Professional Documents
Culture Documents
Submitted in partial fulfilment of the requirement for the award of the degree
of
DIPLOMA
in
Electrical Engineering
Lastly, I would like to thank my parents and fellow trainees who have been a
constant source of inspiration & encouragement and provided support
whenever I needed the most.
1. Introduction
1.1 Introduction to Delhi Transco Limited
1.2 DTL Network
1.3 Grid Diagram of Delhi
4. Protection Systems
4.1 Over Voltage Protection
4.2 Over Current Protection
4.3 Earth Fault Protection
4.4 Primary and Backup Protection
4.5 Relays
4.6 Fuses
4.7 Earthing System
4.8 Control Room
4.9 Battery Banks
Delhi Transco Ltd (DTL) came into existence on 1st July 2002. It was carved out
of Delhi Vidyut Board as a separate entity after restructuring of Power Sector of
Delhi and was accorded the status of State Transmission Utility (STU) of Delhi
state for all purposes. DTL is to discharge the functions of STU in accordance
with the Clause 39(2) of Indian Electricity Act 2003 for transmitting power by
establishing and operating efficient and reliable transmission network in the
Capital of India.
DTL has adopted latest technologies in the field of Transmission such Gas
Insulated Sub-stations (GIS) and laying underground 220 kV and 400 kV cables.
DTL has 4 Nos. 400 kV substations and 39 Nos. 220 kV sub-stations out of these
substations 1 No. 400 kV and 14 Nos.220 kV sub-stations have been built using
the GIS technology.
DTL has implemented Islanding Scheme for the state of Delhi which isolates the
Delhi system from Indian Grid in case of exigencies to save the Delhi system and
to ensure uninterrupted power supply to the essential load of Delhi even in case
of a failure of the Main Grid.
Being the capital of India and the hub of commercial activities in the northern
region, coupled with the prosperity of population, the load requirement of Delhi
has been growing at a much faster pace.
To ensure adequate and efficient power supply, DTL has been continuously
upgrading its technology such as implementation of XLPE 220 kV cable and
constructing GIS substation.
1.2 DTL NETWORK
1.3 Grid Diagram of Delhi
Substation
In the primary side, a large number of breakers and isolators are used to allow
the system for maintenance and repair with a minimum interruption.
Conventional instrument transformers (CTs and PTs) are employed for
metering and protection. At the primary side instead of PTs CVTs are
employed, Capacitive voltage transformers
2.1 Introduction
• Bamnauli circuit 1
• Bamnauli circuit 2
• Dwarka circuit 1
• Dwarka circuit 2
Dwarka circuit 1 and Dwarka circuit 2 is employed for receiving power and
Bamnauli circuits were kept as a backup incoming power source.
Two power transformers are currently being used and the third power
transformer is to be installed in near future to meet the increasing power
demand of the region.
1. Paschim Vihar
2. Goyala Khurd
3. G-2 Dwarka
4. Sagarpur
5. DMI CDC Ckt 1
6. DMI CDC Ckt 2
7. DMI CDC Ckt 3
8. DMI CDC Ckt 4
9. BSES G-6
10. BSES G-7
11. DMRC
2.2 SINGLE LINE DIAGRAM
This picture attached below shows the single line representation of Dwarka
PPK-III substation...
➢ The incoming transmission lines are connected to the double bus bar
system through several equipment. All these lines can be loaded
simultaneously to share the load of the grid substation. In case there is a
breakdown of any one incoming line, the continuity of supply is
maintained, and power supply is not affected as continuity of supply is
maintained.
➢ As seen in the single line diagram each incoming line is connected to the
bus bar in a sequence with several equipment. The equipment between
the incoming line bus bar is connected in a defined sequence as
following:
➢ The substation has a double bus bar system, the incoming lines can be
connected to either of the two bus bars with the help of arrangement of
circuit breakers and isolators called bus coupler. The main advantage of
the bus coupler is that if any maintenance work has to be done on any
one bus bar the whole power supply is not affected and continuity of
supply is maintained.
➢ Each line bus bar at primary side is connected with a CVT (capacitive
voltage transformer) and each bus bar at secondary side relates to a PT
(potential transformer) for metering and protection purposes.
➢ The incoming 220 kV from the feeders passing through several equipment
is received by the transformer arrangement. Each transformer rated 160
MVA steps down the voltage level to 66 kV keeping the frequency and
power constant.
