You are on page 1of 5

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/283642936

Rights & Obligations of Contracting Parties in Engineering Contracts in


Bangladesh

Article  in  International Journal of Mechanical & Mechatronics Engineering · July 2011

CITATIONS READS

0 4,683

3 authors, including:

Mohammad Zoynal Abedin


Dhaka University of Engineering & Technology
38 PUBLICATIONS   163 CITATIONS   

SEE PROFILE

All content following this page was uploaded by Mohammad Zoynal Abedin on 10 November 2015.

The user has requested enhancement of the downloaded file.


International Journal of Mechanical & Mechatronics Engineering IJMME-IJENS Vol: 11 No: 03 31

Rights & Obligations of Contracting Parties in Engineering Contracts in


Bangladesh

Mohammad Anisur Rahman, Md. Moinul Islam, Mohammad Zoynal Abedin

Department of Mechanical Engineering, Dhaka University of Engineering and Technology,


Gazipur-1700, Bangladesh
Email: anis9174@yahoo.com

ABSTRACT
This paper introduces the basics of contracts related to engineering works and services. It also describes the process of
contracting works to give an idea how the contract issues are framed out in the process. In addition, it describes the
relationship and interfaces of engineering and law, definition and meaning of contract, types of contracts, and
prerequisites to the formation of a valid contract, interpretation of contract and performance or breach of contract.
Moreover, it analyzes the elements of contract in the light of the guidelines, rules and regulations to formulate sound
contracts.

It also frames out the model conditions of contract, in which it distinguishes between two types of contract i.e.
“General Conditions of Contract” and “Conditions of Particular Application” and describes all issues that are related
to the first one.

The core objective of this paper is to analyze some special contracting issues, which are vital for both the contractor
and the employer. Furthermore, it finds out the rights and obligations of contractor and employer on those
contracting issues.

KEYWORDS: GoB, Issue, Cross-reference, Model Condition, Contractor, Employer, Financier, FIDIC

1. INTRODUCTION In this process various documents are being generated by


them. Some of these documents eventually become the
In Bangladesh, many development projects are parts of contract. General contracts of a work or project
implemented every year. These development projects may consist of the conditions of contract, terms of negotiations,
be grouped as construction project and engineering project. tender documents and specifications, bids of the contractor.
Most of these projects are implemented by contractors In case of confusion or dispute, all these documents are
under some agreement called contracts. The terms of these studied for possible explanation or resolution.
contracts are mostly taken from common law or business
law. As mentioned above, there are numbers of guidelines for
formulating contracts. The terms of these contracts are
In Bangladesh contract terms vary from contract to contract written in legal styles. Besides, there are many cross-
depending on the financier of the project. Financiers could reference clauses. These create complexity in contract
be Government of Bangladesh (GoB), multilateral donors issues. Since most of the time, contracts are administered
like World Bank, ADB and bilateral donors like SIDA, by people without legal background, it often becomes
CIDA, US AID, JICA, DANIDA, NORAD etc. If a project difficult for them to understand the rights and obligations of
is financed by Government’s own money usually the contract issues. Most of the engineering contracts are
contract terms are guided by the Government’s form administered by the engineers. So the engineers’ knowledge
no.2911 guideline. On the other hand, if the project is on the basics of the law is important in their work. It helps
financed by multilateral or bilateral donor agency, the them recognize situations in which the assistance of a
contract terms are guided by their own guidelines. lawyer should be sought, preferably before difficulties
Federation International Des Ingenieurs-Conseils (FIDIC) actually arise. This interfacing knowledge also helps them
has formulated general guidelines for construction, to fully cooperate with the attorneys they have to work
engineering procurement contact (EPC) and Turnkey with. An engineer must have some generalized
projects, which are widely accepted in Bangladesh. Each of understanding of the law in the following areas for his/her
the multilateral and bilateral donor agencies has their own work.
guidelines for the terms of contracts. Although the donor
agencies have their own guidelines, sometimes they follow  The preparation of contract documents and
the FIDIC guidelines for its versatility. FIDIC guidelines specifications.
are also followed in the case of supplier’s credit projects.  The conduct of contractual relationships and the
handling of claims and payments.
Various organizations and people are involved in project  The interpretation of contract clauses and the
formulation, evaluation, and contract preparation process. settlement of disputes arising there from.
111303-0404 IJMME-IJENS © June 2011 IJENS
IJENS
International Journal of Mechanical & Mechatronics Engineering IJMME-IJENS Vol: 11 No: 03 32

