You are on page 1of 12

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/335240495

Decision Support System for Optimum Soft Clay Improvement Technique For
Highway Construction Projects

Article  in  Ain Shams Engineering Journal · August 2019


DOI: 10.1016/j.asej.2019.08.007

CITATIONS READS

0 110

3 authors:

Ahmed Ebid Ibrahim Mahdi


Future University in Egypt Future University in Egypt
22 PUBLICATIONS   18 CITATIONS    35 PUBLICATIONS   352 CITATIONS   

SEE PROFILE SEE PROFILE

Rana Khallaf
Future University in Egypt
12 PUBLICATIONS   7 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Simplified Construction Scheduling for Field Personnel View project

Cost estimation - project management View project

All content following this page was uploaded by Ahmed Ebid on 27 September 2019.

The user has requested enhancement of the downloaded file.


Ain Shams Engineering Journal xxx (xxxx) xxx

Contents lists available at ScienceDirect

Ain Shams Engineering Journal


journal homepage: www.sciencedirect.com

Civil Engineering

Decision support system for optimum soft clay improvement technique


for highway construction projects
Ibrahim Mahmoud Mahdi, Ahmed M. Ebid ⇑, Rana Khallaf
Structural Engineering and Construction Management Department, Faculty of Engineering, Future University in Egypt, New Cairo, Cairo, Egypt

a r t i c l e i n f o a b s t r a c t

Article history: Identifying a soft clay improvement strategy is a main challenging in highway construction projects due
Received 30 March 2019 to the various conditions involved. Hence, the objective of this paper is to present a Decision Support
Revised 26 July 2019 System (DSS) to select the optimum soft clay improvement technique for this type of projects. Value
Accepted 13 August 2019
Engineering (VE) is integrated with Analytical Hierarchy Process (AHP) for the proposed (DSS). Using
Available online xxxx
the AHP provides a robust means of identifying the relative importance of any criteria or factors for soft
clay improvement alternatives. The scope of this study includes four of the most commonly used tech-
Keywords:
niques for soft clay improvement: soil replacement, pre-loading, vertical drains, and the construction
DSS
VE
of embankments on piles. The proposed methodology was verified using four case studies of highways
AHP under construction in northern Egypt. The results show that the proposed (DSS) successfully predicted
Soft clay improvement the optimum soft clay improvement technique in three out of the four cases.
Highway embankment Ó 2019 THE AUTHORS. Published by Elsevier BV on behalf of Faculty of Engineering, Ain Shams Uni-
versity. This is an open access article under the CC BY license (http://creativecommons.org/licenses/by/4.0/).

1. Introduction to construct a granular filter on the soft soil, load it with embank-
ment load and wait until the soft layer consolidates then reshape
Multiple challenges face construction projects in achieving the the distorted embankment and construct the road (referred to as
project objectives while balancing all the constraints. Therefore, embankment with pre-loading). The third technique is similar to
it is crucial to explore all possible approaches that would help the second one but adds the utilization of vertical drains (wick
reach the project objectives related to cost, time, performance, drains) to speed up the consolidation process (referred to as
and quality. For highway construction projects, soft clay improve- embankment with vertical drains). The fourth alternative, denoted
ment is one of the main items that affect both the cost and time of embankment on piles uses a recently developed system in which
a project. This is particularly important when the highway is the embankment is supported on a grid of piles connected by
founded on a surface layer of soft clay. The main target of soft clay two perpendicular layers of geo-grid at the ground surface. The
improvement in this case is to enhance the mechanical properties arching effect generated in the embankment soil and the tie action
of the existing soft soil. This enables it to support the weight of the provided by the geo-grid layers act together as virtual raft transfer-
highway embankment and the traffic loads acting on it with ring the embankment loads to the grid of piles. A small cap on each
acceptable safety factors and embankment settlement as per the pile is used to prevent punching [31].
project specifications. In this study, four soft clay improvement
alternative techniques are considered. One of these technique is 2. Objective
to replace the whole soft layer with compacted granular soil
(referred to as embankment on replacement), the second one is The aim of this research is to develop a decision support system
(DSS) for optimum soft clay improvement of highway sloped
embankments on soft clay during the early design phase. Value engi-
⇑ Corresponding author. neering (VE) integrated with Analytical Hierarchy Process (AHP) and
E-mail addresses: ibrahim.mahdi@fue.edu.eg (I.M. Mahdi), ahmed.abdelkha- Delphi are used to develop this assessment approach. The developed
leq@fue.edu.eg (A.M. Ebid), rana.khallaf@fue.edu.eg (R. Khallaf).
(DSS) considered eight factors which are cost, construction duration,
Peer review under responsibility of Ain Shams University.
constructability, sustainability, environmental impact, risk impact
and safety, technology impact, and infrastructure conflict to recom-
mend the optimum improvement technique considering all points
of view not just the cost reduction one. Also, using AHP provides a
Production and hosting by Elsevier
robust tool for identifying the relative level of importance of the cri-

https://doi.org/10.1016/j.asej.2019.08.007
2090-4479/Ó 2019 THE AUTHORS. Published by Elsevier BV on behalf of Faculty of Engineering, Ain Shams University.
This is an open access article under the CC BY license (http://creativecommons.org/licenses/by/4.0/).

