Professional Documents
Culture Documents
SUBMISSION PROCEDURES
FOR
\ ARCHITECTS - ENGINEERS - BUILDING OWNERS
POlICE'RINTlNG""ESS ' D E V E L O P E R S - MANAGEMENT CORPORATION
Plans preparation and submission procedures
1st edition
CDD endeavours to improve its services to the building industry over time. It will
formulate new policies and procedures or introduce improvements to existing
systems and these changes will be made known to the building industry.
2 3
CONTENTS
Page
Under what situation must plans of fire safety works be approved by COO? 7
Can the details of fire protection works or air-conditioning & mechanical ventilation
12
works be incorporated in the building plan submission?
Is Building Pian submission required for a change of use of the building
13
premises?
Annex A & A2 22
Annex B 24
4 5
FIRE SAFETY WORKS
Under what situation must plans of fire safety works be approved by
the Civil Defence Department (COD)?
Plans of fire safety works must be submitted and approved by the CDD prior to the
commencement or carrying out of any fire safety works in any new buildings or existing
buildings.
6 7
CODES OF PRACTICE
However, the consultant is required to provide strongjustification to the COD to support
What are the accepted codes of practice?
his waiver application. In addition to the justification, the consultant is also expected
The NFPA 101 is the accepted code of practice. Should other codes be used,
to propose alternative fire safety measure to make up for the shortfall in fire safety.
prior approval must be obtained from the COD stating the areas of application
Therefore, in submitting waiver application to the COD, the consultant is required to
and reasons. Approval for their use shall only be for that particular application or
state the particular provision in the Fire Code to be waived, the reasons for the waiver
project.
and propose alternative fire safety measures to overcome the shortfall. Unless there are
very good reasons for a particular fire safety requirement to be waived, the COD will
CONSULTANTS not accede to such request.
B 9
For ACMV and FP Plans application, the consultant shall submit at the COO for approval
at DFC2 stage. Submission at OFC j stage is not required, unlike BP application. If
there is a need for waiver application, consultant shall submit the application at the
(2art CDO prior to plan application. The following flowchart illustrates this.
_ l Start
. Consultant shall submit the approved preliminary project design (by Planning
Department at DC 1 stage) for comments by the COD
,--
r
___+, • Consultant to decide if there is need to
submit waiver application to COO
°Note: Waiver application,
if any, shall be submitted
• Consultant to decide if there is need before plan application
1
'Note: Waiver application.
to submit waiver application to COD if any, shall be submitted al DFC2 slage.
before plan application
at DFC2 stage.
Yes Waive(
Yes submission
required?
Consultant submits waiver
application at COD for approval No Consultant submits waiver
application at COD
No
'------+1 Consultant submits the Building Plan
application at COD for approval at 1+-----,
DFC2 stage.
'---t~-----' L-_~.Consultant submits ACMV/FP Plan application 1+- --,
at the COD at DFC2 slage for approval
Registration counter checks if
plans and documents are in order ~
Regislration counter checks if
plans and documents are in order
No Registration counter
rejects plan application No {Regislration counter
;:;----'-''''---..;, rejects plans application
Yes
Yes
Registration counter registers plans
Registration counter registers plans
End
I
End
10 11
What are the plans / documents to be submitted?
The following are required for the different types of plan submission: CHANGE OF USE OF PREMISES
Is Building Plan submission required for a change of use of the building premises?
Types of plan submission
If the change of use of the premises results in addition and alteration works to be
Air-conditioning & carried out to the premises or causes the occupant load calculation to be increased
Building Plan Fire Protection Plan Mechanical Ventilation or exit capacity calculation to be reduced, building plan submission is required. The
Plan consultant is required to specify clearly the proposed intention of the change of use in
• 2 sets of plans; • 2 sets of plans; • 2 sets of plans; the project title of the Building Plan.
• Practicing certificate of • Practicing certificate of • Practicing certificate of
consultant; consultant; consultant;
·• Application form;
Occupancy load and exit
• Application form;
• Sprinkler hydraulic
• Application form;
• Pressurization staircase
DETAILS TO BE SHOWN ON PLANS
capacity calculations; calculation where calculation where
• Unprotected opening applicable; and applicable; What are the details to be shown on the different types of plans?
calculation; and • Other supporting • Smoke control The details to be shown on the Bnilding Plan are as follows:
• Other supporting documents, if any. calculation where
documents, if any. applicable; and
• Other supporting (a) Location plan with ratio of at least I: 1000. The location plan shall indicate the
documents, if any. following:
(i) the coloured location of the lot relative to the neighbouring lots; and
(ii) the various roads constituting the access layout of the lot.
All plans, calculations, consultant's reports and application form shall be signed
by the consultant. All plans shall be submitted on standard metric A I or AO size only.
