You are on page 1of 36

18.01.

21 0 FOR APPROVAL GVG VGA VPS


DATE REV. NO. DESCRIPTION PREPARED CHECKED APPROVED
REVISIONS
PROJECT NAME :

DESIGN, ENGINEERING, BUILD AND COMMISSIONING OF 120 MLD CAPACITY SEWAGE TREATMENT PLANT IN
ZONE - II AT KODUNGAIYUR WITH SEQUENTIAL BATCH REACTOR (SBR) WITH POWER GENERATION FROM BIO-
GAS INCLUDING OPERATION AND MAINTENANCE FOR TEN YEARS AT CHENNAI.

CLIENT :

CHENNAI METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD , CHENNAI- 600 002

CONTRACTOR: ECO PROTECTION ENGINEERS PRIVATE LIMITED


PLOT NO:943,54th STREET-TVS COLONY,
ANNA NAGAR WEST EXTN., CHENNAI-600 101.

TITLE :
NAME SIGN DATE

PRED GVG 18.01.2021 STRUCTURAL DESIGN CALCULATION OF RCC GAS HOLDER TANK FOR
CHKD VGA 18.01.2021 120 MLD STP AT KODUNGAIYUR-CHENNAI.
APPD VPS 18.01.2021

SIZE REV.
Doc.No 19_EPE-CHWSSB-STP-120MLD-GHT(RCC Part)-SDC-10
A4 0

RELEASED FOR PRELIMINARY TENDER INFORMATION P APPROVAL CONSTRUCTION

Page 1 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Index ,

Table of Contents Page No.



Introduction 2

Geo-technical Investigation & Soil Data 2
Adopted in Design
• Basis
Design 2
• Design Requirement as per
Specific 3
tender Specifications
• for Hydrodynamic Forces
Check 4
• of RCC Container Wall
Design 9
• of Connecting Platforms
Design 19
• of Foundations for Wall
Design 23
• of Valve Chamber
Design 25
• of Base Slab
Design 29
Design of Slav over Valve Chamber 32
Design of Brackets 33

Page 2 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

1) Introduction:- ,

24.0M ID RCC tank has been provided with 22,5M ID Gas Bell as
per the process requirement to store Bio-Gas of 2580 Cum. The gas
bell moves up and down within 16 Nos of Guide columns. The RCC
tank is designed as circular tank with 16 Nos MC125 Guide channels
embedded in RCC wall for Gas bell vertical movement.

2) Geo-technical Investigation & Soil Data Adopted in Design:-


FGL 4 M
DWT EGL 3.8 M
Proposed founding level 2.05 M
1.0M Below EGL, Net SBC considered at founding level 180 Kn/sqm
Design Water Table 3.2 M
3) Design Basis:-
Liquid Retaining Structures:-
All water retaining structure are designed as per the provisions
in IS 3370-Part II - 2009 with controlled crack width of 0.2mm
as per the specifications. The ground water level for the design is
adopted at level 3.2 M
For strength calculations water shall be taken up to the wall top
assuming all outlets are blocked . For serviceability limit state
condition water level is adopted at service water height level
Strength Calculations will be carried out using limit state design
as per IS456-2000 with load factor of 1.5 .

Page 3 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

4) Specific Design Requirement as per tender Specifications:- ,

Materials for Construction:-


Plain Concrete as Mud mat:-
PCC as mud mat below RCC , 100mm Thick. M15
Concrete Grades for RCC Structures:-
Liquid Retaining Structure M35
All structural concrete will be with aggregates 40mm down for
Footings and base slab and with 20mm down aggregates for all
water retaining and other structures.
Minimum Thickness of Reinforced Concrete:-
Following minimum thicknesses of the members will be provided
Walls of Liquid retaining Structures 250 mm
Bottom Slab of liquid retaining structures 300 mm
Floors , roof slab , walkways , canopy slabs 125 mm
Minimum Cover to any Reinforcement:-
Water retaining elements 50 mm
Beams:- Free face 40 mm
Face in contact with Soil/Liquid 50 mm
Slabs:- Free face 30 mm
Face in contact with Soil/Liquid 50 mm
Foundations :- Bottom , Top 50 mm
Sides 50 mm

