Power Quality
PTS 13.01.01
June 2016
FOREWORD
PETRONAS Technical Standards (PTS) has been developed based on the accumulated knowledge,
experience and best practices of the PETRONAS group supplementing National and International
standards where appropriate. The key objective of PTS is to ensure standard technical practice across
the PETRONAS group.
Compliance to PTS is compulsory for PETRONAS-operated facilities and Joint Ventures (JVs) where
PETRONAS has more than fifty percent (50%) shareholding and/or operational control, and includes
all phases of work activities.
Contractors/manufacturers/suppliers who use PTS are solely responsible in ensuring the quality of
work, goods and services meet the required design and engineering standards. In the case where
specific requirements are not covered in the PTS, it is the responsibility of the
Contractors/manufacturers/suppliers to propose other proven or internationally established
standards or practices of the same level of quality and integrity as reflected in the PTS.
In issuing and making the PTS available, PETRONAS is not making any warranty on the accuracy or
completeness of the information contained in PTS. The Contractors/manufacturers/suppliers shall
ensure accuracy and completeness of the PTS used for the intended design and engineering
requirement and shall inform the Owner for any conflicting requirement with other international
codes and technical standards before start of any work.
PETRONAS is the sole copyright holder of PTS. No part of this document may be reproduced, stored
in a retrieval system or transmitted in any form or by any means (electronic, mechanical, recording or
otherwise) or be disclosed by users to any company or person whomsoever, without the prior written
consent of PETRONAS.
The PTS shall be used exclusively for the authorised purpose. The users shall arrange for PTS to be
kept in safe custody and shall ensure its secrecy is maintained and provide satisfactory information to
PETRONAS that this requirement is met.
PTS 13.01.01
POWER QUALITY June 2016
Page 3 of 22
ANNOUNCEMENT
Please be informed that the entire PTS inventory is currently undergoing transformation exercise from
2013 - 2015 which includes revision to numbering system, format and content. As part of this change,
the PTS numbering system has been revised to 6-digit numbers and drawings, forms and requisition
to 7-digit numbers. All newly revised PTS will adopt this new numbering system, and where required
make reference to other PTS in its revised numbering to ensure consistency. Users are requested to
refer to PTS 00.01.01 (Index to PTS) for mapping between old and revised PTS numbers for clarity. For
further inquiries, contact PTS administrator at ptshelpdesk@petronas.com.my
PTS 13.01.01
POWER QUALITY June 2016
Page 4 of 22
Table of Contents
1.0 INTRODUCTION ..................................................................................................... 5
1.1 SCOPE .............................................................................................................................. 5
1.2 GLOSSARY OF TERM ........................................................................................................ 5
1.3 SUMMARY OF CHANGES ................................................................................................. 7
2.0 GENERAL REQUIREMENTS ..................................................................................... 8
3.0 VOLTAGE DEVIATIONS ......................................................................................... 10
3.1 VOLTAGE DEVIATIONS DURING NORMAL OPERATIONS............................................... 10
3.2 VOLTAGE DIP DURING MOTOR STARTING .................................................................... 10
3.3 VOLTAGE DIP CAUSED BY NETWORK FAULTS ............................................................... 10
3.4 AUTOMATIC TRANSFER SYSTEM ................................................................................... 10
3.5 SYSTEM STABILITY STUDIES .......................................................................................... 11
3.6 MOTOR RE-ACCELETATION ........................................................................................... 11
3.7 SPECIFIC REQUIREMENTS FOR PLANT EQUIPMENT...................................................... 12
3.8 VOLTAGE DIP MITIGATION FOR MOTORS..................................................................... 12
3.9 VOLTAGE DIP MITIGATION FOR VARIABLE SPEED DRIVES (VSD OR VFD)..................... 13
3.10 VOLTAGE SURGE OR SPIKE............................................................................................. 13
4.0 POWER FACTOR .................................................................................................. 14
4.1 POWER FACTOR CORRECTION ...................................................................................... 14
5.0 HARMONICS ........................................................................................................ 15
5.1 HARMONICS LEVELS ...................................................................................................... 15
5.2 MITIGATION OF HARMONICS ....................................................................................... 15
6.0 POWER QUALITY MEASUREMENT ........................................................................ 16
6.1 GENERAL ....................................................................................................................... 16
7.0 FREQUENCY DEVIATIONS ..................................................................................... 17
7.1 LOAD SHEDDING ........................................................................................................... 17
8.0 BIBLIOGRAPHY .................................................................................................... 18
APPENDIX 1: IEC 61000-4-34 (CLASS 3) CURVE................................................................. 20
APPENDIX 2: COIL HOLD-IN DEVICE ................................................................................. 21
APPENDIX 3: DIP-PROOF INVERTER ................................................................................. 22
PTS 13.01.01
POWER QUALITY June 2016
Page 5 of 22
1.0 INTRODUCTION
This PTS gives recommended practices and requirements to attain and maintain power quality
in PETRONAS facilities. It provides an overview of what are required to be done to mitigate
typical power quality problems found in the plant or any facilities in PETRONAS. This PTS is
developed based on lessons learnt, best practices and experiences.
