Jadwal Pelaksanaan Gedung NHSSE Dan Fire Station

Proyek Pembangunan Gedung Site Office, HSSE Office, Dan Laboratorium RDMP RU V Balikpapan - Lawe Lawe
(26074-341-GDS-GCC-S001-00B)
ID Task Name Duration Actual Start Actual Finish Start Finish Baseline Start Baseline Finish April May June July August September October November December January February March April May June July August September
W -1 W1 W2 W3 W4 W5 W6 W7 W8 W 9 W 10 W 11 W12 W 13 W 14 W 15 W 16 W 17 W 18 W19 W 20 W 21 W 22 W 23 W 24 W25 W 26 W 27 W 28 W 29 W 30 W 31 W32 W 33 W 34 W 35 W 36 W37 W 38 W39 W 40 W 41 W 42 W43 W 44 W45 W 46 W 47 W 48 W 49 W50 W 51 W52 W 53 W 54 W 55 W 56 W57 W58 W 59 W 60 W 61 W 62 W63 W 64 W65 W 66 W 67 W 68 W 69 W70 W 71 W72 W 73 W 74 W 75 W76 W 77 W78 W 79
0 NHSSE & FIRE STATION 372.25 days Apr 10 '19 NA Apr 10 '19 Apr 16 '20 Apr 10 '19 Apr 13 '20

