You are on page 1of 8

International Journal of Mining Science and Technology 26 (2016) 753–760

Contents lists available at ScienceDirect

International Journal of Mining Science and Technology


journal homepage: www.elsevier.com/locate/ijmst

Mine production index (MPI)-extension of OEE for bottleneck detection


in mining
Amol Arun Lanke ⇑, Seyed Hadi Hoseinie, Behzad Ghodrati
Division of Operation and Maintenance Engineering, Luleå University of Technology, Luleå 97752, Sweden

a r t i c l e i n f o a b s t r a c t

Article history: Although mining production depends on various equipments, significant amount of production loss can
Received 30 November 2015 be attributed a specific equipment or fleet. Bottleneck is defined not only by production loss but also by
Received in revised form 10 January 2016 our satisfaction from the equipment. The user satisfaction could be measured as machine effectiveness.
Accepted 18 March 2016
Mining literatures on performance improvement and optimization of equipment operations assert
Available online 20 June 2016
importance of availability, utilization and production performance as key parameters. These three param-
eters are useful for evaluating effectiveness of equipment. Mine production index (MPI), which can rep-
Keywords:
resent the effect of these factors, has been applied for continuous operation in mining. MPI uses Fuzzy
Mine production index
Bottleneck seeking
Delphi Analytical Hierarchy Process to determine importance of each three parameter for individual
FDAHP equipment. A case study in a Swedish open pit mine was done to evaluate the field application of MPI.
Production analysis The results reveal that crusher is the bottleneck equipment in studied mine. As a methodical approach,
an algorithm which uses MPI and detects bottleneck in continuous mining operation has been proposed.
Ó 2016 Published by Elsevier B.V. on behalf of China University of Mining & Technology.

1. Introduction which detect the performance of equipment and connect it to rea-


son of specific factors are a few in mining researches. The proposed
Mining is a complex process; output in mining is affected by study aims to detect the bottleneck in core mining operations. It is
various uncertainties relative to operation, management, and envi- also essential to know which uncertainty is leading cause of bottle-
ronment. Production assurance and thus business objective is a neck. In order to have better improvement, the origin of uncertain-
combined effect of these parameters in mining. It is a complicated ties are also needed to be known.
task to evaluate and analyse all these elements without a struc- The overall equipment effectiveness (OEE) has been used for
tured methodology. system performance measurement in various industries including
Demand for mining products increases every year as the world in mining. Equipment with lower OEE is bottleneck in terms of
moves towards more industrialisation [1]. This phenomenon effectiveness of equipment. However since OEE has limitations to
pushes mining industry to produce more and more and prompts overcome these limitations, a new measure termed as MPI was
need to locate the lagging operations. In order to initiate improve- developed and tested for shovels performance in a mining opera-
ment it is necessary to follow a methodical approach which consid- tion [2,3]. The core questions which will be answered in this study
ers the dynamic situation in mining operations. Generally, the are:
limitation causing loss of production traces back to one or two
equipment/operation. These are commonly called as bottlenecks. (1) How MPI can help to locate the bottleneck in mining
Bottleneck from the classic system perspective is the point in sys- operations?
tem which slows down the whole operation. However, in advanced (2) How the analysis of MPI can be further used for identifying
and complex systems bottleneck could be defined as the point the underlying cause of bottleneck formation?
which reduces the system effectiveness and management’ satisfac-
tion from operation or machineries. One of the advantages of The article is structured as follows: literature review section
detecting bottlenecks is that once the bottleneck is detected, focus which reviews the elements of availability, utilization and perfor-
on system improvement becomes easier. Methodical approaches mance efficiency. These elements contribute to effectiveness of
mining equipment. Methodology section gives depth idea about
MPI development and its application. Case study section involves
⇑ Corresponding author. Tel.: +46 920491586.
analysis of the trucks, shovel and crusher for determining the bot-
E-mail address: amol.lanke@ltu.se (A.A. Lanke).