➢ The second bus bar arrangement is also a two-bus bar system each
connected with a potential transformer (PT). There is again a bus coupler
between the two buses to couple them. Here a capacitor bank is provided
to increase the incoming voltage if there is any voltage drop in the
incoming. It can enhance the incoming voltage by 3 to 4 kV.
4.PARTS OF A SUBSTATION
This is the place where the substation receives the incoming power supply at
220 kV through the transmission lines. There are total incoming four incoming
feeders namely Bamnauli 1, Bamnauli 2, Dwarka ckt 1 and Dwarka ckt 2 out of
which two feeders are currently operational, these two feeders are Dwarka ckt
1 and Dwarka ckt 2.
❑ The Incoming 220 kV feeders are first connected to an oxide film Lightning
arrestor which serves the function of protection against lightning or any
abnormal high voltage conditions.
❑ Gas type circuit breaker is connected next to open or close the circuit in
normal and abnormal condition. It is a protection device and prevents
damage to equipment at any abnormal condition.
❑ From the circuit breaker the incoming feeder is fed to the 220 kV double
bus bar system through isolator arrangements so that the connection can
be changed from one bus to another one.
❑ A bus coupler is provided to interconnect both buses for load sharing and
it also makes the system more reliable.
❑ Now from the bus bars the power supply is fed to the transformers rated
160 MVA, 220/66 kV. These transformers step down the incoming 220 kV
to 66 kV. The 66 kV output is fed to the 66 kV double bus bar system.
❑ Gas type Circuit Breakers are connected to the transformer circuit to open
or close the circuit at any normal or abnormal condition. 
❑ Horn gap lightning arrestor is provided just before and after the
transformer circuits to protect it from any damage at abnormal condition.
66 kV Outdoor Yard
❑ After the voltage transformation the output 66 kV is fed to the secondary
side bus bars. This is again a double bus bar system. The two buses are
coupled with the bus coupler.
❑ From the 66 kV bus bars eleven outgoing feeders are drawn and fed to
the consumers as mentioned above.
❑ All the circuits are connected through different switching, measuring and
protection equipment such as isolators, circuit breakers, lightning
arrestors, etc.
❑ The SF6 circuit breaker is aligned in the circuit for tripping whenever any
fault occurs in the circuit.
These are the conductors which transmits the extra high AC voltage (400 kV, 220
kV, 132 kV and 66 kV) from one substation to the other substation
There are various types of conductors used, the type depending upon the
requirement and other factors.
• For 400 kV lines Taran, Tulla and Marcullla conductor
• For 220 kV lines Moose conductor is used
• For 66 kV lines panther conductor is used
The material used for these conductors is A.C.S.R (Aluminium conductor Steel
Reinforced)
3.2 Insulators
Insulators are connected to the cross arm for supporting the conductor at the
desired distance from the ground. The insulator provides necessary insulation
between line conductors and the support structure. Thus, insulators prevent any
leakage current from line conductors to the earth.
220 kV polymer Insulator
Porcelain Insulator
Pin type insulator consists of single or multiple shells that mounted on the
spindle to be fixed to the cross arm of the tower. Multiple shells are provided
to obtain a sufficient length of leakage path so that flash overvoltage between
conductor and pin type insulator is increased.
Pin type insulator is used for transmission and distribution of electric power at
voltage up to 33kv beyond 33kv operating voltage, pin type insulator become
too bulky and uneconomical.
Because of the limitations of pin type insulators for higher voltage, suspension
type Insulators are used. Suspension type insulator consists of one or more
insulator units connected together to form a string and hanged to the cross
arm of the supporting structure or tower and carry a power conductor at its
lowest extremity. This type of composite unit also called a string type insulator.
The conductor is suspended at the bottom end of the string while the other
end of the string is attached to the cross arm of the supporting structure.
In suspension types of insulators, each disc of porcelain is designed to operate
at 11KV, as operating voltage increases the number of discs connected in series
increases. e.g., 220 KV transmission the number of insulator disc required is 24.
It is clearly seen from the data above that copper is better conductor than
aluminium but due to its high-cost copper is not used and aluminium is
preferred.
3.4 Isolators
An isolator is a disconnecting switch is used upon same given part circuit. After
circuit breaker. Thus, isolators’ surge only prevents the voltage from being
applied to same given section of bus. These are essentially off load devices
although they can deal with small charging currents of bus bars and connections.
