A r a b i a n G u l f O i l C o m p a n y

ELECTROMECHANICAL TIE-IN OF WELLS NO HH-86,HH-108 AT


Project Title: MESSLA FIELD, L95 AT SARIR FIELD AND G-315 AT NAFOORA
FIELD
Project No.: 513/19

Contract No.: ECD 513/19

MONTHLY PROGRESS REPORT MPR No.4


REPORTING PERIOD: 21/03/2019 to 23/04/2020

ENGINEERING & CONSTRUCTION


DEPARTMENT

Prepared by: Ammar Jamal / Nidhal TOUMI

JOS Company

March 2020

CONTENTS

Page 1 of 18
ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

1.0 Contract information............................................................................................................................3


2.0 Project Progress Summary &Curves.....................................................................................................4
2.1 Overall Project Progress Summary...................................................................................................4
2.2 Engineering S-Curve...............................................................................................................................5
2.4 Procurement and Supply S-Curve...........................................................................................................6
2.5 Construction Work S-Curve....................................................................................................................7
2.6 All the Project S-Curve :.........................................................................................................................8
2.7 Updated Project Schedule................................................................................................................9
3.0 Detailed Engineering Status for the Reporting Period........................................................................11
3.1 Narrative Description......................................................................................................................11
4.0 Procurement Status for the Reporting Period....................................................................................11
4.1 Narrative Description......................................................................................................................11
5.0 Construction Status for the Reporting Period.....................................................................................12
5.1 Narrative Description......................................................................................................................12
6.0 Finance Status...................................................................................................................................14
6.1 Payment Status...................................................................................................................................14
7.0 Attachments..........................................................................................................................................14
 Document Register Status......................................................................................................................14
 Pictures for the Current Month..............................................................................................................14

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 2 of 18


ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

1.0 Contract information

Date signed : 18/02/2020

Site Handed Over Date : 16/12/2019

Commencement Date : 16/12/2019

Contract Title : EPC Project

Project Period : 170 days

Project Completion Date : 09/06/2020

Contract Amount : 2,468,890LYD

Payment Split : 70% USD Plus 30% LYD

Advance Payment : No Advance payment

Performance Bond : 10% from contract Price

Insurance Policy : Included

Warranty Maintenance Period : 12 Months

2.0 Project Progress Summary &Curves

2.1 Overall Project Progress Summary


Monthly Period Progress Cumulative Perio

Item ACTUA Planne Varianc ACTUA Planne


ACTIVITY weight %
Code L% d% e L% d%
M13-
Engineering 1.65% 100% 100% 0% 1.65% 1.65%
01
All Material Supply with
commissioning tools ,spare
M13-
parts, Required Documents 66.39% 90.90% 100% 9.10%- 60.35% 66.39%
02
,Fabrication of the Three
Manifolds and FAT

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 3 of 18


ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

M13-
Construction 31.96% 82.83%     26.47%  
03
Total 100.00%          

We still ahead of schedule in the whole project and we encountered some obstacle during the
Construction work as mentioned below:

 The well of G-315 is replaced with well C373 in Sarir


 Financial reasons, The LC still not opened
 The escalated travel restrictions due to the Corona Virus are affecting seriously any
mobilization and travel arrangement of labor and staffing.

2.2 Engineering S-Curve

2.4 Procurement and Supply S-Curve

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 4 of 18


ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

120.00%

100.00%

80.00%

60.00%

40.00%

20.00%

0.00%
9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 /1 1 /2 1 /2 1 /2 1 /2 2 /2 2 /2 2 /2 2 /2 3 /2 3 /2 3 /2 3 /2 3 /2 4 /2 4 /2 4 /2 4 /2
/1 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0 /0
29 05 12 19 26 02 09 16 23 01 08 15 22 27 03 10 17 24

