Professional Documents
Culture Documents
Municipality of Sindangan
OFFICE OF THE MUNICIPAL ENGINEER
Labor
Designation No.of Person No.of Days Daily Rate Total
a. Skilled Worker 3.00 19.00 500.00 28,500.00
b. Unskilled Worker 6.00 19.00 400.00 45,600.00
sub-total 74,100.00
Prepared by: Checked and Review by: Recommending Approval by: Approved by:
ENGR.FRANCIS ANGELIE R. RELUYA ENGR. JOSE G. CABAÑOG Jr. ENGR. BONNIE D. MOLINA HON. ROSENDO "Dodoy" S. LABADLABAD
Engineering Staff Engineer II Municipal Engineer Municipal Mayor
Province of Zamboanga del Norte
MUNICIPALITY OF SINDANGAN
OFFICE OF THE MUNICIPAL ENGINEER
PROGRAM OF WORKS
Date:
Name/Location of Project : Appropriation : 530,000.00
CONST./ REHAB/ IMPROV. OF MUN. BLDG. Source of Fund :
(PUBLIC MARKET COMMUNAL TOILET)
Poblacion, Sindangan, Zamboanga del Norte
Authority Release
Project Category : Calendar Days to Complete : 44.00
Building Desirable Starting Date : Upon Approval
Contract/Administration : by Admin.
Project Description :
72.00 sq.m. Tile Works
86.40 sq.m. Ceiling Works
Plumbing Works
I. ESTIMATED COST
A. DIRECT COST
1. Materials 74.80% 396,426.20
2. Labor (including fringe benefits) 24.30% 128,800.00
3. Equipment Expenses
4. Contingencies 0.90% 4,773.80
Prepared by : Approved by :
PURCHASE REQUEST
Municipality of Sindangan
LGU
Department : MEO PR No. : Date :
SAI No.: Date :
Section: ALOBS No. : Date :
OK AS TO APPROPRIATION :
BOBBY S. MAMUGAY
Municipal Budget Officer
Purpose : CONST./ REHAB/ IMPROV. OF MUN. BLDG. (PUBLIC MARKET COMMUNAL TOILET)
Location : Poblacion, Sindangan, Zamboanga del Norte
Charge to:
Signature :
Printed Name : ENGR. BONNIE D. MOLINA GRACE MAE S. ALIP HON. ROSENDO "Dodoy" S. LABADLABAD
Designation : Municipal Engineer OIC-Municipal Treasurer Municipal Mayor
Republic of the Philippines
PROVINCE OF ZAMBOANGA DEL NORTE
Municipality of Sindangan
Function/Project/Activity: CONST./ REHAB/ IMPROV. OF MUN. BLDG. (PUBLIC MARKET COMMUNAL TOILET)
Location: Poblacion, Sindangan, Zamboanga del Norte
Dept./Office/Unit: : MEO
Source of Fund: :
SCHEDULE/MILESTONE OF ACTIVITIES
CODE GENERAL DESCRIPTION QUANTITY SIZE
ESTIMATED BUDGET Jan. Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Tiles 0.60x0.60 200.00 pcs 49,400.00
2 Tile Adhessive 40.00 pcks 18,000.00
3 Portland Cement 100.00 bags 30,000.00
4 Faucet (Shark) Plastic 4.00 pcs. 2,200.00
5 Floor Drain 15X15 cm 4.00 pcs. 1,200.00
6 Floor Drain 10x10 cm 2.00 pcs. 500.00
7 Bedit 10.00 pcs. 10,000.00
8 PPR Pipe #1 10.00 lengths 11,500.00
9 PPR Pipe #1/2 25.00 lengths 18,900.00
10 PPR Pipe #3/4 2.00 lengths 1,900.00
11 PPR Gate Valve #1 5.00 pcs. 2,550.00
12 PPR Gate Valve #1/2 5.00 pcs. 1,570.00
13 PPR Elbow #1 20.00 pcs. 1,060.00
14 PPR Elbow #1/2 70.00 pcs. 2,870.00
15 PPR Elbow w/ Thread 1/2 25.00 pcs. 5,000.00