 The education of attorneys regarding engineering 3. FINDINGS


matters and customs
 The preparation of material for use as trail evidence. One of the issues, which is put in plain words, is shown
 The serving as an expert witness on technical points at bellow:
arbitration hearings and court proceedings.
 The settlement of disputes out of court. Name of the issue: Designs, Quality, Inspection and
 The giving of assistance in tax and valuation problems. Testing
 The handling of engineering matters connected with
purchase and sale of property and goods. 4. SUMMARY
 The preparation of reports on zoning, environmental,
In an engineering project design, quality, inspection and
and other matters involving governmental agencies and
testing issues are part and parcel. In a typical contract
organizations.
document these issues are addressed in clauses related to
Design, Materials, Plant and Workmanship depending on
In order to meet the above work requirements, the
the type of contract.
engineers must be aware of the basics of contracts as well
the elements of contract issues in construction, EPC,
In the “construction” contracts the duties and
turnkey. Although engineers deal with this type of projects
responsibilities are more related to preparation, custody,
in different capacity, they are often not aware of the
implications of the actions. It is felt that a comprehensive privities, and communication of drawings and
specifications.
body of knowledge is essential for the engineers managing
different kinds of contracts.
4.1 Sample Wording
2. METHODOLOGY
 FIDIC 6.1 through 6.5, 7.1 through 7.3, 8.1 and 8.2,
Relevant rules and procedures of the government of 36.1 through 36.5, 37.1 through 37.5, 38.1, 38.2, 39.1
Bangladesh have been collected to study the project and 39.2 for “construction” contracts.
development and implementation processes. Documents  World Bank Clauses 33.1, 34.1, 35.1, 35.2 and 36.1 for
like Bangladesh Form No. 2911, FIDIC guidelines and “construction” contracts.
World Bank guidelines have also been collected and  Clause 11, 15, 16, 17 and 18 of Bangladesh Form No
studied to analyze the rights and obligations for both the 2911, Item Rate Tender and Contract for works.
Employer and the Contractor.
4.2 Contractor’s Obligations
There are different guidelines for different types of
contracts such as Construction Contracts, Engineering and  The Contractor will not release or communicate the
Procurement Contracts, Turnkey Contracts, etc. Here, only drawings, specifications and other documents to any
on the contracts related to construction projects are third party without the consent of the Employer or his
concentrated to study representative. (FIDIC6.1)
 One copy of the drawing shall be kept by the
Various types of contracts and prerequisites to the Contractor on the site and shall make it available to
formation of a valid contract have been studied for getting Employer or his representatives’ at all reasonable time
basic concepts of contract. Besides, various project- for inspection. (FIDIC 6.2)
processing procedures in engineering contract in  The Contractor must notify the Employer of any delay
Bangladesh and the formation process of contract have also in work for any delay in supplying drawings by the
been studied. Finally, project-processing flow diagram has Employer. (FIDIC 6.3)
been drawn to explain the various steps in the processes. It  The Contractor must carry out works according to any
helps the people to understand how the contract issues are supplementary drawings or specifications issued by the
framed in the process. It is also possible to know how some employer or its representative. (FIDIC 7.1)
of the documents, which are being generated during the  Any works designed by the Contractor must be
project-process, become the part of contract. submitted to the Employer and get approved before
execution (FIDIC7.2a). Such approval shall not relieve
The guidelines of GoB, FIDIC and World Bank and all the the Contractor of any of his responsibilities under the
general conditions of contracts have been studied. Some of contract (FIDIC7.3)
the general issues have been analyzed, which are common  The operation and maintenance manual along with
to those guidelines and vital for both the contracting parties drawings of completed permanent works must be
and put them in plain words. So the contract-governing submitted to the Employer for the latter’s approval and
people who have no legal background can easily understand use. (FIDIC7.2b)
the rights and obligations of both the contracting parties.  The Contractor shall carry out the works and remedy
any defects thereof with utmost care and diligence.
(FIDIC 8.1).