29/1 05/0 12/0 19/0 26/0 02/0 09/0 16/0 23/0 01/0 08/0 15/0 22/0 27/0 03/0 10/0 17/0 24/0
2/19 1/20 1/20 1/20 1/20 2/20 2/20 2/20 2/20 3/20 3/20 3/20 3/20 3/20 4/20 4/20 4/20 4/20
Planned 8.86 8.86 8.86 8.86 8.86 8.86 8.86 8.86 8.86 8.86 8.86 2.53 0.00 0.00
percent % % % % % % % % % % % % % %
Actual 10.0 15.0 14.0 15.0 12.0 4.00 5.00 5.00 1.20 1.10 1.10 2.00 1.00 2.00 0.50 1.00 0.50 0.50
Percent 0% 0% 0% 0% 0% % % % % % % % % % % % % %
Planned 8.86 17.7 26.5 35.4 44.3 53.1 62.0 70.8 79.7 88.6 97.4 100. 100. 100. 100. 100. 100. 100.
percent % 2% 8% 4% 0% 6% 3% 9% 5% 1% 7% 00% 00% 00% 00% 00% 00% 00%
Actual 10.0 25.0 39.0 54.0 66.0 70.0 75.0 80.0 81.2 82.3 83.4 85.4 86.4 88.4 88.9 89.9 90.4 90.9
Percent 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

2.5 Construction Work S-Curve

100.% Construction Flow Line project S-Curve


90.%
80.%

70.%
Total Progress

60.%

50.%
40.%

30.%
20.%

10.%

0.%
1

19/ 26/ 02/ 09/ 16/ 23/ 30/ 06/ 13/ 20/ 27/ 05/ 12/ 19/ 26/ 02/ 09/ 16/ 23/

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 5 of 18


ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

12/ 12/ 01/ 01/ 01/ 01/ 01/ 02/ 02/ 02/ 02/ 03/ 03/ 03/ 03/ 04/ 04/ 04/ 04/
19 19 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20
Planne 15. 14. 13. 16. 13.
9.3 5.4 3.3 2.9 2.5 1.4 1.4 0.2 0.0 0.0 0.0 0.0 0.0 0.0
d 83 17 54 25 54
Wee 8% 2% 3% 2% 0% 5% 6% 1% 0% 0% 0% 0% 0% 0%
percent % % % % %
kly
Actual 1.5 4.9 4.3 1.5 1.4 4.2 4.0 9.9 8.2 6.6 6.8 4.0 4.5 3.9 3.0 3.7 2.6 3.2 3.6
Percent 1% 3% 7% 1% 2% 9% 6% 5% 1% 9% 8% 7% 8% 6% 5% 8% 8% 2% 8%
Planne 15. 30. 43. 59. 73. 82. 88. 91. 94. 96. 98. 99. 100 100 100 100 100 100 100
d 83 00 54 79 33 71 13 46 38 88 33 79 .00 .00 .00 .00 .00 .00 .00
Cum
percent % % % % % % % % % % % % % % % % % % %
ulati
10. 12. 13. 18. 22. 32. 40. 46. 53. 57. 62. 66. 69. 73. 75. 79. 82.
ve Actual 1.5 6.4
80 32 74 03 09 03 24 94 82 89 47 43 47 25 93 15 83
Percent 1% 4%
% % % % % % % % % % % % % % % % %

2.6 All the Project S-Curve :

120.00%

100.00%

80.00%

60.00%

40.00%

20.00%

0.00%
01/12/19 20/01/20 10/03/20 29/04/20 18/06/20

16/12/1 23/12 30/1 06/01 13/01 20/01 27/0 03/0 10/02 17/02 24/02 02/0 09/03 16/0
9 /19 2/19 /20 /20 /20 1/20 2/20 /20 /20 /20 3/20 /20 3/20
Planned 6.17 5.88 5.88 5.88 1.68
0.68% 0.68% 5.88% 5.88% 5.88% 5.88% 5.88% 5.88% 5.88%
percent % % % % %
WEEKLY
Actual 8.72 10.64 11.33 9.26 5.83 2.03 2.59
0.58% 2.26% 9.75% 5.94% 5.46% 3.00% 2.20%
Percent % % % % % % %
Cumula Planned 0.68% 1.36% 7.54 13.42 19.30 25.18 31.07 36.95 42.83 48.72 54.60 60.48 66.36 68.0
tive percent % % % % % % % % % % % 4%

