Professional Documents
Culture Documents
ON
“GRID FAILURE AND POWER RESTORATION AFTER
BLACKOUT”
B.TECH- IV (ELECTRICAL)
SUBMITTED BY:
ABHIJEET
(Roll No.: U11EE051)
GUIDED BY:
Dr. SABHA RAJ ARYA
EED, SVNIT
CERTIFICATE
This is to certify that candidate Mr. ABHIJEET bearing Roll No: U11EE051 of B.TECH IV,
7TH Semester has successfully and satisfactorily presented seminar & submitted the Report on
the topic entitled “GRID FAILURE AND POWER RESTORATION AFTER BLACKOUT”
for the partial fulfillment of the degree of Bachelor of Technology (B.Tech) in Nov. 2014.
Head,
EED, SVNIT.
Abstract i
Glossary ii
1 Introduction 1
2 Power grid 4
4 Lessons to be learnt 19
Conclusion 21
References 22
ABSTRACT
India’s power sector is in shambles. We recently suffered what was described as the worlds’
largest power outage in the history of mankind affecting around 60 million lives. Three grids
collapsed bringing most of the country to a complete halt. The major structural reason for the
grid failure stems from the fact that most of the states, which are overdrawing power from grid
compared to the scheduled limits have hardly invested in capacity addition in the past few years.
Additionally, the peak power deficit issue in these states was further accentuated by the
diminishing reservoir levels of the storage based hydro power plants due to current dry spell
with most of the northern states receiving low rains this year. Further, these agricultural states
with current sowing season are yet to ration the water usage, which led to sharp reduction in
water head levels in the dams directly impacting the power generation. Over the last decade,
most of these state distribution companies remained in precarious situation with negligible
reduction in AT&C losses (AT&C losses>35-40%), stagnant tariff vis-à-vis rising power
purchase costs, irregular subsidy payments by states, high cross subsidization resulting into
severe cash crunch.
Thus, decade of under investments in T&D resulted in poor management of load forecasting
abilities with 1) lack of accurate control over load management at feeder level to ascertain exact
nature and behavior of demand and 2) lack of investment in T&D equipments i.e. under
frequency relays which would have averted grid collapse by segregating the notorious load
sections from the regional grid. Interestingly, these states are not even left with an option of
buying power from open market as the state grid is overloaded with no spare capacity to wheel
the power. Consequently, despite penalty mechanism introduced by the regulator in the form of
Unscheduled Interchange (UI), it is cheaper for these states to overdraw power from the grid
rather than buying power through other channels.
This report provides an overview of the objectives and priorities of the Power System
Restoration Plan , describes key actions undertaken to restore the grid to normal operation
following the blackout and identifies opportunities for improvement as a result of lessons-
learned.
i
GLOSSARY
ii
LIST OF FIGURES
iii
CHAPTER 1
INTRODUCTION
In the power industry, electrical grid is a term used for an electricity network which includes the
following three distinct operations:
a. Electricity generation - Generating plants are usually located near a source of water, and away
from heavily populated areas. They are usually quite large to take advantage of the economies of
scale. The electric power which is generated is stepped up to a higher voltage-at which it
connects to the transmission network.
b. Electric power transmission - The transmission network will move (wheel) the power long
distances–often across state lines, and sometimes across international boundaries, until it reaches
its wholesale customer (usually the company that owns the local distribution network).
c. Electric power distribution - Upon arrival at the substation, the power will be stepped down in
voltage—from a transmission level voltage to a distribution level voltage. As it exits the
substation, it enters the distribution wiring. Finally, upon arrival at the service location, the
power is stepped down again from the distribution voltage to the required service voltage(s).
The cheapest and simplest topology for a distribution or transmission grid is a radial structure.
This is a tree shape where power from a large supply radiates out into progressively lower
voltage lines until the destination homes and businesses are reached.
Most transmission grids require the reliability that more complex mesh networks provide. If one
were to imagine running redundant lines between limbs/branches of a tree that could be turned in
case any particular limb of the tree were severed, then this image approximates how a mesh
Page | 1
system operates. The expense of mesh topologies restrict their application to transmission and
medium voltage distribution grids. Redundancy allows line failures to occur and power is simply
rerouted while workmen repair the damaged and deactivated line.
