CNI Lapaopao Block Laterite RKEF Project Phase 1 Page: 1/2 Rev.

: A
CSA Design Condition Notification-First Design Input DOC No.: 922A-DCN-009-E821-1

Project Name : CNI Lapaopao Block Laterite RKEF Project Phase 1

Project No. : 922A

Company : PT. Ceria Metalindo Prima

CSA Design Condition Notification-Roasting and Reduction Plant (Area 009)-


Subject :
Instrument and Information System
CNI Lapaopao Block Laterite RKEF Project Phase 1 Page: 2/2 Rev.: A
CSA Design Condition Notification-First Design Input DOC No.: 922A-DCN-009-E821-1

CNI LAPAOPAO Block Laterite RKEF Project Phase


Project No. 922A Works/Area description Design stage Detailed Design
1-Roasting and Reduction Plant

I. Architecture discipline, structure discipline:


Content and requirements

(1) The scanner for #1 roasting kiln requires 2 installation platforms to be erected, and the ▽8.000 platform should be equipped
with guardrails, as shown in the attached drawings for details. The scanner is installed on ▽8.000 platform, and the platform load
is not less than 4000N/m2.

(2) The above two platforms will be dismantled during the second phase construction, and the scanner will be moved to the platform
of #2 roasting kiln for installation.

Chief Designer Approved by Reviewed by Designed by

Instrument and
Design input by Date 17-Feb-23 Design input to Architecture &Structure Date 17-Feb-23