Inquiries for Ongoing Projects DOCUMENT NUMBER : P-JktGPG-100-14-RPT-0006

Status as of 05 January 2018

New
PIC Issue Target Status Remarks
Forecast
IKK1 (KW-2 x New Brown Board Machines, 3 new 410t/h@130, 3 new
1.0 Postponed
TG@70MW) - Existing Field

2.0 IKK2 (General Items for whole area)


2.1 Soil Investigation AD 4-Aug-17 
2.2 Basic Engineering for Road & Bridge AD 9-Aug-17 
Will use internal resources for manpower &
2.3 Inquiry for new Topography AD 15-Aug-17  equipment
2.4 Temporary Access Road AD 30-Aug-17 
2.5 Site Preparation for Boilers AD 31-Aug-17 
2.6 Basic Engineering for IKK2 (to consultants) AD 15-Sep-17 
2.7 Inquiry for Earthworks for complete site AD 4-Oct-17 
2.8 Overhead Crane technical finalization AD/RX 1-Nov-17 
2.9 Inquiry for New Overhead Cranes AD 1-Nov-17 
2.10 Inquiry for Temporary Facilities AD 10-Jan-18

3.0 IKK2 (KW-BCTMP) - New Greenfield


3.1 Basic Engineering for BCTMP itself (to Andritz) AD 26-Feb-17 
3.2 Inquiry specification for dismantling works (to Canadian contractors) AD 1-Mar-17 
3.3 Inquiry specification for dismantling and erection supervision (to Andritz) AD 5-Mar-17 
3.4 Preparation of Scope of Work for BCTMP upgrade AD 28-Aug-17 
3.5 Inquiry for New BCTMP AD Sep-17 
3.6 Inquiry for Woodhandling plant AD 23-Oct-17 
3.7 Inquiry for Recaustisizing Plant AD 25-Oct-17 
3.8 Inquiry for Evaporation Plant AD 25-Oct-17 
3.9 Inquiry for Lime Kiln AD 26-Oct-17 
3.10 Inquiry for Reccovery Boiler AD 26-Oct-17 
3.11 Detailed Engineering for civil works (rest of plant) AD Feb-18 By GPG Indo
3.12 Detailed Engineering for MEI works - the rest AD May-18 By GPG China
3.13 Detailed Engineering for MEI works - BCTMP (Andritz or consultant) AD Jul-18 Cancelled

4.0 IKK2 ( KW-Ningbo PM1+PM2+PM3 ) - New Greenfield

Inspection services for board machines and stock preparation equipment (for
4.1 AD No need
3rd party inspector to represent APP during dismantling)
Dismantling works for board machines and stock preparation equipment (for
4.2 AD By GPG China
Voith or other contractors)
Inspection services prior to equipment dismantling for Voith and its supervision
4.3 for board machines and stock preparation equipment, Scope of work for Board AD 15-Sep-17 
Machines upgrade (2)
4.4 Inquiry for Stock Preparation AD 19-Oct-17 
4.5 Roll grinding machine - Inquiry release AD/DS 30-Oct-17 
4.6 Finishing house + Auto Warehouses - Inquiry preparation and release AD/RC 30-Oct-17 
4.7 Inquiry for Roll Handling system AD 31-Oct-17 
4.8 Inquiry for Reel wrapping/ Pallet wrapping AD 1-Nov-17 
4.9 BOP areas design criteria (Pulping lines, GCC, CCK, DIP & BOP) JTC 2-Nov-17 
4.10 Cranes relocation assessment inquiry to be issued Jeni/AD 3-Nov-17 
4.11 Inquiry for GCC Plant AD 6-Nov-17 
4.12 Inquiry for DIP Plant AD 6-Nov-17 
4.13 Inquiry for CCK Plant AD 6-Nov-17 
4.14 Detailed Engineering for civil works (to consultants) AD 13-Nov-17  By GPG Indo
4.15 Prepare Inquiry and all relevant documents for Automaton Systems SC Feb-18
4.16 Detailed Engineering for MEI works AD 26-Jan-18 Pending Procurement of main packages
Air compressors assessment and inquiry for Pulping Lines, GCC, CCK, DIP & BOP
4.17 DS 16-Jan-18
areas to be issued

5.0 IKK2 ( 3 new CFB, 3 new TG ) - New Greenfield

5.1 Piling Supply AD 18-Sep-17 


5.2 Cooling Tower (CFB + TG Plant) - Invite Technical Bid SS 18-Oct-17 
5.3 Piling Contract for Power Plant AD 23-Oct-17 
5.4 Water Treatment Plant (WTP) TBD preparation BT 23-Oct-17 
5.5 Demin Plant (TBD preparation) BT 23-Oct-17 
5.6 Condensate Polishing Unit (TBD preparation) BT 23-Oct-17 
5.7 Effluent Treatment Plant (ETP) TBD Preparation BT 27-Oct-17 
5.8 Water Intake System-TBD BT 15-Nov-17 
5.9 Civil contract for Power Plant AD 21-Dec-17 
5.10 Piling Contract for rest of Mill AD 23-Feb-18 Pending Procurement of main packages
5.11 Detail Civil Engineering By Boiler Supplier

Page 1 of 2
Inquiries for Ongoing Projects DOCUMENT NUMBER : P-JktGPG-100-14-RPT-0006

Status as of 05 January 2018

6.0 Perawang MB26 Boiler - To be further handled by Mill


6.1 Basic engineering for BOP (completed) AD 
Detail engineering by Poyry and submitted to
6.2 Detailed engineering for BOP (to consultants) Himmat
Perawang Mill for further action.
6.3 Inquiry for Polisher Himmat 11-Aug-17  Already send to Mill for their review on 26 July
6.4 Inquiry for RO Plant - Demin Himmat 11-Aug-17  2017. Finally comments still not received from Mill

7.0 OKI Tissue Machines


7.1 Basic engineering for civil and MEI for 1 SP and 6 TMs in 3 phases (completed) AD  Re-issued as Rev.1 on 17-Mar

7.2 Detailed engineering for civil for 1 SP and 2 TMs AD  Completed on 24 Mar 17
7.3 Detailed engineering for MEI for 1 SP and 2 TMs (to consultants) AD 31-Mar-17  Completed on 27 Apr 17

8.0 OKI Town Site


8.1 Inquiry specification for master planning of town site (to consultants) DS 17-Mar-17 
Inquiry specification for construction of pre-fabricated houses (to
8.2 DS 17-Mar-17 
suppliers/contractors)

9.0 BU17 - To be further handled by Mill


9.1 Inquiry for Corrugators, Flexos, Gluer Machine BU17 N/A
9.2 Inquiry for Basic Engineering (All Sites) AD 22-Jun-17 

Page 2 of 2