The design of isolators is closely related to the design of substations.
isolators having three identical poles each pole consist of two or three insulator
posts mounted on a fabricate support. The fixed and moving conducting parts
are of copper or aluminium rods. During the opening operation, conducting rods
swing apart and isolation is obtained simultaneously on all 3 poles. The three
poles are mechanically interlocked which operate together by operating a
common operating
The earth switch is connected between the line conductor and earth. Normally,
it is opened when the line is connected. The earth switch is closed so that the
voltage trapped in line is discharge to earth. There some voltage lines due to
changing current. This voltage is significant in high voltage system. Before,
proceeding with the maintenance work. This voltage is discharged to earth by
closing the earth switch. Normally earth switches are maintained on the frame
of isolator.
3.5 TRANSFORMER
INTRODUCTION:
A transformer is a static device that transfers electrical energy from one circuit
to another without changing the frequency. It works on the principle of
electromagnetic induction and can step up or step down the voltage level of an
alternating current (AC) supply. Power transformers are essential for the
transmission, distribution, and utilization of electrical power in various sectors.
1. Laminated core
2. Windings
3. Yoke/ Tank
4. Tap changer
5. Oil Conservator
6. Breather
7. Bushing
8. Cooling equipment
9. Buchholz Relay
10. Explosion vent
11. Protective devices
Laminated core
The core acts as a support to the winding in the transformer. It also provides a
low reluctance path to the flow of magnetic flux. It is made of laminated soft
iron core to reduce eddy current loss and Hysteresis loss. The composition of a
transformer core depends on factors such as voltage, current, and frequency.
The diameter of the transformer core is directly proportional to copper loss and
is inversely proportional to iron loss. If the diameter of the core is decreased,
the weight of the steel in the core is reduced, which leads to less core loss of the
transformer and the copper loss increase. When the diameter of the core is
increased, the opposite occurs.
Windings
While aluminium is lighter and generally less expensive than copper, a larger
cross section of aluminium conductor must be used to carry a current with
similar performance as copper. Copper has higher mechanical strength and is
used almost exclusively in all but the smaller size ranges, where aluminium
conductors may be perfectly acceptable.
Tank
They are constructed from welded sheet, steel, and larger ones from plain
boiler plates. The lids may be of cast iron, or waterproof gasket being used at
the joints. The fitting includes thermometer pockets, drain cock, rollers or
wheels for moving transformer position, eye bolts for lifting, conservators and
breathers, cooling tubes are welded in, but separate radiators are welded and
afterwards bolted. On the outside is applied with anti-corrosive primer paint
and final of synthetic enamel.
Tap changer
It is a normal fact that increase in load lead to decrease in the supply voltage.
Hence the voltage supplied by the transformer to the load must be maintained
within the prescribed limits. This can be done by changing the transformer
turns ratio.
Oil conservator
A conservator tank can be defined as, a tank that is placed on the
transformer’s roof to provide sufficient space for oil expansion in the
transformer. The main function of the conservator tank of a transformer is,
once the transformer is loaded and the ambient temperature rises, then the
volume of the transformer oil will increase. So, it works like a reservoir for
insulating the transformer oil.
Conservator Tank
Construction of Conservator Tank
The shape of the conservator tank in the transformer is cylindrical where both
the ends of the oil container are closed. One side of the container is provided
with a large cover for cleaning and maintaining the tank.
The pipe of the conservator comes from the main tank of the transformer. It is
placed in the conservator tank at the bottom part. The head of this pipe in the
tank has a cap so that oil mud can be prevented and residue to come into the
main tank from the conservator tank.
Generally, the fixing pipe of the silica gel breather goes into the conservator
tank from the top. When this pipe goes from the base, then it should be
projected well on top of the oil level in the tank. This arrangement ensures that
transformer oil does not flow into a silica gel breather even at the maximum
operating level.
Working
The working of the conservator tank is, once the transformer insulating oil
increases because of the ambient temperature and load, then the vacant space
on top of the oil level in the conservator is incompletely occupied through the
extended oil. As a result, the equivalent amount of air in that gap is pushed
away using a breather. Once the transformer load reduces, then the
transformer is turned off similarly, once the ambient temperature reduces, the
transformer oil contracts. This mainly occurs due to the outside air because it
enters the tank through a silica gel breather.
Breather
Bushing
The Bushing of power transformer is a type of porcelain or ebonite post
insulator put on the top or side of the transformer tank through which
connections are made to the external circuit.
Buchholz relay
A Buchholz relay is a safety device mounted on oil-filled power transformers
and reactors, equipped with an external overhead oil reservoir called a
“conservator”. Buchholz relays are used as a protective device, as they are
sensitive to the effects of dielectric failure that can occur inside the equipment
they protect. Buchholz relays are a type of gas detection relay. Buchholz relays
have two main elements.