Page 4 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

5) Seismic Force Circular Tank ,

Hydrodynamic effect on the tank walls is computed as per IS 1893


Part 2 -2014. ( Ground Supported Tank)
Type of Tank Circular
Size of the Tank
Inner dia of the Tank, D 24 M
Wall thickness average 0.3 M
Base Slab Thickness 0.35 M
Wall Height 8.000 M
Free Board 0.50 M
Weight of Tank Wall 4580.3 Kn
Mass of Tank wall mw 466902 Kg
Weight of Tank Base Slab 4159 Kn
Mass of Base Slab mb 423922 Kg
( Service condition) Water Height =H 7.500 M
Average Sewage Height, h 7.500 M
Sewage Weight Density 10.000 Kn/M3
Sewage Mass Density 1019.368 Kg/M3
Weight of Sewage = W 33912 Kn
Mass of Sewage =m 3456881 Kg
Parameters for Spring Mass Model:-
Computation of Masses:- h/D 0.31
Refer Fig. 2, Page No.-3, IS 1893-Part 2 : 2014for the coefficients for the masses
mi/m Impulsive Mass coefficient 0.32
mc/m Convective Mass Coefficient 0.6
mi Impulsive Water Mass 1106202 Kg
mc Convective Water Mass 2074128 Kg

Page 5 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Refer Fig. 2(b), Page No.-3, IS 1893-Part 2 : 2014for the coefficients for, the heights
hi/h Impulsive Mass Ht. coefficient 0.375
hc/h Convective Mass Ht. Coefficient 0.510
hi*/h 1.250
hc*/h 1.250
Impulsive sewage Load hi 2.81 M
Convective sewage Load hc 3.83 M
hi*= 9.375 M
hc*= 9.375 M
Computation of Coefficients:- h/D 0.31
Refer Fig. 5, Page No.-5, IS 1893-Part 2 : 2014for the coefficients for the coefficients
Impulsive Mode coefficient, Ci 5.00
Convective Mode Coefficient, Cc 4.0
Computation of Time Periods:-
Impulsive mode time period is computed as per CL. 4.3.1.1, Page No.-4 of
IS 1893-2014 ( Part2)
Conc Grade 35 E= 5000x(sqrt(fck)) 29580.4 N/Sqmm
2.96E+10 N/M2
Mas Density 1019.368 Kg/M3
Wall thickness 300 mm
Average Ht (M) 7.500 Time Period, Ti 0.06 Sec.
Time Period for Convective mode :- as per CL. 4.3.2.2 (a) of IS:1893(Part-II)-2014
Tc= Cc x Sqrt(D/g)
Tc= 6.26 Sec
Design Horizontal Seismic Coefficients:-
Parameters as per DBR for Civil & Structural Works
Ah= Z/2 x I /R x ( Sa/g)
Z= Zone factor 0.16

Page 6 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

I=Importance Factor , 1.5


Refer Table 3 IS1893-II R for Ground Supported tank 2.5
R for Under Ground Tank 4
Total Height of Tank 7.500 M
Height of Tank below GL 1.5 M
Refer table 3 IS 1893-Part2 R= for Fixed base Tank 3.65
( R adopted for partially burried tank )
Impusive masses:- Time Period 0.06 Sec
Refer damping 5% Sa/g as per IS 1893-Part 1 2.5
Ahi= 0.082
Convective Masses:- Time Period 6.26
Refer Damping 0.5% ( Med Soil)Sa/g as per IS 1893-Part 1 0.60
CL. 4.4 & 4.5.2 of IS:1893 Ahc= 0.020
(Part-II)-2014
Base Shear wall bottom :-
Base shear Impulsive mode Vi= 1265 Kn
Base shear Convective mode Vc= 407 Kn
Resultant Base Shear = V 1329 Kn
%age base shear of Total weight 3.45 %age
Moment at Base of the wall:-
Moment due to impulsive mode Mi= 4005 Kn-M
Moment due to convective mode Mc= 1557 Kn-M
Resultant B.M M= 4297 Kn-M
Check for over Turning:-
Overturning Moment Impulsive Mass Base bottom 10347.3 Kn-M
Overturning Moment Convective Mass Base bottom 3958 Kn-M
Total Over Turning 11078 Kn-M
Restoring Moment Wall+Base+ Water 524607 Kn-M

Page 7 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

FOS against Over Turning , 47.4


>> 1.2 OK
Sloshing Wave Height:-
dmax = Ahi x R x D /2 0.88 M
Anchorage Requiremet:- Overflow will Occur
h/D 0.31
1/Ahi 12.20
Not Required
Impulsive Hydrodynamic Pressure on wall:-
Maximum pressure occurs at the base of wall Refer CL 4.9.1 (a) of
IS 1893-Part 2 -2014 h= 7.500 M
Qiw at base of tank (y=0) 0.859
Ø=0 Piw at base of tank (y=0) 5.5470 Kn/Sqm
Equivalent Pressure:-
Refer CL 4.9.4 IS 1893-Part2 qi= 23.616 Kn/m
( Impulsive) Pr at bottom 5.510 Kn/Sq
Pr at top 0.787 Kn/Sq

0.787

5.5470 5.510
Actual Adopted
Convective Hydrodynamic Pressure on Wall Refer
:- CL 4.9.2 (a) of IS 1893-Part 2 -2014
Convective pressure at wall Base Y=0
Qcw at Y=0