1 Milestone 372.25 days NA NA Apr 10 '19 Apr 16 '20 Apr 10 '19 Apr 13 '20

5 Pre-Eliminary 350 days NA NA Apr 10 '19 Mar 25 '20 Apr 10 '19 Mar 25 '20

6 Pekerjaan Persiapan 350 days NA NA Apr 10 '19 Mar 25 '20 Apr 10 '19 Mar 25 '20

7 Pembersihan Lahan 7 days NA NA Jul 7 '19 Jul 14 '19 Jul 7 '19 Jul 14 '19

8 Pemagaran Proyek 12 days NA NA Jul 7 '19 Jul 18 '19 Jul 7 '19 Jul 18 '19

9 Procurement 250 days NA NA Jun 19 '19 Feb 16 '20 Jun 19 '19 Feb 16 '20

90 Pekerjaan Engineering 120 days NA NA Apr 29 '19 Sep 5 '19 Apr 29 '19 Sep 5 '19

91 Pekerjaan Survey Dan GPR 30 days NA NA Apr 29 '19 May 28 '19 Apr 29 '19 May 28 '19

92 Pekerjaan Soil Investigation 30 days NA NA Apr 29 '19 May 28 '19 Apr 29 '19 May 28 '19

93 Pekerjaan Engineering 120 days NA NA Apr 29 '19 Sep 5 '19 Apr 29 '19 Sep 5 '19

94 DED Struktur 120 days NA NA Apr 29 '19 Sep 5 '19 Apr 29 '19 Sep 5 '19

95 DED ME 120 days NA NA Apr 29 '19 Sep 5 '19 Apr 29 '19 Sep 5 '19

96 Approval Material 60 days NA NA Jun 19 '19 Aug 16 '19 Jun 19 '19 Aug 16 '19

97 Struktur 0 days NA NA Jun 19 '19 Jun 19 '19 Jun 19 '19 Jun 19 '19 6/19

98 Spun Piles 0 days NA NA Jun 19 '19 Jun 19 '19 Jun 19 '19 Jun 19 '19 6/19

99 ME 10 days NA NA Aug 7 '19 Aug 16 '19 Aug 7 '19 Aug 16 '19

119 Pekerjaan Konstruksi 279 days Jul 22 '19 NA Jul 22 '19 Apr 16 '20 Apr 10 '19 Apr 13 '20

120 New HSSE Office 279 days Jul 22 '19 NA Jul 22 '19 Apr 16 '20 Jul 19 '19 Apr 13 '20

121 Pekerjaan Struktur 185 days Jul 22 '19 NA Jul 22 '19 Jan 16 '20 Jul 19 '19 Jan 13 '20

122 Pekerjaan Struktur Bawah 65 days Jul 22 '19 NA Jul 22 '19 Sep 22 '19 Jul 19 '19 Sep 19 '19

123 Pancang Hidrolik 107ttk 1 Set @6 Titik 23 days Jul 22 '19 NA Jul 22 '19 Aug 13 '19 Jul 19 '19 Aug 10 '19

124 Pekerjaan Pemancangan Dan Penyambungan 19 days Jul 22 '19 NA Jul 22 '19 Aug 9 '19 Jul 19 '19 Aug 6 '19

125 Pekerjaan Galian 7 days NA NA Aug 4 '19 Aug 11 '19 Aug 1 '19 Aug 8 '19

126 Pekerjaan Bobok Kepala Spun Piles 6 days NA NA Aug 7 '19 Aug 13 '19 Aug 4 '19 Aug 10 '19

127 Pekerjaan Pondasi 14 days NA NA Aug 19 '19 Sep 1 '19 Aug 16 '19 Aug 29 '19

128 Pondasi Batu Kali 14 days NA NA Aug 19 '19 Sep 1 '19 Aug 16 '19 Aug 29 '19

129 Zona 1 10 days NA NA Aug 19 '19 Aug 28 '19 Aug 16 '19 Aug 25 '19

130 Zona 2 10 days NA NA Aug 23 '19 Sep 1 '19 Aug 19 '19 Aug 29 '19

131 Pekerjaan Tanah 40 days NA NA Aug 11 '19 Sep 18 '19 Aug 8 '19 Sep 15 '19

