Professional Documents
Culture Documents
net/publication/215908492
CITATION READS
1 1,664
2 authors, including:
Kongkoon Tochaiwat
Thammasat University
147 PUBLICATIONS 41 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Kongkoon Tochaiwat on 16 May 2014.
1
Instructor, Department of Innovation in Real Estate Development, Thammasat University, kongkoon@hotmail.com
2
Associate Professor, Department of Civil Engineering, Chulalongkorn University, fcevcc@eng.chula.ac.th
ABSTRACT : This paper aims to present a framework for improving the provisions of the non-international construction contracts.
The procedure begins by analyzing the availability of the important contract provisions by comparing with two well-known
international standard contracts: AIA and FIDIC contracts. Then, the existing provisions are analyzed in order to find their
inadequacies. To illustrate the proposed procedure, the provisions related to claim in Thai public construction contract were
analyzed. The AIA’s A201 (1997) and FIDIC’s Construction Contract (1999) were used as the standards in the analysis process.
The analysis results showed that there are some claim-related inadequacies found in Thai public standard contract which may be
categorized into two types: the absence of important provisions and the inappropriateness of the existing provisions. Some
recommendations to improve the case contract were also discussed. The results of this research enhance the success to projects and
can help saving some national budget.
KEYWORDS : Claim, Construction contract, AIA contract, FIDIC contract, Project management
1. Consequences of Employer’s The contractor is entitled to claim for extension of time, cost and reasonable profit (in some cases) if works,
Risks goods are damaged by a risk specified to be the employer’s risk.
2. Continuing Contract The contractor shall proceed diligently with the performance of the contract and the employer shall continue
Performance to make payments until the final resolution of a claim.
3. Contractor’s Claim for The contractor is entitled to claim for cost and reasonable profit (in some cases) for any matter he considers
Additional Payment himself to be entitled.
4. Delayed Drawings or The contractor is entitled to claim for extension of time, cost and reasonable profit if the engineer fails to
Instructions instruct or issue the drawings within reasonable time notified by the contractor.
5. Delayed Right of Access to The contractor is entitled to claim for extension of time, cost and reasonable profit if the employer fails to
the Site provide the right to access to the site within the time stated in the contract.
6. Delayed Payment The contractor is entitled to claim for the interest from the amount the employer paid to him beyond the
limit of time specified in the contract.
7. Emergency The contractor is entitled to claim for extension of time, cost and reasonable profit if the employer instructs
him to perform any work need to be performed in order to avoid damage to life or property.
8. Failure to Pass Tests on The employer is entitled to deduct the contract price paid to the contractor if the works fail to pass tests on
Completion completion.
9. Failure to Remedy Defects The employer is entitled to claim for the cost if the contractor fails to remedy the defect that the contractor
is responsible. In addition, he is entitled to remedy such defect by his own forces or by employing other
contractor if the contractor fails to perform this liability.
10. Indemnities Both employer and contractor shall indemnify the other party for all claims and damages attributable to
him.
11. Interference with Tests on The contractor is entitled to claim for extension of time, cost and reasonable profit if the employer delays a
Completion test on completion.
12. Omissions The contractor is entitled to claim for the cost already occurred with the items stipulated in the Bill of
Quantities (BOQ) but are later omitted by variation.
13. Rate of Progress The employer is entitled to claim for the cost if he suffers additional cost from the contractor’s revision of
the program which the contractor is responsible to.
14. Retesting The employer is entitled to claim for the cost if he suffers additional cost from retesting which the
contractor is responsible.
4. Inadequacies of the Existing Claim Provisions of Thai about the contractor’s rights to claim for the additional payment
Public Standard Construction Contract from the employer. In addition, the contract provisions do not
stipulate the rights to claim against the other party expressly.
4.1 Overall Structure of the Claim Provisions On the other hand, the contract does specify the duties of both
The standard contract attached with the Office of Prime parties and let the claimant claim against the other on the basis
Minister’s Regulations is silent about many rights to claim, of breach of contract, which is one type of ex-contractual claims
especially the contractor’s rights to claim against the employer, [5]. The drawbacks of this mechanism are that it causes
as shown in Table 1. The existing provisions are also silent obscurity and lead to disputes between both parties.