A wide area synchronous grid or "interconnection" is a group of distribution areas all operating
with alternating current (AC) frequencies synchronized (so that peaks occur at the same time).
This allows transmission of AC power throughout the area, connecting a large number of
electricity generators and consumers and potentially enabling more efficient electricity markets
and redundant generation. In a synchronous grid all the generators run not only at the same speed
but also at the same phase, each generator maintained by a local governor that regulates the
driving torque by controlling the steam supply to the turbine driving it. Generation and
consumption must be balanced across the entire grid, because energy is consumed almost
instantaneously as it is produced. Energy is stored in the immediate short term by the rotational
kinetic energy of the generators.
A large failure in one part of the grid - unless quickly compensated for - can cause current to re-
route itself to flow from the remaining generators to consumers over transmission lines of
insufficient capacity, causing further failures. One downside to a widely connected grid is thus
the possibility of cascading failure and widespread power outage.
High-voltage direct current lines or variable frequency transformers can be used to connect two
alternating current interconnection networks which are not synchronized with each other. This
provides the benefit of interconnection without the need to synchronize an even wider area.
A black start is the process of restoring a power station to operation without relying on the
external electric power transmission network. Normally, the electric power used within the plant
is provided from the station's own generators. If all of the plant’s main generators are shut down,
station service power is provided by drawing power from the grid through the plant’s
transmission line. However, during a wide-area outage, off-site power supply from the grid will
not be available. In the absence of grid power, a so-called black start needs to be performed to
bootstrap the power grid into operation.
Page | 2
Fig 1.1 Electrical grid network
Page | 3
CHAPTER 2
POWER GRID
Power system is divided into five regional grids namely Northern, Western, Southern, Eastern
and North Eastern grids. Except for Southern grid, remaining four regional grid operate in
synchronism. Southern grid is connected to Eastern and Western grids through asynchronous
links.
Major generating stations including Super Thermal Power Stations of NTPC at Rihand and
Singrauli are located in the eastern part of the NR grid. Due to such concentration of generation
in the eastern part of the grid and major load centers in the central and western part of the grid
there is bulk power transmission from eastern to western part over long distances. To handle this
bulk transmission of power, a point to point high voltage DC line viz. HVDC Rihand-Dadri
bipole with capacity of 1500 MW exists and operates in parallel with 400 kV AC transmission
network besides under lying 220 kV network.
Page | 4
Eastern Regional grid operates in synchronism with Western, Northern and North-Eastern
Regional grids.
The power transfer from North-Eastern Region to Eastern Region is taking place over
Bongaigaon – Malda 400 kV D/C lines and Birpara – Salakati 220 kV D/C lines.
2.2.3
Research believes that grid collapse occurred due to problems such as
a. Continued under investment in generation capacity by states leading to acute power deficit. b.
Stagnant hydro capacity unable to address rising peaking demand and c. Recurring and
excessive power overdraw by states significantly beyond scheduled limits.
Page | 6
2.2.4 DEPLETED TRANSMISSION NETWORK
It is observed that one circuit of 400 kV Bina-Gwalior-Agra section was taken under planned
outage by POWERGRID for up gradation to 765 kV level. A number of 400 kV lines were out
prior to the incidence. The outage of 400 kV Bina-Gwalior–Agra for up-gradation work, non
availability of 400 kV Zerda-Kankroli and 400 kV Bhinmal-Kankroli due to insulator problems
in particular weakened the NR-WR Interface. The availability of corridor requires to be
improved by replacing porcelain insulators by polymer insulators at the earliest.
Page | 8
2.3 POST BLACKOUT
If a blackout (a near total loss of generation and load) takes place, efforts have to be taken to
bring back the system to a normal state at the earliest. Once a generator is tripped, restarting it
requires a significant amount of power. Power is required for 2 types of activities:
a) Survival Power: For emergency lighting, battery chargers etc. Usually the requirement is
0.3% of the generator capacity.
b)Startup Power: For starting power plant auxiliaries (pumps etc.) Interestingly, nuclear and
thermal units require approximately 8 % of the unit capacity for auxiliaries alone! Therefore, a
500 MW generator requires approximately 40 MW for running its auxiliaries. Hydro and Gas
units, on the other hand, require only about 0.5-2% of unit capacity for auxiliaries and can be
started usually from in-house DG sets.
