Professional Documents
Culture Documents
Presentation 10 PDF
Presentation 10 PDF
NATM
System for Observational approach to tunnel design
Eurocode 7 (EC7) includes the following remarks concerning an
observational method.
Four requirements shall all be made before construction is started:
• With the excavation of a tunnel the primary stress field in the rock
mass is changed into a more unfavourable secondary stress field.field
Under the rock arch we understand those zones around a tunnel
where most of the time dependent stress rearrangement processes
takes place. This includes the plastic as well as the elastic behaving
zone.
zone
1.Deformation of the
excavated tunnel surface/
Convergence tape
Surveying marks
2 Deformation of the ground
2.Deformation
surrounding the tunnel/
Extensometer
3 Monitoring of ground
3.Monitoring
support element ‘anchor’/
Total anchor force
4.Monitoring of ground
support element
‘shotcrete shell’/
Pressure cells
Embedments gauge
NATM Process on site
Main Pressure
where;
Pi = skin resistance
C = cohesion
ϕ = angle of internal friction
R = radius of the protective zone
r = radius of the cavity
P0 = γ H; overburden
Following the main principle of NATM, the protective ring around the cavity (R-r), is a load carrying
part of the structure. The carrying capacity of the rock arch is formulated as;
S τ R Cos ϕ Sσ nR Sin ϕ
PiR = −
b/2 b/2
where;
Pi = resistance of rock arch (t/m2)
S = length of shear plane (m)
τR = shear strength of rock (t/m2)
ϕ = angle of internal friction (0)
b = height of shear zone (m)
σnR = normal stress on shear plane (t/m2)
ϕ, τR, σnR, can be measured in laboratories, where as S
can be
b measured d iin meters
t , on a d
drawing
i made
d tto scale.
l
• Generally two separate supports are carried
out. The first is a flexible outer arch or
protective support designed to stabilize the
structure accordingly. It consists of a
systematically
t ti ll anchored
h d rock k arch
h with
ith
surface protection, possibly reinforced by ribs
and closed by an invert
invert.
• The behaviour of the protective support and
the surrounding rock during the readjustment
process can be monitored by a measuring
system.
system
The second means of support is an inner concrete arch, generally not
carried out before the outer arch has reached equilibrium. In addition to
acting as a final
final, functional lining (for installation of tunnel equipment
etc.) its aim is to establish or increase the safety factors as necessary.
• The resistance of the lining material (shotcrete) is:
dτ s
Pt =
s
sin α s ( b / 2 )
E
• The lining resistance is:
PiL = Pis + Pist
• The anchors are acting with a radial
pressure:
f σp
st st
Pi =
A
et
• With the lateral pressure given by:
σ3 = pis + pist + piA
and with Mohr’s
Mohr s envelope
envelope, the shear
resistance of the rock mass τR and the
g α is determined,, assuming
shear angle g that
the principal stresses are parallel and at
right angles to the excavation line.
The carrying capacity of the rock arch is
given
i b
by:
S ⋅ τ cos ϕ S ⋅ σ n sin ϕ
R R
Pi =
R
−
b/2 b/2
⋅ σ p cos β
st st
af
Pi = A
et (b
(b / 2)
• The total carrying capacity of the outer arch is then:
Pi = Pi + Pi + Pi ≥ Pi min
w L R A
Numerical example for NATM
• Tunnel size: 12
12.10
10 x 12
12.00
00 m
(fig.10)
• H = 15.0 m overburden
according to tests on samples
f
found:d ϕ= 27º,
27º c = 100 t/t/m²²
(three axial tests). When we
open a cavity the stress
equilibrium spoiled and for
establishing
t bli hi new equilibrium
ilib i
condition achieved by
supporting as follows.
• pp
Use the supporting g ringg which
develops around the cavity after
excavation as a self-supporting
device and select a type of
pp
supporting g which can bear the
developed rock loads and
deformable when necessary.
• Design the inner lining under
final loads
The (1) supporting system is capable of carrying safely the
loads,, the (2)
( ) liningg is for safetyy and to bear the additional
loads which are probable to develop after the supports are
installed.
S
Supporting
ti will
ill consists
i t iin thi
this example:
l
a: Shotcrete (15+10) cm in layers by two shots
b: Bolts spaced 2 2.00
00 x 22.00
00 m in rings with diameter Ø 26 mmmm.
c: Rib steel channel supports (2 x 14)
d: byy g
ground supporting
pp g ringg
To find the radius of disturbed zone R:
Talobre formula:
2sinϕ
R
Values entered into the formula:
ϕ= 27º
ϕ
γ = 2.5 t/m³
H = 15.0 m
P0 = γH = 2.5 x 15.0 = 37.5 t/m²
C = 100 t/m²
R = 6.45 m
[ ]
2 sin 27
6.05 1−sin 27
Pi = −100 × cot g 27 + 100 × cot 27 + 37.5 × (1 − sin 27 ) × (
o o o
)
R 2 x 0.450
[
Pi = −100 × 1.96 + 100 × 1.96 + 37.5 × (1 − sin 27 ) × (o
R
]
6.05 1−0.450
)
1 .66
⎛ 6 .05 ⎞
− 196 .3 + 217 .08 × ⎜ ⎟ =0
⎝ R ⎠
1.66
196.3 ⎛ 6.05 ⎞
=⎜ ⎟
217.08 ⎝ R ⎠
R = 6.45 m
Shotcrete:
d = 25 cm
σc28 = 160 kg/cm² compressive strength shear in
concrete (assume 20% of σc28)
th capacity
the it carrying
i lloadd
τsh = 0.20 · 160 = 32 kg/cm² = 320 t/m²
d = thickness of shotcrete in (cm)
α = π/4 - ϕ/2 angle of shear plane with vertical
b = shear failure height of the cavity (see Fig.10)
sin 31
31.5
5 = 0.520;
0 520;
b/2= r cos α= 6.05xcos31.5=5.15
0.25 ⋅ 320
p =
c
= 29.9 t / m 2
0.52 ⋅ 5.15
i
bolts
Bolt Ø 26 mm
III, σsh = 4000 kg/cm
St III kg/cm²
Spacing=2x2 m
f = 5.3cm²
5.3⋅ 4000
p =
b
= 0.53 kg/ cm2
200⋅ 200
i
p = 5.3 t / m
b
i
2
steel ribs τN = normal stress = 142 t/m²
thus
S = 4.54 m (from figure 17)
ϕ = 27º
b/2 = 5.15 m
τR = 170 t/m²
τN = 142 t/m²
enter the formula
p CR = 78.22 t / m 2
The resistance of the bolts (anchors) against the movement of the
shear bodyy towards the cavityy is:
a ⋅ f ⋅ σ sh ⋅ cos β
p =
b
e⋅t ⋅b/ 2
i