Professional Documents
Culture Documents
Qatar LNG PDF
Qatar LNG PDF
ABSTRACT
The objective of this paper is to present the Qatar Liquefied Gas Company one year
experience with the Advanced Process Control Technology. Advanced Process Control
was implemented in the Onshore Facilities with the objective of Maximizing LNG
production and reducing Steam consumption.
The paper will present details of APC configuration, covering not only the
liquefaction facilities but also treating, sulfur recovery, and fractionation units. An
overview will be presented of the actual APC performance improvement both during
acceptance testing and normal operation after implementation.
PO-58.1
Poster PO-58
I INTRODUCTION
Qatar Liquefied Gas Company is located in Ras Laffan Industrial Area about 90 Km
North of Doha, State of Qatar.
The Qatar Gas company is composed of two major areas i.e. offshore and onshore
Facilities; the offshore facility represents three well head platforms and three gas
treatment (Dehydration) trains. The dehydrated gas and condensate are transported to the
onshore facilities via an 82 km pipeline (32” diameter).
The Company main business objective is to produce Liquefied Natural Gas and
condensate as per design specifications and optimize use of plant facilities.
As part of Qatar Gas Plant optimization effort, Qatar Gas contracted Honeywell Hi
Spec Solution to implement Advanced Process Control (APC) for Upstream, 3 LNG
Process Trains and Acid Gas Enrichment and SRU units at the Ras Laffan facilities in
Qatar.
The three LNG Trains have been de- bottlenecked where a considerable capacity
increase has been reached; an important aspect in the plant operation is that ambient
conditions especially the summer (Day-Night) temperature affects the LNG run down
capacity due to gas turbine limitations.
The APC project second phase implementation was conducted on the Acid Gas
Enrichment (AGE) and Sulfur Recovery Unit (SRU) units; the second phase APC
implementation was initiated after the phase I APC implementation results exceeded the
guaranteed values.
The aim of Advanced Process Control (APC) implementation is to operate the plant at
the best operator conditions all the time without sea line pressure and LNG through put
variation. These new operating conditions were predicted to increase the cumulative LNG
production by 1.0% with the Robust Multi Predictive Controllers Technology (RMPCT)
controllers and additional 0.5 % with the profit Optimizer. The overall steam reduction
(Amine regeneration & fractionation units) was predicted to be reduced by 5 %. For the
SRU and AGE units, the APC objectives were set to increase the sulfur recovery by
0.1%, reduce the SO2 emission by 14.4% and reduce the steam consumption by 5.1% in
the AGE re-boilers units
The project has started in December 14th 2004 for a period of 13 months; the
performance test was conducted from 23 to 29 January 2006 for winter test and from 10
to 17 July 2006 for summer test.
The phase II project was started November 5th 2006, and it’s scheduled for a period of
6 months.
Twenty five (25) RMPCT controllers were connected to the DCS (Foxboro) Platform;
the Profit Optimizer handles the optimization constraints for the all 25 controllers. The
APC was implemented for the following sections:
A. Upstream onshore section
B. Condensate stabilization units
PO-58.2
Poster PO-58
1450 MMSCFD
DOWNSTREAM
LNG PLANT SULFUR
UPSTREAM
SEPARATIO
N
OFF-PLOTS / HARBOUR / JETTY
-53M LNG
CD 82 km TANKERS,LNG,
CONDENSATE,
CONDENSATE STORAGE
SULFUR
OFFSHORE ONSHORE
PO-58.3
Poster PO-58
The stabilized condensate (under RVP control) will be pumped to storage section
from the bottom of strippers, while the strippers overhead gas will be compressed and
mixed with the slug catcher gas to form the LNG trains Feed Gas.
The three identical LNG Trains are composed of the following section:
Acid gas removal section: removes H2S and CO2 under Amine Absorption reactions;
the rich Amine solution is regenerated at low pressure and high temperature in the
Amine regenerator column where the overhead acid gas is send to the Acid Gas
Enrichment unit for further treatment. The sweet gas is under H2S and CO2 on line
control.
Dehydration section: the sweet gas is dehydrated for moisture removal; the dry sweet
gas is under on line moisture content monitoring.
Mercury removal section: removes mercury for exchanger protection.
Liquefaction section: the treated gas is pre-cooled in HP-MP –LP propane Chillers to
reach -30 Deg C before entering the scrub column. The bottom of the scrub column is
directed to fractionation for further separation while the column overhead is sent to the
Main Heat Exchanger for liquefaction.
