3 Pump House Excavation 13616 8443 5173 400 150 5023 complete by june 30
4 Draft Tube Excavation 6402 2150 4252 100 46 4206 Complete by Oct 31
6 Delivery Cistern Excavation 9000 1950 7050 250 0 7050 Complete by Oct 31
Note : Earthwork quantities of Pumphouse and Surgepool will be finalised after fixing pump manufacturer
Concrete Progress for Surgepool & Pumphouse will commence from 01-07-2019
Supply of E&M parts will commence from 01-07-2019