REVISED PROJECT SCHEDULE FOR CONSTRUCTION OF ISHAN CHILDREN AND WOMEN'S HOSPITAL PVT.

LTD,
BASUNDHARA, KATHMANDU
ID Task Name Duration Start Finish Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 202
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug S
CONSTRUCTION OF ISHAN CHILDREN AND WOMEN'S HOSPITAL
1 679 days Mon 4/15/19 Wed 7/7/21
,BASUNDHARA, KATHMANDU
2 Site Mobilization 14 days Mon 4/15/19 Sun 4/28/19 4/15 4/28
3 Site clearance and mobilization with CGI sheets 7 days Mon 4/15/19 Sun 4/21/19 4/15 4/21
4 Establishing Material storage yard, site office, Labor toilets, camps etc. 7 days Mon 4/22/19 Sun 4/28/19 4/22 4/28
5 Construction Phase 665 days Thu 5/2/19 Wed 7/7/21
6 Sub-Structural works 266 days Thu 5/2/19 Mon 3/2/20 5/2 3/6
7 Layout of Building 1 day Thu 5/2/19 Thu 5/2/19 5/2 5/2
8 Shoring and protection work 197 days Fri 5/24/19 Sat 12/28/19 5/24 12/28
9 Shoring & Protection works using MS sheets and MS Pipes 2 days Fri 5/24/19 Sat 5/25/19 5/24 5/25
10 Bored Protection pile works after Revision of Drawings as per soil Condition15 days Mon 6/17/19 Mon 7/1/19 6/17 7/1
11 Pile Cap beams 4 days Sun 6/30/19 Wed 7/3/19 6/30 7/3
12 Diaphragm walls 153 days Sun 7/7/19 Sat 12/28/19 7/7 12/28
13 Excavation for Foundation 189 days Fri 5/3/19 Tue 12/17/19 5/3 12/17
14 Middle section Grid B-F : 1-4 59 days Fri 5/3/19 Wed 7/31/19 5/3 7/31
15 East Section Grid F-G : 1-4 5 days Sun 11/24/19 Thu 11/28/19 11/24 11/28
16 West Section Grid A-B : 1-4 4 days Sat 12/14/19 Tue 12/17/19 12/14 12/17
17 Anti-termite work 184 days Tue 5/28/19 Thu 12/19/19 5/28 12/19
18 Middle section Grid B-F : 1-4 59 days Tue 5/28/19 Fri 8/30/19 5/28 8/30
19 East Section Grid F-G : 1-4 2 days Fri 11/29/19 Sat 11/30/19 11/29 11/30
20 West Section Grid A-B : 1-4 2 days Wed 12/18/19 Thu 12/19/19 12/18 12/19
21 Boulder Soling & PCC for Foundation 185 days Fri 5/31/19 Mon 12/23/19 5/31 12/23
22 Middle section Grid B-F : 1-4 60 days Fri 5/31/19 Tue 9/3/19 5/31 9/3
23 East Section Grid F-G : 1-4 3 days Mon 12/2/19 Wed 12/4/19 12/2 12/4
24 West Section Grid A-B : 1-4 3 days Sat 12/21/19 Mon 12/23/19 12/21 12/23
25 Rebar tying for Raft & Column Erection 188 days Mon 6/3/19 Sun 12/29/19 6/3 12/29
26 Middle section Grid B-F : 1-4 104 days Mon 6/3/19 Wed 11/6/19 6/3 11/6
27 East Section Grid F-G : 1-4 7 days Tue 12/3/19 Mon 12/9/19 12/3 12/9
28 West Section Grid A-B : 1-4 7 days Mon 12/23/19 Sun 12/29/19 12/23 12/29
29 Erection of Formwork for Foundation 187 days Thu 6/6/19 Tue 12/31/19 6/6 12/31
30 Middle section Grid B-F : 1-4 104 days Thu 6/6/19 Sat 11/9/19 6/6 11/9
31 East Section Grid F-G : 1-4 7 days Thu 12/5/19 Wed 12/11/19 12/5 12/11
32 West Section Grid A-B : 1-4 7 days Wed 12/25/19 Tue 12/31/19 12/25 12/31
33 Pouring of Concrete for Foundation 192 days Sun 6/9/19 Wed 1/8/20 6/9 1/8
34 Middle section Grid B-F : 1-4 104 days Sun 6/9/19 Tue 11/12/19 6/9 11/12
