You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/215908492

IMPROVING CONSTRUCTION CLAIM PROVISIONS: A CASE STUDY OF THAI


PUBLIC CONSTRUCTION CONTRACTS

Conference Paper · January 2008

CITATION READS

1 1,664

2 authors, including:

Kongkoon Tochaiwat
Thammasat University
147 PUBLICATIONS   41 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

MIRED Project View project

All content following this page was uploaded by Kongkoon Tochaiwat on 16 May 2014.

The user has requested enhancement of the downloaded file.


การปรับปรุงขอสัญญาเกี่ยวกับการเรียกรองสิทธิในงานกอสราง: กรณีศึกษาสัญญาวาจางกอสรางของ
หนวยราชการไทย
IMPROVING CONSTRUCTION CLAIM PROVISIONS: A CASE STUDY OF THAI
PUBLIC CONSTRUCTION CONTRACTS

กองกูณฑ โตชัยวัฒน (Kongkoon Tochaiwat)1


วิสุทธิ์ ชอวิเชียร (Visuth Chovichien)2

1
Instructor, Department of Innovation in Real Estate Development, Thammasat University, kongkoon@hotmail.com
2
Associate Professor, Department of Civil Engineering, Chulalongkorn University, fcevcc@eng.chula.ac.th

ABSTRACT : This paper aims to present a framework for improving the provisions of the non-international construction contracts.
The procedure begins by analyzing the availability of the important contract provisions by comparing with two well-known
international standard contracts: AIA and FIDIC contracts. Then, the existing provisions are analyzed in order to find their
inadequacies. To illustrate the proposed procedure, the provisions related to claim in Thai public construction contract were
analyzed. The AIA’s A201 (1997) and FIDIC’s Construction Contract (1999) were used as the standards in the analysis process.
The analysis results showed that there are some claim-related inadequacies found in Thai public standard contract which may be
categorized into two types: the absence of important provisions and the inappropriateness of the existing provisions. Some
recommendations to improve the case contract were also discussed. The results of this research enhance the success to projects and
can help saving some national budget.

KEYWORDS : Claim, Construction contract, AIA contract, FIDIC contract, Project management

1. Introduction des Ingenieurs-Conseils (FIDIC), the American Institute of


The use of standard contracts became popular in the Architects (AIA), the Associated General Contractors of
construction industries worldwide due to several advantages America (AGC), the Engineers’ Joint Contract Documents
such as being fair to all parties, completeness of the contract Committee (EJCDC), the Institution of Civil Engineers (ICE),
documents, avoiding misunderstanding, clear definition of both and the Joint Contracts Tribunal (JCT).
parties’ responsibilities, avoiding improper language in the Using non-standard contract form may cause some
specification, using consistent terminology, supporting risk problems to the projects. An example of the projects suffering
management, etc. Up to now, many standard contracts have from the damages caused by the inadequacies of the contract
been issued. They are normally prepared by the well-known provisions is the “Bang Na-Bang Pli-Bang Pakong Expressway
international organizations such as the Federation
 Internationale Project (BBBE)”, a design-build project that became one of the

(CEM) Page 320
most scandalous infrastructure projects in Thailand during the 2. Research Methodology
end of 1990’s. The approximately 580 million dollar project This research was done by performing the following steps.
faced the court decision to pay for additional payment claims Firstly, the related literatures were reviewed. They were those
amounting to about 140 million dollar, part of which is related to the construction law principle, Thai public standard
supposed to compensate for damages suffered by the contractor construction contract (2002), the widely accepted international
for not getting access to the construction site. By reviewing the standard construction contracts: the FIDIC Conditions of
BBBE contract, it was found that there are some inadequacies Contract for Construction (First Edition) or the “Construction
leading to the project problems. They are the provisions related Contract (1999)”, and General Conditions of the Contract for
to excepted risks, and determination of additional payment & Construction (AIA Document A201-1997) or “AIA A201
time extension. [8] (1997)”. Secondly, the availabilities of the necessary claim
In developing countries, there are some efforts to prepare provisions were examined from Thai public standard
their own construction contracts for using in the employment in construction contract. Two international contracts, the
public sectors. The examples of these contracts are the Thai Construction Contract (1999) and A201 (1997), were used as
public standard construction contract prepared in 2002. There the standards in the analysis process. The necessary provisions
have been many former researches related to the deficiencies of that were stipulated in either international contract but were
these standard contracts. For Thai public construction contract, absent from Thai public standard construction contract would
they are those of Kompayak [7], Bunsrangserm [3], and be listed. Then, the existing provisions of Thai public standard
Chovichien and Tochaiwat [9], etc. contract related to claims were analyzed in order to find their
As to construction claims, they are found in almost every inadequacies (if any). Finally, the research results were
construction project. It is the seeking of consideration or concluded and some recommended solutions to mitigate the
change by one of the parties involved in the construction claim inadequacies found were recommended.
process. Nowadays, substantially increasing volume of claims
is the result of the rising complexity of the projects, the price 3. Availability of the Necessary Provisions in Thai
structure of the construction industry and the legal approach Standard Contract
taken by many employers and contractors. Booen [2] summarized the provisions related to
The objective of this paper is to present a framework for construction claims in The Construction Contract (First
analyzing the inadequacies found in non-international Edition). The results of this research were used as the checklist
construction contracts, especially in those of developing in the analysis process. The other claim provisions found in
countries, to find the recommended solution to improve them by A201 (1997) were also added into the checklist. From
using the provisions related to claims of Thai public standard analyzing the availability of the necessary provisions related to
construction contract as a case study, and to present some construction claims of A201 (1997), The Construction Contract
inadequacies found in Thai public standard construction (1999), and Thai public standard construction contract attached
contract and some recommendations for improving this form of to the Office of Prime Minister’s Regulations (2002), it was
contract. found that there are a number of necessary provisions absent
from Thai public standard construction contract. Their topics
and brief descriptions are shown in the Table 1 below.