http://dx.doi.org/10.1016/j.ijmst.2016.05.050
2095-2686/Ó 2016 Published by Elsevier B.V. on behalf of China University of Mining & Technology.
754 A.A. Lanke et al. / International Journal of Mining Science and Technology 26 (2016) 753–760

tleneck in a Swedish open pit mine. Once after identification of root cause analysis and chronic failures in all mine equipment. This
bottleneck, we discuss about the method and characteristics which alternative method of analysis includes logarithmic scatterplots
could be involved in formation of this bottleneck. In the final part, [14]. The case study explored uses measures such as downtime
concluding remarks and improvement potential is presented. and failures of shovel. Hall and Daneshmend have discussed that
equipment reliability is key factors in loss of production and con-
cluded that using reliability analysis technique will be crucial in
2. Literature review determining which part or equipment is cause of competitiveness
loss [15].
2.1. Bottleneck seeking and equipment improvement methods in A model built with production capacity constraint along with
mining industry geological uncertainties by Dimitrakopoulos and Ramazan [16].
The authors claim that the model supposed to produce an optimal
Based on the observation from literature in mining the perfor- mining schedule which could meet the performance criteria.
mance of each equipment used in mining operation is typically Simulation model for a Turkish coal mine, which considered
analysed in isolation. Very little consideration is given for its effect loaders, crusher and conveyer belts, has been demonstrated [17].
on either downstream or upstream processes. However in practical In this study equipment capacity, velocity and performance figures
situation any optimization using such assumption would not be were used to determine the bottleneck operation. Ore storage sim-
useful. In this literature review, article tried to review methodolo- ulation which when subjected to different conditions, determines
gies and techniques which consider multiple equipment in mining the bottleneck in mining downstream [18]. This simulation shows
system and propose common method to improve. These methods that considering the excavation and processing capacities, either
consider either partial continuous operations. mine delivery system or concentrator plant can be bottleneck. Lin-
Simulation has been demonstrated to assess the performance of ear programming and simulation model for truck, shovel and
transport system in mining industry [4]. This study’s conclusion crusher show that crusher is bottleneck in system [19]. In order
ranking of equipment has been given by comparison. The equip- to evaluate the performance of each equipment criteria used were
ment ranking was done by balance of cost and performance for capacity, utilization of equipment and fleet size.
mining system. This is one of the earlier methods for selecting In conclusion of literature review, it can be said that: to detect
the best equipment for better production. and remove the bottleneck in mine operations, researchers have
Analysis of Kiruna iron ore mine for determining the bottleneck stressed need to evaluate equipment availability, utilization and
considering system aspect was done by Huang [5]. The study was production performance. Various models and methods use this
able to determine the optimal fleet size along with improvement type of data to achieve the higher productivity and operation anal-
in ore quality suggestions. ysis. There has been huge research on individual equipment
Boulder size and its effect to determine the bottleneck opera- improvement, however, researchers which consider multiple
tion have been showed in literature by Kumar [6]. Study revealed equipment in mining, for bottleneck seeking and elimination is
that an ore pass gate becomes bottleneck in system when the boul- scarce.
der size is out of limit. It also shows the boulder size result of from The effort with this study is to propose methodology which can
various other processes in operation. be used for bottleneck detection in mining and can be applied to
A method to analyse the maintenance data and reliability to most of the equipment in mining operation. For this purpose, based
determine the failure trends for all underground mining equip- on the literature, three main parameters used in OEE, namely avail-
ment have been shown in study by Vagenas et al. [7]. This study ability, utilization and production performance, have been
uses MTTR and MTBF data to carry out analysis underlining impor- selected. OEE has been used in many industries as a point of refer-
tance of availability as metric to determine effective equipment. ence to measure the performance. However for mining industry
Bottleneck can be determined by the theory of constraints. How- the traditional OEE cannot be used as it is. The limitation of OEE
ever bottleneck seeking would require not only hard (data driven) as a metric for mining industry is explained further following
but also soft (interviews and questionnaires) as proposed by Pau- terms.
ley and Ormerod [8]. In this direction Çelebi used equipment eval- Quality parameter in traditional OEE is ratio of processed pieces
uation model, which was bounded by various constraints such as and defective pieces. In mining industry such distinction is not
diggability, number of passes, and production amount [9]. possible to use. The defective ore or unusable ore is usually the
Simulation of surface mining system which includes shovels, waste, which is eliminated during the operation. The remaining
trucks, drilling machine and employees was carried out by Charl- ore is always processed to give the required final product. Consid-
ton [10]. Study shows that with little assumption, measurement ering this limitation a modified OEE equation for mining was
of time spent on various resources and operations, how the perfor- developed where quality rate is replaced by the utilization of
mance can be improved. The focus of case study was effect of over- equipment [21].
burden, resources and coal seams on the total mine production Depending upon the delivery schedule, types and number of
prediction. available machine, age of machinery and production performance
High productivity of mining equipment is based upon availabil- can change. Studies on truck optimization for mining have shown
ity, maintainability and reliability analysis of the equipment as that cycle time for truck is important. The cycle time for trucks
show in a study by Paraszczak [11]. Study was also able to show involves time spent in loading, hauling, dumping, standby time.
that how the data collection and analysis can be used to achieve Since the main purpose of shovel operation is to move material,
high productivity. Discussion on data analysis to determine equip- the payload and digging rate are key performance measures. Total
ment availability, utilization and production performance can help above mentioned parameters and restrictions affect the production
mine to achieve expected returns [12]. The study concluded that performance. To take account for these considerations it is neces-
mines should move from reactive maintenance practices to proac- sary to modify the OEE equation for mining applications. For exam-
tive maintenance practices with analysis of such data. ple the payload or capacity factor for shovel can directly relate to
In equipment selection process, one of the criteria is productiv- performance efficiency in equation rather than availability of sho-
ity, which is influenced majorly by age and availability [13]. The vel. Cycle time requirement for truck can be directly attributed to
performance is key factor for productivity of equipment [13]. Alter- need of higher utilization. Equipment with high critically for per-
native methods to determine the failure priorities can facilitate formance index may be hampered in performance due to less
A.A. Lanke et al. / International Journal of Mining Science and Technology 26 (2016) 753–760 755