1.1 SCOPE
1.1.1 This PTS gives minimum technical requirements for power quality in electrical installations
both onshore and offshore.
Refer to PTS Requirements, General Definition of Terms, Abbreviations & Reading Guide PTS
00.01.03 for General Definition of Terms & Abbreviations.
No Term Definition
v) Electro-magnetic interference
No Term Definition
No Abbreviation Description
No Abbreviation Description
10 PQ Power Quality
The electrical system shall be design to achieve acceptable power quality suitable for
addressed the following operations:-
ii. Multi-stage batch operations where an interruption during one process can
destroy the value of previous operations or result in off-spec products.
The design shall cater for the effects of poor quality as summarized in the following table:-
Voltage dip Faults in the system, switching of Opening of motor contactors and
large loads e.g. motor starting. control relays, VSD trip, ATS transfer
(undervoltage relays activated),
motor stalling, generator trip
(undervoltage relays), loss of
synchronism.
Under- System overload due to loss of Load shedding, power swing to the
frequency generation capacity (trip) grid, power blackout
System
Over- Loss of large loads, system faults Generator trip, power swing from
frequency the grid
Poor power Large inductive load, lack or loss Low power factor penalty, de-rating
factor of power factor control. of equipment
3.1.1 During normal operation of a plant, the steady state voltage at the main intake bus, generator
terminals and consumer terminals should not deviate by more than +/- 5% from nominal or
rated value. Notwithstanding the above, the limits set by the Public Utility on voltage
deviations caused by consumers at the PCC shall be adhered to.
3.1.2 Where the plant is connected to the utility grid, the interconnection transformer shall have
an on-load tap changer which is normally on automatic control. Where the plant has an ENMC
or PMS to control the interchange of reactive power with the grid, the OLTC control shall be
integrated with the power interchange control and local voltage control.
3.2.1 Any voltage deviation of more than 10% below nominal voltage for duration of 10 ms to 60
seconds is considered a voltage dip. During motor starting, the voltage dip should not be more
than -15% at the switchboard to which the motor is connected or more than +10% / -20% at
motor terminals. Duration of such voltage dips may range from one second to several
seconds. A motor starting study shall be performed during the Engineering stage of a project
to confirm that these deviation limits are not exceeded. Where the study show that the
deviation limits will be exceeded, measures (to be approved by the Owner) shall be taken to
overcome the excessive voltage drop. The dynamic characteristics of the motor and the driven
equipment shall be modeled in the study. Starters to reduce starting current should only be
used if direct-on-line (DOL) start of motors will cause voltage dips exceeding the limits set
above.
3.3.1 The severity of a voltage dip depends on the magnitude of the dip as well as the duration.
Voltage dips caused by network fault typically last less than one second depending on the time
taken by protection to clear the fault. The magnitude of the dip can be as much as 100% i.e.