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
2 I.M. Mahdi et al. / Ain Shams Engineering Journal xxx (xxxx) xxx

teria used for the selection of the optimum soft clay improvement educated opinions to make decisions. The objective of an MCDM is
alternative. The following sections describe the Value Engineering, to structure a problem and identify and evaluate the multiple cri-
Delphi technique, and the AHP conducted in this study. The pro- teria available. These techniques have been used in construction
posed (DSS) is verified using highway under-construction projects management research in areas such as highway management, pro-
in the north of Egypt at current market conditions. ject delivery methods, and risk identification and ranking
[15,32,14,13]. However, no previous research has proposed a DSS
3. Background for soil improvement techniques. In this paper, the selected MCDM
technique is the Analytic Hierarchy Process (AHP).
3.1. Value engineering
3.3. Delphi technique
The construction industry faces numerous challenges in its effort
to achieve project objectives while maintaining project constraints. The Delphi technique is a tool used to collect data and achieve
Therefore, the optimum strategy is to study all possible approaches consensus on an issue. An advantage of this methodology is that it
that increase the value with minimum effort, cost, and time while does not require all experts to be physically located in one place,
achieving optimal performance and quality. Value Engineering which makes it easier to identify experts without any geographic
(VE) was introduced to the construction industry during the late constraints. It also eliminates biases since all experts provide input
nineteen fifties and has been employed worldwide for over 60 years. individually and are not swayed by group dynamics. Multiple
Since its early beginnings, this technique has been widely applied in rounds are conducted to achieve consensus between participants
construction projects [22,7,16,4,10]. VE is a systematic approach, to facilitate decision-making. Hallowell and Gambatese [9]
which aims at achieving value for money by providing all necessary reported that usually 1 to 3 rounds are conducted in a study, which
functions at the lowest cost. Chen et al. [4] classified VE as an orga- mainly depends on the presence of consensus or dissent in the
nized application that uses both technical knowledge and common results of each round. It has been widely used in construction man-
sense to identify and eliminate unnecessary project costs and agement research for reporting and decision-making among other
thereby achieve value-for-money. Chavan [3] categorized VE as uses [21,29,13].
one of the most appropriate and systematic techniques to improve
value in construction projects. The VE process explores con-
3.4. Analytical hierarchy process (AHP)
structability, manufacturability, and maintainability of a project at
the early stages and thereby identifies potential conflicts as well as
It was developed by Saaty [26–27]. The AHP is used to calculate
savings [24,17,5]. The VE process, denoted as a VE job plan, is an
the relative importance and weighting of multiple alternatives and
organized problem-solving technique which consists of several
consists of the following steps: (i) creating a hierarchical arrange-
phases, namely, information, creativity, evaluation, development,
ment of criteria (goals); (ii) performing pair-wise comparison of
and proposal. The creativity phase is the most crucial phase to pro-
criteria and alternatives in the comparison matrix using a proper
duce innovative ideas. This phase requires existing information
scale; (iii) pair-wise evaluation of elements in the hierarchy (goals,
and experiential knowledge from past projects [23]. Dell’lsolla [7]
criteria (sub-criteria) and alternatives); and (iv) calculation of the
utilized his wide practical experience in the construction manage-
maximal eigenvectors (kmax) and the consistency index
ment and value engineering to declare that VE should be performed  
CI ¼ kmax
n1
n
. The consistency of the decision is obtained with con-
as early as possible before securing of funds, approval of services,
sistency ratio CR. If in the comparison matrix CR is less than 0.10,
systems, or design to maximize the value. Potential savings from
then the estimated relative importance of the criteria (priority of
VE applications are much greater with its early application. When
the alternative) is deemed acceptable.
VE is applied at a later stage, increased investment is required to
implement any changes as well as more effort to withstand potential
stronger resistance to change. 3.5. Soft clay improvement techniques for highway projects
Value Engineering (VE) can be viewed as a rigorous, interdisci-
plinary problem solving technique, which focuses on improving 3.5.1. Embankments on soil replacement
the value of the functions that are required to accomplish the This alternative is based on replacing the entire top soft layer
objective of any product, process, service, or organization. The with well-compacted granular soil. The replacement layer should
highest performance in VE is achieved when the focus is mainly be extended horizontally beyond the toe of the slope from both
to increase the value rather than to reduce the costs. Gudem sides at a distance equal to its thickness to ensure that the dissi-
et al. [8] stated that implementing VE in projects can bring about pated embankment load will be contained within the replacement
numerous benefits, such as reducing costs by 20% to 30%, enhanc- layer, as shown in Fig. 1a. It is a simple technique to improve the
ing operational performance by 40% to 50%, and upgrading product soil strength beneath the embankment utilizing the same kind of
quality by 30% to 50%. The application of VE in this research is lim- labor and equipment used for the construction of the embankment.
ited to the determination of the optimum technique to improve This technique may be suitable for top soft layers up to 3.0 m thick,
soft clay layers underlying the highway sloped embankment of but it is uneconomical for thicker layers.
highway projects during the conceptual design phase.
Value study generally involves three stages: (i) pre-workshop 3.5.2. Embankments with pre-loading
(preparation); (ii) workshop (execution of the six-phase job Plan); In this technique, the soil beneath the embankment is improved
and (iii) post-workshop (documentation and implementation) by using the weight of the embankment itself as pre-loading on the
[28]. The most crucial phases in the VE methodology are the func- top soft layer. The soft soil tends to consolidate under loading and
tional analysis, the creativity in finding alternatives, and the eval- the excess water dissipates into the adjacent permeable layers.
uation process. However, consolidation is a very slow process, which may need
weeks or even months to achieve the desired effect depending
3.2. Decision support systems on the properties and the thickness of the soft layer. Because of
that, it is a common practice to use a granular filter on the top of
Decision support systems such as multi-criteria decision- the soft layer to speed up the consolidation process, as shown in
making (MCDM) are created to channel expert judgment and form Fig. 1b. The thickness of this filter is designed to ensure that the

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
I.M. Mahdi et al. / Ain Shams Engineering Journal xxx (xxxx) xxx 3

Fig. 1. Soft clay improvement techniques: (a) Replacement, (b) Pre-loading, (c) Vertical drains and (d) Embankment on piles.

