2 240.00 dst… dst…
5 Pek. Finishing Plesteran Motif Tpk. Depan Unit 4.00 dst… dst…
6 Pek. Cat Dinding Luar M2 500.60 dst… dst…
7 Pek. Cat Dinding Dalam dan Plafon M2 1147.20 dst… dst…
8 Pek. Cat Kusen, Daun Pintu, dan Daun Jendela Unit 28.00 dst… dst…
SUB-TOTAL [Rp.] dst…
TOTAL [Rp.] 80,314,944
Indonesia, 7 Juli 2014
Dibuat Oleh:

proyeksipil.blogspot.com
BOBOT
[%]

0.00
Juli 2014

ogspot.com
No. Activity Value [Rp.]

A Preliminaries Rp. 100,000,000.00


B Foundation Rp. 500,000,000.00
C Structure Rp. 400,000,000.00
D Shell Rp. 400,000,000.00
E Electrical Rp. 100,000,000.00
F Sanitery Rp. 200,000,000.00
G Exteriors Rp. 100,000,000.00
H Interiors Rp. 200,000,000.00
I Finishing Rp. 200,000,000.00

TOTAL Rp. 2,200,000,000.00


Weight Activity

Amount
BOBOT
NO Activity Value
(RP.) (%)
A Preliminaries 100,000,000.00 4.55
B Foundation 500,000,000.00 22.73
C Structure 400,000,000.00 18.18
D Shell 400,000,000.00 18.18
E Electrical 100,000,000.00 4.55
F Sanitery 200,000,000.00 9.09
G Exteriors 100,000,000.00 4.55
H Interiors 200,000,000.00 9.09
I Finishing 200,000,000.00 9.09
JUMLAH = 2,200,000,000.00 100.00
Amount WAKT
BOBOT
NO Activity Value MARET 2017
(RP.) (%) 1 2 3
A Preliminaries 100,000,000.00 4.55 2.27 2.27

B Foundation 500,000,000.00 22.73 7.58

C Structure 400,000,000.00 18.18

D Shell 400,000,000.00 18.18

E Electrical 100,000,000.00 4.55

F Sanitery 200,000,000.00 9.09 BAR-CHART


Exteriors
G 100,000,000.00 4.55

H Interiors 200,000,000.00 9.09

I Finishing 200,000,000.00 9.09

Amount = 2,200,000,000.00 100.00


RENCANA PROGRESS MINGGUAN (%) = 0.00 2.27 2.27 7.58
RENCANA PROGRESS KOMULATIF (%) = 0.00 2.27 4.55 12.12
WAKTU PELAKSANAAN PEKERJAAN = 4 BULAN
ARET 2017 APRIL 2017 MEI 2017 JUNI 2017 KET.
4 1 2 3 4 1 2 3 4 1 2 3 4

7.58 7.58

4.55 4.55 4.55 4.55

4.55 4.55 4.55 4.55

0.76 0.76 0.76 0.76 0.76 0.76

R-CHART 1.30 1.30 1.30 1.30 1.30 1.30 1.30

0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57

1.82 1.82 1.82 1.82 1.82

1.82 1.82 1.82 1.82 1.82

7.58 12.12 9.85 9.85 11.72 8.99 4.44 4.44 5.50 5.50 3.69 2.39 1.82
19.70 31.82 41.67 51.52 63.23 72.22 76.66 81.10 86.61 92.11 95.80 98.18 100.0
Amount WAKT
BOBOT
NO Activity Value MARET 2017
(RP.) (%) 1 2 3
A Preliminaries 100,000,000.00 4.55 2.27 2.27

B Foundation 500,000,000.00 22.73 7.58

C Structure 400,000,000.00 18.18

D Shell 400,000,000.00 18.18

E Electrical 100,000,000.00 4.55

F Sanitery 200,000,000.00 9.09 KURVA-S


G Exteriors 100,000,000.00 4.55

H Interiors 200,000,000.00 9.09

I Finishing 200,000,000.00 9.09

JUMLAH = 2,200,000,000.00 100.00


Planned Progress Weekly (%) = 0.00 2.27 2.27 7.58
Planned Progress Cumulative (%) = 0.00 2.27 4.55 12.12

Realization Progress Weekly (%) 0.00


Realization Progress Cumulative (%) = 0.00

Deviation Weekly (%) = 0.00


Deviation Cumulative (%) = 0.00
WAKTU PELAKSANAAN PEKERJAAN = 4 BULAN
ARET 2017 APRIL 2017 MEI 2017 JUNI 2017 KET.
4 1 2 3 4 1 2 3 4 1 2 3 4
100

7.58 7.58
80
4.55 4.55 4.55 4.55

4.55 4.55 4.55 4.55


60
0.76 0.76 0.76 0.76 0.76 0.76

KURVA-S 1.30 1.30 1.30 1.30 1.30 1.30 1.30 40

0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57

1.82 1.82 1.82 1.82 1.82 20

1.82 1.82 1.82 1.82 1.82


0

7.58 12.12 9.85 9.85 11.72 8.99 4.44 4.44 5.50 5.50 3.69 2.39 1.82
19.70 31.82 41.67 51.52 63.23 72.22 76.66 81.10 86.61 92.11 95.80 98.18 100.0