You are on page 1of 1

RESUME PROGRESS BG RAMP CIKUNIR

UPDATE : 05 Agustus 2019

STATUS PROGRESS BG RAMP CIKUNIR

BENTANG FINISHING PLAN BG ACT BG MINUS BG %


ON FINISH TRIAL READY TO ON FINISH FINISH READY TO OK
PAINTING REPAIR BOX
FABRIKASI FABRIKASI ERECTION BLASTING BLASTING BLASTING COATING SITE DELIVERY
(LAYER 1&2)
100 S2 1 1 7 0 1 6 0 0 0 0 0 16 16 0 100,0%
105 S1 0 0 6 2 1 1 0 1 0 0 5 16 16 0 100,0%
105 S2 0 0 8 0 0 2 2 2 0 0 2 16 16 0 100,0%
108 S1 0 0 8 0 0 5 1 0 0 0 2 16 16 0 100,0%
120 S6 0 0 11 2 0 1 2 0 0 0 2 18 18 0 100,0%
165 S1 0 0 0 0 0 0 0 0 0 0 32 32 32 0 100,0%
TOTAL 1 1 40 4 2 15 5 3 0 0 43 114 114 0 100,0%

RINCIAN PROGRESS BG RAMP CIKUNIR


UPDATE : 05 Agustus 2019

STATUS PROGRES BG RAMP CIKUNIR


SEGMENT BG TOTAL
165 S1 105 S1 105 S2 108 S1 120 S6 100 S2
TRIAL
BG 1 OK DLV OK DLV OK DLV OK DLV OK DLV
ERECTION
TRIAL FINISHING ON
BG 2 OK DLV OK DLV OK DLV
ERECTION PAINTING FABRIKASI
TRIAL TRIAL TRIAL TRIAL
BG 3 OK DLV OK DLV
ERECTION ERECTION ERECTION ERECTION
TRIAL TRIAL FINISH TRIAL TRIAL
BG 4 OK DLV
ERECTION ERECTION BLASTING ERECTION ERECTION
TRIAL FINISH FINISH TRIAL FINISH
BG 5 OK DLV
ERECTION BLASTING BLASTING ERECTION FABRIKASI
TRIAL FINISHING FINISH TRIAL FINISH
BG 6 OK DLV
ERECTION PAINTING BLASTING ERECTION BLASTING
TRIAL FINISH TRIAL TRIAL FINISH
BG 7 OK DLV
ERECTION COATING ERECTION ERECTION BLASTING
FINISH FINISH TRIAL TRIAL FINISH
BG 8 OK DLV
COATING COATING ERECTION ERECTION BLASTING
TRIAL FINISHING TRIAL
BG 9 OK DLV OK DLV OK DLV
ERECTION PAINTING ERECTION
FINISH TRIAL TRIAL
BG 10 OK DLV OK DLV OK DLV
BLASTING ERECTION ERECTION
ON FINISHING FINISHING READY TO TRIAL
BG 11 OK DLV
BLASTING PAINTING PAINTING BLASTING ERECTION
TRIAL TRIAL FINISH FINISH TRIAL
BG 12 OK DLV
ERECTION ERECTION BLASTING BLASTING ERECTION
TRIAL TRIAL FINISH TRIAL FINISH
BG 13 OK DLV
ERECTION ERECTION BLASTING ERECTION BLASTING
READY TO TRIAL TRIAL TRIAL ON
BG 14 OK DLV
BLASTING ERECTION ERECTION ERECTION BLASTING
READY TO TRIAL TRIAL TRIAL FINISH
BG 15 OK DLV
BLASTING ERECTION ERECTION ERECTION BLASTING
FINISH TRIAL TRIAL TRIAL FINISH
BG 16 OK DLV
BLASTING ERECTION ERECTION ERECTION BLASTING
TRIAL
BG 17 OK DLV
ERECTION
READY TO
BG 18 OK DLV
BLASTING
BG 19 OK DLV

BG 20 OK DLV

BG 21 OK DLV

BG 22 OK DLV

BG 23 OK DLV

BG 24 OK DLV

BG 25 OK DLV

BG 26 OK DLV

BG 27 OK DLV

BG 28 OK DLV

BG 29 OK DLV

BG 30 OK DLV

BG 31 OK DLV

BG 32 OK DLV

Catatan :
- Kendala utama saat ini adalah saat trial erection dikarenakan banyak BG yang harus dilubangin
- Untuk BG yang dalam proses trial erectian mayoritas sudah dilakukan blasting primer coating
- Tim drilling untuk trial erection saat ini ada 6 tim ( 1 tim terdiri dari 2 alat drilling )
- Fasilitas blasting /coating di stockyard KM.42 dikarenakan tersendatnya pengiriman BG saat saat ini alat & pekerjanya ditarik oleh subkont
- Data tersebut diambil jam 09.00 WIB