volume of the voids between the particles is large enough to structural system that can transfer the embankment loads to the
absorb the excess water from the consolidating soft layer. It is a piles, as shown in Fig. 1d. This mechanism is based on dividing
common practice to use a geotextile layer below the embankment the embankment loads into three parts. The first part contains
to act as a filter that allows water to pass through and prevents soil the soil in and above the arching zone and is transferred directly
particles from moving. In addition, two perpendicular layers of to the piles by arching action. The second and third parts consist
geo-grid are commonly used below the embankment to increase of the soil below the arching zone. The second part is transferred
the global stability and minimize the differential settlement to the piles through the geo-grid while the third part is supported
caused by consolidation (Sadok et al. [25]). directly on the soft soil layer and causes it to settle [30]. In order to
minimize the third part, van Eekelen [30] recommends that the
3.5.3. Embankments with vertical drains spacing between piles be kept at less than 2.5 m and that the min-
This technique is commonly used for thicker soft-top layers imum embankment height to be equal to 0.66 times the spacing.
(>9.0 m). It uses the same concept of consolidation described pre-
viously with one additional enhancement. Instead of waiting for
4. Methodology
the water to flow through the soft layer to the top or bottom sur-
face, which may take a considerable amount of time, a fast track
4.1. Estimating cost and construction duration for each alternative
vertical path is provided by using vertical sand drains or vertical
wick drains to direct the water from the top filter layer down to
In order to estimate the cost and duration (for construction) of
the permeable bottom layer (refer to Fig. 1c). This system consid-
each alternative, structural design must be carried out to deter-
erably speeds up the consolidation. The down side is that sand
mine the dimensions, specifications, and quantities of materials
drains cost almost as much as piles, while wick drains need special
used. The technical bases of this structural design are described
equipment and highly skilled labor to install [19]. Like pre-loading
for each alternative in Appendix A.
technique, two layers of geo-grid and one layer of geotextile are
used below the embankment.
4.2. Development of the decision support system (DSS) for optimum
3.5.4. Embankments on piles soft clay improvement technique of sloped embankments
This technique avoids loading the top soft layer altogether.
Instead, the loads from the embankment are transferred down to Selecting the optimum technique depends on many factors such
the supporting strata using piles. To achieve this goal without as the soft layer thickness, embankment height, existing highway
using a concrete raft, a combination of arching action in embank- constraints, as well as the characteristics of soft clay improvement
ment soil and tie action in geo-grid layers is utilized to form a technique. In this study, eight factors are considered to identify the

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
4 I.M. Mahdi et al. / Ain Shams Engineering Journal xxx (xxxx) xxx

optimum soft clay improvement alternative. These factors are: (1) to 12 m and using an embankment length equal to 100 m and
cost; (2) construction duration; (3) constructability; (4) sustain- thicknesses of the soft clay layer ranging from 1 m to 9 m. Hence,
ability; (5) environmental impact; (6) risk impact and safety; (7) the cost and duration for each case were calculated using the aver-
technology impact; and (8) infrastructure conflict. These eight fac- age current prices and productivity in the Egyptian market, which
tors are evaluated and ranked using the Delphi technique. are illustrated in Table 1. Those prices were collected from BOQ &
The DSS that combines AHP and Delphi for soft clay improve- Specifications department of (NECB) consultancy firm.
ment alternatives (SIA) with respect to all eight evaluation factors Based on the calculated values, the relative weights for both the
were conducted in one excel sheet for ease of use. The output of cost and the duration for each alternative were calculated for each
this (DSS) is relative weights (or scores) of each alternative for a combination of embankment height and thickness of clay layer.
certain combination of embankment height and thickness of the Tables 2 and 3 show the calculated weights for each alternative.
soft clay layer considering all eight evaluation factors. The alterna- Sample of the calculations is presented in Appendix B.
tive with the highest weight (score) is the optimum choice for that
combination.
5.2. Identifying the relative weights of the factors using the Delphi
technique
5. Applying the developed (DDS) on case of Egypt at present
conditions Eight Egyptian highway construction experts were involved in
this process with the following characteristics: two highway con-
The proposed methodology was applied to highway construc- sultant engineers with an experience of more than 20 years, two
tion projects in Egypt considering the present conditions such as heads of technical office of highway construction companies with
material prices, labor productivity and equipment availability. an experience of more than 15 years, two senior highway design
The details of the calculations are presented in the following engineers with an experience of more than 10 years, and two fac-
sections. ulty staff members at universities (one specialized in soil mechan-
ics and the other specialized in construction management) with an
5.1. Estimating cost and construction duration for each alternative experience of more than 20 years each. The experts were asked to
assess the four soft clay improvement techniques in terms of the
Quantities of each alternative were calculated using eight factors considered. These factors are: cost, construction dura-
Eqs. (1)–(17) (see appendix) for embankment heights from 1 m tion, constructability, sustainability, environmental impact, risk

Table 1
Considered unit price, number of crew, and crew productivity.

Item Unit Cost (LE)/Unit Crew productivity (/month) No. of crew Total productivity (/month)
Pavement (m2) 300 1200 2 2400
road base (m3) 100 4500 2 9000
Pitching (m2) 150 125 6 750
Embankment (m3) 200 4000 6 24,000
Replace./Filter (m3) 250 2000 6 12,000
Wick drain (m) 100 12,000 1 12,000
Geo-grid (m2) 100 7500 1 7500
Pile (m3) 8000 2500 1 2500
Indirect cost (/month) 200,000

Table 2
Samples of relative weights of soft clay improvement alternatives with respect to the cost factor.

Embankment height (m)


4m 8m 12 m
Alternative Soft clay thick.
3m 6m 9m 3m 6m 9m 3m 6m 9m
Embankment on Replacement 87% 64% 48% 90% 71% 59% 91% 76% 64%
Embankment with Pre-Loading 99% 85% 65% 100% 93% 82% 100% 96% 88%
Embankment with VL. drains 100% 99% 93% 99% 100% 100% 99% 100% 100%
Embankment on piles 90% 100% 100% 57% 64% 62% 39% 43% 44%

Table 3
Samples of relative weights of soft clay improvement alternatives with respect to the time factor.