(b) Site plan with ratio of at least I:500. The site plan shall indicate the
following:
INCORPORATION OF FIRE PROTECTION WORKS & AIR- (i) means of access to the site and to the perimeter of each building for
CONDITIONING & MECHANICAL VENTILATION WORKS INTO fire fighting vehicles and equipment;
(ii) the Fire Engine hardstanding of dimension 6m x 15m, with the longer
BUILDING PLAN
side parallel to the fayade of the building and shall withstand the load
of a 40-ton fire appliance.
Can the details of fire protection works or air-conditioning & mechanical ventilation
(iii) location of existing public fire hydrants. Should there be no fire
works be incorporated in the building plan submission?
hydrant or inadequate fire. hydrants on site, provision of adequate.
No. Separate submissions are required for the different scope of fire safety works. As
internal private fire hydrants is required and indicated on plan;
such, Building Plan or Architectural Plan, Fire Protection Plan and Air-Conditioning
& Mechanical Ventilation Plan shall be submitted separately.
12 13
(iv) distances between each building or fire safety works and the relevant (x) the type and extent of provision of hydraulic hosereels, sprinkler
lot boundaries, other proposed or existing buildings or installations systems, wet and dry rising mains and other fire extinguishing systems;
on the site; and and
(v) any other feature on or in the vicinity of the site which is likely to be (xi) the type and extent of provision of smoke control and ventilation
a fire hazard or is likely to cause obstruction to fire fighting vehicles systems and their related air or smoke shafts
and equipment and rescue operations.
(d) Cross-sectional drawings with ratio of I: 100 or I:200, which are necessary to
(c) Every floor plan and roof plan with ratio of I: I00 or I :200. The plans shall fully describe all details and configurations of the proposed building or part
indicate the following: thereof and of the proposed fire safety works and shall include the following:
(i) the proposed or existing use of every part; (i) full height of each storey and the depth of ceiling space;
(ii) the details of all openings and voids penetrating floors including their (ii) details of all openings and voids penetrating floors including their
usage, dimensions and the nature and aITangement of enclosing walls dimensions, usage and height of enclosing walls and barricades;
and barricades; (iii) details of the junction between the roof and any compartment walls;
(iii) the design occupant load for that storey or roof for which means of (iv) the dimensions of treads and risers of staircases;
escape have been provided in accordance with NFPA 101 in case of (v) the dimensions of openings in external walls;
fire; (vi) the clear height of all structures or projections directly above the access
(iv) the fire resistance ratings of all elements of structure, fire doors, shutters, for fire fighting vehicles and equipment;
dampers and any other such fire safety measures; (vii) the clear distance of the external wall from the fire fighting vehicles
(v) the details of all means of escape to the external at ground level from and equipment access, lot boundary, adjacent buildings and other
every part of the floor such as exit doors, corridors, passageways, aisles, structures;
gangways, balconies, lobbies, ramps, exit passageways, escape and fire (viii) the types of materials used in and the thickness of all walls, floors,
fighting staircases and areas of refuge. roofs, ceilings, beams and other related parts of the building; and
(vi) the locations of all existing and proposed fire lifts, fire lift lobbies, Fire (ix) enlarged details of curtain walling at the junction with the typical floor
Command Centre, fire pumps, water tank rooms and generator rooms; slab to show the provision offire stopping or fire cavity barriers.
(vi i) the locations of all areas designated for the storage of flammable liquids (e) Elevational drawings with ratio of at least I:200. The elevational drawings
or gases, boiler rooms, transformer rooms any other area of special shall indicate the following:
risk; (i) the provisions of firemen access panels on the external walls and
(viii) the types and extent of provision of fire detection and alarm systems c1addings; and
and voice communication systems; (ii) the clear distance of the external wall from the fire fighting vehicles and
(ix) the type and ratings of all proposed and existing portable fire equipment access, lot boundary, adjacent buildings and other structures.
extinguishers and their locations;
14 15
The details to be shown on the Air-conditioning and Mechanical Ventilation Plan (iv) the location of smoke detectors; and
and Fire Protection plan are as follows: (v) the location and function of other fire precautionary features.
(a) key features of the building in which the system is to be installed, including the (g) for fire alarm system such additional details as-
details as listed in the Building Plan; (i) plan layout of each Aoor with proper labeling of devices along with conduit
layout showing the starting and ending points;
(b) a schematic diagram of the overall system showing clearly the key features and (ii) schematic diagram with proper labeling/addresses of devices or detectors
their functions, relative locations in the building, sizes, capacities and other & battery capacity of the fire alarm panel; and
essential information including the air distribution design arrangement in the (iii) general layout offire alarm system with wiring diagram.
case of air-conditioning and mechanical ventilation systems; (h) for fire sprinkler system / fire hose cabinet / rising mains / fire hydrant such
additional details as-
(c) the layout of the system on every floor plan showing the various parts and (i) sprinkler layout of each Aoor with proper legend (as per NFPA 170 only),
their functions, location, arrangements, sizes, capacities and other essential including pipe size & sprinkler heads spacing.
information; (ii) schematic diagram (riser diagram) of sprinkler, fire hose cabinet, rising
mains with proper annotation.
