Inquiries for Ongoing Projects DOCUMENT NUMBER : TBA

Status as of 4 August 2017


New
PIC Issue Target Status Remarks
Forecast
IKK1 (KW-2 x New Brown Board Machines, 3 new 410t/h@130, 3 new
1.0 TG@70MW) - Existing Field
1.1 Some very basic technical specification for Valmet AD 1-Mar-17 a
1.2 Basic Engineering for Pindo Deli 2 AD 14-Apr-17 a
1.3 Detailed Civil Engineering for BMs and SPs (to consultants) AD 22-May-17 a
To be issued after down payments to Valmet & SP
1.4 Detailed MEI Engineering for BMs and SPs (to consultants and/or suppliers) AD TBA
Supplier
1.5 Detailed Civil Engineering for BOP areas (to consultants) AD 30-Aug-17
1.6 Detailed MEI Engineering for BOP areas (to consultants and/or suppliers) AD 30-Sep-17

Procurement for Main Equipment To be expanded later in the Procurement Plan


document - Preparation is in-progress
1.7 Inquiry for CFB and TG's AD 30-Mar-17 a
1.8 Inquiry for Stock Preparation AD 30-May-17 a
1.9 Inquiry for Water Treatment, Effluent Treat,emt, Demin and Polisher AD 15-Aug-17
1.10 Inquiries for other main equipment AD 31-Oct-17 Refer to Procurement Plan for details
Construction Contracts

1.11 Inquiry for Soil Investigation Testliner & Corrugating AD 15-May-17 a


1.12 Inquiry for Site Preparation and Temp. Offices AD 15-May-17 a
To be issued after down payments to Valmet & SP
1.13 Inquiry for Piling Works Testliner & Corrugating AD TBA Supplier
1.14 Inquiry for Civil Construction Testliner & Corrugating AD 15-Sep-17
1.15 Inquiry for BOP Civil Construction AD 16-Oct-17
1.16 Inquiry for Tower Construction Testliner & Corrugating AD 15-Jan-18
1.17 Inquiry for MEI Construction Testliner & Corrugating AD 13-Apr-18
1.18 Inquiry for BOP MEI Construction AD 13-Apr-18
2.0 IKK2 (General Items for whole area)
2.1 Basic Engineering for Pindo Deli 4 (to consultants) AD 31-Aug-17
2.2 Basic Engineering for Road & Bridge AD 4-Aug-17 7-Aug-17 Still under reviewed by Pak Faizal Nurdin
2.3 Soil Investigation AD 4-Aug-17 a
2.4 Site Preparation AD 31-Aug-17
2.5 Temporary Access Road AD
2.6 Inquiry for new Topography AD 15-Aug-17
2.7 Inquiry for Temporary Facilities AD 15-Aug-17
2.8 Inquiry for Earthworks AD 15-Aug-17

3.0 IKK2 (KW-BCTMP Relocation) - New Greenfield


3.1 Inquiry specification for dismantling works (to Canadian contractors) AD 1-Mar-17 a
3.2 Inquiry specification for dismantling and erection supervision (to Andritz) AD 5-Mar-17 a
3.3 Basic Engineering for BCTMP itself (to Andritz) AD 26-Feb-17 a
3.4 Detailed Engineering for civil works (to consultants) AD Feb-18 By GPG Indo
3.5 Detailed Engineering for MEI works - BCTMP (Andritz or consultant) AD Jul-18 By GPG Indo
3.6 Detailed Engineering for MEI works - the rest By GPG China
3.7 Preparation of Scope of Work AD 15-Sep-17 By GPG China

4.0 IKK2 ( KW-Ningbo PM1+PM2+PM3 ) - New Greenfield

4.1 Inspection services prior to equipment dismantling (for Voith) AD 26-Feb-17 a


Dismantling and erection supervision for board machines and stock preparation AD
4.2 By GPG China
equipment (for Voith)

4.3 Inspection services for board machines and stock preparation equipment (for AD By GPG China
3rd party inspector to represent APP during dismantling)
Dismantling works for board machines and stock preparation equipment (for
4.4 AD By GPG China
Voith or other contractors)
4.5 Detailed Engineering for civil works (to consultants) AD May-18 By GPG Indo
4.6 Detailed Engineering for MEI works AD By GPG China

5.0 IKK2 ( 3 new CFB, 3 new TG ) - New Greenfield

5.1 Piling Supply AD 1-Nov-17


5.2 Piling Contract AD 15-Nov-17
5.3 Detail Civil Engineeriing AD 15-Oct-17

6.0 Perawang MB26 Boiler - To be further handled by Mill


6.1 Basic engineering for BOP (completed) AD a
6.2 Detailed engineering for BOP (to consultants) AD TBC
6.3 Inquiry for Polisher Himmat 11-Aug-17
Already send to Mill for their review on 26 July
6.4 Inquiry for RO Plant - Demin Himmat 11-Aug-17 2017. Finally comments still not received from Mill

7.0 OKI Tissue Machines


7.1 Basic engineering for civil and MEI for 1 SP and 6 TMs in 3 phases (completed) AD a Re-issued as Rev.1 on 17-Mar

7.2 Detailed engineering for civil for 1 SP and 2 TMs AD a Completed on 24 Mar 17
7.3 Detailed engineering for MEI for 1 SP and 2 TMs (to consultants) AD 31-Mar-17 a Completed on 27 Apr 17

8.0 OKI Town Site


8.1 Inquiry specification for master planning of town site (to consultants) DS 17-Mar-17 a

Page 1 of 2
Inquiries for Ongoing Projects DOCUMENT NUMBER : TBA
Status as of 4 August 2017
Inquiry specification for construction of pre-fabricated houses (to
8.2 suppliers/contractors) DS 17-Mar-17 a

9.0 BU17 - To be further handled by Mill


9.1 Inquiry for Corrugators, Flexos, Gluer Machine BU17 N/A
9.2 Inquiry for Basic Engineering (All Sites) AD 22-Jun-17 a

Page 2 of 2