(CEM) Page 321


Table 1 Necessary Claim Provisions Being Absent from Thai Public Standard Construction Contract
No. Topic Description of the Absent Provision

1. Consequences of Employer’s The contractor is entitled to claim for extension of time, cost and reasonable profit (in some cases) if works,
Risks goods are damaged by a risk specified to be the employer’s risk.
2. Continuing Contract The contractor shall proceed diligently with the performance of the contract and the employer shall continue
Performance to make payments until the final resolution of a claim.
3. Contractor’s Claim for The contractor is entitled to claim for cost and reasonable profit (in some cases) for any matter he considers
Additional Payment himself to be entitled.
4. Delayed Drawings or The contractor is entitled to claim for extension of time, cost and reasonable profit if the engineer fails to
Instructions instruct or issue the drawings within reasonable time notified by the contractor.
5. Delayed Right of Access to The contractor is entitled to claim for extension of time, cost and reasonable profit if the employer fails to
the Site provide the right to access to the site within the time stated in the contract.
6. Delayed Payment The contractor is entitled to claim for the interest from the amount the employer paid to him beyond the
limit of time specified in the contract.
7. Emergency The contractor is entitled to claim for extension of time, cost and reasonable profit if the employer instructs
him to perform any work need to be performed in order to avoid damage to life or property.
8. Failure to Pass Tests on The employer is entitled to deduct the contract price paid to the contractor if the works fail to pass tests on
Completion completion.
9. Failure to Remedy Defects The employer is entitled to claim for the cost if the contractor fails to remedy the defect that the contractor
is responsible. In addition, he is entitled to remedy such defect by his own forces or by employing other
contractor if the contractor fails to perform this liability.
10. Indemnities Both employer and contractor shall indemnify the other party for all claims and damages attributable to
him.
11. Interference with Tests on The contractor is entitled to claim for extension of time, cost and reasonable profit if the employer delays a
Completion test on completion.
12. Omissions The contractor is entitled to claim for the cost already occurred with the items stipulated in the Bill of
Quantities (BOQ) but are later omitted by variation.
13. Rate of Progress The employer is entitled to claim for the cost if he suffers additional cost from the contractor’s revision of
the program which the contractor is responsible to.
14. Retesting The employer is entitled to claim for the cost if he suffers additional cost from retesting which the
contractor is responsible.

4. Inadequacies of the Existing Claim Provisions of Thai about the contractor’s rights to claim for the additional payment
Public Standard Construction Contract from the employer. In addition, the contract provisions do not
stipulate the rights to claim against the other party expressly.
4.1 Overall Structure of the Claim Provisions On the other hand, the contract does specify the duties of both
The standard contract attached with the Office of Prime parties and let the claimant claim against the other on the basis
Minister’s Regulations is silent about many rights to claim, of breach of contract, which is one type of ex-contractual claims
especially the contractor’s rights to claim against the employer, [5]. The drawbacks of this mechanism are that it causes
as shown in Table 1. The existing provisions are also silent obscurity and lead to disputes between both parties.

