You are on page 1of 1

J A D W A L P E L A K S A N A A N (TIME SCHEDULE)

APRIL
NO URAIAN PEKERJAAN BOBOT (%) MINGGU KE-1 MINGGU KE-2 MINGGU KE-3 MINGGU KE-4
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6
1 Pengerjaan Balok
Lantai 10
Balok BL (20x60) 22.86 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09
Balok B15C (25x50) 11.43 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67
Balok B1B (30x60) 17.14 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86
Balok B6 (30x70) 20 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18

2 Pengerjaan Plat Lantai


Lantai 10 28.6 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
Total Bobot Pekerjaan 100.0
Rencana Bobot Mingguan 2.39 3.25 4.43 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.1 3.92 3.25 1.3
Akumulasi Rencana Bobot Mingguan 0 2.39 5.64 10.1 15.2 20.3 25.4 30.5 35.6 40.7 45.8 50.9 56 61.1 66.2 71.3 76.4 81.5 86.6 91.7 95.6 98.8 100

You might also like