Refrigeration section: two main loops are included in this section; Multi refrigerant
MR (N2, C1, C2 & C3) and propane circuits. The MR is compressed in three stages,
cooled in the propane chillers then expanded through two Joule Thomson Valves in
the Main heat exchanger to liquefy the Natural gas via three bundles (warm, middle
and cold).
Fractionation: composed of three columns De-ethanizer, De-Propanizer, De-
Butanizer; the scrub column bottom stream is feeding the De-ethanizer, the de-
ethanizer bottom is feeding the De-propanizer and the De-Propanizer bottom is
feeding the De-Butanizer. The De-Butanizer bottom (mainly C5+) is routed to the De-
Iso- Pentanizer for Iso and Normal C5 separation.
The three columns (De-C2, De-C3, and De-C4) overheads are mixed in a same stream
and pre-cooled in a propane chiller before entering the Main Heat Exchanger and
being mixed with the Natural Gas as an LPG for heating value correction.
Nitrogen section: nitrogen is removed from the LNG to maintain the Heating Value as
per design figure; the nitrogen is extracted at low pressure and temperature from the
LNG in the nitrogen rejection column. The mixture nitrogen-methane from the column
overhead is compressed and mixed with the fuel gas streams
The LNG leaving the nitrogen column at -160 Deg C is pumped to the LNG Storage
tanks.
Helium: the Helium Extraction unit extracts helium from the LNG at low temperature
in a cold box unit; the produced helium is send to Ras Gas Company for storage and
commercialization.
PO-58.4
Poster PO-58
Acid Gas Enrichment AGE: The Qatar Gas Ras Laffan facility has two Acid Gas
Enrichment (AGE) units or trains, in series with two Sulfur Recovery Units (SRU).
These trains receive sour gas from the LNG Trains 1, 2 and 3 Acid Gas Recovery
(AGR) Units through a common header. The AGE process units include an Acid Gas
Absorber, Amine Solution Regenerator, Reject Gas Incinerator and auxiliary
equipment. The operating scheme uses the concept of Acid Gas Enrichment (AGE) to
achieve the design objectives of sulfur recovery unit, with the advantage of separating
most of the hydrocarbons and CO2 from the H2S in the acid gas from the Sulfinol units
prior to this gas being fed to the Claus plants. This increase of H2S in the acid gas
means that the Claus unit should not be susceptible to coking or other problems caused
by carbon formation. The enriched acid gases from the AGE amine regenerators are
combined in one header and fed to the two existing SRU.
Sulfur Recovery Unit: The SRU units process the enriched acid gas feed from the AGE
units and converts the H2S and other sulfur compounds to high purity sulfur. The
Qatar gas SRU utilizes the SuperClaus-99 process for recovering elemental sulfur
from the acid gas. The operating objective is to recover as much of the sulfur in the
feed as possible. The process scheme consists of three ordinary Claus Reactor stages,
followed by a Super Claus Reactor stage in which H2S is selectively oxidized. The
basic philosophy of the SRU operation is to control the partial combustion of H2S with
the ratio of air to maintain a specified H2S concentration at the outlet of the third stage
Claus Reactor. The main reaction in the main burner is:
3
H 2 S + O2 → SO 2 + H 2O + heat
2
The major part of the residual H2S combines with the SO2 to form sulfur, according to
the equilibrium reaction:
3
2 H 2 S + SO2 → S 2 +2 H 2 O − heat
2
By this reaction, known as the Claus reaction, sulfur is formed in vapor phase in the
main burner (X0901) and combustion chamber .The primary function of the waste heat
boiler is to remove the major portion of heat generated in the main burner. The
secondary function of the waste heat boiler is to utilize the above mentioned heat to
produce HP steam.
A. Scope of Work:
The project scope of work was decided based on other LNG plants experience as a
guide line and the Qatar Gas Engineers experience in the existing LNG plant.
PO-58.5
Poster PO-58
a) Slug catcher & Pre-flash drum Controller (# 1) Control the Slug catcher
and Pre-flash Drums levels while using the available buffer capacities. Balance the load
among the three strippers by adjusting the individual feed flows. Condensate.
b) Condensate Stripper controllers (# 3) the design of this RMPCT controller
is to control stabilizer bottoms RVP – derived from pressure compensated temperature.
The stabilizer overheads nC5 – derived from pressure compensated temperature, and the
condensate heater process stream passes temperature difference by balancing the
condensate flow from one pass to another to maintain the Delta T Passes as low as
possible. This will eliminate the high coil skin temperature.