132 Zona 1 38 days NA NA Aug 11 '19 Sep 16 '19 Aug 8 '19 Sep 13 '19

133 Galian 7 days NA NA Aug 11 '19 Aug 18 '19 Aug 8 '19 Aug 14 '19

134 Urugan 7 days NA NA Sep 5 '19 Sep 12 '19 Sep 2 '19 Sep 8 '19

135 Buang Tanah 5 days NA NA Sep 12 '19 Sep 16 '19 Sep 9 '19 Sep 13 '19

136 Zona 2 38 days NA NA Aug 13 '19 Sep 18 '19 Aug 10 '19 Sep 15 '19

137 Galian 7 days NA NA Aug 13 '19 Aug 19 '19 Aug 10 '19 Aug 16 '19

138 Urugan 7 days NA NA Sep 7 '19 Sep 14 '19 Sep 4 '19 Sep 10 '19

139 Buang Tanah 5 days NA NA Sep 14 '19 Sep 18 '19 Sep 11 '19 Sep 15 '19

140 Pekerjaan Lantai Kerja 39 days NA NA Aug 16 '19 Sep 22 '19 Aug 13 '19 Sep 19 '19

141 Pondasi Batu Kali 11 days NA NA Aug 16 '19 Aug 26 '19 Aug 13 '19 Aug 23 '19

142 Zona 1 7 days NA NA Aug 16 '19 Aug 22 '19 Aug 13 '19 Aug 19 '19

143 Zona 2 7 days NA NA Aug 20 '19 Aug 26 '19 Aug 17 '19 Aug 23 '19

144 Pile Cap & Sloof 12 days NA NA Aug 18 '19 Aug 29 '19 Aug 15 '19 Aug 26 '19

145 Zona 1 10 days NA NA Aug 18 '19 Aug 27 '19 Aug 15 '19 Aug 24 '19

146 Zona 2 10 days NA NA Aug 20 '19 Aug 29 '19 Aug 17 '19 Aug 26 '19

147 Lantai Dasar 15 days NA NA Sep 8 '19 Sep 22 '19 Sep 5 '19 Sep 19 '19

148 Zona 1 7 days NA NA Sep 8 '19 Sep 15 '19 Sep 5 '19 Sep 11 '19

149 Zona 2 7 days NA NA Sep 16 '19 Sep 22 '19 Sep 13 '19 Sep 19 '19

150 Pekerjaan Pile Cap & Sloof 27 days NA NA Aug 23 '19 Sep 17 '19 Aug 19 '19 Sep 14 '19

151 Zona 1 25 days NA NA Aug 23 '19 Sep 15 '19 Aug 19 '19 Sep 12 '19

152 Bekisting 14 days NA NA Aug 23 '19 Sep 5 '19 Aug 19 '19 Sep 2 '19

153 Pembesian 14 days NA NA Aug 30 '19 Sep 13 '19 Aug 27 '19 Sep 9 '19

154 Pengecoran 14 days NA NA Sep 2 '19 Sep 15 '19 Aug 30 '19 Sep 12 '19

155 Zona 2 25 days NA NA Aug 24 '19 Sep 17 '19 Aug 21 '19 Sep 14 '19

156 Bekisting 14 days NA NA Aug 24 '19 Sep 7 '19 Aug 21 '19 Sep 4 '19

157 Pembesian 14 days NA NA Sep 1 '19 Sep 15 '19 Aug 29 '19 Sep 11 '19

158 Pengecoran 14 days NA NA Sep 4 '19 Sep 17 '19 Sep 1 '19 Sep 14 '19

159 Pekerjaan Struktur Atas 132 days NA NA Sep 11 '19 Jan 16 '20 Sep 8 '19 Jan 13 '20

160 Lantai Satu 22 days NA NA Sep 11 '19 Oct 2 '19 Sep 8 '19 Sep 29 '19

161 Zona 1 14 days NA NA Sep 11 '19 Sep 24 '19 Sep 8 '19 Sep 21 '19

162 Zona 2 14 days NA NA Sep 19 '19 Oct 2 '19 Sep 15 '19 Sep 29 '19

163 Lantai Dua 48 days NA NA Sep 24 '19 Nov 10 '19 Sep 21 '19 Nov 6 '19

164 Zona 1 40 days NA NA Sep 24 '19 Nov 2 '19 Sep 21 '19 Oct 30 '19

