Ajor International SA REV 01

Client :- EDCO VK Refractory Relining Plant 2

Ajor International Date: March 13, 2019 Days Expanded During the Month March 2019 Days Expanded During the Month April 2019

12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Refractory application in EDCO Plant 2 VK (Vertical Kiln)- Look

Direct Men
Ahead Schedule and Progress
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W M T

Finish
Start
Sl.
Description
No.
(1) VK phase 1 (C,D,E Upper Parts)
Backup 1st layer 55mm thick 30%
1a). 12-Mar-19 18-Mar-19
Al2O3 application
Above (1.a)Actual Progress
2nd layer 100mm thick 40% Al2O3
1b). 16-Mar-19 24-Mar-19
application
Above (1.b)Actual Progress
Final HF layer 125mm thick 75%
1c). 31-Mar-19 8-Apr-19
Al2O3 application
Above (1.c)Actual Progress
(2) VK phase 2 (A Section Bottom part)

2a). Anchor Welding on section A 17-Mar-19 23-Mar-19


Above (2.a)Actual Progress
Backup 1st layer 55mm thick 30%
2b). 21-Mar-19 31-Mar-19
Al2O3 application
Above (2.a)Actual Progress
2nd layer 100mm thick 40% Al2O3
2c). 26-Mar-19 3-Apr-19
application
Above (2.b)Actual Progress
Final HF layer 125mm thick 57%
2d). 29-Mar-19 6-Apr-19
Al2O3 application
Above (2.c)Actual Progress
(3) VK phase 2 (B Section Middle part)
Backup 1st layer 55mm thick 30%
3a). 1-Apr-19 11-Apr-19
Al2O3 application
Above (3.a)Actual Progress
2nd layer 100mm thick 40% Al2O3
3b). 5-Apr-19 13-Apr-19
application
Above (3.b)Actual Progress
3c). Final HF layer 125mm thick 75% 10-Apr-19 18-Apr-19
Al2O3 application
Above (3.c)Actual Progress
Dismatteling of Scaffolding and
3c). 19-Apr-19 21-Apr-19 PLAN
housekeeping
ACTUAL

Section 1.2 1 of 1 Prepared By: _______________ Checked By: _______________