availability during the operation. Each mining equipment is crusher volume, material characteristics and speed of crusher
selected during mine design process for a specific purpose. [48–60].
Literature review in mining industry has specified components
which impacts equipment availability, utilization and production
performance. For the evaluation purpose, the availability, utiliza- 3. Methodology
tion and production performance defined by equations are pre-
sented in next part. Taking the mentioned operational constraints into considera-
tion, the OEE for mining application can be modified with introduc-
tion of weight for each factor. Since assigned weights can be
2.2. Basic definitions
applied to all equipment and can give impact of each factor on
entire mine production, it is termed as mine production index
2.2.1. Availability
(MPI). The MPI equation can be written as follows:
In presented index, the availability is taken into consideration
as the operational availability. Operational availability is ratio of MPI ¼ Availability
w1
 Utilization
w2 w3
 Performance ð5Þ
time of the equipment available for the operation to the total oper-
ational time [20]. Availability is calculated by Eq. (1) [21]: The main problem in clarifying the mentioned idea is to assign a
reasonable weight for each parameter (finding w1 to w3). For this
ðTH  DTÞ purposes, it was decided to use the experts’ opinions because there
Availability ¼ ð100Þ ð1Þ
TH is no mathematical or regression method to find this kind of
where TH is total available hours; and DT the downtime hours. unknown parameters in such equations. Multi-criteria decision
Assumed total hours are total calendar hours i.e. 24 h or what- making (MCDM) methods are powerful tools for solving this kind
ever which is decided by mine operation and production managers. of problems. Among the available MCDM methods, Fuzzy Delphi
Based on the literature, mining equipment availability is affected Analytical Hierarchy Process (FDAHP) was used.
by following factors: reliability of subsystems, time planning, In OEE measure, equipment with higher score is most effective
availability of spare parts, early detection of failure and environ- equipment and thus contributes most to system performance. Sim-
mental conditions [12,13,15,22–36]. ilarly MPI value can indicate not only effectiveness of equipment
but also contribution of equipment for overall mining system avail-
ability, utilization and production performance. Analysis of the fac-
2.2.2. Utilization
tor which mostly affects MPI will lead to find the root cause of
Utilization of mining equipment can be defined as the quotient,
detected bottleneck for that specific equipment.
expressed in hours, of the consumption within a specified period
In general, preferences in analytical hierarchy process (AHP) are
(e.g., year, month, day, etc.), and the maximum or other specified
assigned by linguistics variables. These terms can be imprecise and
demand occurring within the same period [37]. In other words, uti-
dubious for application and calculation. To deal with such fuzzi-
lization is the time consumed by an equipment for producing the
ness, AHP was appended by incorporating fuzzy characteristics
required tonnage production within available time and it is calcu-
and developed a new process known as FDAHP [61]. FDAHP thus
lated using Eq. (2) [21].
helps decision makers in dealing with imprecision and subjective-
 