165 Zona 2 40 days NA NA Oct 2 '19 Nov 10 '19 Sep 29 '19 Nov 6 '19

166 Lantai Tiga 64 days NA NA Oct 8 '19 Dec 8 '19 Oct 5 '19 Dec 5 '19

167 Zona 1 40 days NA NA Oct 8 '19 Nov 15 '19 Oct 5 '19 Nov 12 '19

168 Zona 2 40 days NA NA Oct 31 '19 Dec 8 '19 Oct 28 '19 Dec 5 '19

169 Lantai Empat 54 days NA NA Oct 23 '19 Dec 14 '19 Oct 20 '19 Dec 11 '19

170 Zona 1 40 days NA NA Oct 23 '19 Dec 1 '19 Oct 20 '19 Nov 28 '19

171 Zona 2 40 days NA NA Nov 6 '19 Dec 14 '19 Nov 3 '19 Dec 11 '19

172 Lantai Atap Ruang Tangga 40 days NA NA Dec 9 '19 Jan 16 '20 Dec 6 '19 Jan 13 '20

173 Zona 2 40 days NA NA Dec 9 '19 Jan 16 '20 Dec 6 '19 Jan 13 '20

174 Tangga 56 days NA NA Nov 10 '19 Jan 3 '20 Nov 7 '19 Dec 30 '19

175 Lantai Satu 14 days NA NA Nov 10 '19 Nov 23 '19 Nov 7 '19 Nov 20 '19

176 Lantai Dua 14 days NA NA Nov 23 '19 Dec 7 '19 Nov 20 '19 Dec 3 '19

177 Lantai Tiga 14 days NA NA Dec 7 '19 Dec 20 '19 Dec 4 '19 Dec 17 '19

178 Lantai Empat 14 days NA NA Dec 20 '19 Jan 3 '20 Dec 17 '19 Dec 30 '19

179 Pekerjaan Arsitektur 162 days NA NA Nov 10 '19 Apr 14 '20 Nov 7 '19 Apr 11 '20

180 Lantai Satu 120 days NA NA Nov 10 '19 Mar 4 '20 Nov 7 '19 Mar 1 '20

181 Lantai Dua 120 days NA NA Nov 23 '19 Mar 18 '20 Nov 20 '19 Mar 15 '20

182 Lantai Tiga 120 days NA NA Dec 7 '19 Mar 31 '20 Dec 4 '19 Mar 28 '20

183 Lantai Atap 120 days NA NA Dec 20 '19 Apr 14 '20 Dec 17 '19 Apr 11 '20

184 Façade 120 days NA NA Dec 20 '19 Apr 14 '20 Dec 17 '19 Apr 11 '20

185 Pekerjaan Lain-Lain 100 days NA NA Jan 9 '20 Apr 14 '20 Jan 5 '20 Apr 11 '20
Jadwal Pelaksanaan Gedung NHSSE Dan Fire Station
Proyek Pembangunan Gedung Site Office, HSSE Office, Dan Laboratorium RDMP RU V Balikpapan - Lawe Lawe
(26074-341-GDS-GCC-S001-00B)
ID Task Name Duration Actual Start Actual Finish Start Finish Baseline Start Baseline Finish April May June July August September October November December January February March April May June July August September
W -1 W1 W2 W3 W4 W5 W6 W7 W8 W 9 W 10 W 11 W12 W 13 W 14 W 15 W 16 W 17 W 18 W19 W 20 W 21 W 22 W 23 W 24 W25 W 26 W 27 W 28 W 29 W 30 W 31 W32 W 33 W 34 W 35 W 36 W37 W 38 W39 W 40 W 41 W 42 W43 W 44 W45 W 46 W 47 W 48 W 49 W50 W 51 W52 W 53 W 54 W 55 W 56 W57 W58 W 59 W 60 W 61 W 62 W63 W 64 W65 W 66 W 67 W 68 W 69 W70 W 71 W72 W 73 W 74 W 75 W76 W 77 W78 W 79
186 Pekerjaan Interior 128 days NA NA Nov 29 '19 Mar 31 '20 Nov 26 '19 Mar 28 '20