The upper element consists of a float. The float is attached to a hinge in such a
way that it can move up and down depending upon the oil level in the
Buchholz relay container. A mercury switch is fixed on the float. The alignment
of the mercury switch hence depends upon the position of the float. The lower
element consists of a baffle plate and a mercury switch. This plate is fitted on a
hinge just in front of the inlet (main tank side) of the Buchholz relay in a
transformer in such a way that when oil enters in the relay from that inlet in
high pressure the alignment of the baffle plate along with the mercury switch
attached to it, will change.
Explosion vent
Explosion vent is a metallic safety pipe or plate used to protect an equipment
or building against excessive explosion-incurred internal pressure. It is also
known as rupture panel. It prevents explosion by releasing excessive pressure
to the atmosphere. It is installed on the main tank and its level is normally
mentioned above the level of the conservator tank. It is only installed in high
rated power transformer. It is simple and efficient protective system.
Protective devices
An oil level indicator is a device used to monitor the oil level inside a
transformer tank or conservator. It can display the oil level directly or through
a leakage-proof magnetic clutch. An oil level gauge is necessary to maintain the
correct oil level in a transformer, as if the oil level falls below the level of the
radiator inlet, flow through the radiator will cease, and the transformer will
overheat.
Dehydrating breather
The dehydrating breather is a device that removes moisture from air entering
oil-filled transformers or conservators. The breather is automated to
regenerate the silica gel desiccant at a user selectable time interval, relative
humidity (RH) or PPM thresholds, reducing unnecessary maintenance costs
over time. Alarms and digital communications allow for remote monitoring of
moisture levels and breather status.
Earthing arrangements
A) Core Earthing
Connecting leads from core and end frame are terminated at the top of the
cover, by connecting them to tank cover, core and frame becomes earthed.
Insulation resistance between the leads from core and end frame or between
leads from core and earth point can be checked by 500 volts megger. Leads
from end frame are brought out and properly earthed for end frame.
Tank to tank Earthing done by connecting a copper braid between tank rim and
tank cover with the help of the bolts used to tight the tank cover and tank
together.
C) Earthing of Tank
For Earthing of tank nut-bolts are required to make the perfect connection
between the pads on tank and external Earthing strip.
The primary winding is connected in series with the line and the MI is
connected across the current transformer. The secondary winding of the CT
should never leave open, if kept open no current will flow through the
secondary winding.
Properties of a CT
• CT steps down high line current into lower values
• CT is connected in series with the line carrying current to be measured
and therefore the primary current is dependent on the load connected
to the system.
• The primary winding consists of thick conductor with a smaller number
of turns
• The secondary winding consists of thinner conductor with more turns.
• A CT is basically a step-up voltage transformer.
• Ammeter is connected directly across the secondary winding terminals.
The CT has five different cores through which five secondary coils are drawn
out. Among these coils one is connected to measuring instrument, one is
earthed, and remaining others are connected to protective relays.
Therefore, a CT is not useful for metering purpose but also for protection
purposes.
The figure below shows the name plate of a primary side 220 kV Current
Transformer.
The capacitive voltage transformer step-down the high voltage input signals and
provide the low voltage signals which can easily measure through the measuring
instrument. The Capacitive voltage transformer (CVT) is also called capacitive
potential transformer.
The capacitive potential divider, inductive element and the auxiliary transformer
are the three main parts of the capacitive potential transformer.
CVT is rated for high voltage levels above 100 kV, while PTs aren’t designed for
such large values. CVT’s offer the advantage that the voltage divider capacitor,
being itself relatively smaller and lighter, configuration makes the transformer’s
iron core much smaller in size, and hence more economical, versus what it would
be if a pure magnetic transformer would be used.
Also, the CVT’s can be tuned to the fundamental frequency of the line, and the
capacitance prevents the inductive fire-back of the coils in the transformer when
a breaker trips. PTs can’t provide such advantage.
A Capacitive Voltage Transformer
All of the circuit breakers at primary side as well as secondary side at DTL PPK-
III Sulphur hexafluoride (SF6) type.
Grounding wire running over the tower or substation provides good protection
to the electrical system against direct lightning stroke, but they fail to provide
protection against traveling high voltage or current waves that reach to
terminal equipment. The lightning arrester or surge arresters provide
protection against such waves.
The lightning arrestor provides an easy conductive path with relatively low
impedance for the flow of current which the system voltage increases more
than the desired value and against its original properties of an insulator at
normal operating voltage.
