PACKAGE - V OF IFFC DAILY PROGRESS REPORT

Total Balance Completed as Balance as on Programme for Progress on


S.No. Description of work Balance Remarks
Qty (cum) on 15-06-2019 16-06-2019 16-06-2019 16-06-2019
Tunnel Bed lining in progress at 10.66 km ; Complete
1 Main Tunnel Lining 63144 1442 61702 160 0 61702 by june 15 2020

2 Surge pool Excavation 1793 1290 503 0 0 503 complete by june 30

Surge pool Concrete 8310 0 8310 0 0 8310 commence from 01-07-19

3 Pump House Excavation 13616 8443 5173 400 150 5023 complete by june 30

Pump House Concrete 11879 0 11879 0 0 11879 commence from 01-07-19

4 Draft Tube Excavation 6402 2150 4252 100 46 4206 Complete by Oct 31

Draft Tube Concrete 4766 0 4766 0 0 4766 commence from 01-09-19

DM 1 EL: 382.00 ; DM 2 EL : 377.90 ; DM 3 EL : 378.00


5 Delivery Mains Excavation 11394 459 10935 10 10 10925 ; Complete by Oct 31

Delivery Mains Concrete 4889 0 4889 0 0 4889 commence from 01-09-19

6 Delivery Cistern Excavation 9000 1950 7050 250 0 7050 Complete by Oct 31

Delivery Cistern Concrete 12000 0 12000 0 0 12000 commence from 01-09-19

Note : Earthwork quantities of Pumphouse and Surgepool will be finalised after fixing pump manufacturer
Concrete Progress for Surgepool & Pumphouse will commence from 01-07-2019
Supply of E&M parts will commence from 01-07-2019