187 Lantai Satu 100 days NA NA Nov 29 '19 Mar 4 '20 Nov 26 '19 Mar 1 '20

188 Lantai Dua 100 days NA NA Dec 13 '19 Mar 18 '20 Dec 9 '19 Mar 15 '20

189 Lantai Tiga 100 days NA NA Dec 26 '19 Mar 31 '20 Dec 23 '19 Mar 28 '20

190 Pekerjaan MEP 157 days NA NA Nov 16 '19 Apr 16 '20 Nov 13 '19 Apr 13 '20

191 Pekerjaan Mekanikal Plumbing 157 days NA NA Nov 16 '19 Apr 16 '20 Nov 13 '19 Apr 13 '20

192 Instalasi 150 days NA NA Nov 16 '19 Apr 9 '20 Nov 13 '19 Apr 6 '20

193 Testing & Commisioning 7 days NA NA Apr 9 '20 Apr 16 '20 Apr 6 '20 Apr 13 '20

194 Pekerjaan Elektrikal 157 days NA NA Nov 16 '19 Apr 16 '20 Nov 13 '19 Apr 13 '20

195 Instalasi 150 days NA NA Nov 16 '19 Apr 9 '20 Nov 13 '19 Apr 6 '20

196 Testing & Commisioning 7 days NA NA Apr 9 '20 Apr 16 '20 Apr 6 '20 Apr 13 '20

197 Pekerjaan Sistem Fire Protection 157 days NA NA Nov 16 '19 Apr 16 '20 Nov 13 '19 Apr 13 '20

198 Instalasi 150 days NA NA Nov 16 '19 Apr 9 '20 Nov 13 '19 Apr 6 '20

199 Testing & Commisioning 7 days NA NA Apr 9 '20 Apr 16 '20 Apr 6 '20 Apr 13 '20

200 Pekerjaan Sistem Keamanan 92 days NA NA Jan 18 '20 Apr 16 '20 Jan 15 '20 Apr 13 '20

201 Instalasi 85 days NA NA Jan 18 '20 Apr 9 '20 Jan 15 '20 Apr 6 '20

202 Testing & Commisioning 7 days NA NA Apr 9 '20 Apr 16 '20 Apr 6 '20 Apr 13 '20

203 Pekerjaan Sistem Telekomunikasi Dan IT 92 days NA NA Jan 18 '20 Apr 16 '20 Jan 15 '20 Apr 13 '20

204 Instalasi 85 days NA NA Jan 18 '20 Apr 9 '20 Jan 15 '20 Apr 6 '20

205 Testing & Commisioning 7 days NA NA Apr 9 '20 Apr 16 '20 Apr 6 '20 Apr 13 '20

206 Fire Station 250 days NA NA Aug 11 '19 Apr 8 '20 Apr 10 '19 Dec 20 '19

207 Pekerjaan Struktur 188 days NA NA Aug 11 '19 Feb 8 '20 Apr 10 '19 Oct 21 '19

208 Pekerjaan Struktur Bawah 56 days NA NA Aug 11 '19 Oct 4 '19 Apr 10 '19 Jun 16 '19

209 Pekerjaan Pondasi 35 days NA NA Aug 11 '19 Sep 14 '19 Apr 10 '19 May 13 '19

210 Pondasi Spun Piles 14 days NA NA Aug 11 '19 Aug 24 '19 Apr 10 '19 Apr 23 '19

211 Pemancangan 14 days NA NA Aug 11 '19 Aug 24 '19 Apr 10 '19 Apr 23 '19

212 PDA Test 2 days NA NA Aug 21 '19 Aug 22 '19 Apr 19 '19 Apr 21 '19

213 Pondasi Batu Kali 10 days NA NA Sep 4 '19 Sep 14 '19 May 4 '19 May 13 '19

214 Pekerjaan Tanah 44 days NA NA Aug 23 '19 Oct 4 '19 Apr 21 '19 Jun 16 '19

215 Galian 10 days NA NA Aug 23 '19 Sep 1 '19 Apr 21 '19 May 1 '19

216 Urugan 10 days NA NA Sep 20 '19 Sep 29 '19 May 19 '19 May 29 '19

217 Buang Tanah 5 days NA NA Sep 29 '19 Oct 4 '19 May 29 '19 Jun 16 '19