A lightning arrestor should have following desired characteristics:
• It should not earth any current on the working voltage of the system in
other words it should behave as an insulator it must provide at normal
operating voltage.
• It must provide a conducting path as and when abnormal transient
voltages occur on the system.
• It must be capable to carry the discharge current without getting any
damage to the equipment protected under abnormal conditions.
3.8.1 Types of Lightning Arrestors
When a travelling wave reaches the arrestor, its sparks over at a certain
prefixed voltage as shown in the figure below. The arrestor provides a
conducting path to the waves of relatively low impedance between the line
and the ground. The surge impedance of the line restricts the amplitude of
current flowing to ground.
The lightning arrester provides a path of low impedance only when the
travelling surge reaches the surge diverter, neither before it nor after it.
B) External Causes
• Lightning
Lightning stroke can affect the system in two ways i.e.,
Direct stroke
Indirect stroke
• Ground Wires
• Earth Screens
• Lightning Arrestors or Surge Diverter
Ground Wire
To protect the transmission lines against direct lightning stroke, one or more
bare conductors are run at the top of the tower known as ground wires. These
wires are earthed at regular intervals preferably at every tower the area of
cross section of ground wire is based upon their mechanical strength rather
than their electrical conductivity. These wires should have high mechanical
strength and should be non-corrosive in nature.
The ground wires not only take the lightning of the direct strokes but also
provides a certain amount of electrostatic screening. This reduces the voltage
induced in the line conductors by lightning due to neighbouring clouds. They
also provide effect in attenuating any travelling wave that may be set up in the
lines, by acting as a short circuited secondary of the line conductors.
The main limitations to ground wires are the additional cost and the possibility
of the wire rupture and falling on the line conductors and causing a direct short
circuit.
Earthing Screen
A network of copper conductors earthed at various points, and placed over
and above all around the substation is known as earthing screen. It provides an
electrostatic shield against external fields and protects the system. It protects
the system from direct lightning strokes but does not provide any protection
against any high voltage waves which may still reach at the terminals of
equipment.
Lightning Arrestors
Lightning arrestors are installed at various spots before and after the
transformers, circuit breakers, at starting of each incoming line feeders and at
the distribution side feeders also.
Lightning arrestors protects the equipment from damage by surge voltages or
lightning.
Relays
A relay is a low-powered device used to activate a high-powered device. Relays
are used to trigger circuit breakers and other switches in substations and
transmission and distribution systems. The electrical quantities which may
change under fault condition are:
• Voltage
• Current
• Frequency
• Phase angle
Through the change in one or more of these quantities, the fault signals their
presence type and location to the protective relay is obtained. Moving detect
the fault, the relay operates close the trip circuit of the breaker. This result in
the opening of the breaker and disconnect the fault section.
TYPES OF RELAYS
FEEDER RELAYS:
• Out of step blocking relay
• Directional current relay
• Directional earth fault relay
• Fuse failure relay
• Auxiliary relay type
• Tripping relay
• Instantaneous Earth Fault relay
Protection Relays
1. Differential Relay
The differential relay is one that operates when there is a difference between
two or more similar electrical quantities exceeds a predetermined value. In the
differential relay scheme circuit, there are two currents come from two parts
of an electrical power circuit. These two currents meet at a junction point
where a relay coil is connected. According to Kirchhoff Current Law, the
resultant current flowing through the relay coil is nothing but the summation
of two currents, coming from two different parts of the electrical power circuit.
If the polarity and amplitude of both the currents are so adjusted that the
phasor sum of these two currents, is zero at normal operating condition.
Thereby there will be no current flowing through the relay coil at normal
operating conditions. But due to any abnormality in the power circuit, if this
balance is broken, that means the phasor sum of these two currents no longer
remains zero and there will be non-zero current flowing through the relay coil
thereby relay being operated.
2 Distance Relays
Distance relays are the protecting equipment that functions based on the
distance of the fault point on the transmission line. The distance is calculated
from the generating unit. Based on the distance, the impedance is calculated by
evaluating the fault voltage and fault current.
The major principle of distance relay is it functions depending on the distance of
fault in the transmission line. Its operation depends on the impedance between
the point of fault and the point where the relay is installed. The impedance
between the point of fault and the location of the relay is calculated based on
the voltage and currents of the transmission line during the fault case. The
impedance at that particular point becomes the operating quantity for the relay.
4. IDMT RELAY:
The IDMT relay work on the induction principle, where an aluminium or copper
disc rotates between the poles of electromagnet and damping magnet. The
fluxes induce eddy current in the disc which interact and produce rotational
torque. The disc rotates to a point where it operates a pair of contact that breaks
the circuit and removes the fault condition.