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 6 of 18


ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

Actual 11.55 22.19 31.94 43.27 52.53 58.36 64.31 69.76 72.76 74.79 76.99 79.5
0.58% 2.84%
Percent % % % % % % % % % % % 8%
3/23/20 3/30/ 4/6/ 4/13/ 4/17/ 4/24/ 5/1/ 5/8/ 5/15/ 5/22/ 5/29/ 6/5/ 6/12/
20 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020
Planned 4.33 1.73 1.06 0.47
5.06% 4.53% 5.19% 4.33% 3.00% 0.93% 0.80% 0.46% 0.07%
percent % % % %
WEEKLY
Actual 1.19 0.00 0.00 0.00
1.64% 2.54% 1.69% 1.51% 0.33% 0.00% 0.00% 0.00% 0.00%
Percent % % % %
Planned 77.63 81.96 87.15 91.48 94.47 96.21 97.27 98.20 99.00 99.47 99.93 100.0
73.10%
Cumula percent % % % % % % % % % % % 0%
tive Actual 83.75 84.94 86.63 88.14 88.47
81.22%
Percent % % % % %

2.7 Updated Project Schedule

3.0 Detailed Engineering Status for the Reporting Period

3.1 Narrative Description


3.1.1 This Month

 Engineering work finished and executing construction work

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 7 of 18


ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

3.1.2 Next Month

 Engineering work finished and executing construction work


 To start the necessary measurement for the as built drawings

4.0 Procurement Status for the Reporting Period

4.1 Narrative Description

4.1.1 This Month

 All the material are approved by AGOCO and under procurement process

Description Supplier Origin Status


Already Received and started
Pipes Tubos Renudos (Approved by AGOCO) Spain
transfer to the Field
Fittings are gathered in Italy and
Fittings TWS (Approved by AGOCO) Italy will be shipped soon

Fire safety valves fabrication in UK


is stopped in 70% progress due to
Fire safety Valves Edmund Valve (Approved by AGOCO) UK
pandemic CVID-19

OTDS electrical material fabrication


in UK is stopped in 70% progress
Electrical Material OTDS (Approved by AGOCO) UK
due to pandemic CVID-19

4.1.2 Next Month

 To monitor the situation and continue procurement Process according to the Schedule

5.0 Construction Status for the Reporting Period

5.1 Narrative Description

5.1.1 This Month

- Welding of C-373 flow line in Sarir Field

- Welding of C-373 above ground piping

- Installation of piping supports inside satellite S13

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 8 of 18


ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

- Excavation of C-373 flow line trenching

- Coating and double wrapping of C-373 flow line

- Pouring of structural concrete of C-373 piping supports and anchor blocs

- Welding of C-373 crush barrier in site

- Installation of L-95 anchor blocs and Tie-In joints

- Installation of L-95 sharing point valve box

- Welding of Tie-In joints of L-95 sharing point with L-29 flow line

- Painting of HH-86 and HH-108 well head above ground piping

- Painting of HH-86 crush barrier

- Installation of HH-86 & HH-108 anchor blocs and Tie-In joints

- Flushing of HH-86 & HH-108 flow lines with air compressor

- Final connection of electrical cables in HH-108, HH-86 and L-95 flow lines

5.1.2 Next Month

- Welding of C-373 flow line

- Connection of C-373 flow line from two sites to wellhead and satellite S13

- Excavation of C-373 flow line trenching

- Coating & double wrapping of C-373 flow line

- Welding & installation of C-373 crush barrier in site

- Installation of C-373 above ground piping in site

- Installation of C-373 wellhead piping supports and anchor blocs

- Painting of above ground piping, piping supports and crush barrier for all well heads

- Hydrostatic Test of HH-108, HH-86 and L-95 flow lines

- Final connection (Tie-Off) of electrical poles in HH-86, HH-108 and L-95 flow lines

5.1.3 Mechanical work:

The following Table represent the actual progress of the mechanical Tie in of the wells HH-108,HH-86,L95
and C-375, knowing that the work in the well C-373 started recently on 08-03-2020 after contract change
order of the well G-315 .