218 Pekerjaan Lantai Kerja 32 days NA NA Sep 1 '19 Oct 2 '19 May 1 '19 Jun 14 '19

219 Pondasi Batu Kali 7 days NA NA Sep 1 '19 Sep 8 '19 May 1 '19 May 7 '19

220 Pile Cap & Sloof 10 days NA NA Sep 1 '19 Sep 11 '19 May 1 '19 May 10 '19

221 Lantai Dasar 10 days NA NA Sep 22 '19 Oct 2 '19 May 22 '19 Jun 14 '19

222 Pekerjaan Pile Cap & Sloof 20 days NA NA Sep 11 '19 Sep 30 '19 May 11 '19 May 30 '19

223 Bekisting 10 days NA NA Sep 11 '19 Sep 20 '19 May 11 '19 May 20 '19

224 Pembesian 14 days NA NA Sep 14 '19 Sep 27 '19 May 13 '19 May 27 '19

225 Pengecoran 14 days NA NA Sep 17 '19 Sep 30 '19 May 16 '19 May 30 '19

226 Pekerjaan Struktur Atas 144 days NA NA Sep 22 '19 Feb 8 '20 May 22 '19 Oct 21 '19

227 Struktur Beton 84 days NA NA Sep 22 '19 Dec 12 '19 May 22 '19 Aug 24 '19

228 Lantai Satu 14 days NA NA Sep 22 '19 Oct 6 '19 May 22 '19 Jun 17 '19

229 Lantai Dua 40 days NA NA Oct 6 '19 Nov 13 '19 Jun 18 '19 Jul 26 '19

230 Lantai Atap 40 days NA NA Nov 4 '19 Dec 12 '19 Jul 17 '19 Aug 24 '19

231 Struktur Baja 60 days NA NA Dec 13 '19 Feb 8 '20 Aug 24 '19 Oct 21 '19

232 Rangka Baja Atap 60 days NA NA Dec 13 '19 Feb 8 '20 Aug 24 '19 Oct 21 '19

233 Pekerjaan Arsitektur 150 days NA NA Nov 14 '19 Apr 6 '20 Jul 26 '19 Dec 18 '19

234 Lantai Satu 120 days NA NA Nov 14 '19 Mar 8 '20 Jul 26 '19 Nov 19 '19

235 Lantai Dua 120 days NA NA Nov 27 '19 Mar 22 '20 Aug 9 '19 Dec 2 '19

236 Lantai Tiga 120 days NA NA Dec 13 '19 Apr 6 '20 Aug 24 '19 Dec 18 '19

237 Façade 120 days NA NA Dec 13 '19 Apr 6 '20 Aug 24 '19 Dec 18 '19

238 Pekerjaan Lain-Lain 100 days NA NA Jan 1 '20 Apr 6 '20 Sep 13 '19 Dec 18 '19

239 Pekerjaan Interior 130 days NA NA Dec 3 '19 Apr 6 '20 Aug 15 '19 Dec 18 '19

240 Lantai Satu 100 days NA NA Dec 3 '19 Mar 8 '20 Aug 15 '19 Nov 19 '19

241 Lantai Dua 100 days NA NA Dec 16 '19 Mar 22 '20 Aug 28 '19 Dec 2 '19

242 Lantai Tiga 100 days NA NA Jan 1 '20 Apr 6 '20 Sep 13 '19 Dec 18 '19

243 Pekerjaan MEP 152 days NA NA Nov 14 '19 Apr 8 '20 Jul 26 '19 Dec 20 '19

244 Pekerjaan Mekanikal Plumbing 152 days NA NA Nov 14 '19 Apr 8 '20 Jul 26 '19 Dec 20 '19

245 Instalasi 140 days NA NA Nov 14 '19 Mar 28 '20 Jul 26 '19 Dec 8 '19

246 Testing & Commisioning 12 days NA NA Mar 28 '20 Apr 8 '20 Dec 8 '19 Dec 20 '19

247 Pekerjaan Elektrikal 152 days NA NA Nov 14 '19 Apr 8 '20 Jul 26 '19 Dec 20 '19

248 Instalasi 140 days NA NA Nov 14 '19 Mar 28 '20 Jul 26 '19 Dec 8 '19

249 Testing & Commisioning 12 days NA NA Mar 28 '20 Apr 8 '20 Dec 8 '19 Dec 20 '19