111303-0404 IJMME-IJENS © June 2011 IJENS


IJENS
International Journal of Mechanical & Mechatronics Engineering IJMME-IJENS Vol: 11 No: 03 33

 `The Contractor shall provide all materials, plants and 4.5 Employer’s Rights
workmanship as specified in the contract and in
accordance with the instruction of the Employer’s  The employer has the right to get notice of any delay or
representative. (FIDIC 36.1 and GoB 11) disruption of work. (FIDIC 7.1).
 The Contractor shall supply necessary assistance,  The employer has the right to decide on any additional
labor, electricity, fuels, apparatus and instruments for tests other than the ones provided in the contract. The
the purpose of testing as required by the Employer at Employer has the right to decide whether such tests
the place of manufacture, fabrication or preparation, would warrant time extension of cost provision.
or on the site or at such other places as specified in the (FIDIC 36.4, 37.5).
contract. (FIDIC 36.1)  The Employer has the right to access and inspect
 Cost of samples and cost of tests clearly intended or works any time with a 24- hour notice to the
provided for in the contract shall be borne by the contractor. (FIDIC 37.1,37.2,AND 37.3)
Contractor.  The Employer has the right to reject any work or
 The Contractor shall agree to timing and place of test material if found defective after testing .However, he
provided Employer has notified at least 24 hours must give reasons for such rejection. (FIDIC 37.4)
before such test(s). Also the Contractor shall obtain  The Employer has the right to delegate inspection and
necessary permission for the employer or its testing to any third party. (FIDIC 37.5).
representative’s access to places other than  The Employer has the right to issue instruction to
Contractor’s to carry out such tests. remove, replace materials or plants or workmanship if
 The Contractor shall not cover up or put out of view he thinks they are not in accordance with the contract.
any works without giving notice to the employer for The Employer has the right to employ and pay other
inspection and subsequent approval of the Employer’s persons to carry out the above if the Contractor is in
representative. In breach of this responsibility, the default to obey the instructions. (FIDIC 39.1 and 39.2)
Contractor shall, at his cost, open up the works as
demanded by the Employer. 5. CONCLUSIONS

4.3 Contractor’s Rights This paper explores most of the people dynamically in the
field of contracts, which is not utterly unknown to them. In
 To obtain 2 copies of the drawings and specification. addition, it provides information in boosting up the people
(FIDIC 6.1) to complete an engineering contract fruitfully.
 To extension of time or provision of cost if any delay in
delivery of drawing or instruction from the employer Most of the time people who guide the contract usually do
due to employer’s negligence. (FIDIC 6.4) not want to comprehend carefully the contract issues
 If the Employer or its representative instructs the because of cross-reference clauses. This paper eliminates a
Contractor to carry out any test without their presence, few vital cross-reference clauses as much as possible for
then the results of such test must be accepted by the easy realization of the contract issues. This realization will
Employer. (FIDIC 37.3). assist the people of various government organizations who
 To obtain notice of any delegation of testing and guide the contract to make a sound contract. Not only the
inspection to any third parties by the Employer. Employer but also the Contractor should read the contract
(FIDIC 37.5). issues before the signing of the contract to refrain from
making a huge amount of losses or from counting
4.4 Employer’s Obligations compensation.

 To supply 2 copies of the drawings and specification to ACKNOWLEDGEMENTS


the Contractor. (FIDIC 6.1).
 To agree to test results if instructed the Contractor to The authors are very much grateful to Late Dr. Mahiuddin
carry out any test without his presence. (FIDIC 37.3). Ahmed, Ex-Professor & Head, Department of Industrial
 To give notice of any delegation of testing and and Production Engineering, Bangladesh University of
inspection to any third parties. (FIDIC 37.5) Engineering and Technology (BUET), Bangladesh, for his
constant guidance, valuable suggestions and moral supports
 To respond to notices by the Contractor of any delay or
throughout the study.
disruption due to some drawing or instruction from the
Employer and determine time extension or cost
provision for any delay in providing necessary drawing REFERENCES
or instruction. (FIDIC 6.3 and 6.4).
[1] “Conditions of Contract for Works of Civil Engineering
 To inspect and measure works once the Contractor
Construction”, FIDIC, Fourth Edition 1987.
gives notice of readiness of the work or part of it for
[2] “Standard Bidding Documents”, The World Bank,
inspection and measurement. The Employer cannot
September 5, 2000.
delay such inspection unreasonably. (FIDIC 38.1).
[3] “Item Rate Tender and Contract For Works”,
Bangladesh Form No.-2911.

111303-0404 IJMME-IJENS © June 2011 IJENS


IJENS
International Journal of Mechanical & Mechatronics Engineering IJMME-IJENS Vol: 11 No: 03 34

4]“Managing Project In Bangladesh”- Dr.


Skylark Ishwaran S. Chadha, Second revised
edition 1989

[5]“General Instruction and Guidelines On


Planning, Programming, Processing and
Implementation Of Technical Assistance (TA)”-
Economic Relations Division , Ministry of
Finance, GoB, May,1992

111303-0404 IJMME-IJENS © June 2011 IJENS


IJENS

View publication stats

You might also like