S I T E U P DAT E

Former Healy School Site


Fall River, MA
U.S. EPA | H A Z A R D O U S W A S T E P R O G R A M A T E P A N E W E N G L A N D

THE EMERGENCY RESPONSE


A N D R E M O V A L P R O G R A M responds
to chemical, biological and radiological releases and large-scale
national emergencies, including homeland security incidents. EPA conducts
short term cleanups in the removal program when necessary to protect human
health and the environment by either funding response actions directly or
overseeing and enforcing actions conducted by potentially responsible parties.

K E Y C O N TAC T S :

SITE DESCRIPTION
In June of 2018, the Massachusetts Department of Environmental Protection (MassDEP) Z A N E T TA P U R N E L L
responded to a neighbor’s complaint regarding an excessive volume of dust generated U.S. EPA Community Involvement
from the Healy School building demolition. MassDEP inspected the Site following the Coordinator
demolition activities, observed the demolition activities and collected debris samples 617-918-1306
which indicated elevated levels of asbestos and metals. purnell.zanetta@epa.gov

In May 2019, after a MassDEP request, EPA conducted a Preliminary Assessment/ T O M H AT Z O P O U L O S


U.S. EPA On-Scene Coordinator
Site Investigation (PA/SI) at the Site. Bulk/soil samples were collected and analyzed
617-918-1284
for asbestos, metals, and polychlorinated biphenyl content. The EPA PA/SI confirmed
hatzopoulos.athanasios@epa.gov
MassDEP’s data that the demolition debris is contaminated with asbestos and metals.

BAC KG RO U N D CYNTHIA BARAN


During the school demolition activities, asbestos containing materials (ACM) were Massachusetts Department of
crushed, rendered friable, significantly commingled, and spread throughout the Site. Environmental Protection
MassDEP after its investigation issued a Unilateral Administrative Order (UAO) to the Southeast Region
owner and demolition contractor requiring that all Site work cease, and all demolition 508-946-2887
debris be wetted and covered until all (ACM) debris is removed and the Site is returned cynthia.baran@state.ma.us
to compliance in accordance with MassDEP’s asbestos regulations (310 CMR 7.09 and
TOLL-FREE
7.15). Since December 2018, the (ACM) debris at the Site have been consolidated and CUS TOMER SERVICE
covered with reinforced polyethylene sheeting to prevent the migration. 1-888-EPA-7341

E PA’ S I N V O LV E M E N T L E A R N M O R E AT:
EPA has been involved with the Site since MassDEP’s referral in February of 2019. response.epa.gov/
formerhealyschool

continued >>

October 2019
NEXT S TEPS/WHAT TO EXPECT
EPA’s goal for community involvement and segregation of hazardous waste free could become airborne during cleanup
is to provide the public with accurate, debris; repairing all response-related activities. If monitors detect airborne
timely, accessible, and understandable damage; and demobilization from Site. contamination, all work will be stopped,
information about the project as it and actions taken to evaluate and
moves forward. EPA and its contractors will begin address the issue. One may expect to see
mobilizing to the Site the week of heavy equipment, workers in protective
The Removal Action activities that will October 20th, 2019. EPA will generally clothing (i.e., white suits), and trucks
be performed include: mobilization of work from 7am to 5pm. The Removal occasionally which may have a slight
personnel and equipment; performing Action is expected to take 3 to 6 effect on traffic. EPA will coordinate with
air monitoring during working hours; months. Throughout the work day, EPA the City of Fall River to determine the
removing and disposing of building will be monitoring air and dust at the most appropriate route for truck traffic.
debris contaminated with metals and or Site for the safety of site workers and Contaminated soil will be secured on
asbestos; provisions for demolition of the the surrounding community. Monitoring site temporarily while awaiting shipment
interior standing portions of the building, stations setup at the site are purposed offsite to an EPA-approved facility.
onsite decontamination of larger debris, to measure particulate material that