TH  DT  SH ness in pair wise comparison easily. The FDAHP method provides a
Utilization ¼ ð2Þ structured framework for setting priorities using pair-wise com-
TH  DT
parisons that are quantified. As demonstrated by many research-
where SH is the standby hours (idle time). ers, FDAHP process has been used successfully in mining sector
The factors which affect the utilization of mining equipment are for example [62,63].
mine planning, production scheduling, location of equipment, General steps performed in this study for building the FDAHP
logistic planning, and idle time due to legislative/incidental rea- are as follow:
sons [12,16,38–46].
(1) Polling and interview by the experts: in this stage, the opin-
2.2.3. Production performance ions of the experts were asked by questioners using the
The performance of equipment can be defined as the ability of quantitative or qualitative parameters. It was asked from
an item to meet a service demand of given quantitative character- experts to mark the importance of each parameter in ques-
istics; this performance is based on the capability and availability tionnaires in a very simple way. In order to use the question-
of equipment [37]. The production performance is given by Eq. naires data in FDAHP method, for each importance level an
(3) [21]. intensity number from 1 to 9 was assigned. In total, 12 com-
  pleted questionnaires; five from industrial experts (from the
AP
case study mine) and seven academic experts were received.
Production performance ¼ THDTSH
ð3Þ
RC From the polling the importance levels were obtained for
availability, performance and utilization. For clarifying some
where AP is the total actual output by equipment; and RC the rated details in mine operation, the industrial experts were
capacity of the equipment. Production efficiency in terms of time interviewed.
can be given by Eq. (4) [47]. (2) Establishment of pair-wise comparison matrixes: in order to
  establish the main pair-wise comparison matrix using
APT
Production efficiency ¼ ð4Þ FDAHP method, it is essential to have comparison matrix
ATT
of parameters based on each expert’s opinion. For this pur-
where APT is the actual productive time; and ATT the actual total pose, according to questionnaires, a comparison matrix is
time. established for each machine view point of each expert’s
Based on the literature, production performance is affected by opinion.
following factors in mines: (1) shovel, including bucket capacity,
cycle time, bucket fill factor and operator/job efficiency; (2) trucks, Let C1, C2, . . ., Cn denote the set of elements, while aij represents
including capacity and cycle time; and (3) crushers, including a quantified judgment on a pair of elements Ci and Cj. The relative
756 A.A. Lanke et al. / International Journal of Mining Science and Technology 26 (2016) 753–760

importance of two elements is obtained from division rate of Ci on to a usual number) is based on geometric average method as Eq.
rate of Cj based on questionnaire. This yields an n  n matrix A as (14) [64]:
shown in Eq. (6). !1=3
Y
3
Wi ¼ xj ð14Þ
i¼1

In this research, major pair-wise comparison matrixes (Tables


ð6Þ 1–3) were established by the procedure described above and total
weights were determined. Total weights of all factors are listed in
Table 4.
Using the weights presented in Table 4, Eq. (5) can be built up
for each machine as presented in Eqs. (15)–(17).
(3) Establishment of major pair-wise comparison matrix: for
establishing of major pair-wise comparison matrix in Fuzzy MPIShovel ¼ A0:30  U 0:37  P 0:33 ð15Þ
Delphi method and calculation of the relative fuzzy weights
of the decision elements, three steps should be done as
follow: MPITrucks ¼ A0:28  U 0:41  P 0:30 ð16Þ