Page 8 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Cosh(3.674xY/D) , 1.0
Cosh(3.674xh/D) 1.735
Qcw= 0.3242
Pcw at y=0 1.0374 Kn/sqm
Qcw at Y=h
Cosh(3.674xY/D) 1.735
Cosh(3.674xh/D) 1.735
Qcw= 0.5625
Pcw at y=h 1.800 Kn/sqm
Equivalent Pressure:-
Refer CL 4.9.4 IS 1893-Part2 qc= 10.800 Kn/m
( Convective) Pressure top 1.5264 Kn/Sqm
Pressure bottom 1.354 Kn/Sqm
1.800 1.5264

1.0374 1.354
Actual Adopted
Pressure due to wall Inertia:- Refer CL 4.9.5 of IS 1893-Part 2 -2014
Pww (uniform) 0.615 Kn/sqm
Pressure due to vertical Excitation:- Refer CL 4.10.1 of IS 1893-Part 2 -2014
Time period vertical excitation 0.3
Sa/g 2.5
Ah=2/3x(Z/2xI/RxSa/g) 0.05
Pressure at base due to vertical ground acceleration 3.75 Kn/Sqm

Page 9 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA
,
Resultant Hydrodynamic Pressure as per clause 4.10.2, Page-15 of IS:1893(Part-II)-2014
Max pressure at wall base :- Pr1 at h = 7.500 7.308 Kn/Sqm
Max Pressure at top service water Level:- Pr2 2.0727 Kn/Sqm
Wall is checked conservatively for UDL 7.5 Kn/sqm
under service condition
6) Design of The RCC Container Wall:-
Check for Ultimate Condition:-
a) Normal Condition:- ( Tank Full, Fixed at base )
Tank Full Condition:- H= 8.0 M
D= 24 M
For B,M higher Thickness T= 0.45 M
adopted H x H /( D x T ) 5.93
Say 6.00 M
Check for B.M at Base:-
Refer IS 3370- Part Table 10 for Coeffcient
B.M coefficient at base 0.0187
B.M at Base= M 95.74 Kn-M
D= 450 MM
d= 450-50-8 392 MM
Mu= 1.5 M 144 Kn-M
Mu/b/d/d 0.935 Mpa
Fe 500 Pt= 0.242 %age
Ast= 949 Sqmm/M
Min Pt 0.350 %age
Ast Min 788 Sqmm/M
Steel Required 949 Sqmm/M
Provided T12-180+ T12-180 1255 Sqmm/M
Pt Provided 0.320 %age

Page 10 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Check for Shear at Base:- ,

Refer Table 11 for Shear at base 0.197


Shear Force = V 126 Kn
Ultimate Shear = 1.5 x V 189 Kn
Shear Stress 0.482 Mpa
As per Table 61 allowable shear stress = Tc 0.380 Mpa
Allowing for shear enhancement as per Cl 40.5 of IS 456 for
sections close to support. Allowable Shear Stress 2 x Tc 0.760 Mpa
OK.
Check for Span B.M:- B.M Coefficient 0.0051
B.M in Span M 26.112 Kn-M
D= 350 MM
d= 450-50-6 294 MM
Mu= 1.5 M 39.168 Kn-M
Mu/b/d/d 0.453 Mpa
Fe 500 Pt= 0.200 %age
Ast= 588 Sqmm/M
Min Pt 0.350 %age
Ast Min 613 Sqmm/M
Steel Required 613 Sqmm/M
Provided T12-200 565 Sqmm/M
b) Seismic Condition :- ( Tank Service, Fixed at base )
H= 8.0 M
D= 24 M
For B,M higher Thickness T= 0.45 M
adopted H x H /( D x T ) 5.93
Say 6.00 M
Check for B.M at Base:-

Page 11 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Refer IS 3370- Part Table 10 for Coeffcient ,

B.M coefficient at base Triang. 0.0187


Refer Table 10 B.M coefficient at base UDL 0.0242
B.M at Base= M 91.94 Kn-M
D= 450 MM
d= 450-50-8 392 MM
Mu= 1.5 M 138 Kn-M
Mu/b/d/d 0.897 Mpa
Fe 500 Pt= 0.215 %age
Ast= 843 Sqmm/M
Min Pt 0.350 %age
Ast Min 788 Sqmm/M
Steel Required 843 Sqmm/M
Provided T12-180+ T12-180 1255 Sqmm/M
Pt Provided 0.320 %age
Check for Shear at Base:-
Refer Table 11 for Shear at base Triangular Load 0.197
Udl Load 0.222
Shear Force = V 135 Kn
Ultimate Shear = 1.5 x V 202 Kn
Shear Stress 0.516 Mpa
As per Table 61 allowable shear stress = Tc 0.380 Mpa
Allowing for shear enhancement as per Cl 40.5 of IS 456 for
sections close to support. Allowable Shear Stress 2 x Tc 0.760 Mpa
OK.
Check for Span B.M:- B.M Coefficient Triang. Load 0.0051
B.M Coefficient UDL Load 0.0049
B.M in Span M 26.832 Kn-M

