You are on page 1of 2

One Week Acheivement Plan - Mechanical & Strucutral

Duration covered 27-Jan-18 3-Feb-18


Material
# Activity Discipline Completion /Equipment Other Requirement
Date
Required

1 Complete Welding procedure qualification for Piping Quality 30-Jan-19 N.A Expedite with SIER Lab

2 Collect the remaining Siba 6 Piping Material Mechanical 30-Jan-19 Crane /Trailer expedite with KEIL

3 Start Fit Up and Welding Works Mechanical 3-Feb-19 N.A N.A

Complete welding of the remaining two crossing pipes for


4 Mechanical 1-Feb-19 N.A N.A
Siba 6

5 Complete the coating Siba 6 casings Mechanical 28-Jan-19 N.A N.A

Complete crossing installation for at least 1 open-cut Approval of Method


6 crossing (Prefered near Hub1 ) Mechanical 2-Feb-19 N.A
statement
Need to solve the painting
7 Painting work for Pipe show Material for Siba 6 Mechanical 3-Feb-19 N.A
material issue
Starting Material
8 Starting the fabrication of Wellhead Pipe support Mechanical 2-Feb-19
Procurement

10
One Week Acheivement Plan - Civil
Duration covered 27-Jan-18 3-Feb-18
Material
# Activity Discipline Completion /Equipment Other Requirement
Date
Required
Method statement for
1 Complete the remaining blinding works for Siba 6 Civil 1-Feb-19 N.A Excavation of the two
Flowline supports near Siba 6

2 Concrete Casting of 60 Concrete Support Pedetal Civil 3-Feb-19 N.A N.A

Excavation and Subgrade compaction of remaining 11 Method statement for


3 Support in Siba 6 Flowline Civil 28-Jan-19 N.A Excavation of the two
supports near Siba 6

Sub Base Layer 1 & Layer 2 compaction and Testing for M. Amer to advise is Surveyor
4 the remaining 11 Support in Siba 6 Flowline Civil 2-Feb-19 N.A Sajad is required
Two cranes and Two
5 Installation of minimum 20 precast Support for Siba 6 Civil 2-Feb-19 Mainly for Corners
trailers

6 Completion of Chemical Injection Package Concrete Civil 29-Jan-19 N.A N.A

Blinding Concrete for the stripp footing , Supports and


7 Shelter in Siba 6 WH Civil 30-Jan-19 N.A N.A

8 Anchor Bolts and Grouting for Chemical Injection Package Civil 1-Feb-19 Grout Mixing Drill Approval of Anchor Bolt and
Grout (both with Noor)

9 Completing the foundation for Generator and Fuel tanls Civil 1-Feb-19 Grout Mixing Drill Drawings of Generator and
tank foundations

Precast Concrete for Wellhead Control Panel and Catch


10 Basin Civil 29-Jan-19 N.A N.A

11 Concrete works for Stripp footing in Siba 6 WH Civil 3-Feb-19 N.A N.A

12 Coating for Siba 6 installed supports Civil 3-Feb-19 N.A N.A

M. Amer to advise is Surveyor


13 Surveying works for Siba 6 crossings Civil 30-Jan-19 N.A Sajad is required

You might also like