Professional Documents
Culture Documents
® 8
PRINCE2 Practitioner Resource Book
The project is now at the end of Stage 3. Using the project scenario answer these questions.
1 At the end of Stage 3, 10% of the cost tolerance has been used. Which statement is true?
2 Having planned Stage 4 the project Manager has to do a number of other activities. Which of
these is true?
A. Raise an Exception Plan to cover the Project Plan updates for Stage 4.
B. Consider whether the Project Product Description should be updated.
C. Update the Project Plan and reflect any changes in the Project Plan in the Business
Case.
D. Update the Quality Register with the results of the stage 3 reviews.
3 Having reviewed the amount of work to be undertaken in Stage 4 the Project Manager has
been told that the Project Board require more control. Which two of these actions would give
the Project Board more control?
4 Having looked at the Work Packages planned for Stage 4 the Project Manager wants to make
sure they are under control. Which two actions will give the Project Manager more control?
Question Part
4 A A B C D E
1
2
3
4