Page 12 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

D= , 350 MM
d= 450-50-6 294 MM
Mu= 1.5 M 40.248 Kn-M
Mu/b/d/d 0.466 Mpa
Fe 500 Pt= 0.120 %age
Ast= 353 Sqmm/M
Min Pt 0.350 %age
Ast Min 613 Sqmm/M
Steel Required 613 Sqmm/M
Provided T12-180 627 Sqmm/M
Steel Provided at bottom : T12-180 + T12-180 on Inner Face
T12-180 + T10-180 on Outer Face
Steel Provided in Span : T12-180 on Both Faces.
c) Service Water :- ( Tank Service, Fixed at base )
H= 8.0 M
D= 24 M
For B,M higher Thickness T= 0.45 M
adopted H x H /( D x T ) 5.93
Say 6.00 M
Check for B.M at Base:-
Refer IS 3370- Part Table 10 for Coeffcient
B.M coefficient at base Triang. 0.0187
Refer Table 10 B.M coefficient at base UDL 0.0000
B.M at Base= M 89.76 Kn-M
Check for Span B.M:- B.M Coefficient Triang. Load 0.0051
B.M Coefficient UDL Load 0.0000
B.M in Span M 24.480 Kn-M

Page 13 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Check for Crack Width at Base:- B,M , 89.760 Kn-M

<< 0.2MM OK

Page 14 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Check for Crack width in The Span:- B.M , 24.480 Kn-M

<<< 0.2 MM OK

Page 15 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Design for Hoop Forces: ( Hinged at base Condition adopted) ,

H= 8.0 M
D= 24.0 M
T= 0.35 M
H x H /( D x T ) 7.619
Say 8.0000
Tank Full case : Triangular Load 80 Kn/Sqm
UDL 0.0 Kn/Sqm
Ast. Provided
Ht Coeff Tr. Coeff Udl Force ( T)Force (Tu) Ast
Kn Kn Sqmm
T12-150 0.0H -0.015 0.985 -14.4 -21.60 0.00
T12-150 0.1H 0.096 0.996 92.16 138.24 317.79
T12-150 0.2H 0.208 1.088 199.68 299.52 688.55
T12-150 0.3H 0.324 1.024 311.04 466.56 1072.55
T12-150 0.4H 0.443 1.043 425.28 637.92 1466.48
T12-100 0.5H 0.564 1.064 541.44 812.16 1867.03
T12-100 0.6H 0.661 1.061 634.56 951.84 2188.14
T16-125 0.7H 0.697 0.997 669.12 1003.68 2307.31
T16-125 0.8H 0.621 0.821 596.16 894.24 2055.72
T12-150 0.9H 0.386 0.486 370.56 555.84 1277.79

-ve Sign Shows Compression

Page 16 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Tank Seismic : Triangular Load , 75 Kn/Sqm


UDL 7.5 Kn/Sqm
Ast Provided
Ht Coeff Tr. Coeff Udl Force ( T)Force (Tu) Ast
Kn Kn Sqmm
T12-150 0.0H -0.015 0.985 75.15 112.73 259.14
T12-150 0.1H 0.096 0.996 176.04 264.06 607.03
T12-150 0.2H 0.208 1.088 285.12 427.68 983.17
T12-150 0.3H 0.324 1.024 383.76 575.64 1323.31
T12-150 0.4H 0.443 1.043 492.57 738.86 1698.52
T12-100 0.5H 0.564 1.064 603.36 905.04 2080.55
T12-100 0.6H 0.661 1.061 690.39 1035.59 2380.66
T16-125 0.7H 0.697 0.997 717.03 1075.55 2472.52
T16-125 0.8H 0.621 0.821 632.79 949.19 2182.03
T12-150 0.9H 0.386 0.486 391.14 586.71 1348.76
Tank Service : Triangular Load 75 Kn/Sqm
UDL 0.0 Kn/Sqm
Ht Coeff Tr. Coeff Udl Force ( T)
Kn
T12-150 0.0H -0.015 0.985 -13.5
T12-150 0.1H 0.096 0.996 86.4
T12-150 0.2H 0.208 1.088 187.2
T12-150 0.3H 0.324 1.024 291.6
T12-150 0.4H 0.443 1.043 398.7
T12-100 0.5H 0.564 1.064 507.6
T12-100 0.6H 0.661 1.061 594.9
T16-125 0.7H 0.697 0.997 627.3
T16-125 0.8H 0.621 0.821 558.9
T12-150 0.9H 0.386 0.486 347.4

Page 17 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Check For Crack width Hoop Force , 627.3 Kn


Provided T16-125 Both Faces

<< 0.2MM OK
Check For Crack width Hoop Force 594.5 Kn
Provided T12-100 Both Faces

<< 0.2MM

Check for Crack Width:- Hoop Force 398.7 Kn


Provided
Page 18 ofT12-150
34 Both Faces
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA
,

<< 0.2 MM OK

Page 19 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

7) Design of connecting Platform and Staircase:- ,

Staircase is provided with sringer Beam 350MM x 750 Deep.