Embankment height (m)


4m 8m 12 m
Alternative Soft clay thick.
3m 6m 9m 3m 6m 9m 3m 6m 9m
Embankment on Replacement 100% 85% 70% 100% 93% 79% 100% 100% 87%
Embankment with Pre-Loading 64% 35% 19% 73% 48% 29% 78% 60% 39%
Embankment with VL. drains 79% 70% 61% 83% 80% 73% 85% 89% 82%
Embankment on piles 95% 100% 100% 91% 100% 100% 86% 100% 100%

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
I.M. Mahdi et al. / Ain Shams Engineering Journal xxx (xxxx) xxx 5

impact and safety, technology impact, and infrastructure conflict. calculated for both factors. The results of the AHP are summarized
After collecting and analyzing the results, they were sent to the in Table 5. Sample of the calculations is presented in Appendix B.
experts for a second round. The results received showed some dis-
sent so a third round was necessary. The results of applying the 5.4. Mapping the optimum improvement technique using the
Delphi method for the considered eight factors are illustrated in developed (DSS)
Table 4. Sample of the calculations is presented in Appendix B.
Combining relative weights of each alternative with respect to
cost and duration with those of the remaining evaluating factors
5.3. Development of the analytical hierarchy process (AHP) model and triangulating them using the results of the Delphi methodol-
ogy for each combination of embankment height and soft clay
The AHP process was used as described in the previous section to layer thickness gives a clear map for the optimum choice of soft
estimate the relative weights of soft clay improvement alternatives clay improvement for any combination. This map is illustrated in
with respect to six of the eight evaluation factors: constructability, Table 6 and can be used by researchers or practitioners to deter-
sustainability, environmental impact, risk impact and safety, tech- mine the optimum method to choose in case of similar conditions
nology impact, and infrastructure conflict. The remaining factors to those in Egypt.
(cost and duration) were calculated depending on the respective
characteristics of each alternative since quantitative data could be 5.5. Varifiing the optimum improvement technique map
Table 4
Relative weights of evaluation factors using Del- The (DSS) optimum choices shown in Table 7 were selected
phi method. directly from Table 6 based on embankment height and thickness
Evaluation factors Relative weight
of soft clay layer and verified using case studies of highway pro-
jects under-construction in Northern Egypt where soft clay layers
Cost 41.5%
Construction duration 23.7%
are commonly encountered. (NECB) was the contractor’s consul-
Constructability 7.6% tant in the following four case studies:
sustainability 4.2%
Environmental impact 5.1%
(i) 30 June highway – Port Said; it is a new strategic highway
Risk impact and safety 5.9%
Technology impact 4.2% passes in the soft clay at Suez Canal zone. The embankment
Infrastructure conflict 7.6% at the considered section was 6.0 height (at crossing tunnel)
and was located on 32.0 to 35.0 m thick soft clay, the soil

Table 5
Relative weights of soft clay improvement alternatives with respect to evaluation factors.

Soft clay improvement alternative Constructability Sustainability Environmental Risk and Safety Technology Infrastructure
Alt.1 Embankment on Replacement 32% 32% 12% 32% 16% 30%
Alt.2 Embankment with Pre-Loading 38% 14% 34% 38% 14% 40%
Alt.3 Embankment with VL. drains 12% 16% 33% 12% 36% 12%
Alt.4 Embankment on piles 18% 38% 21% 18% 34% 18%

Table 6
Optimum soft clay improvement alternatives for different embankment heights and soft layer thickness.

REP: Embankment on replacement.


PRE: Embankment with pre-loading.
VL.: Embankment with vertical drains.
PILE: Embankment on piles.

Table 7
Case study results.

Project Embankment Soft clay Actual Soil (DSS) Soil


height (m) thickness (m) improvement technique used improvement technique
30 June highway – Port Said (14 + 400 to 21 + 450) 6.0 >30 VL. VL.
Port Said-Damietta highway At Ashtom El-Gamil City 4.0 >30 PILE PILE
Banha-El Mansoura highway At Kafr-Shokr (45 + 500) 5.5 9.0 REP. PILE
Zagazeg – Elsemballawen highway (19 + 800 to 21 + 400) 5.0–8.0 2.0–4.5 REP. REP.

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
6 I.M. Mahdi et al. / Ain Shams Engineering Journal xxx (xxxx) xxx

report suggested both pre-loading and vertical drains tech- ment height between (3.0–12.0 m). This mapping leads to the
niques to improve the soft layer and the contractors (DETAC following findings:
Co. & Misr Delta Co.) chose the vertical drains techniques.
(ii) Port Said-Damietta highway; the location was at the approach  For thin soft soil layers (3.0–4.0 m thick), replacement is the
of Ashtom-Elgamil bridge near Port-Said. Embankment optimum choice regardless of embankment height. This makes
height was 4.0 m and rested on 26.0 m of soft clay. Both con- sense because it eliminates any negative impact of soft soil lay-
sultant and contractor (EL-Safa Co.) agreed to use piles option. ers at a reasonable cost and with little impact on time and
(iii) Banha-El Mansoura highway; the considered zone was the constructability.
approach of new bridge at Kafr-Shokr village, approach  For soft clay layers thicker than 4.0 m, the embankment height
height was 5.5 m and rested on 9.0 m of soft clay. Both has a greater significance on deciding the optimum soft clay
replacement and piles techniques were suggested in the soil improvement technique. In case of lower embankment heights
report and the contractor (SAMCO) chose the replacement (up to 5 m), embankment on piles technique is the most suit-
alternative. able choice. This result is reasonable because the relatively
lightweight embankment significantly reduces the cost of piles.
(iv) Zagazeg – Elsemballawen highway, this project aims to dou-
On the other hand, for thicker embankments (more than 5 m),
ble the width of the existing highway, the embankment
the best choice for soft clay improvement is the vertical drains
height was varied between 5.0 m in typical sections and
technique. This result is logical because this technique is much
8.0 m at crossing tunnels, that soft clay layer thickness was
cheaper than piles and a noticeable reduction in indirect cost is
about 2.0 to 4.5 m and the contractor was El-Salam Interna-
also realized by avoiding the longer construction duration
tional Co. which carried out the recommended replacement
required for a piled alternative.
layer as per soil report.
 Embankment with pre-loading is the optimum choice for a lim-
ited range of conditions. For thicknesses of the soft clay layer in
Case studies locations are shown in Fig. 2. Real recommended
the 3.0–4.0 m range and embankment heights of more than
improvement techniques were collected by the authors from their
9.0 m, this technique is suitable. This is because the relatively
consulting work. Verification results shows good matching between
long time required to construct the high embankment is suffi-
the actual chosen soft clay improvement technique and the pro-
cient to consolidate the relatively thin soft clay layer, which
posed optimum technique calculated by the (DSS). The improve-
minimizes the indirect cost of the project.
ment technique recommended in real-life matched the technique
calculated using the (DSS) in three out of four of the projects.
It should be noted that these findings are based on the relative
weights, prices, and rates of productivity that are used in the DSS.
6. Verification results and discussion This makes the findings valid for highway construction projects in
Egypt in the current (2018) market conditions and the boundaries
Table 6 summarized the results of applying the developed (DSS) between alternatives will shift with changes in the weights and
considering the present conditions in Egypt. It covers all combina- market conditions.
tions of soft clay thickness between (1.0 to 9.0 m) and embank-