0V at the point of fault, neglecting any fault impedance. The voltage dip experienced by other
parts of the network differs according to network topology. The severity of the dip can cause
plant interruptions e.g. motors to drop out or ATS to operate
3.4.1 Auto transfer systems (ATS) are usually implemented using under-voltage schemes. ATS
under-voltage settings shall be coordinated with voltage dip statistics to minimize
unnecessary ATS operation. ATS systems are inherently break-before-make systems which can
cause momentary voltage loss to downstream equipment. As a minimum, the following is
required for ATS systems:-
i. ATS schemes at different voltage levels shall be coordinated such that those for
higher voltages switchboards (upstream) shall operate first thus preventing the
lower voltages switchboards (downstream) ATS from operating.
PTS 13.01.01
POWER QUALITY June 2016
Page 11 of 22
ii. ATS undervoltage settings shall be such that nuisance operation is minimised for
voltage dips.
iii. The trip of an incomer (circuit breaker open) due to relay or manual operation
shall immediate initiate the ATS operation without waiting for the undervoltage
relay to operate.
iv. When either incomers or feeders experience under-voltage at the same time, the
ATS operation shall be blocked.
vi. ATS shall be modeled in system studies including motor re-acceleration to ensure
robustness of the overall system.
vii. ATS selector switch shall have auto and manual function as minimum.
3.5.1 Transient stability studies shall be carried out for plants or projects which have synchronous
machines. Attention shall be paid to the critical clearance time of faults to prevent generator
pole slipping or to ensure motor re-acceleration is successful. Reference is made to PTS
13.00.02 Section 6.2.3. The CCT shall be determined for both internal plant faults and external
grid faults.
3.5.2 In addition to fast fault clearance as determined by CCT, pole slipping protection (out-of-step
relay) may be considered for generators and interconnection with the grid. The out-of-step
relays shall be coordinated with generator loss-of-field (LOF) relays since the LOF relays may
also operate during pole slipping conditions.
3.6.1 A motor re-acceleration scheme shall be implemented to restart motors after a voltage dip.
This will require motor re-acceleration studies to be carried out. Fault clearance times shall be
determined to allow successful re-acceleration.
3.6.2 Process requirements or constraints during motor restart shall be taken into consideration.
Voltage at switchboards busbars shall be maintained at minimum 90% during motor re-
acceleration. Motors shall be equipped with restarting facility as required by the Owner. For
system studies modeling, the actual contactor drop-out voltages shall be used which must be
supported by factory tests. In the absence of such tests, a value of 65% nominal voltage may
be assumed for contactor drop-out.
3.6.4 Motors controlled by circuit breakers or motors controlled by external supplies from UPS shall
be equipped with under-voltage relays and restart relays to trip the motors. This is to prevent
motors from stalling which can restrain voltage recovery or subject the motor to overcurrent
during under-voltage condition. Under-voltage relays shall be inherently self resetting to allow
automatic restart.
3.6.5 For sequential restart, motors shall be restarted in batches based on criticality or process
requirements. Attention shall be given to start permissive signals originating from process
instrumented systems.
3.7.1 Plant equipment shall have voltage dip immunity characteristics in accordance with IEC 61000-
4-11, 61000-4-34 and 61000-2-4.
3.7.2 Manufacturer shall provide motor contactor voltage drop-out value which shall be verified by
testing.
3.7.3 For plants equipped with generators, dynamic response tests shall be carried out to fine-tune
the governor and excitation systems for proper dynamic behavior (refer PTS 13.00.02 Sections
7.3 and 7.4 and PTS 13.02.01 Section 4.3.1.3.4). This should be done during FAT or
commissioning.
3.7.4 Emergency diesel generators are designed to start up automatically and supply power to plant
vital loads in the event of voltage loss / dips. This function shall be tested on a regular basis as
part of plant routine testing of equipment (auto start test). It shall also be part of the testing
regiment to load the machines either by synchronising them to the plant electrical system/grid
or using a load bank. For new installations, the design of the emergency switchboard shall
allow auto-start functional test (break-before-make) to be carried out without causing any
voltage dip to the essential loads.
3.8.1 Since motor contactors will inherently drop out if the voltage dip is severe enough, a
successful motor re-acceleration scheme is vital to avoid or minimize interruption to plant
operation. In general, plant equipment shall comply with the voltage dip immunity
characteristics as per IEC 61000-4-34 (Appendix 1).
3.8.2 Motors with control circuit power supply from UPS will not drop out during voltage dips.
However, to prevent these motors from stalling, under-voltage protection shall be provided.
