You are on page 1of 5

Geothermal Power

Plant

Review and
Master Plan Pre Design Design Construction Facility Start-Up Safety/Environment
Contracts
Geothermal Power Plant

Master Plan Pre- Design

Problem Definition Utilities Evaluation

Site Search Site Layout

Conceptual Project Design System Design Criteria

Site Observation : Data Architectural Design


Collection Criteria

Site Observation : Data Electrical/SCADA Design


Sampling Criteria

Resident Interview Prepare of Preliminary


Engineering Report

Data Collection for


Treatment Process Prepare of Probable Cost
Observation Report

Treatment Process
Observation Residual Management

HAZOP Study

Environmental Impact
Study

Early Site Permit


Geothermal Power Plant

Design Review and Contracts

Civil Drawing Obtain Building Permit

Architectural Drawing Update Design Documents

Structural Drawing Bidding

Mechanical Drawing Contract Award

HVAC Drawing

Plumbing Drawing

Instrumentation Drawing

Electrical Drawing
Geothermal Power
Plant

Construction

Engineering Erosion Building Air Water Fire Interior


Procurement Preparation Excavation Concrete Piping Electricity CCTV
Support Control Structure Conditioning Installation Extinguisher Finisher

Placement of
Orders on
Vendor

Equipment
Manufacturing

Equipment
Delivery
Geothermal Power Plant

Facility Start-Up Safety/Environment

Electricity Installation Test Document Completion

HVAC Test Safety Analysis :


Preliminary Report

Miscellanous Test Safety Analysis : Final


Report

Process Test Risk Assessment :


Preparation

Security Test Risk Assessment : Review


and Report

Integrity Test

Manual Report

Operating Information

Operating Condition

Operating Procedure

Operational Documenteries