250 Pekerjaan Sistem Fire Protection 152 days NA NA Nov 14 '19 Apr 8 '20 Jul 26 '19 Dec 20 '19

251 Instalasi 140 days NA NA Nov 14 '19 Mar 28 '20 Jul 26 '19 Dec 8 '19

252 Testing & Commisioning 12 days NA NA Mar 28 '20 Apr 8 '20 Dec 8 '19 Dec 20 '19

253 Pekerjaan Sistem Keamanan 102 days NA NA Jan 1 '20 Apr 8 '20 Sep 13 '19 Dec 20 '19

254 Instalasi 90 days NA NA Jan 1 '20 Mar 28 '20 Sep 13 '19 Dec 8 '19

255 Testing & Commisioning 12 days NA NA Mar 28 '20 Apr 8 '20 Dec 8 '19 Dec 20 '19

256 Pekerjaan Sistem Telekomunikasi Dan IT 102 days NA NA Jan 1 '20 Apr 8 '20 Sep 13 '19 Dec 20 '19

257 Instalasi 90 days NA NA Jan 1 '20 Mar 28 '20 Sep 13 '19 Dec 8 '19

258 Testing & Commisioning 12 days NA NA Mar 28 '20 Apr 8 '20 Dec 8 '19 Dec 20 '19

259 Bangunan Reservoir 228 days NA NA Sep 1 '19 Apr 8 '20 May 1 '19 Dec 20 '19

260 Pekerjaan Struktur 104 days NA NA Sep 1 '19 Dec 10 '19 May 1 '19 Aug 22 '19

261 Pekerjaan Tanah 48 days NA NA Sep 1 '19 Oct 17 '19 May 1 '19 Jun 29 '19

262 Galian 10 days NA NA Sep 1 '19 Sep 11 '19 May 1 '19 May 10 '19

263 Urugan 10 days NA NA Oct 3 '19 Oct 13 '19 Jun 15 '19 Jun 24 '19

264 Buang Tanah 5 days NA NA Oct 13 '19 Oct 17 '19 Jun 24 '19 Jun 29 '19

265 Pekerjaan Pondasi Dan Sloof 23 days NA NA Sep 18 '19 Oct 10 '19 May 17 '19 Jun 21 '19

266 Pembesian 10 days NA NA Sep 18 '19 Sep 27 '19 May 17 '19 May 27 '19

267 Bekisting 10 days NA NA Sep 21 '19 Sep 30 '19 May 20 '19 May 30 '19

268 Pengecoran 10 days NA NA Sep 30 '19 Oct 10 '19 May 30 '19 Jun 21 '19

269 Pekerjaan Lantai Kerja 40 days NA NA Sep 11 '19 Oct 19 '19 May 11 '19 Jul 1 '19
Jadwal Pelaksanaan Gedung NHSSE Dan Fire Station
Proyek Pembangunan Gedung Site Office, HSSE Office, Dan Laboratorium RDMP RU V Balikpapan - Lawe Lawe
(26074-341-GDS-GCC-S001-00B)
ID Task Name Duration Actual Start Actual Finish Start Finish Baseline Start Baseline Finish April May June July August September October November December January February March April May June July August September
W -1 W1 W2 W3 W4 W5 W6 W7 W8 W 9 W 10 W 11 W12 W 13 W 14 W 15 W 16 W 17 W 18 W19 W 20 W 21 W 22 W 23 W 24 W25 W 26 W 27 W 28 W 29 W 30 W 31 W32 W 33 W 34 W 35 W 36 W37 W 38 W39 W 40 W 41 W 42 W43 W 44 W45 W 46 W 47 W 48 W 49 W50 W 51 W52 W 53 W 54 W 55 W 56 W57 W58 W 59 W 60 W 61 W 62 W63 W 64 W65 W 66 W 67 W 68 W 69 W70 W 71 W72 W 73 W 74 W 75 W76 W 77 W78 W 79
270 Pondasi 7 days NA NA Sep 11 '19 Sep 17 '19 May 11 '19 May 17 '19