PTS 13.01.01
POWER QUALITY June 2016
Page 13 of 22
3.8.3 To eliminate the risk of critical motors not restarting successfully, the following methods
should be implemented to improve the immunity of these motors during voltage dips. The
behavior of such voltage dip mitigation devices need to be modeled and included in the
transient stability and motor re-acceleration studies.
a) The hold-in device is connected between the power source and the
contactor coil (Appendix 2. During voltage dips, sufficient current flow
is maintained through the contactor coil to hold the main contacts in
place. The circuit shall be designed to provide hold-in current for dips
down to about 25% remaining voltage.
3.9 VOLTAGE DIP MITIGATION FOR VARIABLE SPEED DRIVES (VSD OR VFD)
3.9.1 VSD shall be able to ride-through voltage dips in accordance with IEC 61000-4-34 (APPENDIX
1).
3.10.1 If specified, an overvoltage study shall be carried out to determine the requirement for surge
arrestors. Surge arrestors shall be install as close as possible to the equipment to be protected.
3.10.2 Calculation of separation distances shall be in accordance with IEEE Standard C62.22-19
whereas calculation of arrestor protective zones shall comply with IEC 60071-2.
PTS 13.01.01
POWER QUALITY June 2016
Page 14 of 22
4.1.2 Where capacitors are used, measurements and / or studies shall be carried out to verify that
they do not cause any resonance or overvoltage effects in the system. If necessary, the
capacitors shall be de-tuned accordingly by adding a reactor in series.
PTS 13.01.01
POWER QUALITY June 2016
Page 15 of 22
5.0 HARMONICS
5.1.2 Reference is to be made to IEEE 519 for allowable harmonic current levels. Harmonics
generated in static UPS, VSD and power electronics devices shall comply with the EMC
requirements as specified in:
5.2.2 To mitigate excessive harmonics, harmonic filters shall be installed. The type of filter to be
installed should be decided based on effectiveness, reliability and economic considerations.
There are generally two types of filters; passive and active filters. Where passive filters
consisting of LC elements are installed, they should be of the acceptor circuit type (L and C in
series). The filters shall be connected in parallel with the supply.
5.2.3 Active harmonic filters shall be connected in parallel with the supply. In general, they shall be
connected as close as possible to the harmonic source.
PTS 13.01.01
POWER QUALITY June 2016
Page 16 of 22
6.1 GENERAL
6.1.1 Permanently installed PQ analyser with disturbance recording function should be installed at
each Point of Common Coupling with the grid. As a minimum, plant switchboards shall have
facilities for plug-in measurement of 3-phase voltage and current by a portable PQ analyzer.
6.1.2 Portable PQ measuring instruments are recommended for quick snapshots of power quality
at the point of measurement. Plant personnel should be trained to use them and to analyze
the results.
PTS 13.01.01
POWER QUALITY June 2016
Page 17 of 22
7.1.1 During normal operation, frequency shall be maintained at 50 Hz or 60 Hz +/- 2% as per PTS
13.00.01 Section 3.
7.1.2 For plants which are connected to the grid, the system frequency will be determined by the
grid. Plants with their own generation and can run on island mode shall have a load shedding
scheme (PTS 13.30.01 Section 4). Dynamic studies for load shedding schemes shall be carried
out accordingly.
7.1.3 During island operation, plants that run N+ 1 generator normally allow for the trip of the
largest generator without causing any impact to the plant. In such a trip scenario, the dynamic
response of the remaining N generators shall be such that the system frequency will not drop
to a value that initiates load shedding. The prime mover dynamic characteristics shall be fine-
tuned by testing in accordance with PTS 13.00.02 Section 7 and PTS 13.02.01 Section 4.
PTS 13.01.01
POWER QUALITY June 2016
Page 18 of 22
8.0 BIBLIOGRAPHY
INTERNATIONAL STANDARDS
Recommended Practice and Requirements for Harmonic Control IEEE 519
in Electrical Power Systems
Electromagnetic Compatibility (EMC) IEC 61000
Environment - Compatibility levels in industrial plants for low- IEC 61000-2-4:
frequency conducted disturbances 2002