After a blackout a few islands may survive due to separation of the system in time. A few hydro
or gas generators could be black started using in-house D-G sets. Therefore some small pockets
will be there in the otherwise blacked out grid wherein generators are supplying some loads.
However, the situation in these islands is usually precarious due to the small number of
generators within the island (having very little cumulative inertia).
The initial rate of change of frequency is determined by cumulative machine inertia and the
Page | 9
initial load-generation imbalance, while the final settling frequency is determined by the
governor and load frequency characteristics.
Therefore if the load in the island is fluctuating (for instance, traction loads), the rate of change
of frequency within the island due to fluctuating loads may be quite large -- large enough for the
island to collapse due to excessive frequency variations - causing generators to trip. Therefore
control of generated power (by governors) and frequency based tripping or energization of load
is important.
Black-starting of large generators is done by availing startup power from other started
generators or islands. Startup power may also be availed from neighboring synchronous grids if
an AC transmission link exists (normally disabled). Unfortunately, startup power cannot be
availed via DC links (which use AC line voltages for commutating thyristors), because AC
voltages are not available in the system which is blacked out.
Therefore a generator at Vindyachal (near the border of the western region and northern region
grid of India, which are not synchronized but exchange power through DC asynchronous links
during normal conditions) can avail startup power through an AC line from the northern grid.
Page | 10
2.3.2 EXTENDING POWER TO LOADS FROM GENERATORS WHICH ARE BLACK
STARTED
The next step in power system restoration is to supply loads from black-started generators.
Some of these loads may be in the form of the startup (auxiliary) loads of other larger
generating plants which need to be black-started.
These loads are supplied via transmission lines. Energizing a transmission line initially without
any load can cause over-voltages . This is avoided by:
1 Energizing fewer high voltage lines
2Operating generators at minimum voltage levels (by keeping filed
excitation low) 3 Deactivating switchable capacitors
4 Connecting shunt reactors and tertiary reactors
5 Adjusting of transformer taps
6 Pickup loads with lagging power factor
7 Charging more transformers
8 Charging shorter lines
9 Operating synchronous condensers / SVCs where available
10 Avoiding charging lines with series capacitors.
Note that an important step in reconnecting islands to one another is "synchronization". While
each generator has synchronizing facilities, the interconnection of two islands may have to be
done at some bus in the network wherein such facilities are available. The basic requirements for
successful synchronization of two systems are the same as those for an individual generator
connected to a large grid . In particular, the frequencies should be practically the same and phase
angular difference at the instant of connection should be small. If two systems are connected at
an inappropriate instant, then the generators in both islands will not synchronize, and the
situation will be akin to an out-of-step scenario; the link will have to be disconnected.
Page | 12
Fig 2.5 Synchronized islands
Page | 13
CHAPTER 3
GRID COLLAPSE 2012 AND 2014
On 31st July, 2012, after NR got separated from the WR due to tripping of 400 kV Bina-Gwalior
line, the NR loads were met through WR-ER-NR route, which caused power swing in the
system. On this day the center of swing was in the ER, near ER-WR interface, and, hence, after
tripping of lines in the ER itself, a small part of ER (Ranchi and Rourkela), along with WR, got
isolated from the rest of the NEW grid. This caused power swing in the NR-ER interface and
resulted in further separation of the NR from the ER+NER system. Subsequently, all the three
grids collapsed due to multiple tripping attributed to the internal power swings, under frequency
and overvoltage at different places.
The WR system, however, survived due to tripping of few generators in this region on high
frequency on both the days.
The Southern Region (SR), which was getting power from ER and WR, also survived on 31st
July, 2012 with part loads remained fed from the WR and the operation of few defense
mechanism, such as AUFLS and HVDC power ramping.