Mechanical Work
Well  Number Location Length(m) Weight % Actual % Actual Cumulative %
HH-108 1,100 16.50% 88.90% 14.67% HH-108

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 9 of 18


ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

HH-86 3,900 45.35% 89.80% 40.72% HH-86


L-95 750 11.36% 83.20% 9.45% L-95
C-373 2,000 26.79% 67.14% 17.99% C-373
Total 7,750 100.00%   82.83%

General Note:

The well C-373 work started recently on 8/03/2020 after the contract change order by AGOCO Committee.

 Remaining only the hydrostatic test for the wells HH-108,HH86 and L95
 The Well C373 work is in progress in welding , wrapping and excavation work

5.1.4 Electrical work:

The following table represent the actual progress of the Electrical work of the wells HH-108,HH86 in Messla
andG L-95 in Sarir.

Electrical Work
Locatio Length(m Actual %
Well  Number n ) Weight % Actual Cumulative %
HH-108 Messla 500 31.25% 100% 31.25%
HH-86 Messla 500 31.25% 100% 31.25%
L-95 Sarir 600 37.50% 100% 37.50%
Total 1,600 100.00%   100%

Note:

 All the electrical work has been done according to scope of work and international standards for all
the wells and remaining only some touch up in the punch list and final connection

6.0 Finance Status

6.1 Payment Status

 LC still not opened


 Engineering Invoice already submitted and still not Paid
 Construction Progress payment already signed by ECD coordinator in the field and
submitted to head office.

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 10 of 18


ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

7.0 Attachments

 Document Register Status

 Pictures for the Current Month

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 11 of 18


Document Register Status
N° Description Document Number N° of Size REV Approval Status Approval
Page Date
s REV0 REV1 REV2 REV3
1 Inspection Test Plan
1.1 Civil Inspection Test Plan JOS-MTI-CV-ITP-01-00 7 A4 X Approved 30/10/2019
1.2 Mechanical Inspection Test Plan JOS-MTI-MEC-ITP-01-00 9 A4 X Approved 27/10/2019
2 Mechanical Engineering Docs
2.1 General method statement A4 X SUBMITTED R0
2.2 Mechanical Site Survey Report A4 X SUBMITTED R0
2.3 Messla manifold tie-in HH-108 Drawing MS-ECD513-110-M-003-1/2 1 A3 X X Approved 06/11/2019
2.4 Messla wellhead tie-in HH-108 Drawing MS-ECD513-110-M-003-2/2 1 A3 X X Approved 06/11/2019
2.5 Messla manifold tie-in HH-86 Drawing MS-ECD513-110-M-002-1/2 1 A3 X X Approved 06/11/2019
2.6 Messla Wellhead tie-in HH-86 Drawing MS-ECD513-110-M-002-2/2 1 A3 X X Approved 06/11/2019
2.7 Nafoora manifold tie-in HH-G-315 Drawing NF-ECD513-110-M-004-1/2 1 A3 X X Approved 06/11/2019
2.8 Nafoora Wellhead tie-in HH-G-315 Drawing NF-ECD513-110-M-004-2/2 1 A3 X X Approved 06/11/2019
2.9 Pipe Bending Detail GEN-ECD513-111-M-005 1 A3 X X Approved 06/11/2019
2.10 L-95 sharing tie-in at L-29 SR-ECD513-170-M-001-2/2 1 A3 X X Approved 06/11/2019
2.11 Wellhead barriers SR/MS-5091-M-101 1 A3 X X Approved 06/11/2019
2.12 Sarir Wellhead drawing L-95 SR-ECD513-170-M-001-1/2 1 A3 X X Approved 06/11/2019
3 Civil Engineering Docs
3.1 Topographic Survey Drawing G-315 SOB-2019-051-001-CI-001 5 A3 X Approved 17/11/2019
3.2 Topographic Survey Drawing HH-108 SOB-2019-051-001-CI-002 3 A3 X Approved 17/11/2019
3.3 Topographic Survey Drawing HH-86 SOB-2019-051-001-CI-003 4 A3 X Approved 17/11/2019
3.4 Topographic Survey Drawing L-95 SOB-2019-051-001-CI-004 2 A3 X X Approved 17/11/2019
3.5 Anchor Block Drawing SOB-2019-051-001-CI-005 1 A3 X X X X Approved 18/12/2019
3.6 Pipe Supports Drawing SOB-2019-051-001-CI-006 1 A3 X X X X Approved 18/12/2019
3.7 Root Selection DWG-Messla SOB-2019-051-001-CI-007 1 A3 X Approved 17/11/2019
3.8 Root Selection DWG-Nafoora SOB-2019-051-001-CI-008 1 A3 X Approved 17/11/2019
3.9 Root Selection DWG-Sarir SOB-2019-051-001-CI-009 1 A3 X X Approved 17/11/2019
3.10 Anchor Block Calculation SOB-2019-051-001-CI-010 4 A4 X SUBMITTED R3
3.11 Root Selection Report JOS-MTI-CV-REP-01-00 12 A4/A3 X X Approved 30/10/2019
3.12 Civil Works Procedure JOS-MTI-CV-PR-01-00 11 A4 X Approved 30/10/2019