MPICrusher ¼ A0:24  U 0:36  P0:40 ð17Þ


(a) Computation of triangular fuzzy numbers (TFNs); ãij. In this
work, the TFNs (Fig. 1 and Eq. (7)) that represent the pes- where A is the availability; U the utility; and P the production per-
simistic, moderate and optimistic estimate are used to rep- formance. The flowchart for applying the MPI for bottleneck detec-
resent the opinions of experts about each parameter. tion is represented in Fig. 2. To have impact of decision made for
improvement sufficient time must be given for full implication.
aij ¼ ðaij ; dij ; cij Þ ð7Þ Considering such factor, authors recommend to evaluate the MPI
every three months.
aij ¼ Minðbijk Þ ðk ¼ 1; . . . ; kÞ ð8Þ
!1=k
Y
k
dij ¼ bijk ðk ¼ 1; . . . ; kÞ ð9Þ 4. A case study
k¼1

cij ¼ Maxðbijk Þ ðk ¼ 1; . . . ; kÞ ð10Þ For testing the applicability of MPI measure, a case study car-
ried out in a Swedish open pit mine operated in Sweden. For this
where aij 6 dij 6 cij is obtained from Eqs. (7)–(10); aij the lower purpose fleet of mine production chain consisted of machineries
bound; cij the upper bound; bijk the relative intensity of importance consists of shovels, dump trucks and crushers are studied. The size
of expert k between parameters i and j; and k the number of experts of fleet and basic operation data are presented as follows: they
in the decision making. have 4 shovels each with 40 m3 capacity; fleet of 31 trucks is pre-
(b) Following above outlines, a fuzzy positive reciprocal matrix sent; 21 trucks has rated capacities of 217 tonnes whereas remain-
A can be calculated [64]: ing 10 trucks has better capacity of 313 tonnes. The three crushers
e ¼ ½a
A ~ij ; ~ij  a
a ~ij  1; 8i; j ¼ 1; 2; . . . ; n ð11Þ present across the mine has average capacities of 7000 tonne/h.
The average loading cycle time is 2.3 min. Since the waste
or dumping sites are placed strategically along with crusher sites
2 3 the unloading time is also very low for these trucks. The dispatch-
ð1; 1; 1Þ ða12 ; d12 ; c12 Þ ða13 ; d13 ; c13 Þ
6
e ¼ 4 ð1=c ; 1=d12 ; 1=a12 Þ 7 ing of trucks is done manually with help of GPS system guiding the
A 12 ð1; 1; 1Þ ða23 ; d23 ; c23 Þ 5
trucks. The data for study is gathered for a period of five months in
ð1=c13 ; 1=d13 ; 1=a13 Þ ð1=c23 ; 1=d23 ; 1=a23 Þ ð1; 1; 1Þ 2013. This data included availability, performance and utilization
ð12Þ percentages. For shovels and trucks idle time and downtime data
are also considered. The total crusher processing and total shovel
(c) Calculation of relative fuzzy weights of the evaluation fac-
output were also collected. Trucks availability and utilization were
tors using Eq. (13) [64].
  calculated using this data since direct data for trucks was not avail-
ei ¼ a
Z ~in 1=n ;
~ij  . . .  a fi ¼ Z
W ei  ðZ
ei  . . .  Z
enÞ ð13Þ able. The mine is operated for 24 h with seven days a week. Each
~1  a
~2 ¼ ða1  a2 ; d1  d2 ; c1  c2 Þ;  the multiplication of shift is 8 h except during the weekends in which it is 12 h. The sho-
where a
vel operators are changed periodically every two hours by the
fuzzy numbers;  the addition of fuzzy numbers; and W f i a row vec-
operator on trucks and wheel loaders. The truck and shovel opera-
f
tor in consist of a fuzzy weight of the ith factor ( W i = (x1, x2, . . ., tors have a break after replacement from shovel operation for
xn), i = 1, 2, . . ., n). The defuzzification (changing the fuzzy number 15 min. Crusher is manned by two operators per shift.
The production performance is total output by each fleet of
μ ( x)
equipment. In given organization, performance is measured in
1
terms of activity i.e. for efficiency the formula used by organization
includes productive time (actual loading time) over the available

Table 1
Fuzzy matrix for shovel formed from expert opinions.

