ID Task Mode Task Name Duration Start Finish Predecessors

Dec 30, '18 Jan 6, '19 Jan 13, '19 Jan 20, '19 Jan 27, '19 Feb 3, '19 Feb 10, '19 Feb 17, '19 Feb 24, '19 Mar 3, '19 Mar 10, '19 Mar 17, '19 Mar 24, '19 Mar 31, '19 Apr 7, '19 Apr 14, '19 Apr 21, '19 Apr 28, '19 May 5, '19 May 12, '19 May 19, '19 May 26, '19 Jun 2, '19
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
0 Internship Program 100 days? Wed 1/2/19 Fri 5/31/19
1 Collage Bussines 61 days? Thu 2/28/19 Fri 5/31/19
2 Collage Presentation 1 day? Thu 2/28/19 Thu 2/28/19 Ajik,Bobby
3 Final Project 1 day? Fri 5/31/19 Fri 5/31/19 Ajik,Bobby
4 Presentation
Drawing existing work 6 days Wed 1/2/19 Thu 1/10/19
5 area
3D target machine 6 days Wed 1/2/19 Thu 1/10/19 Bobby
6 3D target layout area 6 days Wed 1/2/19 Thu 1/10/19 Ajik
7 Design 40 days Wed 1/2/19 Thu 2/28/19
8 Mi-SCADA 30 days Wed 1/2/19 Thu 2/14/19
9 Tools 15 days Wed 1/2/19 Wed 1/23/19 Bram,Vembri
10 Installation 15 days Thu 1/24/19 Thu 2/14/19 9 Bram,Vembri
11 ScoreBoard 2.0 30 days Fri 1/11/19 Fri 2/22/19
12 Tools 20 days Fri 1/11/19 Fri 2/8/19 6 Ajik,Bram
13 Installation 10 days Mon 2/11/19 Fri 2/22/19 12 Ajik,Bram
14 Electronics 5S 30 days Fri 1/11/19 Fri 2/22/19
15 Storage
Tools 25 days Fri 1/11/19 Fri 2/15/19 5 Bobby,Didik
16 Installation 5 days Mon 2/18/19 Fri 2/22/19 15 Bobby,Didik
17 Visual Development 4 days Mon 2/25/19 Thu 2/28/19
18 Board
Tools 2 days Mon 2/25/19 Tue 2/26/19 13 Ajik,Didik
19 Installation 2 days Wed 2/27/19 Thu 2/28/19 18 Ajik,Didik
20 Locking Capacity 30 days Wed 1/2/19 Thu 2/14/19
21 Tools 25 days Wed 1/2/19 Thu 2/7/19 Wimpy
22 Installation 5 days Fri 2/8/19 Thu 2/14/19 21 Wimpy
23 Material Usage 3.25 days Fri 2/15/19 Wed 2/20/19
24 Sensor
Tools 3 days Fri 2/15/19 Tue 2/19/19 22 Bram,Wimpy
25 Installation 2 hrs Wed 2/20/19 Wed 2/20/19 24 Bram,Wimpy
26 Presentation 55 days? Fri 3/1/19 Thu 5/23/19
27 Pre-Project 1 day Fri 3/1/19 Fri 3/1/19 19 Bram,Didik,Ajik,Bobby
28 Post Project 1 day? Thu 5/23/19 Thu 5/23/19 60 Ajik,Bobby,Bram,Didik
29 Development 61 days Fri 2/15/19 Fri 5/17/19
30 Mi-SCADA 60 days Fri 2/15/19 Thu 5/16/19
31 Tools 30 days Fri 2/15/19 Fri 3/29/19 10 Bram,Vembri
32 Installation 30 days Mon 4/1/19 Thu 5/16/19 31 Bram,Vembri
33 ScoreBoard 2.0 55 days Mon 2/25/19 Fri 5/17/19
34 Tools 30 days Mon 2/25/19 Tue 4/9/19 13 Ajik,Bram
35 Installation 25 days Wed 4/10/19 Fri 5/17/19 34 Ajik,Bram
36 Electronics 5S 55 days Mon 2/25/19 Fri 5/17/19
37 Storage
Tools 50 days Mon 2/25/19 Fri 5/10/19 16 Bobby,Didik
38 Installation 5 days Mon 5/13/19 Fri 5/17/19 37 Bobby,Didik
39 Visual Development 35 days Fri 3/1/19 Wed 4/24/19
40 Board
Tools 30 days Fri 3/1/19 Mon 4/15/19 19 Ajik,Didik
41 Installation 5 days Tue 4/16/19 Wed 4/24/19 40 Ajik,Didik
42 Locking Capacity 35 days Fri 2/15/19 Mon 4/8/19
43 Tools 30 days Fri 2/15/19 Fri 3/29/19 22 Wimpy
44 Installation 5 days Mon 4/1/19 Mon 4/8/19 43 Wimpy
45 Material Usage 40 days Fri 2/15/19 Mon 4/15/19
46 Sensor
Tools 20 days Fri 2/15/19 Fri 3/15/19 22 Bram
47 Installation 5 days Tue 4/9/19 Mon 4/15/19 44 Wimpy
48 Testing 28 days Tue 4/9/19 Tue 5/21/19
49 Mi-SCADA 1 day Fri 5/17/19 Fri 5/17/19 32 Didik,Bram
50 ScoreBoard 2.0 2 days Mon 5/20/19 Tue 5/21/19 35 Bram
51 Electronics 5S Storage 2 days Mon 5/20/19 Tue 5/21/19 38 Didik
52 Visual Development 2 days Thu 4/25/19 Fri 4/26/19 41 Didik
53 Board
Locking Capacity 1 day Tue 4/9/19 Tue 4/9/19 44 Wimpy
54 Material Usage 2 days Tue 4/16/19 Thu 4/18/19 47 Wimpy
55 Sensor
Training 1 day Wed 5/22/19 Wed 5/22/19
56 ScoreBoard 2.0 1 day Wed 5/22/19 Wed 5/22/19 64 Bram,Didik
57 Electronics 5S Storage 1 day Wed 5/22/19 Wed 5/22/19 64 Bram,Didik
58 Visual Development 1 day Wed 5/22/19 Wed 5/22/19 64 Bram,Didik
59 Board Capacity
Locking 1 day Wed 5/22/19 Wed 5/22/19 64 Bram,Didik
60 Material Usage 1 day Wed 5/22/19 Wed 5/22/19 64 Bram,Didik
61 Sensor
Documentation 9 days Mon 5/20/19 Fri 5/31/19
62 Final Project Script 9 days Mon 5/20/19 Fri 5/31/19 38 Ajik,Bobby
63 Standard Operasional 3 days Mon 5/20/19 Wed 5/22/19 49 Bram,Didik
64 Procedure
Work Instruction 2 days Mon 5/20/19 Tue 5/21/19 49 Bram,Didik

Project: Internship Program Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress
Date: Mon 1/7/19

Page 1