2- Downstream
The down stream area optimization philosophy objectives are to maximize the LNG
run down from each train without exceeding any design or safety limit parameters.
Achieving the above optimization targets without exceeding the below constraints:
Sweet Gas H2S & CO2 content as per design limitations.
Regenerator bottom temperature as per vendor specifications.
b) Liquefaction (# 3):
One profit controller (RMPCT) per train is handling the Manipulated Variables (MV)
and the Controlled Variables (CV) for the liquefaction and the refrigeration units to
maximize the LNG production per train. The philosophy is:
Maintain MR gas turbine close to the Machine Limited conditions all the time.
Maintain the Propane gas turbine close to the machine limited conditions all the time.
Maintain the LNG temperature outlet the Main Heat Exchanger constant at a desired
value all the time.
Scrub column overhead C5+ to be controlled at the design minimum value.
LNG Heating Value to be controlled at the desired value.
PO-58.6
Poster PO-58
End Flash Gas Compressor load to be controlled below the alarm setting.
The above conditions will optimally react to the day-night feed gas fluctuation and
therefore the best operator will be on duty all the time.
c) Fractionation (# 9):
Three profit controllers (RMPCT) per train will be optimizing respectively the De-
ethanizer, De-propanizer and De-Butanizer operating conditions as follows:
Maintain De-Ethanizer Column Pressure & Temperature Profiles constant as per
desired values (Design conditions).
Maximize the De-C2 overhead Ethane recovery.
Minimize the De-C2 Re-boiler steam flow.
Maintain the De-C3 Column pressure & temperature profiles constant as per preferred
values (Design cases).
Maximize the De-C3 overhead propane recovery.
Minimize the De-C3 Re-boiler Steam Flow.
Maintain the De-C4 Column pressure & temperature profiles constant as per preferred
values (Design cases).
Maximize the De-C4 overhead butane recovery.
Minimize the De-C4 Re-boiler Steam Flow.
OptimizetheDe-C4 bottom RVP by inferential calculation
2 profit controllers: The SRU units process the enriched acid gas feed from the AGE
units and converts the H2S and other sulfur compounds to high purity sulfur. The
operating objective is to recover as much of the sulfur in the feed as possible. The
process scheme consists of three ordinary Claus Reactor stages, followed by a Super
Claus Reactor stage in which H2S is selectively oxidized, and all associated ancillary
equipment. For the SRU, two Profit Controllers are envisioned, one for Train 1 SRU and
one for Train 2 SRU.
PO-58.7
Poster PO-58
3 Profit optimizer: The profit optimizer controller is linked to the twenty five profit
controllers, where all the constraints for the overall plant are handled in order to maintain
the total plant at Optimum Conditions (Maximum LNG rundown and minimum
acceptable energy consumption) without violating the design specifications and
equipments characteristics.
J = − ∑i
P i × Y i + ∑ j
P j × F j + ∑
k
P k × U k
Where
J = the objective function to be minimized (QR/h)
Pi = the marginal value of the i’th product (QR/m3)
Yi = the flow of the i’th product (m3/h)
Pj = the marginal cost of the j’th feedstock (QR/m3)
Fj = the feed rate of the j’th feedstock (m3/h)
Pk = the marginal cost of the k’th utility, e.g. (QR/unit)
PO-58.8
Poster PO-58
Profit Controller
Profit Controller
Profit Controller
Profit Optimiser
Profit Controller
Profit Controllers
PO-58.9
Poster PO-58
Load
Distribution
Controller
Load
Distribution Profit Controller 1 Per Train
Controller
PO-58.10
Poster PO-58
Feed gases for other trains were floating on sea line pressure (Pressure maintained
between 79.8: 80.5 Barg).
Train-2 lean amine flow limited by a fixed high limit value to protect the lean amine
pump from power over load.
Lean Amine to Feed Gas Ratio floating between 1.64 to 1.8 m3/MMscft.
A. Tangible benefits
The below table shows a comparison between the main benefit objectives agreed and
the results obtained during the performance tests conducted during six days respectively
in winter and summer periods.
1
: steam flow reduction target hasn’t been reached due to the Lean Amine to the Feed Gas Ratio was
set at a wide range (Design R =1.6 m3/MMscft) to avoid any sudden breakthrough of H2S or CO2 at
very high feed rate.
The below table gives the comparison results from 2004 to 2006 respectively pre and
post APC:
The above results are not only from the APC implementation but also due to:
Full involvement of Operation personnel during the two performance test periods.
Better tuning of the main plant controllers.
The below table gives the APC phase II average guaranteed parameters.
