You are on page 1of 6

PUBLIC HEALTH AND MUNICIPAL

ECO PROTECTION ENGINEERS PRIVATE LTD., ENGINEERING DEPARTMENT


RAJAMAHENDRAVARAM AP

SEWAGE AND SEPTAGE MANAGEMENT WITH DOCUMENT NUMBER


CONSTRUCTION OF 5MLD STP IN
PROJECT
BHIMAVARAM MUNICIPALITY UNDER AMRUT
PROJECT 2016-2020 18-EPE-BVRM-STP-SBR-STR-201-A

SBR C Tech Basin Qauntity Estimate Prepared Checked Approved Date


TITLE considering SBC as 50kN/m2 after Geo
Stabilization RKK VJ MGK

Estimation SBR (CONCRETE QUANTITY)


Rect Trap
Concrete
No Length (m) Depth (m) Width (m)
(m3)

Basin 1 32.4 0.15 28.7 139.49

Plinth beam 2 2.7 0.15 0.6 0.49

Total 139.98
Wastage
10% 13.998
TOTAL 153.978

2. RCC (M30)

Rect Trap
Concrete
No Length (m) Depth (m) Width (m) a (m) b (m) h(m) (m3)
Raft
Long Wall (Toe) A-
A 1 14.2 0.600 2.1 17.9
Long Wall Heel
(rect) 1 14.2 0.600 0.6 5.12
Long Wall Heel
(Trap) 1 14.2 0.6 0.3 1.6 10.224
Short Wall (Toe) 6-
6 1 28.6 0.750 2.75 58.99
Short Wall Heel
(rect) 1 28.6 0.750 0.75 16.09
Short Wall Heel
(Trap) 1 28.6 0.75 0.3 2.75 41.3
Short Wall (Toe) 2-
2 1 28.6 0.750 2.75 58.99
Short Wall Heel
(rect) 1 28.6 0.750 0.75 16.09
Short Wall Heel
(Trap) 1 28.6 0.75 0.3 2.75 41.3
Middle Short Wall
4-4 1 26.2 0.750 2.25 44.22
Middle Short Wall
(Trap) 2 26.2 0.75 0.3 1.65 22.7
Middle Short Wall
(Sunken portion) 1 5.55 0.750 1.8 7.5
Middle Short
Wall(locally raised) 1 2.3 0.800 1.8 3.32
Long Wall Toe
along F-F 1 14.2 0.450 1.05 6.71
Long Wall Heel
along F-F 1 14.2 0.450 1.5 9.59

1
Base Slab 2 21.7 0.300 7.1 92.45

Total 452.494
Wastage
10% 45.2494
Total Raft 497.7434
Wall

Long Wall (rect) 1 13.4 2.000 0.2 5.36

Long Wall (trap) 1 13.4 0.6 0.2 4 13.4


Long Wall 0.6m at
T junction (rect) 1 8.2 2.000 0.45 7.38
Long Wall 0.6m at
T junction (trap) 1 8.2 0.6 0.45 4 12.3
Long Wall (rect) 1 13.4 2.850 0.2 7.638

Long Wall (trap) 1 13.4 0.45 0.2 4 11.39


Long Wall 0.45m at
T junction (rect) 1 8.2 6.000 0.45 22.14
Short Wall 0.75m
(rect) 1 38.6 2.000 0.2 15.44
Short Wall 0.75m
(trap) 1 38.6 0.75 0.2 4 44.39
Middle Short Wall
0.75m (rect) 1 24.4 2.000 0.2 9.76
Midlle Short Wall
0.75m (trap) 1 24.4 0.75 0.2 4 28.06
Wall parallel to
0.3m thick wall 1 22.6 6.000 0.3 40.68

Baffle Wall 4 3.8 2.900 0.2 8.82

Baffle Wall 6 3.8 5.800 0.2 26.45


Corner Wall along
Long wall 4 6 0.4 0.2 1.5 13.2
Corner Wall along
Long wall 4 6 0.4 0.2 1.5 13.2
Corner Wall along
Short wall 4 6 0.75 0.45 1.5 26.1

Wall inside 1 5.1 1.500 0.4 3.06

Wall inside 1 1.8 1.500 0.4 1.08

Wall round sump pit 1 9.2 0.550 0.3 1.52

Wall outlet 1 16 1.500 0.2 4.8

Outlet Base Slab 1 16 0.200 0.7 2.24

Inlet Channel 1 5.3 1.500 0.2 1.59


Inlet Channel from
PTU 1 7.7 1.000 0.2 1.54
Platform Slab all
round 1 52.2 1.200 0.15 9.4
Platform Slab
Central Wall 1 26.75 1.200 0.15 4.82

Platform Flight 2 1.7 1.200 0.15 0.62

Beam 2 2.8 0.300 0.3 0.51

2
Beam 4 2.4 0.300 0.3 0.87

Column 4 10.3 0.300 0.3 3.71

Staircase Beam 1 1.35 0.450 0.3 0.19

Staircase Beam 5 1.35 0.450 0.3 0.92

Staircase Flight 3 3.025 0.150 1.2 1.64

Landing Slab 1 2.1 0.150 1.2 0.38

Column C1 2 6 0.300 0.3 1.08

Actuator Column 4 6 0.750 0.45 8.1

Decanter Support 4 1.2 1.500 0.3 2.16

Decanter Support 4 1.2 0.300 0.75 1.08

Pit 3 2.5 1.000 0.2 1.5

Total 358.518
Wastage
10% 35.8518
Total Wall + all other 394.3698

Total Quantity (Raft + all other) 892.1132

3
PUBLIC HEALTH AND MUNICIPAL
ECO PROTECTION ENGINEERS PRIVATE LTD., ENGINEERING DEPARTMENT
RAJAMAHENDRAVARAM AP

SEWAGE AND SEPTAGE MANAGEMENT WITH DOCUMENT NUMBER


CONSTRUCTION OF 5MLD STP IN
PROJECT BHIMAVARAM MUNICIPALITY UNDER AMRUT
PROJECT 2016-2020 18-EPE-BVRM-STP-SBR-STR-201-A

Prepared Checked Approved Date


SBR C Tech Basin Qauntity Estimate
TITLE
considering SBC as 150kN/m2
RKK VJ MGK

Estimation SBR (CONCRETE QUANTITY)


