ID Task Task Name Start Finish Baseline Start Baseline Finish May 2019 June 2019 July 2019 August 2019 September 2019Octobe
Mode 2328 3 8 13182328 2 7 12172227 2 7 12172227 1 6 1116212631 5 1015202530 5
0 CFA PILES - May 6 '19 Sep 4 '19 NA NA
7 Bore Test 1 and test 2 piles (6 piles ) for test rig (T/G Building) May 24 '19 May 28 '19 NA NA
8 Setup pile test rig & test pile 1 (11 day cure) (T/G Building) Jun 10 '19 Jun 14 '19 NA NA
9 Setup pile test rig & test pile 2 (11day cure) (T/G Building) Jun 19 '19 Jun 25 '19 NA NA
12 Piles Installatio at Level -5.5m (45 piles) (around turbine ext) Jul 1 '19 Jul 8 '19 NA NA
13 Execution Pile Integrity Tests (PET) +report (45 piles) Jul 19 '19 Jul 25 '19 NA NA
14 Piles Installation at Level -5.5m (55 piles) Jul 9 '19 Jul 17 '19 NA NA
15 Execution Pile Integrity Tests (PET) +report (55 piles) Jul 30 '19 Aug 6 '19 NA NA
16 Piles Installation at Level -3.0m (41 piles) Jul 18 '19 Jul 25 '19 NA NA
17 Execution Pile Integrity Tests (PET) +report (41 piles) Aug 7 '19 Aug 13 '19 NA NA
18 Piles Intallation at level -12m (hotwell) (10 piles) Jul 26 '19 Jul 30 '19 NA NA
19 Execution Pile Integrity Tests (PET) +report (10 piles) Aug 12 '19 Aug 15 '19 NA NA
20 Piles Installtion level -8.5m (turbine base) (80 piles) Jul 31 '19 Aug 13 '19 NA NA
21 Execution Pile Integrity Tests (PET) +report (80 piles) Aug 26 '19 Sep 4 '19 NA NA