Fig. 2. Locations of case studies in north of Egypt.

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
I.M. Mahdi et al. / Ain Shams Engineering Journal xxx (xxxx) xxx 7

7. Conclusions ment with a top width (B top), length (L embankment), slope


height (H slope), and replacement thickness (H rep.), the following
The conclusions of this research could be summarized as quantities may be calculated as follows:
follows:
Pavement area ðm2 Þ
 Using the (AHP) along with the Delphi technique allowed cap- ¼ ðBtop  2:0ÞL embankment ð1Þ
turing tacit and implicit knowledge through the use of a combi-
nation of calculations and expert opinion. Base layer volume ðm3 Þ
 The developed (DSS) needs surveying for market prices and ¼ 0:35  B top  L embankment ð2Þ
expert opinions to be tuned for certain country/region and cer-
tain market conditions Embankmentvolume ðm3 Þ
 Applying the tuned (DSS) on a range of soft clay thicknesses in ¼ L embankment  H slope ðB top þ 2 H Þ ð3Þ
combined with a range of embankment heights produces a map
for the optimum improving technique.
Slope pitching area ðm2 Þ
 The generated map of optimum improving technique is accu-
rate only for the considered country/region and market ¼ ð4:5 H slope þ 4:0Þ:L embankment ð4Þ
conditions
 The optimum improving technique could be selected directly Required land area ðm2 Þ
from the generated map based on thickness of soft clay and ¼ ðB top þ 4 H slope þ 2 H repÞ:L embankment ð5Þ
embankment height without any farther calculations of cost
and time because they are already estimated for each combina- In addition to these quantities that are common to all alterna-
tion during generating the map. tives, additional quantities should be calculated based on the
 The tuned (DSS) for Egypt in current market conditions was suc- specific soft clay improvement technique as shown in the follow-
cessfully applied and verified using four highway construction ing section.
projects.
A. Embankment on soil replacement
This research was concerned in sloped embankments only
where is no restriction on bottom embankment width. For farther Volume of replacement ðm3 Þ
studies, the same (DSS) technique could be used select the opti- ¼ ðRequired land areaÞ  ðH repÞ ð6Þ
mum retaining system for restricted sites highway projects.
B. Embankment with pre-loading
Appendix A. (Technical bases for geotechnical design)
Filter thickness ðmÞ ¼ H clay=6 ð7Þ
Generally, the design of the highway embankment itself does
not depend on the soft clay improvement technique as long as 2
Consolidation time ðmonthÞ ¼ H clay =3 ð8Þ
the minimum embankment height required in the piled technique
is observed. Hence, this part of design is common for all alterna- Geotextile area ðm2 Þ ¼ Required land area ð9Þ
tives. The compacted soil of embankment is usually specified as
non-plastic granular soil (Class A-1 & A-2) according to the Geo  grid area ðm Þ ¼ 2  Required land area
2
ð10Þ
AASHTO classification [20]. The safe embankment side slope
C. Embankment with vertical drains
depends on the unit weight of the soil and its shear strength
parameters. Generally for the previously mentioned AASHTO
Total wick drain length ðmÞ
classes, the unit weight ranges from 1.8 to 2.2 t/m3, the angle of
internal friction ranges between 36° and 40°, and cohesion ¼ 0:25 ðRequired land areaÞ  ðH clay þ Hrep:Þ ð11Þ
strength ranges between 0.0 and 5.0 t/m2, Bowles [1]. Accordingly,
Consolidation time ðmonthÞ ¼ H clay=3 ð12Þ
the side slope ranges between 2V:3H and 1V:2H depending on soil
type and embankment height.
D. Embankment on piles
Side slopes must be protected against erosion; usually 40 cm
thick pitching or 15 to 20 cm lean concrete is used [2]. Road base In order to estimate the quantities parametrically, the ultimate
and pavement are constructed on the top surface of the embank- pile capacity was estimated based on standard penetration test
ment. The base layer is usually built of crushed stone with depth values (N30),[18]. Considering (N30) for the dense granular soil
depending on the structural design of the roadway pavement. Traf- equals to 50, bearing strength reduction factor for board piles
fic load on the road are provided by applicable design code but may equals to 7, and safety factor equals 2.0, the allowable working
be approximately taken as 2.0 t/m2 [12]. load of pile with diameter (D) and stock length (L stock) could be
Common values of pavement layers and embankment soil calculated as follows:
parameters were considered in this study. These parameters are
as follows: (i) thickness of base layer = 0.35 m; (ii) thickness of PilecapacityðtonÞ ¼ 133D2 þ 15:7D  Lstock ð13Þ
asphalt pavement = 0.15 m; (iii) unit weight = 2.0 t/m3; (iv) angle Maximum pile load could be calculated as follows considering
of internal friction = 38°; and no cohesion (Yang 2004). Based on spacing of 2.5  2.5 m:
the previous parameters, in order to achieve an acceptable safety
Pile Load ðtonÞ
factor of 1.5 against slope failure, the side slope angle should not
exceed 27.5°, which is equivalent to a slope of (1V:2H) [6]. ¼ 2:5  2:5  2:0  H slope ¼ 13:5 H slope ð14Þ
Considering a 1.0 m width sidewalk on each side of the roadway From Eqs. (13) and (14), and assuming that (D ¼ Hslope=18),
and a side slope protected with 0.4 m thick pitching with 1.0 m then stock length (L stock) equals (0.4 H slope) and total pile length
width flat toe at top and bottom of slope. Hence, for an embank- equals to (L stock + H clay):