Design of Stair Case ( With Stringer Beam ) :-
Fck ( Mpa) 25 Total Span of the Stiar Case 13 M
Fy ( Mpa) 500 Laanding Left Side 0 M
b(MM) 450 Landing Right Side 0 M
D(MM) 800 Riser 150 MM
Width (M) 1.2 Tread 250 MM
Waste Slab thickness 150 MM
Simply Stair Case Slope 30.9795 Degree
Supported Dead Load Landing +50th. Finish 15.3 Kn/M
Sloping Part Dead Load ( Beam + Slab + step + 50 th. Finish ) 19.8 Kn/M
Live Load 5 Kn/sqm
Total load from Staircase 354.82 Kn
Rleft= 177.41 Kn
Point of Zero Shear from left 6.50 M
Bending Moment in Beam 608.26 Kn-M
Bar Diameter 25.00 MM
Clear Cover (MM)
40 Effective . Depth d= 737.5 MM
B.M Mu/b/d/d Pt=
(Mpa) Ast(Sqmm)
Refer SP 16 608.26 1.68 1.10 3646.97
Nos of Bars provided 9 Nos
Ast Provided 4415.625 Sqmm
Pt Provided in the span 1.33 %age

Page 20 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

At top Provided 4 Nos T16 Nominal Steel. , Ok


Check for Deflection :- Refer Cl.23.2.1 of IS456-2000
Basic Value of Span/effective Depth
20 Continuity1fact.
fs=Steel Reqd./SteelProv. X 0.58Fy 239.5178
Ref. Fig 4 IS 456-2000 Modification factor 0.93
Depth required d ( MM ) 697.94 Ok
Check for Shear:- R left 177.41 Kn
R Right 177.41 Kn
Max S.F Vu = 266.11 Kn
Shear Stress Tc= 0.80 Mpa
Allowable shear Stress in Conc. 0.71 Mpa
Shear Taken By Concrete Vc= 256.22 Kn
Vus= 9.89 Kn
Bar Diameter 8.00 MM
No of legs 4.00 Nos
Area of Steel in shear 200.96 Sqmm
Spacing of stps 200.00 MM
Shear Capacity 267.55 Kn
OK
In the steps as cantilever is only 0.425m Provided Nominal
150th. Slab with T10-200 Main Bars.
Also the reaction on column is only 177Kn, provided 450X
500 column with nominal 0.8% steel ( Provided 4 T25 +
6 Nos T16 and Links T8-200). For footing provided 2.0M Sq
with 350 Th, and T12-150 bottom steel bothways.
Design of top Beam:-
Span of the beam 8.00 M
Beam width Provided 0.45 M

Page 21 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Beam Depth Provided , 0.90 M


Self Load Beam 10.13 Kn/M
Loading from walk way 150th + LL+ Finish - 1.2 M wide 12.30 Kn/M
Total UDL 22.43 Kn/M
Staircase Reaction 177.41 Kn
B.M in Beam simply Supported 534.22 Kn-M
Shearing Force 178.40 Kn
Bending Moment in Beam 534.22 Kn-M
Bar Diameter 25.00 MM
Clear Cover 40 Effective . Depth d= 837.5 MM
B.M Mu/b/d/d Pt=
(Mpa) Ast(Sqmm)
Refer SP 16 534.22 2.54 0.62 1817.38
Nos of Bars provided 4 Nos
Ast Provided 1962.5 Sqmm
Check for Shear:- R left 178.40 Kn
R Right 178.40 Kn
Max S.F Vu = 267.61 Kn
Shear Stress Tc= 0.91 Mpa
Allowable shear Stress in Conc. 0.56 Mpa
Shear Taken By Concrete Vc= 164.15 Kn
Vus= 103.46 Kn
Bar Diameter 8.00 MM
No of legs 4.00 Nos
Area of Steel in shear 200.96 Sqmm
Spacing of stps 200.00 MM
Shear Capacity 303.83 Kn
OK
Provided at top Nominal 4 T16

Page 22 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Design of Top Walkway all around:- ,