Rect Trap
Concrete
No Length (m) Depth (m) Width (m)
(m3)

Basin 1 31.88 0.15 28.739 137.43

Total 137.43
Wastage
10% 13.743

TOTAL 151.173

2. RCC (M30)

Rect Trap
Concrete
No Length (m) Depth (m) Width (m) a (m) b (m) h(m) (m3)
Raft
Long Wall
(Grid A) 2 26.5 0.400 4.45 94.34
Short Wall
(Gird 6 & 2) 1 26.8 0.400 4.5 48.24

Central Wall 1 26.5 0.400 4.75 50.35


Short Wall
(Grid F) 1 26.8 0.400 1.65 17.69

Base Slab 2 21.9 0.300 9.35 122.86

Total 333.48
Wastage
10% 33.348
Total Raft 366.828
Wall
Long Wall
(rect) 1 13.4 2.000 0.2 5.36
Long Wall
(trap)
Long Wall 1 13.4 0.6 0.2 4 13.4
0.6m at T
junction
Long (rect)
Wall 1 8.2 2.000 0.45 7.38
0.6m at T
junction (trap) 1 8.2 0.6 0.45 4 12.3
Long Wall
(rect) 1 13.4 2.850 0.2 7.638
Long Wall
(trap) 1 13.4 0.45 0.2 4 11.39

1
PUBLIC HEALTH AND MUNICIPAL
ECO PROTECTION ENGINEERS PRIVATE LTD., ENGINEERING DEPARTMENT
RAJAMAHENDRAVARAM AP

SEWAGE AND SEPTAGE MANAGEMENT WITH DOCUMENT NUMBER


CONSTRUCTION OF 5MLD STP IN
PROJECT BHIMAVARAM MUNICIPALITY UNDER AMRUT
PROJECT 2016-2020 18-EPE-BVRM-STP-SBR-STR-201-A

Prepared Checked Approved Date


SBR C Tech Basin Qauntity Estimate
TITLE
considering SBC as 150kN/m2
RKK VJ MGK
Long Wall
0.45m at T
junction (rect) 1 8.2 6.000 0.45 22.14
Short Wall
0.75m (rect) 1 38.6 2.000 0.2 15.44
Short Wall
0.75m (trap)
Middle Short 1 38.6 0.75 0.2 4 44.39
Wall 0.75m
(rect)
Midlle Short 1 24.4 2.000 0.2 9.76
Wall 0.75m
(trap)
Wall parallel 1 24.4 0.75 0.2 4 28.06
to 0.3m thick
wall 1 22.6 6.000 0.3 40.68

Baffle Wall 4 3.8 2.900 0.2 8.82

Baffle
CornerWall
Wall 6 3.8 5.800 0.2 26.45
along Long
wall
Corner Wall 4 6 0.4 0.2 1.5 13.2
along Long
wall
Corner Wall 4 6 0.4 0.2 1.5 13.2
along Short
wall 4 6 0.75 0.45 1.5 26.1

Wall inside 1 5.1 1.500 0.4 3.06

Wall inside 1 1.8 1.500 0.4 1.08


Wall round
sump pit 1 9.2 0.550 0.3 1.52

Wall outlet 1 16 1.500 0.2 4.8


Outlet Base
Slab 1 16 0.200 0.7 2.24

Inlet Channel 1 5.3 1.500 0.2 1.59


Inlet Channel
from PTU 1 7.7 1.000 0.2 1.54
Platform Slab
all round 1 52.2 1.200 0.15 9.4
Platform Slab
Central Wall 1 26.75 1.200 0.15 4.82
Platform
Flight 2 1.7 1.200 0.15 0.62

Beam 2 2.8 0.300 0.3 0.51

Beam 4 2.4 0.300 0.3 0.87

Column 4 10.3 0.300 0.3 3.71


Staircase
Beam 1 1.35 0.450 0.3 0.19
Staircase
Beam 5 1.35 0.450 0.3 0.92
Staircase
Flight 3 3.025 0.150 1.2 1.64

2
PUBLIC HEALTH AND MUNICIPAL
ECO PROTECTION ENGINEERS PRIVATE LTD., ENGINEERING DEPARTMENT
RAJAMAHENDRAVARAM AP

SEWAGE AND SEPTAGE MANAGEMENT WITH DOCUMENT NUMBER


CONSTRUCTION OF 5MLD STP IN
PROJECT BHIMAVARAM MUNICIPALITY UNDER AMRUT
PROJECT 2016-2020 18-EPE-BVRM-STP-SBR-STR-201-A

Prepared Checked Approved Date


SBR C Tech Basin Qauntity Estimate
TITLE
considering SBC as 150kN/m2
RKK VJ MGK

Landing Slab 1 2.1 0.150 1.2 0.38

Column C1 2 6 0.300 0.3 1.08


Actuator
Column 4 6 0.750 0.45 8.1
Decanter
Support 4 1.2 1.500 0.3 2.16
Decanter
Support 4 1.2 0.300 0.75 1.08

Pit 3 2.5 1.000 0.2 1.5

Total 358.518
Wastage
10% 35.8518

Total Wall + all other 394.3698


Total Quantity (Raft + all other) 761.1978