4. TRIPPING RELAY:
This type of relay is in the conjunction with main relay. When main relay sense
any fault in the system, it immediately operates the trip relay to disconnect the
faulty section.
5. Auxiliary Relay
An auxiliary relay is used to indicate the fault by glowing bulb alert.
FUSES
Fuse is an essentially a short piece of metal (or a fusible material) inserted in a
circuit which melts when a predetermined value of current flows through it
and thus breaks the circuits. The protective element of the fuse is a fuse-link
inserted in series with the circuit being protected. The most generally material
used for fuse element is a low melting point material such as tin, lead or zinc.
Fuses may be low voltage type or high voltage type: low voltage can be further
divided into two classes namely semi-enclosed rewire able fuse and the
cartridge type fuse.
EARTHING SYSTEM
The provision of an Earthing system for an electric system is necessary for the
following reason.
PROCEDURE OF EARTHING:
Technical consideration the current carrying path should have enough capacity
to deal with more faults current. The resistance of earth and current path
should be low enough to prevent voltage rise between earth and neutral. The
earth electrode must be driven into the ground to a sufficient depth to as to
obtain lower value of earth resistance. To sufficient lowered earth resistance, a
number of electrodes are inserted in the earth to a depth, they are connected
to form a mesh. The resistance of earth should be for the mesh in generally
inserted in the Earth at 0.5m depth the several points of mesh then connected
to earth electrode or ground conduction. The earth electrode is metal plate
copper is used for earth plate.
NEUTRAL EARTHING:
Neutral Earthing of power transformer all power system operates with
grounded neutral. Grounding of neutral offers several advantages the neutral
point of generator transformer is connected to earth directly or through a
reactance in some cases the neutral point is earthed through an adjustable
reactor of reactance matched with the line.
• The earth fault protection is based on the method of Neutral Earthing.
• The neutral Earthing is associated switchgear. The neutral Earthing is
provided for the purpose of protection arcing grounds unbalanced voltages
with respect to protection from lightening and for improvement of the system.
An earthed neutral system has the following advantages: -
SAFETY EARTHING: -
It is required to provide protection to the operating staff working in the yard
and substation from any injury during fault condition by keeping the voltage
gradient within safe limits. The above two parts have common earth mat from
which flat iron risers are taken out to connect all the non-current carrying
metal parts of the equipment. At the same time the earth mat conductor rises
to voltage, which is equal to the resistance of the earth mat multiplied by
ground fault current. This difference of potential results in voltage gradients.
Control Room
Control panel contain meters, control switches and recorders located in the
control building, also called the dog house. These are used to control the
substation equipment to send power from one circuit to another or to open or
to shut down circuits when needed.
Measuring Instruments used:
• ENERGY METER: To measure the energy transmitted energy meters are
fitted to the panel to different feeders the energy transmitted is
recorded after one hour regularly for it MWhr, meter is provided.
• WATTMETERS: It is attached to each feeder to record the power
exported from GSS.
• FREQUENCY METER: To measure the frequency at each feeder there is
the provision of analog or digital frequency meter.
• VOLTMETER: It is provided to measure the phase to phase voltage .It is
also available in both the analog and digital frequency meter.
• AMMETER: It is provided to measure the line current. It is also available
in both the forms analog as well as digital.
• MAXIMUM DEMAND INDICATOR: There are also mounted the control
panel to record the average power over successive predetermined
period.
• MVAR METER: It is to measure the reactive power of the circuit.
Battery Room
Battery is the heart of power system control and protection as all the power
system protection equipment and the communication equipments works on
D.C supply. In the event of failure of station supply if standby D.C supply is not
available then it will be dangerous for the breaker and other protective
equipment so also the communication system will be great hampered and
during such emergency there will be no communication for help or to transmit
information to the concerned authorities and the fault would be attended very
late.
Thus, battery installation, its commissioning and subsequent maintenance
plays very important role. Batteries are to be installed in a room in close
vicinity of control room. This room should be constructed in a such a way that
it is well ventilated, and the dimension of the room should be such that it can
easily accommodate the stands provided for supporting desired number of
cells. There should be adequate provision for artificial lightning and the
windows should be located in such a way that direct sunlight on the cells be
avoided. Exhaust fan for ventilation of gases, when on quick charge at high rate
possible. Room temperature should be maintained b/w 20 C to 35 C for getting
best results. Higher temperature reduces the capacity. Battery cells should be
arranged on the stands in such a way that each cell can be easily accessed for
any maintenance purpose viz., inspection, topping up, etc.,
Battery room should always be kept dry as damp room is dangerous due to
possible leakages from the battery. Storage of the battery is the most
dependable source of supply of DC power required for closing and tripping of
CB , RELAY, signalling equipment, remote control apparatus, telephone service,
SCADA, emergency light etc. Battery room is the heart line of D.C. system. In
case of failure of the A.C. system the control system should remain operative
so we use D.C. control system through DC set.