Fck ( Mpa) 30 Clear Short Span =Lxc 1.5 M


Fy ( Mpa) 500 Clear Long Span =Lyc 0 M
b(MM) 1000 Slab Thickness Provided =T 0.175 M
Effective Short Span = Lx 1.5 M
Effecctive Long Span =Ly 0 M
Dead Load Slab 4.375 Kn/sqm
Floor Finish 1.5 Kn/sqm
Live Load 5 Kn/sqm
Total UDL 10.875 Kn/sqm
Clear Cover (MM)
25 Adopting 10MM bar Eff. Depth d= 145 MM
B.M coefficients B.M Mu/d/d/d Pt=
(Mpa) Ast(Sqmm)
S.Span B.M Top0.5 12.23 0.87 0.21 301.55
Ast provided at Top T10-200
Ok 392 Sqmm
Pt Provided 0.270 %age
Check for Deflection :- Refer Cl.23.2.1 of IS456-2000
Basic Value of Span/effective Depth
7 Continuity1fact.
fs=Steel Reqd./SteelProv. X 0.58Fy 223.0821
Ref. Fig 4 IS 456-2000 Modification factor 1.700
Depth required d 126.06 MM
OK

Page 23 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

8) Design of Foundations for The Wall:- ,

Loading on The wall:-


Self Load wall 70 Kn/M
2.4 M Height Wall Thickening at bottom 10.5 Kn/M
Top Walkway 16.31 Kn/M
Self Load footing:-
Width Provided 2.45 M
Thickness provided 0.45 M
Footing Load 27.5625 Kn/M
Loading from the Guide Frame:-
16 Nos Verticals provided ISMB 300 56.576 Kn
Bracings 2 Ls 65 x 65 x 6 46.4 Kn
2 nos Box 150 49.856 Kn
Total Load 152.832 Kn
Adopted in Design 200 Kn
Load/M 2.603839 Kn/M
Total D.L 126.98 Kn/M
Base pressure 51.8281 Kn/M
Water Load effect:- Water Height 8.0 M
Footing Projection 1 M
Water Load 80.00 Kn/M
B.M at base due to water 95.74 Kn-M
Net B.M 37.744 Kn-M
Additional Base Pressure OS 70.38134 Kn/Sqm
Additional Base Pressure IS -5.075219 Kn/Sqm
Base pressure in-Combination with DL
OutSide ( OS) 122.2094 Kn/sqm
Inside ( IS) 46.75288 Kn/sqm

Page 24 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Soil Load effect:- Water Height , 1.5 M


Footing Projection 1 M
Soil Load 30.00 Kn/M
B.M at base due to Soil 0.00 Kn-M
Net B.M -21.75 Kn-M
Additional Base Pressure IS -9.496043 Kn/Sqm
Additional Base Pressure OS 33.98584 Kn/Sqm
Maximum Base Pressure:- OS 156.1953 Kn/Sqm
IS 37.25684 Kn/sqm
<< 180 Kn/sqm OK
Design of Footing Projection:- Oustside Projection
Tank Full + No Soil Max pressure 156.1953 Kn/Sqm
Deucting Self Load Footing + Soil , Design Pressure = 114.9453 Kn/Sqm
( Adopted UDL Conservatively) Say 120 Kn/sqm
Footing Projection 1 M
B.M = M 60 Kn-M
D= 450 MM
d=450-50-6 394 MM
Mu/b/d/d 0.579762 Mpa
Pt ( Fe 500) 0.18 %age
Ast= 709.2 Sqmm/M
Provided T12-150 753 Sqmm/M
Min top steel 0.35%, Ast= 450x0.35x1000/100/2= 787.5 Sqmm/M
Provided Top T12-125 904 Sqmm/M
Shearing Force 120 Kn
Shear Stress 0.456853 Mpa
Allowable allowing for shear enhancement at support= 0.58 Mpa OK
( Refer table 61 SP 16)
,

Page 25 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

9) Design of Walls of Valve Chamber:- ,

Wall Top level 4.3 M


Wall base level 0.5 M
Wall Height 3.8 M
Soil Level Outside 4 M
Subsoil water Level 3.2 M
Dry Soil Ht. 0.8 M
Wet Soil Ht 2.7 M
Pressure at base Triangular 48.5 Kn/Sqm
Live Load surcharge 10 Kn/Sqm
Lateral Pressure UDL 5 Kn/Sqm
Wall is designed using Moody's Charts
Boundary Condition
Top Free
Bottom & sides Fixed
Thickness provided in bottom 0.25 M
Thickness provided at top 0.25 M
Average thickness provided =T 0.25 M
Triangular Pressure 48.5 Kn/sqm
Clear Horizonatal Span =H 2.5 M
Vertical Span 4.3 M
2a Horizontal Span = H+T 2.75 M
b Vertical Span 4.3 M
a/b 0.319767
Adopted in design 0.375
Loading is split in to two parts UDL + Triangular Load
UDL 5 Kn/Sqm
UDL 5 Kn/sqm

Page 26 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Triangular Load , 48.5 Kn/sqm