16 PPR Tee #1 10.00 pcs. 770.00
17 PPR Tee #1/2 20.00 pcs. 1,060.00
18 PPR Elbow #3/4 10.00 pcs. 360.00
19 PPR Tee #3/4 5.00 pcs. 216.00
20 PPR Coupling Reducer 1x 1/2 6.00 pcs. 2,712.00
21 PPR Coupling Reducer 1x 3/4 2.00 pcs. 962.00
22 PPR Coupling #1 10.00 pcs. 300.00
23 PPR Coupling #1/2 20.00 pcs. 400.00
24 PPR Tee w/ Thread 1/2 20.00 pcs. 4,000.00
25 Angle Valve 1/2 x 1/2 (Shark) 20.00 pcs. 7,000.00
26 Flexible Hose 1/2 x 1/2 15.00 pcs. 23,520.00
27 Teflon 3/4 20.00 pcs. 627.20
28 Polyetelene Hose #1 1.00 roll 71.00
29 Compression tee 1x1 4.00 pcs. 1,120.00
30 Compression Coupling 5.00 pcs. 925.00
31 Sanitary Pipe #4 (S-1000) 10.00 lengths 10,080.00
32 Sanitary Pipe #2 (S-1000) 10.00 lengths 3,100.00
33 Sanitary Elbow #4x 90 30.00 pcs. 4,050.00
34 Sanitary Elbow #4x 45 30.00 pcs. 4,050.00
35 Sanitary Wye # 4x4 15.00 pcs. 3,705.00
36 Sanitary Tee # 4x4 6.00 pcs. 1,482.00
37 Sanitary Wye # 4x2 6.00 pcs. 1,080.00
38 Sanitary Tee # 4x2 4.00 pcs. 672.00
39 Sanitary Clean Out #4 4.00 pcs. 540.00
40 Sanitary P-Trap #4 4.00 pcs. 1,128.00
41 Sanitary Elbow 2x90 30.00 pcs. 1,680.00
42 Sanitary Elbow 2x45 25.00 pcs. 1,125.00
43 Sanitary Wye 2x2 5.00 pcs. 725.00
44 Sanitary Tee 2x2 6.00 pcs. 480.00
45 Sanitary P-Trap 2x2 8.00 pcs. 960.00
46 Solvent 25.00 cans 7,850.00
47 Adjustable Leg Foot 3/4 30.00 pcs. 11,760.00
48 Indicator Lock 7.00 set 1,260.00
49 Hook Hanger 7.00 pcs. 784.00
50 Hinges 15.00 pcs. 8,745.00
51 Knob Handle 7.00 set 1,260.00
52 Corner Bracket 112.00 pcs. 8,176.00
53 12mm x 3m Channel Top Rail 4.00 lengths 3,360.00
54 Marine Melamine 3/4 20.00 pcs. 64,960.00
55 4.5mm Cement Board (Gardner) 30.00 pcs. 19,500.00
56 Blind Revits 1/2 2.00 box 1,000.00
57 Blind Revits 3/4 2.00 box 1,100.00
58 Drill Bit 1/8 2.00 box 200.00
59 Cutting Disc (Nitavo) 25.00 pcs. 3,250.00
60 Welding Rod 2.5 kgs. 5.00 box 1,385.00
61 Reviter 2.00 pcs. 800.00
62 Wall Angle Metal Furring 0.4mm x 25mm x 3m 20.00 pcs. 1,700.00
63 Silicone Sealant Clear 10.00 pcs. 2,800.00
64 Tex Screw 2" 500.00 pcs. 1,500.00
65 1½" dia. X 6.0m Stainless Steel Pipe, 1.5mm 2.00 lenghts 4,704.00
66 1½" dia Stainless Steel Flange w/ cover 2.00 pcs. 1,232.00
67 1 1/2" dia SS End Pipe Holder (disc type) 4.00 pcs. 944.00
68 Screw w/ Toks 30.00 pcs. 210.00
69 WeldIng Rod Stainless Steel 10.00 kgs. 8,400.00
70 Cutting Disc (Nitavo) 30.00 pcs. 3,900.00
71 Grinding Stone 1.00 pcs. 96.00
72 Labor Cost: 1.00 l.s. 128,800.00
73 Contingencies: 1.00 l.s. 4,773.80
Total: 530,000.00
NOTE: Technical Specification for each Item / Project being proposed shall be submitted as part of the PPMP
ENGR. FRANCIS ANGELIE R. RELUYA ENGR. BONNIE D. MOLINA BOBBY S. MAMUGAY HON. ROSENDO "Dodoy"S. LABADLABAD
Engineering Staff Municipal Engineer Municipal Budget Officer Municipal Mayor