(CEM) Page 322


From analyzing the claim provisions of the international (b) payment of any such Cost, which shall be
standard contract, A201 (1997) and the Construction Contract included in the Contract Price…
(1999) seem to have more well-arranged structures. Both have
many sub-clauses that directly stipulate the rights to claim for The margin words such as “Consequences of Suspension”,
many specific reasons to either employer or contractor “Suspension of Work” and “Contractor’s Claim” give the topics
completely. Furthermore, there are mechanisms that make the of the sub-clauses or the referred sub-clauses. The provisions
scopes of the employer’s and the contractor’s cover all issues stipulated in item (a) and (b), which entitle the rights to claim
which can result from the construction activities. Sub-clause for an extension of time and an additional payment respectively,
4.3.1 of A201 (1997) specifies the definition of claim which are separated and stipulated in similar wording with other claim
cover both employer’s & contractor’s claim while Sub-clause sub-clauses. This makes it is very easy to find what sub-clause
2.5 & sub-clause 20.1 of the Construction Contract (1999) entitles the rights to claim to both parties.
directly stipulate the rights of the employer and the contractor,
respectively, to claim against the other in case of any matter he 4.2 Error in the Details Provided by the Employer
thinks he is entitled to claim. Thai public standard construction contract refuses to give
Another salient aspect of the claim provisions of the the right to claim for cost and reasonable profit (in some cases)
Construction Contract (1999) conditions of contract is its occurring from errors in contract documents to the contractor.
easiness to find and to refer to. Because the provision entitles As to Clause 14 of the contract, the contractor agreed that he
the right to claim for additional payment or extension of time is has deliberately reviewed all drawings and specifications and
stipulated in a separate paragraph for each sub-clause and is agrees to follow the employer’s instruction in case there is any
worded with the same pattern with the other sub-clauses, it is mistake or error found in these documents, without any claim
easy to find sub-clauses that stipulate the rights to claim. for increased cost. This provision is not fair to the contractor
Moreover, the margin word system, which specifies the whole and causes disputes to the project. Because construction is
idea of each sub-clause, provides the convenience to find the complex, unique, and dynamic, it is very difficult to prepare a
required claim provisions. To illustrate the said aspects, Sub- set of all contract documents without any mistake or error. In
clause 8.9 [Consequences of Suspension] is presented as an case the contractor has reviewed the documents with reasonable
example. care, he deserves the compensation for the mistakes or the
errors which the employer is responsible to.
8.9 If the Contractor suffers delay and/or incurs Cost from Thai public standard construction contract should be
complying with the Consequences of Engineer’s modified by allowing the contractor to claim for compensation
instructions under Sub-Clauses 8.8[Suspension of Work] if he suffers any damage from the errors in drawings or
and/or Suspension from resuming the work, the Contractor specifications which the employer is responsible to. From sub-
shall give notice to the Engineer and shall be entitled clause 2.2.3 of A201 (1997), the contractor is entitled to rely on
subject to Sub-Clause 20.1[Contractor’s Claims] to: the accuracy of information furnished by the employer. This
(a) an extension of time for any such delay, if provision gives right to claim for the errors of the employer in
completion is or will be delayed, under Sub- the documents supplied to the contractor. As to the
Clause 8.4[Extension of Time for Completion] Construction Contract (1999), sub-clause 1.9 stipulated the duty
and of the engineer, as the employer’s representative, to provide any
necessary drawing or instruction required by the contractor in

(CEM) Page 323


order to perform the works continuously. The contractor is Sub-clause 8.7 of the Construction Contract (1999)
entitled to claim for an extension of time for completion and specifies the employer’s right to the delay damages stated in the
payment of any cost plus reasonable profit if the engineer fails appendix to tender for the contractor’s failure to complete the
to issue such drawing or instruction. works within the time to completion, adjusted by any extension
of time. These damages shall be paid for every day which
4.3 Delay Damages elapses between the relevant time for completion and the date
If the contractor can not complete his responsibilities stated in the taking-over certificate. It should be noted that the
within time to completion, adjusted by all extension of times the liquidated damages provision is an option in AIA Conditions of
contractor is entitled, Thai public standard construction contract Contract. This is the reason why A201 (1997) does not contain
specifies the contractor to pay the employer the liquidated such provision.
damages stipulated in the contract, in the form of per diem rate.
However, the contract also stipulates the employer’s entitlement 5. Discussion
to the consultant remuneration he has paid and the additional From analyzing Thai public standard construction contract,
damages (if any) that occur from the delay that is caused by the there are fourteen important claim-related provisions absent,
contractor which exceeds the liquidated damages collected from which are summarized in Table 1, including the contractor’s
the contractor. rights to claim for additional payment. In addition, the existing
From the construction law principle, liquidated damages provisions were found to have many inadequacies such as the
for contractor’s delay completion are predetermined in order to overall structure of the claim provisions, the error in the details
avoid the difficulty of the employer or a court to accurately provided by the employer, and the delay damages. As to the
compute the amount the employer has lost owing to the late overall structure of the claim provisions, Thai contract has
completion [6]. This is the reason why the contract should not problems related to the obscure and dispute-leading mechanism
stipulate the contractor to pay both liquidated damages and of stipulating the rights to claim into the contract and the
actual damages at the same time for his delay. By stipulating difficulty to find and to refer to the required provisions.
both damages, the per diem rate predetermined seems to be only From the said inadequacies, the recommended solutions
as a penalty to the contractor. The actual damages still have to that Thai government should adopt to improve such standard
be calculated and the contractor may pay more than the actual form of contract comprise:
damages caused by his delay if such actual damages are less 1) inserting the absent necessary claim provisions, as
than those calculated from the per diem rate. shown in Table 1, into Thai public standard construction
Thai public standard construction contract should be contract,
improved in this issue in order to increase fairness to the 2) stipulating the claimant’s rights to claim in the
contractor and acceptance from all relevant people, especially in provisions expressly,
the international projects. The contract should stipulate only 3) improving easiness to find and to refer to the contract
one method for calculating the employer’s damages caused by clause. The standard format of wording, and the margin word
the contractor’s delay. The liquidated damages approach has system can help achieving this goal,
advantage of the easiness to calculate and can help both parties 4) modifying the provision related to the contractor’s right
to avoid disputes. However, the actual damages approach may to claim for the error in details provided by the employer by
be selected for a project. allowing the contractor to claim for compensation if he suffers