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
8 I.M. Mahdi et al. / Ain Shams Engineering Journal xxx (xxxx) xxx

2
Pile volume ðm3 Þ ¼ H slope  ðL stock þ H clayÞ=400 ð15Þ B. Sample of Cost and Time Calculations:
Time and cost for the previously calculated BOQ could be calcu-
Total volume of piles ðm Þ 3
lated using the unit prices and productivity rates listed in Table 1
¼ Pile volume  Required land area=6:25 ð16Þ as follows:
For embankment on soil replacement
Regarding the two layers of geo-grid, they area could be calcu-
lated considering 50% lap as follows:
Item Cost (LE) Time (month)
Geo  grid Area ðm2 Þ ¼ 1:5  2  Required land area ð17Þ
Pavement 1800  300 1800/2400
Eqs. (1)–(17) were used to calculate the quantities and duration = 540 000 = 0.75
needed for each alternative. The Application section provides the Base layer 700  100 700/9000
steps taken and a discussion of the steps for the proposed DSS. = 70 000 = 0.08
Embankment 11200  200 11 200/24 000
Appendix B. (Sample of DSS Calculations) = 2 240 000 = 0.47
Slope pitching 2200  150 2200/750
A. Sample of BOQ Calculations: = 330 000 = 2.93
The BOQ of different alternatives for embankment length, Replacement 12600  250 12 600/12 000
height and top width of 100.0 m, 4.0 m and 20.0 m respectively = 3 150 000 = 1.05
with side slopes of 1V:2H rested on 3.0 m thick soft clay layer Site preparation – 4200/4200
could be calculated as follows: = 1.0
Indirect cost 6.3  200 000 –
= 1 260 000
Pavement area (m2) Total 7 590 000 6.30
= ð20:0  2:0Þ  100:0 = 1800
Base layer volume (m3)
= 0:35  20:0  100:0 = 700 For embankment with pre-loading
Embankment volume (m3)
= 100:0  4:0  ð20 þ 2  4:0Þ = 11200 Item Cost (LE) Time (month)
Slope pitching area (m2) Pavement 1800  300 1800/2400
= ð4:5  4:0 þ 4:0Þ  100:0 = 2200 = 540 000 = 0.75
For embankment on soil replaceement (H rep = 3.0 m) Base layer 700  100 700/9000
Required land area (m2) = 70 000 = 0.08
= ð20:0 þ 4  4:0 þ 2  3:0Þ  100 = 4200 Embankment 11 200  200 11 200/24 000
Volume of replacement (m3) = 2 240 000 = 0.47
= 4200  3:0 = 12600 Slope pitching 2200  150 2200/750
For embankment with pre-loading (H rep = 0.5 m) = 330 000 = 2.93
Filter thickness (m) = 3:0=6 = 0.5 Filter 1850  250 1850/12 000
Required land area (m2) = 462 500 = 0.15
= ð20:0 þ 4  4:0 þ 2  0:5Þ  100 = 3700 Site preparation – 3700/4200
Filter volume (m3) = 3700  0:5 = 1850 = 0.88
Consolidation time (month) = 3:02 =3 = 3.0 Geotextile 3700  100 3700/7500
Geotextile area (m2) = 3700 = 3700 = 370 000 = 0.50
Geo-grid area (m2) = 2  3700 = 7400 Geo-grid 7400  100 7400/7500
For embankment with vertical drains (H rep = 0.5 m) = 740 000 = 1.00
Filter thickness (m) = 3:0=6 = 0.5 Consolidation time – 3.0
Required land area (m2) Indirect cost 9.76  200 000 –
= ð20:0 þ 4  4:0 þ 2  0:5Þ  100 = 3700 = 1 952 000
Filter volume (m3) = 3700  0:5 = 1850 Total 6 704 500 9.76
Geotextile area (m2) = 3700 = 3700
Geo-grid area (m2) = 2  3700 = 7400
Consolidation time (month) = 3:0=3 = 1.0 For embankment with vertical drains
Total wick drain length (m)
= 0:25  3700  ð3:0 þ 0:5Þ = 3238 Item Cost (LE) Time (month)
For embankment on piles (H rep = 0.0 m)
Required land area (m2) Pavement 1800  300 1800/2400
= ð20:0 þ 4  4:0 þ 2  0:0Þ  100 = 3600 = 540 000 = 0.75
Pile Diameter (D) (m) = 4:0=18 = 0.22 Base layer 700  100 700/9000
Stock length (L stock) (m) = 0:4  4:0 = 1.60 = 70 000 = 0.08
Pile length (m) =Max½10mOrð1:6 þ 3:0Þ = 10.0 Embankment 11 200  200 11 200/24 000
3 2 = 2 240 000 = 0.47
Pile volume (m ) = 0:785  0:22  10:0 = 0.38
Slope pitching 2200  150 2200/750
Total volume of piles (m3) = 0:38  3600=6:25 = 219
= 330 000 = 2.93
Geo-grid Area (m2) = 1:5  2  3600 = 10800
Filter 1850  250 1850/12 000
= 462 500 = 0.15

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
I.M. Mahdi et al. / Ain Shams Engineering Journal xxx (xxxx) xxx 9

(Sample of DSS Calculations) (continued) Relative weight of VL. drains alternative


