20181203/SPC/M/EEI/xxx

01 July 2019
To : EEI CORPORATION
Attention : MR. EDGAR P. ABEJERO
Project Manager
Cc : FLI (RBLachica / ABBadillo / JRAntonio)
Re : The Seasons Residences Project
8th Ave. Corner 36th Street, Bonifacio Global City, Taguig City.
RESPONSE TO EEI’S LETTER REGARDING INSUFFICIENT
DELIVERY OF REBAR ESPECIALLY 12MM AND 16MM AFFECTING
SCHEDULE OF CONCRETE CASTING SCHEDULE

1. References:
1.1 EEI’s Letter re: Rebar Fabrication and Availability Status by SPC on 26 June 2019
1.2
1.3 EEI’s Letter re: Rebar Fabrication and Availability Status by SPC on 26 June 2019
1.4 CCM and PTG Meeting held on 25 and 26 June 2019 respectively
1.5 Revised Blocking Schedule as of 25 June 2019 See Annex – D
1.6 Status of 4th to 7th Floor Tower as of 10 to 25 June 2019 – Annex A
2. This is to acknowledge receipt of item 1.2 above and we respond thereto further with reference
to the reconciliation between SPC and EEI on 28 June 2019 as documented per item 1.1
above:
2.1 “(first table) Updated Rebar Fabrication & Availability Status as of 25 June 2019”, 1st Para.

Leve Loc. EEI Remarks Status as of 25 June 2019 (Annex -A)


l
7F Tower A No 12mm and 16mm Vertical Structures at 6F-7F not yet
reinforcement available concreted. Ongoing installation of
formworks for slab (H-Frames only).
6F Podium B No 12mm and 16mm 5F Slab not yet concreted, still ongoing
reinforcement available formworks installation for slab.
One (1) Floor behind.
6F Tower C No 12mm and 16mm 5F Slab not yet concreted, still ongoing
reinforcement available formworks installation for slab.
.One (1) Floor behind
6F Podium C No 12mm and 16mm 4F Slab not yet concreted, balance MEPF
reinforcement available block-outs. Two (2) Floors behind.
5F Podium C No 12mm and 16mm 4F Slab not yet concreted, balance MEPF
reinforcement available block-outs. One (1) Floor behind.

 Based on the actual progress in item 1.5 above of the above-mentioned affected
areas per EEI, the alleged unavailability of 12mm and 16mm does not merely
affect its respective schedule since there was a slippage in its precedent
activities. Further, should the Rebars were completely delivered on 25 June 2019,
EEI could still not proceed with the installation of such on the said areas even

1 of 4
with consideration to 2-3 days fabrication period (as informed by EEI in item 1.3
above).
association for
project management
20181203/SPC/M/ EEI/xxx
Corporate 6th Floor, The Linden Suites, San Miguel Avenue, Ortigas Center, Pasig City 1603 Philippines
01 July 2019 Member tel. nos. (632) 637-5951 to 52 fax no. (632) 637-5763 email : spcastro@spcastro.com
Subject: Membership No. R35255
RESPONSE TO
website EEI’S LETTER REGARDING
: www.spcastro.com
REBAR FABRICATION & AVAILABILITY STATUS
Read : ___________ Checked : ___________

Floor Area A. Baseline B. Catch Up C. Catch Up Remarks


Level Schedule Schedule 1 Schedule 2 (C -A)
5F Tower D Z1 15-May-19 05-Jun-19 20-Jun-19 36 days
Podium D Z2 18-Jun-19 16-Jul-19 27-Jul-19 39 days
6F Podium B Z2 06-Jul - -
Podium B Z3 06-Jul - -
Tower C Z1 26-May-19 09-Jun-19 20-Jun-19 25 days
Tower C Z2 16-Jul-19 - -
Tower C Z3 16-Jul-19 - -
Tower D Z1 04-Jun-19 23-June-19 04-Jul-19 30 days
Podium D Z2 08-Jul-19 - -
7F TA Z1 & All 19-May-19 16-Jun-19 17-Jun-19 15 days
Remaining
Areas
Amenity All Areas