On both the days, no evidence of any cyber attack has been found.
Page | 14
Fig 3.1 Power system in India
Page | 15
Measures that could have saved the system from collapse
a. In an emergency system operating condition, such as on 30th and 31st July 2012, even some of
the corrective measures out of the list given below might have saved the system from the
collapse.
b. Better coordinated planning of outages of state and regional networks, specifically under
depleted condition of the inter-regional power transfer corridors.
d. Under-frequency and df/dt based load shedding relief in the utilities’ networks.
e. Dynamic security assessment and faster state estimation of the system at load dispatch centers
for better visualization and planning of the corrective actions.
g. Better regulation to limit over drawl under UI mechanism, specifically under insecure
operation of the system.
i. Deployment of adequate synchrophasor based Wide Area Monitoring System and System
Protection Scheme.
Page | 16
3.2 BANGLADESH GRID COLLAPSE 2014
A huge power cut in Bangladesh left tens of millions of people nationwide without electricity for
hours on November 1, 2014. It began around 11 a.m. Saturday, causing widespread disruption
across the nation of more than 160 million people. But the country hadn't experienced a
nationwide blackout since the aftermath of a powerful cyclone in 2007.
There are flaws in the setup of the Bheramara power sub-station, as a result when it tripped, the
entire national electricity grid collapsed.
Bangladesh began importing power from India in October last year through a 400-kilovolt
transmission line that runs from Baharampur in West Bengal to the southwestern Bangladesh
town of Bheramara.
The sub-station can receive more than 400MW power at a time. But on 1st of Nov, 444MW was
supplied [from India] in the morning, triggering a technical glitch. As a result, some power
stations in the Ashuganj area tripped as frequency came down to 45hz from the normal level of
48.9hz-51hz.
Ideally, generation should always be exactly the same as demand at any given point in time.
Frequency slowdown is generally caused by shortfall in generation compared to demand. When
frequency falls below the normal level, power stations trip, professionals say.
When the technical glitch occurred at Bheramara, the supply from that source stopped, causing a
generation shortfall. Instantly, because of the slowed down frequency, some other stations started
tripping, bringing frequency further down and eventually leading to the countrywide blackout.
Professionals have also said even if there is a 10% gap between generation and demand, the
national grid may collapse. As a result, when the Bheramara sub-station tripped, it took out
444MW power from the grid which was roughly 10% of the demand of 4,500MW at that point.
Page | 17
Fig 3.2 Bangladesh grid failure on 1st November 2014
Page | 18
CHAPTER 4
LESSONS TO BE LEARNT
Based on the discussions brought out in the foregoing paragraphs, the suggestions for faster
restoration of thermal power stations are as under
A well coordinated and documented process for supply of start-up power may be put in place
under the overall coordination of NLDC clearly bringing out the following:
a. Existing Black start procedures should be frequently reviewed in line with the fast changing
grid scenario and addition of generation capacity. The facilities available with existing and
upcoming IPPs should also form part of these procedures for the purpose of extending start up
supply to black starting units in the vicinity.
b. Explicit instructions to all stake holders to supply start-up power without any commercial
considerations that could be settled later.
c. Micro level load management for lines and loads may be envisaged for extending start-up
power through pre-defined arrangement for availability of loads under emergency conditions so
as to avoid frequent tripping while extending start-up supply.
d. Authorizing Load dispatch centres to advise action to the concerned utilities for extending
power supply immediately to the black-starting units through exchange of special emergency
code between the concerned load dispatch centres.
e. A normative or bench mark time frame for extending start-up power to each of the TPS.
This may be evolved by the RPC in consultation with the constituents and RLDC so as to
ensure that significant delays are not faced in extending start-up power.
Page | 19
Key installations/sub-stations should be managed by experienced manpower particularly
during odd hours – like Qualified operating personnel having undergone orientation courses
under certification programme.
Large variations are observed in time taken for initiation of unit start up (Boiler light up) by the
stations after availability of start-up power and also for start ups/light up of subsequent units.
Also, while subsequent start-ups were very fast (10-20 minutes) in some of the units, in other
cases they took considerably longer – several hours.