= 6.3/8.0 = 0.79
Item Cost (LE) Time (month)
Relative weight of Emb. on piles alternative
Site preparation – 3700/4200 = 6.3/6.6 = 0.95
= 0.88 D. Sample of Calculations for Alternatives Relative Weights
Geotextile 3700  100 3700/7500 with Respect to rest of considered factors (Tables 4 and 5):
= 370 000 = 0.50
Geo-grid 7400  100 7400/7500 Relative weights of considered factors shown in Table 4 were
= 740 000 = 1.00 calculated by applying (AHP) on the questioner results. The 1st
Consolidation time – 1.0 request in the questioner is to evaluate the importance of consider
wick drain 3238  100 3238/12 000 factor from 1 for less important to 10 for most important. In the
= 323 800 = 0.27 3rd round, the evaluations were settled and the average evaluation
Indirect cost 8.0  200 000 – for the considered factors were 9.80, 5.60, 1.80, 1.00, 1.20, 1.40,
= 1 600 000 1.00 and 1.80 for cost, construction duration, constructability,
Total 6 676 300 8.0 sustainability, environmental impact, risk impact and safety,
technology impact, and infrastructure conflict respectively.
Accordingly, the relative weight of certain factor is the ratio
For embankment on piles between its evaluations to the sum of the evaluations. For example,
the relative weight of cost is 9:8=ð9:80 þ 5:60 þ 1:80 þ 1:00þ
Item Cost (LE) Time (month) 1:20 þ 1:40 þ 1:00 þ 1:80Þ ¼ 0:463
Similar approach was used to estimate the relative weights of
Pavement 1800  300 1800/2400
each improvement technique with respect to considered factors.
= 540 000 = 0.75
The 2nd request in the questioner is to arrange the four alterna-
Base layer 700  100 700/9000
tives from 1 for less favorable to 4 for most favorable alternative
= 70 000 = 0.08
with respect to each considered factor regardless cost and duration
Embankment 11200  200 11 200/24000
which relative weights could be calculated from BOQ. For example,
= 2 240 000 = 0.47
the average evaluations of alternatives with respect to con-
Slope pitching 2200  150 2200/750 = 2.93
structability were 3.2, 3.8, 1.2 and 1.8 for Replacement, Pre-
= 330 000
loading, Vertical drains and embankment on piles respectively,
Site preparation – 3600/4200
hence, the relative weight of replacement alternative with respect
= 0.86
to constructability is 3:2=ð3:2 þ 3:8 þ 1:2 þ 1:8Þ ¼ 0:32
Geo-grid 10800  100 10 800/7500
= 1 080 000 = 1.44
E. Sample of Alternative Score Calculations (Table 6):
Piles 219  8000 219/2500
= 1 752 000 = 0.09
The optimum soft clay improvement technique for certain
Indirect cost 6.6  200 000 –
embankment height on a certain soft clay thickness is the alternative
= 1 320 000
with highest score. Those optimum alternatives were mapped in
Total 7 332 000 6.6
Table 6 for embankment height ranged between 3.0 and 12.0 m
and soft clay thickness ranged between 1.0 and 9.0 m. The score of
each alternative is the sum of multiplied factor relative weight from
C. Sample of Calculations for Alternatives Relative Weights Table 4 by corresponding alternative relative weight from Tables 2, 3
with Respect to Cost & Time (Tables 2 and 3): and 5. For example, the scores of the four alternatives in case of 4.0 m
embankment height on 3.0 m soft clay thickness are:
Relative weights of alternatives shown in the 1st column of
Table 2 could be calculated as the ratio between minimum cost
to alternative cost as follows:

Relative weight of Replacement alternative


= 6 676 300/7 590 000 = 0.87 Total
Relative weight of Pre-loading alternative
= 6 676 300/6 704 500 = 0.99 Similarly, the score of Pre-loading, VL. Drains and Embankment
Relative weight of VL. drains alternative on piles are 0.674, 0.666 and 0.678 respectively. Accordingly,
= 6 676 300/6 676 300 = 1.00 Replacement is the optimum alternative for this case.
Relative weight of Emb. on piles alternative
= 6 676 300/7 332 000 = 0.90 F. Results of case study (Table 7):

Similarly, the relative weights of alternatives shown in the 1st The optimum improvement techniques for each of four cases in
column of Table 3 could be calculated as the ratio between mini- Table 7 were selected directly from Table 6 based on the embank-
mum duration to alternative duration as follows: ment height and soft clay thickness.

Relative weight of Replacement alternative


= 6.3/6.3 = 1.00 Appendix C. (Samples for the expertise questioners)
Relative weight of Pre-loading alternative
= 6.3/9.76 = 0.64 See Fig. 3.

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
10 I.M. Mahdi et al. / Ain Shams Engineering Journal xxx (xxxx) xxx

Fig. 3. Samples for the expertise questioners.

References [5] Cooke J. Improving the value of products and processes by combining value
analysis techniques and lean methods with TRIZ. In: TRIZ FUTURE
CONFERENCE – Global Innovation Convention. p. 2.
[1] Bowles J. Foundation analysis and design. 5th ed. New York, NY, USA: McGraw-
[6] Das B. Advanced soil mechanics. New York, NY, USA: Taylor & Francis; 2008.
Hill; 1997.
[7] Dell’lsolla AJ. Value engineering: Practical Applicationsfor Design,
[2] Brockenbrough R. Highway engineering handbook: building and rehabilitating
Construction, Maintenance and Operation, 1997. Kingston, USA: R.S.Means;
the infrastructure. 3rd ed. The McGraw-Hill Companies; 2009.
1998.
[3] Chavan AJ. Value engineering in construction industry. Int J Appl Innov Eng
[8] Gudem M, Steinert M, Welo T, Leifer L. Redefining customer value in lean
Manage 2013;2(12):18–26.
product development design projects. J Eng, Des Technol 2013;11(1):71–89.
[4] Chen WT, Chang PY, Huang YH. Assessing the overall performance of value
[9] Hallowell MR, Gambatese JA. Qualitative research: Application of the Delphi
engineering workshops for construction projects. Int J Project Manage 2010;28
method to CEM research. J Constr Eng Manage 2010:99–107. doi: https://doi.
(5):514–27.
org/10.1061/(ASCE)CO.1943-7862.0000137.