Coefficeients for Triangular Load:-
Refer Coefficients as per MOODY's Chart ( Refer Figure 4)
Coefficent for B.M at base 0.02
Coefficent for B.M at V.span 0.0061
Coeffcient B.M Horz. Support 0.021
Coefficnt for B.M Horz. Span 0.01
Coefficent for reaction at base 0.265
Coefficentt for reaction at H.ends 0.2
Coefficients for UDL Load :- Refer Fig 1
Coefficent for B.M at base 0.029
Coefficent for B.M at V.span 0.0082
Coeffcient B.M Horz. Support 0.0476
Coefficnt for B.M Horz. Span 0.025
Coefficent for reaction at base 0.341
Coefficentt for reaction at H.ends 0.375
Bending moment = P x Coeff. x b xb , Reaction = Coeff.xPxb
B.M at base 20.61635 Kn-M
B.M at V.span 6.228357 Kn-M
B.M Horz. Support 23.23269 Kn-M
B.M Horz. Span 11.2789 Kn-M
Reaction at base 62.59725 Kn
Reaction at H.ends 49.7725 Kn
Design of section at Base :-
B.M at Base = M 20.61635 Kn-M
Ultimate B.M = 1.5 x M 30.92453 Kn-M
D provided 250 MM
d= D-50-6 194 MM

Page 27 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

B= , 1000 MM
Mu/b/d/d 0.821674 Mpa
Refer table 3 SP16,Fe 500 Pt= 0.2 %age
Ast= 388 Sqmm
Min. Pt for Section 0.35% Ast Min. 437.5 Sqmm
Required Ast 437.5 Sqmm
Provided at bottom T12-100
Ast Provided 565 Sqmm OK
Check for Shear Force :- Shear Force V = 62.59725 Kn
Ultimate Shear = 1.5 X V 93.89588 Kn
Shear Stress T 0.483999 Mpa
Pt provided 0.291237 %age
Refer table 61 SP16 Allowable Shear Stress Tc 0.4 Mpa OK
Design of section Vertical Span :-
B.M at Span = M 6.228357 Kn-M
Ultimate B.M = 1.5 x M 9.342535 Kn-M
D provided 250 MM
d= D-50-6 194 MM
B= 1000 MM
Mu/b/d/d 0.248234 Mpa
Refer table 3 SP16,Fe 500 Pt= 0.1 %age
Ast= 194 Sqmm
Min. Pt for Section 0.35% Ast Min. 437.5 Sqmm
Required Ast 437.5 Sqmm
Provided at span T12-200
Ast Provided 565 Sqmm OK
Design of section at Horizontal ends :-
B.M at ends = M 23.23269 Kn-M

Page 28 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Ultimate B.M = 1.5 x M , 34.84903 Kn-M


D provided 250 MM
d= D-50-6-12 182 MM
B= 1000 MM
Mu/b/d/d 1.052078 Mpa
Refer table 3 SP16,Fe 500 Pt= 0.252 %age
Ast= 458.64 Sqmm
( Compression) Axial Force in wall = T 0 Kn
Ultimate Force = 1.5 x T=Tu 0 Kn
=Tu/2/(0.87 xFy) Ast for axial force each face 0 Sqmm
Total Steel 458.64 Sqmm
Min. Pt for Section 0.35% Ast Min. 437.5 Sqmm
Required Ast 458.64 Sqmm
Provided at ends T12-200
Ast Provided 565 Sqmm OK
Check for Shear Force :- Shear Force V = 49.7725 Kn
Ultimate Shear = 1.5 X V 74.65875 Kn
Shear Stress T 0.410213 Mpa
Pt provided 0.31044 %age
Allowable Shear Stress Tc 0.4 Mpa OK
Design for Horizontal B.M at Span :-
B.M at span = M 11.2789 Kn-M
Ultimate B.M = 1.5 x M 16.91835 Kn-M
D provided 250 MM
d= D-50-12-6 182 MM
B= 1000 MM
Mu/b/d/d 0.510758 Mpa
Refer table 3 SP16,Fe 500 Pt= 0.15 %age

Page 29 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Ast= , 273 Sqmm


Axial Force in wall = T 0 Kn
Ultimate Force = 1.5 x T=Tu 0 Kn
=Tu/2/(0.85 xFy) Ast for axial force each face 0 Sqmm
Total Steel 273 Sqmm
Min. Pt for Section 0.35% Ast Min. 437.5 Sqmm
Required Ast 437.5 Sqmm
Provided at Horz. Span T12-200
Provided 565 Sqmm
Provided above steel in shorter walls also.
10) Design of Base Slab:-
Base Slab is designed for net uplift pressure deducting the self
load of the base slab.
Uplift Prssure 10.3005 Kn/sqm
Self Load Slab 8.75 Kn/sqm
q= Net Design Pressure 1.5505 Kn/sqm
2a= Span Diameter of the Base slab 24.45 M
B.M in Base Slab as Circular Slab:-
B.M = q x a x a ( 3 + v )/16 B.M 45.621
v= 0.15 Poisson ratio
Mu= 68.43076 Kn-M
d=350-12-6-50 282 MM
Mu/b/d/d 0.860504
Pt= 0.2 %age
Ast= 564 Sqmm
Min Steel top 0.35% 612.5 Sqmm/M
Provided at top T12-175 Both faces , at bottom as surfacezone is 100 MM
Provided T12-250