Reasons for the delays in attempting first start-up and subsequent start-ups may be examined by
the utilities in consultation with CEA. A standard procedure for preparatory activities and
sequence of start up may be put in place by the stations to restore units as early as possible.
Large variations have also been observed in time taken by the stations for synchronization after
Boiler light up which are normally not expected. Detailed analysis of times taken especially
from BLU to synchronization may be made by the utilities in consultation with CEA so as to
identify constraints/bottlenecks faced during unit start-up for remedial action.
The large variations in synchronization times and successive synchronization times achieved
with many of the stations achieving timelines far better to others is indicative of the potential
improvements possible in most of the stations with better/faster preparation. Further, in most
cases the start-up times appear to be considerably higher than the manufacturers/OEM
recommendations. Optimal start-up/ restoration procedures by the stations in consultation with
OEMs.
Long start-up times taken by most Gas turbine units need to be investigated to develop Gas
turbine units as reliable source of fast restoration power.
Page | 20
CONCLUSION
st
Power sector in India presents a grim scenario which has the needs of 21 century and
th
infrastructure of 19 century. It is high time we give some serious thought to this ever increasing
deficit between demand and supply. The power sector has been facing various issues which has
deteriorated its health over the past two years. The precarious situation of power sector can only
be addressed through key structural reforms such as 1) Coal pooling mechanism to improve
power generation from coal based plants 2) investment in hydel capacity (especially storage
based or pumped storage power plants) to effectively manage peaking load 3)Allow open access
to reduce regional deficits and 4) incentivize states to invest in T&D to curb AT&C losses and
make the power distribution business model self sustainable.”
Instructions must be issued to strictly adhere and maintain grid discipline, detailing 1) the
constituent states should not resort to any over drawl when the grid frequency is below 49.5 Hz
and comply with provisions of Grid code 2) the states should ensure that Under Frequency
Relays (UFR) are kept in service all the times and feeders used for load shedding are different
from feeders used for manual load shedding so that grid security is not compromised and 3) all
users/ SLDC/SEBs/distribution licensee should comply with direction of RLDC/SLDC and carry
out requisite load shedding or back down generation capacity in case of transmission line
congestion to ensure safety and reliability of system.
It is also imperative for the states to go beyond politics and stop announcing free power which
seriously affects the health of Power companies. We will not be needing many new thermal
power stations if we change our infrastructure and invest more in automatic relays apart from
being strict on power theft offenders.
Unless we introspect and learn from the recent disaster, there can never be a guarantee that
BLACKOUT will not occur in near future and we might face the same situation very soon.
Page | 21
REFERENCES
[1] Phabha Kundur, “Power System Stability and Control”, Electrical Power Research Institute,
1993.
[2] Robert H. Miller and James H. Malinowski, “Power System Operation”, Third edition,
McGraw-Hill, Inc. 1993
[3] PTI, “PSS/E 26 Program Application Guide: Volume I”, Power Technologies, Inc., 1998
[4] Jan Maehowski, Janusz W. Bialek and James R. Bumby, ‘Power System Dynamics and
Stability”, John Wiley & Sons, 1997
[5] S. Lee, “For the good of the whole”, IEEE Power Energy Mag., vol. 5, no. 5, pp.24 -35
2007
[6] T. Daido, Y. Miura, T. Ise and Y. Sato, “A Study on Start-up Method during Blackout of
Wound-rotor Induction Generator Applied to Gas Engine Cogeneration System”, JIASC 2010,
Vol. 1, pp. 481-484 (2010) (in Japanese).
[7] Final Report on August 14, 2003 Blackout in the United States and Canada, U.S.-Canada
Power System Outage Task Force, April 2004. [Online]. Available: www.nrcan-rncan.gc.ca/
media/docs/final/finalrep-e.htm.
[8] Final Report of the Investigation Committee on September 28, 2003 Blackout in Italy,
UCTE, 2004, p. 128. [Online]. Available: http://www.ucte.org/ pdf/News/ 20040427-UCTE-IC-
Final-report.pdf.
Page | 22