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
I.M. Mahdi et al. / Ain Shams Engineering Journal xxx (xxxx) xxx 11

[10] Ismail A, Aminzadeh R, Aram A, Arshad I. Science publications value Ibrahim Mahmoud Mahdi is a Professor of Project
engineering application in highway projects applying lean thinking in Management at the Future University in Egypt. He
construction and performance improvement. Am J Eng Appl Sci 2010;3 received his Ph.D. from University of Southampton,
(4):699–703. England UK. Dr. Mahdi has over 30 years of professional
[12] Kezdi, A. Stabilized earth roads. Copyright (r) by Akademiai Kiado, Budapest, experience in all project management aspects including
Hungary; 1979. Planning; Cost a, Risk management and Project Control.
[13] Khallaf R, Naderpajouh N, Hastak M. A systematic approach to develop risk He has been responsible for many assignments of highly
registry frameworks for complex projects. Built Environ Project Asset Manage technical projects in Egypt, Kuwait and Gulf area espe-
2018. doi: https://doi.org/10.1108/BEPAM-08-2017-0051. cially KSA and UAE. His experience includes Preparing
[14] Li F, Phoon KK, Du X, Zhang M. Improved AHP method and its application in
tender’s packages; receiving and analyzing tenders,
risk identification. J Constr Eng Manage ASCE 2013;139:312–20.
making consultant and contractor recommendations,
[15] Liang R, Pensomboon G. Multicriteria decision-making approach for highway
slope hazard management. J Infrastruct Syst 2010;16:50–7. issuing, executing and administering contracts; and
[16] Male S, Kelly J, Gronqvist M, Graham D. Managing value as a management finally, supervising the construction to insure quality and schedule requirements
style for projects. Int J Project Manage 2007;25(2):107–14. are met Dr. Mahdi has wide work experience in education and practicing project
[17] Nawi MM, Jalaluddin SMFWS, Zulhumadi F, Ibrahim JA, Baharum F. A strategy management.
for improving construction projects sustainability through value management
approach. Int J Appl Eng Res 2014;9(24):28377–85.
[18] NAVFAC DM-7.02 (Naval Facilities Engineering Command) (1986). Found Ahmed M. Ebid is an Assistant Professor at the Future
Earth Struct.; 1986. University in Egypt. He received his Ph.D. in soil
[19] Nicholson P. Soil improvement and ground modification methods. Elsevier Inc; mechanics from Ain-Shams Uni.-Egypt 2004. He is a
2015. consultant in both geotechnical engineering and
[20] Nikolaides A. Highway engineering pavements, materials and control of designing concrete structures since 2012, He published
quality. Ó 2015 by Taylor & Francis Group, LLC; 2015. 14 researches in geotechnical engineering, soil
[21] Okoli C, Pawlowski SD. The Delphi method as a research tool: an example,
mechanics, repairing using FRP and optimizing the
design considerations and applications. Inform Manage 2004;42:15–29.
design of concrete elements.
[22] Palmer A, Kelly J, Male S. Holistic appraisal of value engineering in
construction in United States. J Constr Eng Manage 1996;122(4):324–8.
[23] Parker DE. Value engineering theory. Washington, D.C: Lawrence D. Miles
Value Foundation; 1985. p. 62–4.
[24] Perera S, Hayles CS, Kerlin S. An analysis of value management in practice: the
case of Northern Ireland’s construction industry. J Finan Manage Property
Constr 2011;16(2):94–110.
[25] Benmebarek Sadok, Berrabah Fouad, Benmebarek Naïma. Effect of
geosynthetic reinforced embankment on locally weak zones by numerical Rana Khallaf is an Assistant Professor at the Structural
approach. Comput Geotech 2015;65:115–25. and Construction Management Department, Faculty of
[26] Saaty TL. The analytic hierarchy process and the analytical network process: Engineering and Technology, Future University in Egypt
planning, priority setting, resource allocation. New York, USA: McGraw-Hill; (FUE). Dr. Rana has over 7 years of experience working
2003.
in Egyptian and American companies in the field of
[27] Saaty TL. Decision making with the analytic hierarchy process. Int J Serv Sci
construction project management consulting. She has
2008;1(1).
[28] SAVE International. Value methodology standard and body of knowledge also previously cofounded a Project Management Con-
Retrieved 2012, January 10 from http://www.value-eng.org, ; 2007. sultancy, which served US-based projects. She received
[29] Sourani A, Sohail M. The Delphi method: review and use in construction her PhD in Civil Engineering (Specialization: Construc-
management research. Int J Constr Edu Res 2015;11(1):54–76. doi: https://doi. tion Engineering and Management) from Purdue
org/10.1080/15578771.2014.917132. University in the United States. She then worked as a
[30] van Eekelen S. Basal Reinforced Piled Embankments Experiments, field studies Lecturer at Purdue University before joining the Future
and the development and validation of a new analytical design model Ph.D University in Egypt. Prior to that, she received her Bachelors and Masters degrees
thesis. Technische Universiteit Delft; 2015. from Ain shams University. She is active in research and her current interests
[31] Wahls H. Design and construction of bridge approaches. Transport Res Board include: Public-private partnerships, Integrated project delivery, Game theory, Risk
Natl Res Council 1990. analysis, Disaster risk reduction, as well as other contemporary topics.
[32] Xia B, Chan APC, Yeung JFY. Developing a fuzzy multicriteria decision-making
model for selecting Design-Build operational variations. J Constr Eng Manage
2011;137(12):1176–84.

Please cite this article as: I. M. Mahdi, A. M. Ebid and R. Khallaf, Decision support system for optimum soft clay improvement technique for highway con-
struction projects, Ain Shams Engineering Journal, https://doi.org/10.1016/j.asej.2019.08.007
View publication stats

You might also like