You are on page 1of 3

Estimation SBR (CONCRETE QUANTITY)

Rect Trap
Concrete
No Length (m) Depth (m) Width (m)
(m3)

Basin 1 32.4 0.15 28.7 139.49

Plinth beam 2 2.7 0.15 0.6 0.49

Total 139.98
Wastage
10% 13.998
TOTAL 153.978

2. RCC (M30)

Rect Trap
Concrete
No Length (m) Depth (m) Width (m) a (m) b (m) h(m) (m3)
Raft

Long Wall (Toe) A-A 1 14.2 0.600 2.1 17.9

Long Wall Heel (rect) 1 14.2 0.600 0.6 5.12

Long Wall Heel (Trap) 1 14.2 0.6 0.3 1.6 10.224

Short Wall (Toe) 6-6 1 28.6 0.750 2.75 58.99

Short Wall Heel (rect) 1 28.6 0.750 0.75 16.09

Short Wall Heel (Trap) 1 28.6 0.75 0.3 2.75 41.3

Short Wall (Toe) 2-2 1 28.6 0.750 2.75 58.99

Short Wall Heel (rect) 1 28.6 0.750 0.75 16.09

Short Wall Heel (Trap) 1 28.6 0.75 0.3 2.75 41.3

Middle Short Wall 4-4 1 26.2 0.750 2.25 44.22

Middle Short Wall (Trap) 2 26.2 0.75 0.3 1.65 22.7


Middle Short Wall (Sunken
portion) 1 5.55 0.750 1.8 7.5
Middle Short Wall(locally
raised) 1 2.3 0.800 1.8 3.32

Long Wall Toe along F-F 1 14.2 0.450 1.05 6.71

Long Wall Heel along F-F 1 14.2 0.450 1.5 9.59

Base Slab 2 21.7 0.300 7.1 92.45

Total 452.494
Wastage
10% 45.2494
Total Raft
497.7434
Wall

Long Wall (rect)


1 13.4 2.000 0.2 5.36

Long Wall (trap) 1 13.4 0.6 0.2 4 13.4

1
Long Wall 0.6m at T
junction (rect) 1 8.2 2.000 0.45 7.38
Long Wall 0.6m at T
junction (trap) 1 8.2 0.6 0.45 4 12.3
Long Wall (rect)
1 13.4 2.850 0.2 7.638

Long Wall (trap) 1 13.4 0.45 0.2 4 11.39


Long Wall 0.45m at T
junction (rect) 1 8.2 6.000 0.45 22.14

Short Wall 0.75m (rect) 1 38.6 2.000 0.2 15.44

Short Wall 0.75m (trap) 1 38.6 0.75 0.2 4 44.39


Middle Short Wall 0.75m
(rect) 1 24.4 2.000 0.2 9.76
Midlle Short Wall 0.75m
(trap) 1 24.4 0.75 0.2 4 28.06
Wall parallel to 0.3m thick
wall 1 22.6 6.000 0.3 40.68

Baffle Wall 4 3.8 2.900 0.2 8.82

Baffle Wall 6 3.8 5.800 0.2 26.45


Corner Wall along Long
wall 4 6 0.4 0.2 1.5 13.2
Corner Wall along Long
wall 4 6 0.4 0.2 1.5 13.2
Corner Wall along Short
wall 4 6 0.75 0.45 1.5 26.1

Wall inside 1 5.1 1.500 0.4 3.06

Wall inside 1 1.8 1.500 0.4 1.08

Wall round sump pit 1 9.2 0.550 0.3 1.52

Wall outlet 1 16 1.500 0.2 4.8

Outlet Base Slab 1 16 0.200 0.7 2.24

Inlet Channel 1 5.3 1.500 0.2 1.59

Inlet Channel from PTU 1 7.7 1.000 0.2 1.54

Platform Slab all round 1 52.2 1.200 0.15 9.4

Platform Slab Central Wall 1 26.75 1.200 0.15 4.82

Platform Flight 2 1.7 1.200 0.15 0.62

Beam 2 2.8 0.300 0.3 0.51

Beam 4 2.4 0.300 0.3 0.87

Column 4 10.3 0.300 0.3 3.71

Staircase Beam 1 1.35 0.450 0.3 0.19

Staircase Beam 5 1.35 0.450 0.3 0.92

Staircase Flight 3 3.025 0.150 1.2 1.64

Landing Slan 1 2.1 0.150 1.2 0.38

Column C1 2 6 0.300 0.3 1.08

Actuator Column 4 6 0.750 0.45 8.1

2
Decanter Support 4 1.2 1.500 0.3 2.16

Decanter Support 4 1.2 0.300 0.75 1.08

Pit 3 2.5 1.000 0.2 1.5

Total 358.518
Wastage
10% 35.8518
Total Wall + all other
394.3698
Total Quantity (Raft + all other)
892.1132