Maintenance of Battery
• For effective and trouble free services of station batteries following
maintenance activities are suggested:-
• Battery Room and Ventilation
• Herein battery rooms door are kept closed, exhaust fan checked for air
circulation, metal structures checked for corrosion and painted if
necessary.
• Intercell Connectors and Terminals
• Terminals cleaned for corrosion and sulphation.
• Charge output of charging equipment is adjusted for normal
conditioning of battery, ampere meter should show as fraction of
ampere.
• Annual Maintenance
• Voltage of each cell which should be b/w 2.15 to 2.2 V per cell during
trickle charge is checked.
• Electrolyte
• Electrolyte level and add distilled water as it is necessary, specific gravity
and electrolyte is checked. Keep the distilled water container and keep
some storage of distilled water always ready for topping.
VRLA Battery
A Valve regulated lead–acid (VRLA) battery, commonly known as a sealed
lead–acid (SLA) battery,[1] is a type of lead–acid battery characterized by a
limited amount of electrolyte (“starved” electrolyte) absorbed in a plate
separator or formed into a gel; proportioning of the negative and positive
plates so that oxygen recombination is facilitated within the cell; and the
presence of a relief valve that retains the battery contents independent of the
position of the cells.
Transmission of Data
Below in figure, main equipment from substation/power house to its subLDC
has been shown
Current Transformers (CTs) and Potential Transformers (PTs), installed on
transmission lines, provide inputs to transducers of SIC (Supervisory interface
& Control) & RTU (Remote Terminal Unit) panel. Circuit breakers & isolators’
status are extended up to SIC panel. If for such extension extra potential free
contacts are not available in the Control Panels, Contact Multiplying Relays
(CMRs) are used to provide potential free contacts. The output of RTU is
connected to the communication equipment, through Modem. In between
substation & subLDC, a communication link has been shown. Telephone
exchanges are connected with the communication equipment. Such
communication links can be of any type.
DTL has got its own three different type of communication systems, i.e. PLCC
(Power Line Carrier Communication), microwave and fibre-optic. Modem
output at receive side is connected with the CFE (Communication End Frame).
Its output is connected with data takes over. Each RTU is automatically polled
by Server of Sub LDC to obtain each data of repeats at least once in 10 sec and
is stored in the database of subLDC. This data is processed in database formats
and is retrieved for different applications. These formats or graphics are
displayed or printed as per requirement. At sub LDC, System Control Officers
use this data to monitor and analyse position of the grid.
SCADA SYSTEM
In SCADA system measured values, i.e., analogue (measured value) data (MW,
MVAR, V, Hz Transformer tap position), and Open/Closed status information,
i.e., digital data (Circuit Breakers/Isolators position i.e., on/off status), are
transmitted through telecommunication channels to respective sub-LDCs. For
this purpose, Remote Terminal Units (RTUs) at 400KV, 220KV sub-stations have
been installed. System values & status information below 66 KV have not been
picked up for data transmission, except for 33KV Bus isolator position and LV
side of generators. Secondary side of Current Transformers (CT) and Potential
Transformer (PT) are connected with ‘Transducers’. The output of transducers
is available in dc current form (in the range of 4mA to 20mA). Analogue to
digital converter converts this current into binary pulses. Different inputs are
interleaved in a sequential form and are fed into the CPU of the RTU. The
output of RTU, containing information in the form of digital pulses, is sent to
subLDC through communication links. Depending upon the type of
communication link, the output of RTU is connected, directly or through
modem, with the communication equipment. At subLDC end, data received
from RTU is fed into the data servers. In general, a SCADA system consists of a
database, displays and supporting programmes. In DTL, subLDC use all major
functional areas of SCADA except the ‘Supervisory Control/Command’
function. The brief overview of major ‘functional areas’ of SCADA system is as
below:
SLDC Minto road has a large and active ‘Mimic Board’ in its Control room. This
mimic board displays single line diagram of intra State transmission system i.e.