(d) necessary cross-sectional views as superimposed on the building or part thereof (iii) general layout of the systems, depicting all pipes and their materials,
to fully describe the details and configurations of the system; hanger support details & fire cable specification.
(iv) hydraulic calculation to verify fire pump capacity & water requirement of
(e) a colour scheme to clearly distinguish the various distinct parts of the system system.
and the different systems f,:oin.QI:e another; (v) isometric drawing of the most critical group of sprinklers to support
hydraulic calculation with proper node number & pipe number.
(f) for air-conditioning and mechanical ventilation systems such additional details (vi) where applicable, endorsement on plan that the design and installation of
as - the above system is in accordance with the relevant NFPA e.g. NFPA 10,
(i) the volumetric rate of Aow of air at each point of inlet and outlet of each 13 (or 13R), 14,20 & 22.
system including those serving protected staircases, exit passageways,
lobbies, areas of refuge, the Fire Command Centre, fire pump rooms, Where necessary, such plans shall be accompanied by a report identifying and
generator rooms, rooms used for the storage of flammable liquids or gas or describing each system installed in the building and its design, features and operational
other areas of special risk; arrangements and design calculations.
(ii) the location offire compartment walls, Aoors and air shafts;
(iii) the location offire dampers;
16 17
The details to be shown on all plans i.e. Building Plan, Air-conditioning and ENDORSEMENTS ON PLANS
Mechanical Ventilation Plan and Fire Protection plan are as follows:
What are the endorsements to be shown on the plans?
(a) Have on every sheet an outlined rectangular space measuring 150mm x
100mm provided at its top right hand corner for CDD official stamps and Building Plan
endorsement (See Annex B for illustration).
(b) Title blocks showing the project title, full names, addresses and signatures The following shall be endorsed on every sheet of the Building Plan by the
of the project consultant and the Building Owner/Developer/Management appropriate consultant who prepared the plan:
Corporation (See Annex B for illustration).
(c) All symbols to be in accordance with NFPA 170 and correctly reflected in the 1) " I Identification Card No.
legend. Only show the relevant symbols in the legend, which is to be reflected / Passport No. being a consultant hereby certify that the fire
on every sheet of drawing. safety works as shown on these plans have been designed in accordance with
(d) All proposed works shall be shown coloured on plan (except for works in the provisions of the *NFPA 101 / (other relevant codes and
new buildings) and these shall be differentiated from deletion works, if any standards), subject to waivers granted by the Managing Director of Qatar Civil
(existing approved works and fire protection system not to be coloured). Defence.
(e) All scales, grid references, dimensions and page numberings shall be shown
on every sheet of plan. Name and signature of consultant
(f) Type of standard used for fire-related materials / equipments e.g. UL listed/
FM approved. Address of consultant
(g) Drawings on plans shall be arranged in the following sequential manner:
o Location plan and site plan (on the front page) Date
o Lowest level floor plan * Delete where applicable"
o Ground floor plan
o Higher floors (each floor plan or typical floor plan) The above i.e. consultant endorsement of fire safety compliance, shall be
o Roofplan on the right hand side of the plan (See Annex B for illustration).
o Sectional and elevational drawings
o Miscellaneous drawings. 2) Where applicable, all three plans, i.e. Building Plan, Fire Protection
Plan, Air-conditioning & Mechanical Ventilation Plan are to be submitted
These plans are to be stapled in a set. together to CDD. In this instance, the consultant shall endorse on the Building
Plan either of the following:
18 19
'The fire safety works shown on this building plan do not
FP/ACMV Plans
affect the fire protection system and mechanical ventilation system in the
building. '
The following shall be endorsed on every sheet of the FP/ACMV Plan by
Or
the appropriate consultant who prepared the plan:
'The fire safety works shown on this building plan affect the
"fire protection system / "mechanical ventilation system in the building
and the *FP Plan / *ACMV Plan "is / "are submitted together with the
" I - - - - - - - - - - - - Identifieation Card No.
Bnilding Plan.
/ Passport No. being a consultant hereby certify that
the proposed system has been designed in
"Delete where applicable'
aecordance with the provisions of (please state the
code used).
However, ifal13 plans cannot be submitted together, consultant will submit
Building Plan first and endorse on the Building Plan either of the following:
The above i.e. whether fire safety works on building plan affects fire
protection system/mechanical ventilation system shall be endorsed on the right
hand side of the plan (See Annex B for illustration)
20 21
ANNEXA2
Description of Building Type
ANNEXA
Qualification ofConsultants for Building Plans, Air-Conditioning & Mechanical Building Purpose for which building or part of the
Type building is IIsed 01" intended to be used
Ventilation Plans & Fire Protection Plans to be submitted to the Civil Defence
Department. Accommodation for residential purposes to include villas, flats,
Residential maisonettes, apartments etc.
22 23
ANNEXB
Illustration showing Format of Plan of Fire Safety Work
150mm