35 East Section Grid F-G : 1-4 5 days Sat 12/7/19 Wed 12/11/19 12/7 12/11
36 West Section Grid A-B : 1-4 7 days Thu 1/2/20 Wed 1/8/20 1/2 1/8
37 Tying of rebar for Shear wall and column of lower basement 192 days Sun 6/16/19 Wed 1/15/20 6/16 1/15
38 Middle section Grid B-F : 1-4 104 days Sun 6/16/19 Tue 11/19/19 6/16 11/19
39 East Section Grid F-G : 1-4 5 days Tue 12/10/19 Sat 12/14/19 12/10 12/14
40 West Section Grid A-B : 1-4 5 days Sat 1/11/20 Wed 1/15/20 1/11 1/15
41 Erection of Formwork for Shear wall and column of lower basement 191 days Sun 6/23/19 Tue 1/21/20 6/23 1/21
42 Middle section Grid B-F : 1-4 104 days Sun 6/23/19 Tue 11/26/19 6/23 11/26
43 East Section Grid F-G : 1-4 7 days Thu 12/12/19 Wed 12/18/19 12/12 12/18
44 West Section Grid A-B : 1-4 5 days Fri 1/17/20 Tue 1/21/20 1/17 1/21
45 Pouring of Concrete for Shear wall and column of lower basement 193 days Wed 6/26/19 Sun 1/26/20 6/26 1/26
46 Middle section Grid B-F : 1-4 104 days Wed 6/26/19 Fri 11/29/19 6/26 11/29
47 East Section Grid F-G : 1-4 5 days Mon 12/16/19 Fri 12/20/19 12/16 12/20
48 West Section Grid A-B : 1-4 5 days Wed 1/22/20 Sun 1/26/20 1/22 1/26
49 RCC Cover Slab for Lower Basement(Upper basement slab) 153 days Thu 8/22/19 Fri 2/7/20
50 Erection of formwork 92 days Thu 8/22/19 Sun 1/5/20 8/22 1/5
51 Tying of rebar for lower basement cover slab 100 days Thu 8/29/19 Mon 1/20/20 8/29 1/20
52 Pouring of Concrete 118 days Tue 9/3/19 Fri 2/7/20 9/3 2/7
53 RCC Cover Slab for Upper Basement(G.F. slab) 124 days Fri 10/25/19 Mon 3/2/20 10/25 3/6
54 Tying of rebar for Shear wall and column of upper basement 10 days Thu 1/23/20 Wed 2/12/20 1/23 2/12
55 Erection of Formwork for Shear wall and column of upper basement 10 days Sat 1/25/20 Mon 2/3/20 1/25 2/3
56 Erection of formwork for upper basement cover slab 10 days Wed 2/5/20 Fri 2/14/20 2/5 2/14
57 Tying of rebar for upper basement cover slab 10 days Sat 2/15/20 Mon 2/24/20 2/15 2/24
58 Pouring of upper Basement Floor Cover slabs(G.F. slab) 7 days Tue 2/25/20 Mon 3/2/20 2/25 3/2
59 Waterproofing and Backfilling 40 days Fri 10/25/19 Mon 12/9/19 10/25 12/9
60 Super structural work 179 days Thu 3/5/20 Tue 12/1/20 3/5 7/22
61 Cover slab of Ground floor (F.F. slab) 27 days Thu 3/5/20 Mon 6/22/20
62 Tying of Rebar for Ground Floor Columns 3 days Thu 3/5/20 Sat 3/7/20 3/5 3/7
63 Erection of Formwork for Ground Floor Columns 3 days Sat 3/7/20 Mon 3/9/20 3/7 3/9
64 Pouring of Concrete for Ground Floor Columns 3 days Sun 3/8/20 Tue 3/10/20 3/8 3/10
65 Erection of Formwork for Ground Floor Cover Slabs 6 days Fri 3/13/20 Wed 3/18/20 3/13 3/18
66 Tying of Rebar for Ground Floor Cover slabs 6 days Mon 6/15/20 Sat 6/20/20 6/15 6/20
67 Pouring of Ground Floor Cover slabs(F.F. slab) 4 days Fri 6/19/20 Mon 6/22/20 6/19 6/22
68 cover slab of First Floor Structure (second floor slb) 57 days Fri 6/19/20 Fri 8/14/20
69 Tying of Rebar for First Floor Columns 10 days Fri 6/19/20 Sun 6/28/20