(CEM) Page 324


any damage from the errors in drawings or specifications which contract, Thailand will get many benefits such as reduction of
the employer is responsible to. project disputes, reduction of project cost, the fairness to both
5) modifying the provision related to delay damages by parties, efficient contract management, and acceptance in the
stipulating only one method for calculating the employer’s international level.
damages caused by the contractor’s delay in the contract. The
liquidated damages approach should be adopted because of its 7. References
easiness to calculate, and ability to help both parties to avoid [1] American Institute of Architects [AIA], 1999. Commentary on AIA
disputes. Document A201-1997. Washington D.C.: The American Institute of
Architects.
[2] Booen, Peter L., 2001. Claims & Adjustments of the Contract. FIDIC
6. Conclusion and Recommendation
Global Conditions of Contract. New Delhi,
This paper proposes a framework for analyzing the <http://www.fidic.org/resources/contracts/booen_k.asp> (19 March
inadequacies of non-international construction contracts, 2001)
especially those used in developing countries, finding the [3] Bunsrangserm, Nujjaree, 2000. A Study of the Deficiencies in the
recommend solution to improve them. The framework Contractual Conditions of the Government Construction Contract,
proposed in this paper can be a very useful tool for improving Master’s Degree Thesis, Chulalongkorn University.
[4] Federation Internationale des Ingenieurs-Conseils [FIDIC], 1999.
construction contract provisions. It can help the analyzer to
Conditions of Contract for Construction for Building and Engineering
find the inadequacies and recommended solutions to solve the Works Designed by the Employer, First Edition. Lausanne: FIDIC.
inadequacies systematically. [5] Hughes, G A and Barber, J N., 1992. Building and Civil Engineering
Even though Thai public standard construction contract has Claims in Perspective. London : Longman Scientific & Technical.
been used for procurement in Thai construction industry for a [6] Jervis, B M., 1988. Construction Law – Principles and Practice. New
long time, it still has some inadequacies including those York: McGraw-Hill.
[7] Kompayak, Palm, 1999. Contract Administration Procedures in the
involving construction claims. They can be classified into two
Thai Construction Industry. Master’s Degree Thesis. Asian Institute
categories: the absence of the necessary claim provisions, and
of Technology.
the inadequacies of the existing claim provisions. There are [8] Tochaiwat, Kongkoon and Chovichien, Visuth, 2003. Contract
some contract modifications that Thai government should adopt Provision Inadequacies in Infrastructure Design-Build Contract: A
in order to improve Thai public standard construction contract: Case Study. Proceedings of the Fourth Regional Symposium on
inserting the absent necessary claim provisions, stipulating the Infrastructure Development in Civil Engineering. Bangkok: D2-9 –
claimant’s rights to claim in the provisions expressly, D2-18.
[9] Tochaiwat, Kongkoon and Chovichien, Visuth, 2003. The
improving easiness to find and to refer to the related contract
Applicability of Construction Client/ Consultant Form of Agreement
clauses, modifying the provision related to errors provided by in Thai Public Construction Projects. Proceedings of The Ninth East
the employer, and modifying the provision related to delay Asia-Pacific Conference on Structural Engineering and Construction.
damages. By improving the claim provisions of this form of Bali: CEM-16.

(CEM) Page 325


View publication stats

You might also like