ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4
M13-
Construction 31.96% 82.83% 26.47%
03
Total 100.00%
We still ahead of schedule in the whole project and we encountered some obstacle during the
Construction work as mentioned below:
120.00%
100.00%
80.00%
60.00%
40.00%
20.00%
0.00%
9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 /1 1 /2 1 /2 1 /2 1 /2 2 /2 2 /2 2 /2 2 /2 3 /2 3 /2 3 /2 3 /2 3 /2 4 /2 4 /2 4 /2 4 /2
/1 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0
29 05 12 19 26 02 09 16 23 01 08 15 22 27 03 10 17 24
29/1 05/0 12/0 19/0 26/0 02/0 09/0 16/0 23/0 01/0 08/0 15/0 22/0 27/0 03/0 10/0 17/0 24/0
2/19 1/20 1/20 1/20 1/20 2/20 2/20 2/20 2/20 3/20 3/20 3/20 3/20 3/20 4/20 4/20 4/20 4/20
Planned 8.86 8.86 8.86 8.86 8.86 8.86 8.86 8.86 8.86 8.86 8.86 2.53 0.00 0.00
percent % % % % % % % % % % % % % %
Actual 10.0 15.0 14.0 15.0 12.0 4.00 5.00 5.00 1.20 1.10 1.10 2.00 1.00 2.00 0.50 1.00 0.50 0.50
Percent 0% 0% 0% 0% 0% % % % % % % % % % % % % %
Planned 8.86 17.7 26.5 35.4 44.3 53.1 62.0 70.8 79.7 88.6 97.4 100. 100. 100. 100. 100. 100. 100.
percent % 2% 8% 4% 0% 6% 3% 9% 5% 1% 7% 00% 00% 00% 00% 00% 00% 00%
Actual 10.0 25.0 39.0 54.0 66.0 70.0 75.0 80.0 81.2 82.3 83.4 85.4 86.4 88.4 88.9 89.9 90.4 90.9
Percent 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
70.%
Total Progress
60.%
50.%
40.%
30.%
20.%
10.%
0.%
1
19/ 26/ 02/ 09/ 16/ 23/ 30/ 06/ 13/ 20/ 27/ 05/ 12/ 19/ 26/ 02/ 09/ 16/ 23/
12/ 12/ 01/ 01/ 01/ 01/ 01/ 02/ 02/ 02/ 02/ 03/ 03/ 03/ 03/ 04/ 04/ 04/ 04/
19 19 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20
Planne 15. 14. 13. 16. 13.
9.3 5.4 3.3 2.9 2.5 1.4 1.4 0.2 0.0 0.0 0.0 0.0 0.0 0.0
d 83 17 54 25 54
Wee 8% 2% 3% 2% 0% 5% 6% 1% 0% 0% 0% 0% 0% 0%
percent % % % % %
kly
Actual 1.5 4.9 4.3 1.5 1.4 4.2 4.0 9.9 8.2 6.6 6.8 4.0 4.5 3.9 3.0 3.7 2.6 3.2 3.6
Percent 1% 3% 7% 1% 2% 9% 6% 5% 1% 9% 8% 7% 8% 6% 5% 8% 8% 2% 8%
Planne 15. 30. 43. 59. 73. 82. 88. 91. 94. 96. 98. 99. 100 100 100 100 100 100 100
d 83 00 54 79 33 71 13 46 38 88 33 79 .00 .00 .00 .00 .00 .00 .00
Cum
percent % % % % % % % % % % % % % % % % % % %
ulati
10. 12. 13. 18. 22. 32. 40. 46. 53. 57. 62. 66. 69. 73. 75. 79. 82.
