1 Complete Welding procedure qualification for Piping Quality 30-Jan-19 N.A Expedite with SIER Lab
2 Collect the remaining Siba 6 Piping Material Mechanical 30-Jan-19 Crane /Trailer expedite with KEIL
10
One Week Acheivement Plan - Civil
Duration covered 27-Jan-18 3-Feb-18
Material
# Activity Discipline Completion /Equipment Other Requirement
Date
Required
Method statement for
1 Complete the remaining blinding works for Siba 6 Civil 1-Feb-19 N.A Excavation of the two
Flowline supports near Siba 6
Sub Base Layer 1 & Layer 2 compaction and Testing for M. Amer to advise is Surveyor
4 the remaining 11 Support in Siba 6 Flowline Civil 2-Feb-19 N.A Sajad is required
Two cranes and Two
5 Installation of minimum 20 precast Support for Siba 6 Civil 2-Feb-19 Mainly for Corners
trailers
8 Anchor Bolts and Grouting for Chemical Injection Package Civil 1-Feb-19 Grout Mixing Drill Approval of Anchor Bolt and
Grout (both with Noor)
9 Completing the foundation for Generator and Fuel tanls Civil 1-Feb-19 Grout Mixing Drill Drawings of Generator and
tank foundations
11 Concrete works for Stripp footing in Siba 6 WH Civil 3-Feb-19 N.A N.A