Professional Documents
Culture Documents
Building
Building
Building Sub-Station
+116.5m to +117.5m
EAST
WEST
Infrastructure +115.5m
+113.5m
Building Building
Building
INTRODUCTION
114.5
113.5~114.5
ROOF SLAB
B1 SLAB
B2 SLAB
B3 SLAB
INTRODUCTION
117.5
115.5
114.5
ROOF SLAB
B1 SLAB
B2 SLAB
B3 SLAB
1. INTRODUCTION OF THE INFRASTRUCTURE
SITE
KAKI BUKIT STATION:
GEOLOGICAL PROFILE GEOLOGICAL PROFILE
Infrastructure
Infrastructure
OA (D)
OA (C)
OA (B)
+91.65m
1. INTRODUCTION OF THE INFRASTRUCTURE
2. GEOLOGICAL BACKGROUND AND GROUND CONDITIONS
FILL
OA (E)
DERIVATION OF DESIGN PARAMETERS
OA (D)
OA (C)
DERIVATION OF DESIGN PARAMETERS
OA (B)
OA (A)
DERIVATION OF DESIGN PARAMETERS
KAKI BUKIT STATION
PLAN VIEW OF RETAINING WALLS
DERIVATION OF DESIGN PARAMETERS
KAKI BUKIT STATION
PLAN VIEW
Proposed OF RETAINING
Geotechnical WALLS
Parameters for Design using OM
1. INTRODUCTION OF THE INFRASTRUCTURE
2. GEOLOGICAL BACKGROUND AND GROUND CONDITIONS
3. DERIVATION OF CHARACTERISTIC AND MOST PROBABLE PARAMETERS
B1 LEVEL
B2 LEVEL
DESIGN INFORMATION
8 11 Strut Layout (GL8 & GL11)
Strut S1 (above roof) 8 11 Strut S3 (B1 Slab)
GL8
GL11
Strut S5 (between B2 and Base)
8 11
DESIGN INFORMATION: Section Views
PROPOSED OMISSION OF STRUT
1. Studies on omission of proposed struts based on OM have been carried out.
3. Removing struts at slab opening are considered not significant in time and cost
saving.
4. Omission of S5 struts between B2 and B3 slab has been considered in the present
study using OM.
Studies on omission of
S5 struts using OM
S5
GEOLOGICAL PROFILE AT SECTION OF ANALYSIS
FILL
O(D) O(D)
O(C)
O(B) O(B)
O(A) O(A)
ANALYSES USING CHARACTERISTIC AND MOST PROBABLE
PARAMETERS
Analysis Models
S1
FILL
FILL
OA(D)
Analysis model OA(C)
with S5 struts S5
(Characteristic Formation
OA(A)
OA(A)
S1
FILL
FILL
OA(A)
OA(A)
ANALYSES RESULTS
ERSS Wall Deflection: SLS
Characteristic Parameters
Most Probable Parameters
ANALYSES RESULTS: Characteristic Parameters
Characteristic Parameters: Bending Moment & Shear (SLS)
ANALYSES RESULTS: Most Probable Parameters
Most Probable Parameters: Bending Moment & Shear (SLS)
ANALYSES RESULTS: Characteristic Parameters
Characteristic Parameters: DA1C1
ANALYSES RESULTS: Most Probable Parameters
Most Probable Parameters: Bending Moment & Shear (DA1C1)
(DA1C1)
ANALYSES RESULTS: Characteristic Parameters
Stage 1 S1 (10mm)
Stage 4 B2
(21mm) Stage S5
(20mm)
Stage S5
(35mm)
Stage 6 FEL
(40mm)
Stage 6 FEL
(51mm)
(Not Applicable)
DESIGN APPROACH USING OM
Reinforcement Provision
SLS (based on crack width)
DESIGN APPROACH USING OM: Reinforcement Design
Most Probable Parameters: Bending Moment & Shear (SLS)
Reinforcement Provision
SLS (based on crack width)
DESIGN APPROACH USING OM: Reinforcement Design
Characteristic Parameters: Bending Moment & Shear (DA1C1)
Reinforcement
Provision (ULS)
DESIGN APPROACH USING OM: Reinforcement Design
Most Probable Parameters: Bending Moment & Shear (DA1C2)
Reinforcement
Provision (ULS)
1. INTRODUCTION OF THE INFRASTRUCTURE
2. GEOLOGICAL BACKGROUND AND GROUND CONDITIONS
3. DERIVATION OF CHARACTERISTIC AND MOST PROBABLE PARAMETERS
4. ANALYSES AND DESIGN
5. DESIGN APPROACH USING OBSERVATIONAL METHOD (OM)
5
APPLICATION OF OM
GL 1 to 10 GL 10 to 12 GL 12 to 15
S5 can be omitted S5 to be remained S5 can be omitted
1. INTRODUCTION OF THE INFRASTRUCTURE
2. GEOLOGICAL BACKGROUND AND GROUND CONDITIONS
3. DERIVATION OF CHARACTERISTIC AND MOST PROBABLE PARAMETERS
4. ANALYSES AND DESIGN
5. DESIGN APPROACH USING OBSERVATIONAL METHOD (OM)
6. APPLICATION OF OM BASED ON MEASURED DEFLECTIONS
7. BACK ANALYSES
8. CONCLUSIONS
BACK ANALYSES
Back analyses of excavation were carried out using c’=35kPa; φ’=34o for OA(A) & OA(B)
based on Orihara & Khoo, 1998
115
GL11 GL8
110 GL11 GL8
GL11
GL11
GL8 E = 2N MPa 105 E = 2N MPa
100
95 GL8
Max: 28mm Max: 50mm
90
85
80
75
1. S5 struts at grid lines GL1-10 & GL12-14 at station box can be omitted
based on the measured wall deflection at Excavation Stage 5
(excavation to 1m below S5 strut)
2. At GL10-12, S5 struts in the original design must be provided
3. Larger increment in ERSS wall deflection at GL10-12 during
excavation to B1 slab were measured
4. These could be due to steel struts provided at B1 slab were not as
rigid as those areas directly support with slab
5. With omission of the S5 struts from GL1-10 & GL12-14, the cost
saving could amount to half of the total strutting cost for this project.
The time saving for omission of these struts is estimated to be about 2
months.