70 Erection of Formwork for First Floor Columns 10 days Sat 6/20/20 Mon 6/29/20 6/20 6/29
71 Pouring of Concrete for First Floor Columns 15 days Sat 6/20/20 Sat 7/4/20 6/20 7/4
72 Erection of Formwork for FF Cover Slabs 20 days Thu 7/9/20 Tue 7/28/20 7/9 7/28
73 Tying of Rebar for First Floor Cover slabs 20 days Sun 6/28/20 Tue 8/11/20 6/28 8/11
74 Pouring of First Floor Cover slabs 2 days Thu 8/13/20 Fri 8/14/20 8/13 8/14
75 cover slab of Second Floor Structure (Third floor slab) 34 days Mon 8/17/20 Sat 9/19/20
76 Tying of Rebar for Second Floor Columns 3 days Mon 8/17/20 Wed 8/19/20 8/17 8/19
77 Erection of Formwork for Second Floor Columns 7 days Tue 8/18/20 Mon 8/24/20 8/18 8/24
78 Pouring of Concrete for Second Floor Columns 6 days Sun 8/23/20 Fri 8/28/20 8/23 8/28
79 Erection of Formwork for Second Floor Cover Slabs 7 days Sun 8/30/20 Sat 9/5/20 8/30 9/5
80 Tying of Rebar For Second Floor Cover slabs 10 days Sun 9/6/20 Tue 9/15/20 9/6 9/15
81 Pouring of Second Floor Cover slabs 2 days Fri 9/18/20 Sat 9/19/20 9/18 9/19
82 cover slab over Third Floor Structure (Fourth floor slab/roof slab) 29 days Sun 9/20/20 Sun 10/18/20
83 Tying of Rebar for Third Floor Columns 3 days Sun 9/20/20 Tue 9/22/20 9/20 9/22
84 Erection of Formwork for Third Floor Columns 3 days Wed 9/23/20 Fri 9/25/20 9/23 9/25
85 Pouring of Concrete for Third Floor Columns 3 days Sun 9/27/20 Tue 9/29/20 9/27 9/29
86 Erection of Formwork for Third Floor Cover Slabs 7 days Fri 10/2/20 Thu 10/8/20 10/2 10/8
87 Tying of Rebar For Third Floor Cover slabs 7 days Thu 10/8/20 Wed 10/14/20 10/8 10/14
88 Pouring of Third Floor Cover slabs 2 days Sat 10/17/20 Sun 10/18/20 10/17 10/18
89 Cover slab over staircase/lift 31 days Sun 10/25/20 Tue 12/1/20
90 Tying of Rebar for top Floor Columns 7 days Sun 10/25/20 Tue 11/3/20 10/25 11/3
91 Erection of Formwork for Top Floor Columns 3 days Sun 11/1/20 Tue 11/3/20 11/1 11/3
92 Pouring of Concrete forTop Floor Columns 3 days Mon 11/2/20 Wed 11/4/20 11/2 11/4
93 Erection of Formwork for top Floor Cover Slabs 15 days Thu 11/5/20 Tue 11/24/20 11/5 11/24
94 Tying of Rebar For Top Floor Cover slabs 6 days Tue 11/24/20 Sun 11/29/20 11/24 11/29
95 Pouring of Cover slabs over stircase voids etc 2 days Mon 11/30/20 Tue 12/1/20 11/30 12/1
96 Finishing Works 235 days Fri 11/6/20 Mon 6/28/21
97 Laying and erection of brickwalls/AAC blocks in Ground Floor 22 days Fri 11/6/20 Fri 11/27/20 11/6 11/27
98 Laying and erection of brickwalls/AAC blocks in First Floor with concrete band 22 days Sat 11/28/20 Sat 12/19/20 11/28 12/19
99 Laying and erection of brickwalls/AAC blocks in Second Floor with concrete band 22 days Sun 12/20/20 Sun 1/10/21 12/20 1/10
100 Laying and erection of brickwalls/AAC blocks in Third Floor with concrete band25 days Mon 1/11/21 Thu 2/4/21 1/11 2/4
101 Laying and erection of brickwalls/AAC blocks in Fourth Floor with concrete band 10 days Fri 2/5/21 Sun 2/14/21 2/5 2/14