PO-58.11
Poster PO-58
In addition to the above non tangible benefits, a survey results from Operation
Department (End users) is presented in the below table:
Criteria Rating
Overall satisfaction Very Good
Benefit value of APC Very good
Work load Less with APC
Process values meeting the Automatic and will not exceed the fixed ranges
set points
Interface Man-Machine Friendly
V- CONCLUSION
Advanced Process Control Technology Qatar Gas experience is less than 1 Year since
the phase I project commissioning.
The results obtained during the performance are exceeding the guaranteed value
regarding the LNG production.
Results of APC implementation is convincing. APC has helped to maintain sea line
pressure and load distribution among the three downstream trains.
APC has helped to reduce variation in many important parameters such as LNG trains
feed gas day- night variation.
Overall benefit figures in terms of production rise and energy savings are valuable.
PO-58.12
Poster PO-58
VI- APPENDIX:
A. Performance test Process Data Trends Comparison:
The process data were compared during 6 days performance test before and after APC
implementation.
100
95
90
85
80
75
23-Jan-05 24-Jan-05 25-Jan-05 26-Jan-05 27-Jan-05 28-Jan-05 29-Jan-05
100
95
90
85
80
75
23-Jan-06 24-Jan-06 25-Jan-06 26-Jan-06 27-Jan-06 28-Jan-06 29-Jan-06
PO-58.13
Poster PO-58
110.0%
107.5%
105.0%
102.5%
100.0%
97.5%
95.0%
92.5%
90.0%
2005-01-23 2005-01-24 2005-01-25 2005-01-26 2005-01-27 2005-01-28 2005-01-29
110.0%
107.5%
105.0%
102.5%
100.0%
97.5%
95.0%
92.5%
90.0%
2006-01-23 2006-01-24 2006-01-25 2006-01-26 2006-01-27 2006-01-28 2006-01-29
PO-58.14
Poster PO-58
1000
980
960
940
LNG Rundown M3/H
920
900
860
840
820
800
10-Jul-04 11-Jul-04 12-Jul-04 13-Jul-04 14-Jul-04 15-Jul-04 16-Jul-04 17-Jul-04
Date
2FI805.PV
1100
1080
1040
LN G R un do w n M 3/H
1020
1000
980
960
940
920
Summer Base Line = 937 M3/H
900
12-Jul-06 12-Jul-06 13-Jul-06 13-Jul-06 14-Jul-06 14-Jul-06 15-Jul-06 15-Jul-06 16-Jul-06 16-Jul-06
Date
2FI805.PV
PO-58.15
Poster PO-58
130
120
110
Steam to Amine Ratio Kg/M3
100
90
70
60
2003-12-30 2004-02-18 2004-04-08 2004-05-28 2004-07-17 2004-09-05 2004-10-25 2004-12-14
Year 2004
130
120
110
Total SteamTo Total Amine Ratio
100
90
80
70
60
2005-12-29 2006-02-17 2006-04-08 2006-05-28 2006-07-17 2006-09-05
Year 2006
PO-58.16
Poster PO-58
3000
2900
LNG Run Down M3/H
2800
2700
2600
2500
2300
2200
29-Dec-05 17-Feb-06 08-Apr-06 28-May-06 17-Jul-06 05-Sep-06 25-Oct-06 14-Dec-06
Year 2006
3100
3000
2900
LN G ru n d o w n M 3/H
2800
2700
2600
2500
2400
Average LNG production = 2657 M3/H
2300
2200
30-Dec-03 18-Feb-04 08-Apr-04 28-May-04 17-Jul-04 05-Sep-04 25-Oct-04 14-Dec-04
Year -2004
PO-58.17
Poster PO-58
5.00
4.50
4.00
Condensate Heater Passes DT C
3.50
3.00
2.50
2.00
1.50
1.00
0.50
0.00
2005-12-29 2006-02-17 2006-04-08 2006-05-28 2006-07-17 2006-09-05 2006-10-25 2006-12-14
Year-2006
Absolute Heater passes Delta T U-H8100 DEG C Absolute Delta T U-H8200 DEG C
5.00
4.50
4.00
3.50
Heater passes DT C
3.00
2.50
2.00
1.50
1.00
0.50
0.00
2003-11-25 2004-01-14 2004-03-04 2004-04-23 2004-06-12 2004-08-01 2004-09-20 2004-11-09 2004-12-29 2005-02-17
Year-2004
Absolute Heater Passes Delta T U-H8100 DEG C Absolute Heater Passes Delta T U-H8200 DEG C
PO-58.18