grid network of 400KV, 220KV and important 66 KV substations, transmission
lines, thermal powerhouses. Outgoing feeders, shown in the mimic board,
have ‘achieve’ (LED display) coloured indications, of three different colours, to
show the range of power flow at any moment i.e. ‘Normal’, ‘Nominal’ or
‘Maximum’ of its line capacity. For new substations and lines, displays in active
and passive forms are required to be made in the Mimic diagram. But, Mimic
Board has a limitation that it cannot incorporate/add large volume of displays
for substations/power houses/transmission lines in ‘active’ form due to space
constraint and congestion. Due to this Mimic Board is going to be
supplemented with a Video Projection System (VPS) at SLDC, Minto Road in
near future. Also in SLDC & subLDC, displays of single line diagrams of RTU sub-
stations/power house are viewed on VDUs of large size (21”).
6 Operation and Maintenance of 220KV Substation
6.1 INTRODUCTION
Maintenance is a key activity for utilities in order to assure the proper
operation of the networks. And it implies a huge amount of human and
economic resources. Saving Maintenance costs means that it is needed to
proper operation of substation equipments. The availability of reliable and
quality power has made the job of substation more important. This can be
achieved by establishing the new substation, with most efficient and reliable
equipments and taking more care in their operation and maintenance.
Maintenance may be defined as the upkeep of the substation electrical
equipment in proper working and efficient condition to derive the Reliable and
efficient operation, optimum utilization Availability of quality power, reduced
down time, detection of premature faults, Minimizing revenue losses etc. To
meet the above requirement, the equipment has to be checked, attended to,
trouble shoots and operated under specified conditions. A large percentage of
failure of electrical equipment are due to deterioration of insulation, loose
contact, abnormal operating condition etc. Many of these failure can be
anticipated by regular application of simple tests and timely maintenance . If
the fault condition leading to failure is detected in the early stage itself, the
extent of damage can be reduced and the equipment can be reconditioned
and put back in to service. Any abnormality will be followed by warming signal
like variation in sound, excess temperature, vibration, sparks, blown out fuses,
frequent trappings, tripping before full load. The detection of incipient faults in
electrical equipment depends up on use of proper diagnostic tools, its effective
use, correlation and proper interpretation of test results and observation
based on experience, manufacturers guidance etc.
MAINTENANCE ACTIVITY
• Corrective or breakdown maintenance: Corrective or breakdown
maintenance is carried out as and when necessary. This applies only to
low value and auxiliary equipments, breakdown of which does not affect
the continuity of power supply.
• Preventive maintenance: Preventive maintenance calls for advance plan
is made to carry out preventive maintenance. The advantage lies in
uninterrupted power supply, increased availability of the equipment and
reduction in maintenance cost.
• Condition based maintenance: Condition base maintenance is based on
condition assessment of the equipment by tests ON or OFF the line. This
is ideal for prevention of equipment failure and other associated
consequent damages.
• Reliability centred maintenance: Reliability centred maintenance is
generally carried out on old equipment by conducting ‘ remaining life
assessment studies’ and based on economics, life extension techniques
are adopted without sacrificing reliability and availability. The
maintenance costs are also reduced.
• Equipment failure analyses: Equipment failure analysis is the major
responsibility of maintenance personnel to prevent repeated failure of
equipment and provide inputs foe necessary change in design
parameters, new equipment design, quality control plan, erection and
subsequent maintenance technique.
• Techniques for reducing down time: Techniques of reducing down time
play a vital role in continuity of power supply. Hot line maintenance of
one line of double circuit\ line with other circuit in live condition,
deployment of emergency restoration system etc., is few examples.
• Spare management: Spares management ensures availability of right
spares most frequently required and at the right location and thereby
help immediate restoration of power supply.
• Documentation/ computerization on maintenance: The documentation
is a record of the type of maintenance activity carried out, any
abnormalities noticed during checking etc., chronologically documented
and computerized for further analysis and action.
6.2 MAINTENANCE SCHEDULE
Maintenance schedule is categorized into daily, weekly, monthly, quarterly and
yearly maintenance schedules.
Maintenance Schedule of 160 MVA Power Transformer
• Check and re-condition of silica jelly.
• Check the working cooling fans, pumps
• Release gas from BH relay
• Clean the bushing, radiator, body etc.,
• Check Earthing connection
• Check jump connections
• Check OLTC motor drive and control panel
• Lubricate bearing and cleaning
• Check the gear box oil level
• Check operation of limit switch, sequence switch with
• Transformer in off conditions
• Check gasket joints for oil leakage