ve Actual 1.5 6.4
80 32 74 03 09 03 24 94 82 89 47 43 47 25 93 15 83
Percent 1% 4%
% % % % % % % % % % % % % % % % %
120.00%
100.00%
80.00%
60.00%
40.00%
20.00%
0.00%
01/12/19 20/01/20 10/03/20 29/04/20 18/06/20
16/12/1 23/12 30/1 06/01 13/01 20/01 27/0 03/0 10/02 17/02 24/02 02/0 09/03 16/0
9 /19 2/19 /20 /20 /20 1/20 2/20 /20 /20 /20 3/20 /20 3/20
Planned 6.17 5.88 5.88 5.88 1.68
0.68% 0.68% 5.88% 5.88% 5.88% 5.88% 5.88% 5.88% 5.88%
percent % % % % %
WEEKLY
Actual 8.72 10.64 11.33 9.26 5.83 2.03 2.59
0.58% 2.26% 9.75% 5.94% 5.46% 3.00% 2.20%
Percent % % % % % % %
Cumula Planned 0.68% 1.36% 7.54 13.42 19.30 25.18 31.07 36.95 42.83 48.72 54.60 60.48 66.36 68.0
tive percent % % % % % % % % % % % 4%
Actual 11.55 22.19 31.94 43.27 52.53 58.36 64.31 69.76 72.76 74.79 76.99 79.5
0.58% 2.84%
Percent % % % % % % % % % % % 8%
3/23/20 3/30/ 4/6/ 4/13/ 4/17/ 4/24/ 5/1/ 5/8/ 5/15/ 5/22/ 5/29/ 6/5/ 6/12/
20 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020
Planned 4.33 1.73 1.06 0.47
5.06% 4.53% 5.19% 4.33% 3.00% 0.93% 0.80% 0.46% 0.07%
percent % % % %
WEEKLY
Actual 1.19 0.00 0.00 0.00
1.64% 2.54% 1.69% 1.51% 0.33% 0.00% 0.00% 0.00% 0.00%
Percent % % % %
Planned 77.63 81.96 87.15 91.48 94.47 96.21 97.27 98.20 99.00 99.47 99.93 100.0
73.10%
Cumula percent % % % % % % % % % % % 0%
tive Actual 83.75 84.94 86.63 88.14 88.47
81.22%
Percent % % % % %
All the material are approved by AGOCO and under procurement process
To monitor the situation and continue procurement Process according to the Schedule
- Welding of Tie-In joints of L-95 sharing point with L-29 flow line
- Final connection of electrical cables in HH-108, HH-86 and L-95 flow lines
- Connection of C-373 flow line from two sites to wellhead and satellite S13
- Painting of above ground piping, piping supports and crush barrier for all well heads
- Final connection (Tie-Off) of electrical poles in HH-86, HH-108 and L-95 flow lines
The following Table represent the actual progress of the mechanical Tie in of the wells HH-108,HH-86,L95
and C-375, knowing that the work in the well C-373 started recently on 08-03-2020 after contract change
order of the well G-315 .
Mechanical Work
Well Number Location Length(m) Weight % Actual % Actual Cumulative %
HH-108 1,100 16.50% 88.90% 14.67% HH-108
General Note:
The well C-373 work started recently on 8/03/2020 after the contract change order by AGOCO Committee.
Remaining only the hydrostatic test for the wells HH-108,HH86 and L95
The Well C373 work is in progress in welding , wrapping and excavation work
The following table represent the actual progress of the Electrical work of the wells HH-108,HH86 in Messla
andG L-95 in Sarir.
Electrical Work
Locatio Length(m Actual %
Well Number n ) Weight % Actual Cumulative %
HH-108 Messla 500 31.25% 100% 31.25%
HH-86 Messla 500 31.25% 100% 31.25%
L-95 Sarir 600 37.50% 100% 37.50%
Total 1,600 100.00% 100%
Note:
All the electrical work has been done according to scope of work and international standards for all
the wells and remaining only some touch up in the punch list and final connection
7.0 Attachments
Page 12 of 18
ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4
Page 14 of 18
Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 15 of 18
Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 16 of 18
Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 17 of 18
Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 18 of 18