PIC Issue Target Status Remarks
Forecast
IKK1 (KW-2 x New Brown Board Machines, 3 new 410t/h@130, 3 new
1.0 Postponed
TG@70MW) - Existing Field
Inspection services for board machines and stock preparation equipment (for
4.1 AD No need
3rd party inspector to represent APP during dismantling)
Dismantling works for board machines and stock preparation equipment (for
4.2 AD By GPG China
Voith or other contractors)
Inspection services prior to equipment dismantling for Voith and its supervision
4.3 for board machines and stock preparation equipment, Scope of work for Board AD 15-Sep-17
Machines upgrade (2)
4.4 Inquiry for Stock Preparation AD 19-Oct-17
4.5 Roll grinding machine - Inquiry release AD/DS 30-Oct-17
4.6 Finishing house + Auto Warehouses - Inquiry preparation and release AD/RC 30-Oct-17
4.7 Inquiry for Roll Handling system AD 31-Oct-17
4.8 Inquiry for Reel wrapping/ Pallet wrapping AD 1-Nov-17
4.9 BOP areas design criteria (Pulping lines, GCC, CCK, DIP & BOP) JTC 2-Nov-17
4.10 Cranes relocation assessment inquiry to be issued Jeni/AD 3-Nov-17
4.11 Inquiry for GCC Plant AD 6-Nov-17
4.12 Inquiry for DIP Plant AD 6-Nov-17
4.13 Inquiry for CCK Plant AD 6-Nov-17
4.14 Detailed Engineering for civil works (to consultants) AD 13-Nov-17 By GPG Indo
4.15 Prepare Inquiry and all relevant documents for Automaton Systems SC Feb-18
4.16 Detailed Engineering for MEI works AD 26-Jan-18 Pending Procurement of main packages
Air compressors assessment and inquiry for Pulping Lines, GCC, CCK, DIP & BOP
4.17 DS 16-Jan-18
areas to be issued
Page 1 of 2
Inquiries for Ongoing Projects DOCUMENT NUMBER : P-JktGPG-100-14-RPT-0006
7.2 Detailed engineering for civil for 1 SP and 2 TMs AD Completed on 24 Mar 17
7.3 Detailed engineering for MEI for 1 SP and 2 TMs (to consultants) AD 31-Mar-17 Completed on 27 Apr 17
Page 2 of 2