Task External Milestone Manual Summary Rollup Critical Split


Split Inactive Task Manual Summary Progress

HIMALAYAN BUILDERS AND ENGINEERS PVT. LTD Milestone Inactive Milestone Start-only Manual Progress
BABARMAHAL-11, KATHMANDU, NEPAL Summary Inactive Summary Finish-only
Wed 12/2/20
Project Summary Manual Task Deadline
External Tasks Duration-only Critical
REVISED PROJECT SCHEDULE FOR CONSTRUCTION OF ISHAN CHILDREN AND WOMEN'S HOSPITAL PVT. LTD,
BASUNDHARA, KATHMANDU
ID Task Name Duration Start Finish Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 202
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug S
102 Metal related work of whole building 100 days Sun 11/1/20 Sat 2/13/21 11/1 2/13
103 Plaster works for Ground Floor walls 18 days Thu 12/3/20 Sun 12/20/20 12/3 12/20
104 Plaster works for First Floor walls 18 days Fri 12/25/20 Mon 1/11/21 12/25 1/11
105 Plaster works for Second Floor walls 18 days Sat 1/16/21 Tue 2/2/21 1/16 2/2
106 Plaster works for Third Floor walls 18 days Wed 2/10/21 Sat 2/27/21 2/10 2/27
107 Plaster works for Fourth Floor walls 8 days Sat 2/20/21 Sat 2/27/21 2/20 2/27
108 Putty work 90 days Tue 1/5/21 Sun 4/4/21 1/5 4/4
109 Erection of Partition wall with aerorated concrete fill in basement 1 10 days Sat 11/28/20 Mon 12/7/20 11/28 12/7
110 Erection of Partition wall with aerorated concrete fill in ground floor 15 days Tue 12/8/20 Tue 12/22/20 12/8 12/22
111 Erection of Partition wall with aerorated concrete fill in first floor 15 days Wed 12/30/20 Wed 1/13/21 12/30 1/13
112 Erection of Partition wall with aerorated concrete fill in second floor 15 days Thu 1/21/21 Thu 2/4/21 1/21 2/4
113 Erection of Partition wall with aerorated concrete fill in third 15 days Mon 2/15/21 Mon 3/1/21 2/15 3/1
114 Erection of Partition wall with aerorated concrete fill in fourth floor 15 days Thu 2/25/21 Thu 3/11/21 2/25 3/11
115 Screeding and punning works 97 days Fri 12/18/20 Wed 3/24/21 12/18 3/24
116 Laying of Tiles, marbles etc on floor 40 days Thu 3/25/21 Mon 5/3/21 3/25 5/3
117 Laying of tiles and bricks for wall cladding 40 days Thu 3/25/21 Mon 5/3/21 3/25 5/3
118 Laying of laminated parquet for office floor 30 days Thu 3/25/21 Fri 4/23/21 3/25 4/23
119 Installation of Door and window frames 40 days Wed 4/14/21 Sun 5/23/21 4/14 5/23
120 Installationof railings for staircase, terrace 30 days Tue 5/4/21 Wed 6/2/21 5/4 6/2
121 First Coat of painting works at all floors 60 days Mon 4/5/21 Thu 6/3/21 4/5 6/3
122 Second Coat of painting works at all floors 20 days Fri 6/4/21 Wed 6/23/21 6/4 6/23
123 MEP Works 286 days Mon 9/14/20 Tue 7/6/21
124 Electrical works 250 days Mon 9/14/20 Mon 5/31/21 9/14 5/31
125 Sanitary Works 120 days Thu 3/25/21 Thu 7/22/21 3/25 7/22
126 HVAC Works 120 days Thu 3/25/21 Thu 7/22/21 3/25 7/22
127 Close Out works 14 days Thu 6/24/21 Wed 7/7/21
128 Walk Through Inspection 1 day Thu 6/24/21 Thu 6/24/21 6/24 6/24
129 Rectification of punchlist 7 days Fri 6/25/21 Thu 7/1/21 6/25 7/1
130 Final Walk Through inspection 1 day Fri 7/2/21 Fri 7/2/21 7/2 7/2
131 Cleaning and Demobilization from site 5 days Sat 7/3/21 Wed 7/7/21 7/3 7/7
132 Handover of Project 0 days Wed 7/7/21 Wed 7/7/21 7/7

Task External Milestone Manual Summary Rollup Critical Split


Split Inactive Task Manual Summary Progress

HIMALAYAN BUILDERS AND ENGINEERS PVT. LTD Milestone Inactive Milestone Start-only Manual Progress
BABARMAHAL-11, KATHMANDU, NEPAL Summary Inactive Summary Finish-only
Wed 12/2/20
Project Summary Manual Task Deadline
External Tasks Duration-only Critical