Page 30 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Check for F.OS Against Uplft:- ,

Volume of Water Replaced;-


Base Slab Diameter 26.9 M
Thickness 0.35 M
Volume Displaced 198.8118 Cum
Walls Wall thickness 0.45 M
Wall Height Submerged 0.7 M
Volume Displaced 24.20275 Cum
Internal Volume Displace V Internal 316.512 Cum
Total Volume Displaced 539.5266 Kn
Uplft Force 5292.756 Kn
Downward Force:-
Self Load base Slab 4970.296 Kn
Self Load Wall 0.275 Th. 1361.25 Kn
Top Walkway 165.7031
Soil Load on Projections
( Adopted 18 Kn/Sqm) Soil Load /Sqm 14.96 Kn/Sqm
Soil Load 1217.218 Kn
Total Load 7714.467 Kn
FOS against Uplift 1.311797
>> 1.2 OK

Page 31 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

Check for Crack Width Base Slab:- ,

Page 32 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

11) Design of The Slab over Valve Chamber ,

Fck ( Mpa) 35 Clear Short Span =Lxc 2.5 M


Fy ( Mpa) 500 Clear Long Span =Lyc 2.5 M
b(MM) 1000 Slab Thickness Provided =T 0.15 M
Effective Short Span = Lx 2.65 M
Effecctive Long Span =Ly 2.65 M
All Edge Aspect Ratio Ly/Lx 1
Cont. As aspect ratio < 2 Two Way
Dead Load Slab+6 MM Plaster 3.876 Kn/sqm
Floor Finish 1.5 Kn/sqm
Live Load 5 Kn/sqm
Total UDL 10.376 Kn/sqm
Clear Cover (MM)
30 Adopting 10MM bar Eff. Depth d= 115 MM
B.M coefficients B.M Mu/d/d/d Pt=
(Mpa) Ast(Sqmm)
S.Span B.M Top0.032 2.33 0.26 0.06 70.57
S.Span B.M Bot.0.024 1.7 0.20 0.05 52.81
L.Span B.M Top0.032 2.33 0.26 0.06 70.57
L.Span B.M Bot.0.024 1.75 0.20 0.05 52.81
Ast provided bottom Short Span T8-200
250 Sqmm
Pt Provided in the span 0.22 %age
Check for Deflection :- Refer Cl.23.2.1 of IS456-2000
Basic Value of Span/effective Depth 20 Continuity1.3
fact.
fs=Steel Reqd./SteelProv. X 0.58Fy 61.2591 Mpa
Ref. Fig 4 IS 456-2000 Modification factor 2.00
Depth required d 50.96 MM
Provided at Short Span Spt. T8-200 OK
Provided at Long Span Spt. T8-200 Long Span
T8-200

Page 33 of 34
Design, Engineering, Build and Commissioning of 120 MLD Capacity STP Doc.,No. Rev 0
PROJECT: in Zone II at Kodungaiyur with SBR, with Power Generation from Bio Gas 19-EPE-CHWSSB-STP-120MLD-
including Operation and Maintenance for Ten Years at Chennai. GHT(RCC)-SDC-10
Designed Checked Approved
TITLE: Structural Design Calculations of Gas Holding Tank ( RCC part)
VPS VGA VGA

12) Design of Bracket BR1:- 900 Deep x 500 Wide x 250 ,

This bracket supports supports the Steel Guide and bolts of the
Guides are anchored in the bracket.
Bracked Width Provided 550 MM
Depth Provided 900 MM
As such Guides will be sitting on the Main wall and bolts will be
anchored in the bracket. Cantilver span of the bracket from wall
face being only 0.25M. Nominal Steel is provided.
( In 550 Width) Steel Provided 6 Nos T16 1200 Sqmm
Stps Provided in 250 2 Nos T12
Design of Bracket BR2:-
( Reaction from Beam) Reaction on the Bracket 178.40 Kn
Max Cantilever 0.175 M
B.M 31.22072 Kn-M
b= 750 MM
D= 800 MM
d= 744 MM
Mu/b/d/d 0.112805 Mpa
Nominal 0.2%, Ast 1116 Sqmm
Provided 6 Nos T16 1200 Sqmm
Vu= 267.6062 Kn
Vu/d 3.596857 Kn/Cm
Refer Table 62 SP16 Provided T10 6 L 100 16.8 Kn/Cm
Capacity

Page 34 of 34

You might also like