271 Lantai Dasar 7 days NA NA Oct 13 '19 Oct 19 '19 Jun 24 '19 Jul 1 '19

272 Pekerjaan Struktur Atas 54 days NA NA Oct 19 '19 Dec 10 '19 Jul 1 '19 Aug 22 '19

273 Elevasi +0.00 14 days NA NA Oct 19 '19 Nov 2 '19 Jul 1 '19 Jul 14 '19

274 Elevasi +4.00 40 days NA NA Nov 2 '19 Dec 10 '19 Jul 15 '19 Aug 22 '19

275 Pekerjaan Arsitektur 43 days NA NA Dec 11 '19 Jan 21 '20 Aug 22 '19 Oct 3 '19

281 Pekerjaan MEP 124 days NA NA Dec 11 '19 Apr 8 '20 Aug 22 '19 Dec 20 '19

285 Bangunan Rumah Genset 218 days NA NA Sep 11 '19 Apr 8 '20 May 11 '19 Dec 20 '19

286 Pekerjaan Struktur 90 days NA NA Sep 11 '19 Dec 7 '19 May 11 '19 Aug 18 '19

301 Pekerjaan MEP 128 days NA NA Dec 7 '19 Apr 8 '20 Aug 18 '19 Dec 20 '19

305 Bangunan Check Point 208 days NA NA Sep 21 '19 Apr 8 '20 May 20 '19 Feb 11 '20

306 Pekerjaan Struktur 123 days NA NA Sep 21 '19 Jan 17 '20 May 20 '19 Sep 29 '19

322 Pekerjaan Arsitektur 85 days NA NA Jan 17 '20 Apr 8 '20 Nov 21 '19 Feb 11 '20

330 Bangunan Jembatan Pipa 87 days NA NA Sep 27 '19 Dec 20 '19 May 27 '19 Sep 1 '19

331 Pekerjaan Struktur 87 days NA NA Sep 27 '19 Dec 20 '19 May 27 '19 Sep 1 '19

343 Perkerasan Jalan Dan Drainase 90 days NA NA Oct 26 '19 Jan 21 '20 Jul 8 '19 Oct 3 '19

344 Pekerjaan Tanah 30 days NA NA Oct 26 '19 Nov 24 '19 Jul 8 '19 Aug 6 '19

345 Pekerjaan Lantai Kerja 30 days NA NA Nov 24 '19 Dec 23 '19 Aug 6 '19 Sep 4 '19

346 Pekerjaan Beton Bertulang K-300 30 days NA NA Dec 23 '19 Jan 21 '20 Sep 4 '19 Oct 3 '19

347 Pekerjaan Beton Bertulang K-250 30 days NA NA Dec 23 '19 Jan 21 '20 Sep 4 '19 Oct 3 '19

348 Pekerjaan Lanskap 127 days NA NA Nov 24 '19 Mar 26 '20 Aug 6 '19 Dec 6 '19

349 Pekerjaan Kawasan 120 days NA NA Nov 24 '19 Mar 19 '20 Aug 6 '19 Nov 30 '19

350 Pekerjaan Pos Jaga 1 60 days NA NA Jan 21 '20 Mar 19 '20 Oct 3 '19 Nov 30 '19

351 Pekerjaan Toilet Pos Jaga 1 30 days NA NA Feb 19 '20 Mar 19 '20 Nov 1 '19 Nov 30 '19

352 Pekerjaan Ornamen Gerbang Pos Jaga 1 60 days NA NA Jan 21 '20 Mar 19 '20 Oct 3 '19 Nov 30 '19

353 Pekerjaan Pos Jaga 2 60 days NA NA Jan 21 '20 Mar 19 '20 Oct 3 '19 Nov 30 '19

354 Pekerjaan Furniture 7 days NA NA Mar 19 '20 Mar 26 '20 Nov 30 '19 Dec 6 '19

355 Pekerjaan Pagar Keliling 60 days NA NA Jan 21 '20 Mar 19 '20 Oct 3 '19 Nov 30 '19

356 Additional Item 150 days NA NA Nov 16 '19 Apr 9 '20 Nov 13 '19 Apr 6 '20

357 Pekerjaan Tangki Foam 90 days NA NA Jan 13 '20 Apr 9 '20 Jan 10 '20 Apr 6 '20

358 Pekerjaan Tangki Sprinkler 90 days NA NA Jan 13 '20 Apr 9 '20 Jan 10 '20 Apr 6 '20

359 Pekerjaan Tangki Air Bersih Rooftop 90 days NA NA Jan 13 '20 Apr 9 '20 Jan 10 '20 Apr 6 '20

360 Pekerjaan Air Compressor Untuk Fire Station 90 days NA NA Jan 13 '20 Apr 9 '20 Jan 10 '20 Apr 6 '20

361 Pekerjaan Pompa Pemadam Kebakaran & Pengisian Fire truck 90 days NA NA Jan 13 '20 Apr 9 '20 Jan 10 '20 Apr 6 '20

362 Pekerjaan IT/Telecom W arehouse LLP 90 days NA NA Nov 16 '19 Feb 11 '20 Nov 13 '19 Feb 8 '20

363 Pekerjaan Process Safety LLP W arehouse 90 days NA NA Nov 16 '19 Feb 11 '20 Nov 13 '19 Feb 8 '20

364 Serah Terima Pekerjaan 0 days NA NA Apr 16 '20 Apr 16 '20 Apr 13 '20 Apr 13 '20