Reliance Infrastructure Limited

Project : Improvement & Augmentation of Four Laning from Km 0.000 to Km 60.250 (Design Chainage Km 0.000 to Km 65.960) from Vikaravandi to Sethiyathopu section of NH-45C in the State of Tamil Nadu on EPC mode under NHDP Phase IV.

S - Curve
800.00

724.42 724.42
696.22
700.00
654.02

601.05
600.00 574.97

521.16

500.00 479.87
442.76
407.51
400.00
347.56
306.16
300.00 272.18
252.85

208.62
191.61
200.00 162.63
153.89
130.47
94.85
100.00
46.18
20.39
- - -
-
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

-100.00

Amount for the Month Milestone PLANNED ACHIEVED

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
MONTH 2018 2019 2020
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
ACHIEVED PLANNED MILESTONE

Stage MS I ( 150 days-16 Aug 18, 10% ) MS II ( 330 days-12 Feb 19, 30% ) MS III ( 510 days-11 Aug 19, 60% ) Scheduled Completion ( 18 Mar 20)

IN AMOUNT 71.10 213.30 426.60

In % 10.0% 30.0% 60.0%

IN AMOUNT - - - 20.39 25.79 48.67 35.62 23.42 8.74 28.98 17.01 44.23 19.33 33.98 41.40 59.95 35.25 37.11 41.29 53.81 26.08 52.97 42.20 28.20 -

CUM AMOUNT - - - 20.39 46.18 94.85 130.47 153.89 162.63 191.61 208.62 252.85 272.18 306.16 347.56 407.51 442.76 479.87 521.16 574.97 601.05 654.02 696.22 724.42 724.42

In % 0.0% 0.0% 0.0% 2.9% 6.5% 13.3% 18.4% 21.6% 22.9% 26.9% 29.3% 35.6% 38.3% 43.06% 48.9% 57.3% 62.3% 67.5% 73.3% 80.9% 84.5% 92.0% 97.9% 101.9% 101.9%

IN AMOUNT 5.05 1.07 0.57 2.49 3.48 2.00 21.91 15.73 4.22 5.14 8.34 4.95 6.30 7.13 7.00

CUM AMOUNT - - - 5.05 6.11 6.68 9.17 12.66 14.66 36.57 52.30 56.52 61.66 70.00 74.95 81.25 88.38 95.38

In % 0.00% 0.00% 0.00% 0.71% 0.86% 0.94% 1.29% 1.78% 2.06% 5.14% 7.36% 7.95% 8.67% 9.84% 10.54% 11.43% 12.43% 13.41%