2.2 “(second table) Rebar Inventory and Status Report as of 24 June 2019”, 1st Para.
 In line with the reconciliation between SPC and EEI on 28 June 2019 as conveyed in
item 1.1 above, we wish to correct EEI’s report which overly emphasized to 12mm,
16mm and Total Balance for Delivery as of 24 June 2019:
a. 12mm and 16mm

2 of 4
b. Total Balance for Delivery (Combined Grade 40 & Grade 60)

SPC EEI VARIANCE


1,095,733.10 kgs 1,164,173.96 kgs 68,440.86 kgs

2.3 “The total balance of undelivered request rebars as of 24 June 2019…


the impact of which to the Project Schedule shall be continuously assessed”, last Para.
 UPDATE AS OF 28 JUNE 2019:
A. Capitol Steel was able to deliver 43.7 tons of 12mm and 56.44 tons of 16mm from
26 – 28 June 2019. See Annex B – Capitol Delivery Monitoring
B. Steel Asia was able to complete its delivery of 12mm on 24 June 2019 and was able
to deliver 49.47 tons of 16mm on 26 June 2019 that made it complete its delivery.
Note that this P.O under sub-structure was used to aid the undelivered 12mm and
16mm for Capitol and PAGASA. See Annex C – Steel Asia Delivery Monitoring

C. PAGASA completed its delivery of 12mm on 03 June 2019 and was able to deliver
141.3 tons of 16mm from 25 – 28 June 2019 that made it complete its delivery for
Batch 1 Rebar Order List. See Annex D – PAGASA Delivery Monitoring

20181203/SPC/M/ EEI/123
01 July 2019
Subject: RESPONSE TO EEI’S LETTER REGARDING
REBAR FABRICATION & AVAILABILITY STATUS

Continuation…

 To summarize, below is the inventory of 12mm and 16mm rebar delivered from 25 – 28
June 2019 and total remaining balance for delivery:
Diameter 12mm 16mm
Delivered 43.7 Tons 247.21 Tons

3 of 4
For Delivery 74.76 Tons 260.76 ons

 Balance for delivery in Totality:

Items As of 24-June-19 As of 28-June-19 Remarks


Grade 40 0.00 0.00 DONE!
Grade 60 1,095.73 Tons 462 Tons 633.73 Tons were
delivered in 4 days

3. In lieu of items deliberated in 2.1 and 2.3 above, the balance for delivery ( in which the
impact to the Project Schedule is to be continuously assessed by EEI) has been
addressed and we find that the alleged affected schedule as mentioned above are not
attributable to the unavailability of 12mm and 16mm rebars.

3.1 As re-confirmed by EEI in item 1.3 above, the Rebar Order Lists that were requested is
allocated up to 6th Floor Level only. Thus, we wish to remind EEI on the summary of Status
of Concreting Works as of 25 June 2019. See Annex - D

 - Concreted X - Not yet Concreted

AREA FLOOR LEVEL


4F 5F 6F
TOWER A   
PODIUM A   
TOWER B   X
PODIUM B  X X
TOWER C  X X
PODIUM C X X X
TOWER D X X X
PODIUM D  X X
REMARKS 2 areas left 5 areas left 6 areas left

3.2 With the foregoing status above, please be informed that the said balance for delivery is the
deficit from the requested Rebar Order List as a whole yet it does not mean that this
quantity should have been installed by EEI already.

4. In this regard, we wish to remind EEI on its immediate submission of Rebar Order List for 7 th
Floor and also expedite its submission of Cutting List for Amenity Level so as to avoid effect on
the schedule of delivery due to late submission of Rebar Request.
20181203/SPC/M/ EEI/123
01 July 2019
Subject: RESPONSE TO EEI’S LETTER REGARDING
REBAR FABRICATION & AVAILABILITY STATUS

5. In view thereof, we urged EEI to have its monitoring checked and verified or better reconcile
first
in order not to cause misconception between parties.

6. For common record, guidance and EEI’s immediate action to item 4 above.

Thank you.

4 of 4
SPCastro, Inc. Noted by:

DENNIS F. GALICINAO VANESSA S. POCOT


Senior Civil/Structural Coordinator Construction Management Leader

CEZAR A. TALABUCON, JR.


Deputy Supervising Director