Professional Documents
Culture Documents
PYRENEES, SPAIN
FACE DRILLING 31
FD3/12 p31-34 29/3/04 7:26 am Page 32
PYRENEES, SPAIN
Geology
From south to north, towards Vielha, the
massif is comprised of moraines for
210 m, followed by 420 m of fractured
granite, and 2,100 m of massive granite.
Then the Civis formation appears in con-
tact with the granite. This is a highly meta-
morphic rock of the Devonian period,
consisting mostly of slates, and will be the
trickiest tunnelling zone. After that, there
is a 1,600 m portion with quartzites, mixed
with shales in the next 250 m. The align-
ment crosses 420 m of Carboniferous shale
and blackish Silurian shale towards the
north portal.
The excavated cross section is 127 sq m,
and the lined section will be 95 sq m. The
View of the equipment parking area at Other safety equipment includes 67 south portal lies at 1,595 m and the north
the Vielha south portal. CCTV cameras, 12 variable message entrance at 1,396 m, resulting in a gradient
panels, traffic lights, barriers to prevent of 4.57%.
cars from entering the tunnel, SOS posts, a Weather conditions can be extreme, as
network of telephones, radio communica- was the case in late 2002, with tempera-
tions and loudspeakers, a fire detection tures below –20°C. Work takes place all
system, water supply to fire hydrants at year round, in three shifts/day from
the roadside and sprayers in the ceiling, Monday 8 am to Saturday 2 pm. Each team
and automatic incident detection (AID). is composed of a foreman, six workers, a
The technical management of all these mechanic and an electrician.
systems will be handled in a new
control centre located 400 m from the Computerized Drillrigs
south portal.
The road surfacing will be vibrated con- The JV acquired four Atlas Copco drillrigs:
crete on thin concrete. It is fireproof, thus two Rocket Boomer WL3 C models for the
avoiding fire propagation peculiar to main tunnel, and two Rocket Boomer L2 C
asphalt mixtures that contain bitumen. models to excavate the shelters and cross
Under the roadway, there will be a 3 m x passages to the existing tunnel.
2.25 m service tunnel for the electric The Rocket Boomer WL3 C is a fully
wiring and water duct that will feed the computerized drilling jumbo with three
Long view to the face at Vielha. hydrants of the anti-fire niches. booms and basket, capable of handling sec-
tions up to 155 sq m. The Rocket Boomer
L2 C is a twin boom drillrig for sections up
to 90 sq m. Both are equipped with COP
1838 rock drills and Secoroc drill bits.
These machines feature RCS, or rig
control system, an intelligent software that
can be adapted to the number of booms,
the level of automation and the introduc-
tion of new functions without need to
install an expensive and powerful computer
in the smaller and less complex rigs. This
system is reliable, flexible and easily
expandable, allowing new units to be
added anywhere along the data bus, with-
out adding another cable.
To improve the reliability of the system
for a multi-boom rig operating in the full
automation mode, two-level circuit com-
munication has been implemented. The
32 FACE DRILLING
FD3/12 p31-34 29/3/04 7:26 am Page 33
PYRENEES, SPAIN
South Drive
At the south portal, on the Vilaller side,
construction started with a canopy of spiles
in the first 210 m of moraine. The 15 m-
long umbrella vaults were composed of 65
steel pipes, 89 cm in diameter, beneath
which a 12 m-deep top heading was exca-
vated. The next canopy was then installed
with a 3 m overlap and the process repeat-
ed throughout the soft ground. HEB 180
steel arches were erected, and sprayed with
two layers of shotcrete, with and without
fibres.
When the granite was reached, a ramp
was developed downwards to open the full
section, and the Rocket Boomer WL3 C
FACE DRILLING 33
FD3/12 p31-34 29/3/04 7:26 am Page 34
PYRENEES, SPAIN
Mucking-out
The total tunnel system, including the
cross passages between the new tunnel and
the existing one, will generate 671,337 cu m
Rocket Boomer L2 C drilling for There is some water ingress, which col- of spoil. This is being transported to
Swellex bolts. lects at the face and requires pumping dumps at the north portal and 5 km away
round the clock. from the south portal. The granite is
processed in a crushing plant to produce
North Drive aggregates. There is one concrete plant at
each portal.
Progress at the north drive, on the Vielha The machinery used for the mucking-
side, had reached 1,700 m by mid- out at the south drive include five 25 t
November, 2003. Some 60 m had been dumpers Volvo A25 and a loader. A
excavated using the second Rocket Boomer second loader and two 25 t dumpers are
L2 C on cross passage number 12, 54 m on used at the north drive.
number 11, and 2 m on number 10. There is still one year of tunnelling
The main tunnel excavation began with required to breakthrough, which should be
the widening to 127 sq m of a 1,350 m- accomplished by end-2004. ■
long, 60 sq m ventilation tunnel that con-
nected with the existing Vielha tunnel. Acknowledgements
Support is made up of a 5 cm fibre-
reinforced shotcrete layer, Swellex Mn Atlas Copco is grateful to UTE Túnel
rockbolts at one unit per sq m, wire mesh, de Vielha, and in particular to project
more bolts at five units per lineal m, and administrator Pedro García Borjabad and
6 cm of shotcrete without fibres. project manager Ángel Martín Aragón, for
There is a fault approximately 400 m their assistance with the site visit on which
inbye of the widened ventilation tunnel, at this article is based.
Table 1: Four types of ground support have been designed to suit the various ground
conditions and are shown in the table.
1A 3 cm 3 cm – 1 per 2 sq m – –
1B 3 cm 7 cm – 1 per 2 sq m – –
2 3 cm 6 cm 6 cm 1 per 1.5 sq m – –
3A 3 cm 11 cm 3 cm 1 per 1.5 sq m TH – 21 –
3B 3 cm 9 cm 9 cm 1 per 1.5 sq m HEB – 180 –
4 3 cm 10 cm 10 cm – HEB – 180 150 mm-
diameter,
12 m-long
34 FACE DRILLING