Page 12 of 18
ELECTROMECHANICAL TIE-IN OF WELLS NO HH-
86,HH-108 AT MESSLA FIELD, L95 AT SARIR FIELD
AND G-315 AT NAFOORA FIELD
Monthly Progress Report :April 2020
Jabel Oil Services ECD 513/19
MPR No.4

3.13 Civil Works ITP JOS-MTI-CV-ITP-01-00 7 A4 X Approved 30/10/2019


3.14 Pipe markers drawing NF-ECD513-110-CV-004 1 A4 X X Approved 06/11/2019
3.15 Fire safety valve box drawing MS-ECD513-110-CV-03 1 A3 X X Approved 02/12/2019
3.16 Valve box drawings SR-ECD513-170-CV-002 1 A3 X X Approved 02/12/2019
4 Electrical Engineering Docs
4.1 Electrical Site Survey Report A4/A3 X SUBMITTED R0
4.2 Electrification of Oil Well HH-86 in MESSLA MS-ECD513-110-EL-002 A4/A3 X X X X Approved 17/11/2019
4.3 Electrification of Oil Well HH-108 in MESSLA MS-ECD513-110-EL-003 A4/A3 X X X X Approved 17/11/2019
4.4 Electrification of Oil Well L-95 in SARIR SR-ECD513-170-EL-001 A4/A3 X X X X Approved 17/11/2019
5 Quality Docs
5.1 WPS & PQR JOS-MTI-Q-WPS & PQR-00 A4 X Approved 01/12/2019
5.2 Handling Procedure JOS-MTI-MEC-PR-06-00 A4 X Approved 27/10/2019
5.3 Flow lineHydro test Procedure JOS-MTI-MEC-PR-01-01 A4 X Approved 07/11/2019
5.4 Piping Hydro test Procedure JOS-MTI-MEC-PR-02-01 A4 X Approved 07/11/2019
5.5 Coating & wrapping Procedure JOS-MTI-MEC-PR-04-01 A4 X Approved 07/11/2019
5.6 Painting Procedure JOS-MTI-MEC-PR-03-01 A4 X Approved 07/11/2019
6 HSE
6.1 Job Safety Analysis JOS-MTI-HSE-JSA-01-00 9 A4 X Approved 27/10/2019
6.2 HSE Plan JOS-MTI-HSE-PL-01-00 10 A4 X Approved 27/10/2019

Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 13 of 18


PHOTOS OF THE CURRENT MONTHS

Page 14 of 18
Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 15 of 18
Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 16 of 18
Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 17 of 18
Issued: 26/03/2020 / MPR No.4 / Rev. 0 Page 18 of 18