A P U
A 1, 1, 1 0.77, 1.8, 1.05 0.77, 1.8, 1.05
0 αij δij γ ij P 0.55, 1.28, 0.94 1, 1, 1 0.77, 1.28, 0.95
U 0.55, 1.28, 0.94 0.77, 1.28, 1.04 1, 1, 1
Fig. 1. Representation of fuzzy numbers.
A.A. Lanke et al. / International Journal of Mining Science and Technology 26 (2016) 753–760 757

Table 2 95%
Fuzzy matrix for trucks formed from expert opinions. Shovel Truck Crusher
90%
A P U
85%
A 1, 1, 1 0.71, 1.8, 0.98 0.77, 1.8, 1.1
P 0.55, 1.4, 1.01 1, 1, 1 0.77, 1.8, 1.21 80%
U 0.55, 1.28, 0.83 0.77, 1.28, 0.82 1, 1, 1
75%

70%

Table 3 65%
Fuzzy matrix for crushers formed from expert opinions.
60%

ch

il

ay
r
A P U

be

ar

pr
ua

ar

M
nu
em

A
M
br
Ja
ec

Fe
A 1, 1, 1 0.71, 3, 1.4 0.55, 1.8, 1.04

D
P 0.33, 1.4, 1.01 1, 1, 1 0.77, 1.8, 1.15
U 0.55, 1.28, 0.83 0.55, 1.8, 1 1, 1, 1 Fig. 3. Availability of studied fleets.

performance with high availability and utilization is very low with


Table 4
Weights obtained using FDAHP method. average of 28%. For crusher the average availability of all crushers
is 72%, utilization is 51% and performance is 21%. Trucks have had
Availability Utilization Performance
the average availability of 77%, average utilization of 86% and
Shovel 0.30 0.37 0.33 average performance of 26%. The shovel has high availability
Truck 0.28 0.41 0.30
compared to truck and crusher. However, trucks utilization has
Crusher 0.24 0.36 0.40
higher values than the shovel except for month of December.
Comparing the performance at equipment level, it is seen that
shovels have highest production performance. They have also com-
time. Considering the output as function of the productive time, we parable utilization with truck in most of the months; however their
assume the performance in terms of efficiency. performance is only 8% and 2% better than crushers and trucks
The field data from the case study mine is presented in respectively. Utilization and performance of trucks have difference
Figs. 3–8. It is seen that even though shovel availability is 86% in of 60% whereas for crusher difference between utilization and
average and the utilization is averaging at 78% where production performance is 30% and for shovels it is more than 50%, leading

Improvement
Mining
solutions and
operation
workorders

Production and
Repeat the analysis
machineries
every 3 months
data

Continuation
of operation

Prtoduction and fleet


databae: total operation
hours, total production, Is actual production Decision
number of active desired production making for
machineries, TBF, TTR, improvment
downtimes, idel times.
No

Calculating the
Calculating Calculating
production
the availablity the utilisation
performance

MPI calculation &


evaluation
Effectiveness
measures

Bottelneck
detection

Fig. 2. Flowchart for applying the MPi for bottleneck detection in mining operation.
758 A.A. Lanke et al. / International Journal of Mining Science and Technology 26 (2016) 753–760

100% Availability Utilization Performance


Shovel Truck Crusher 80%
90%
70%
80%
60%
70%
50%
60%
40%
50%
30%
40%
20%
30%
10%
y

ry

ch

il

ay
r
be

ar

ry

ch

il

ay
r
pr
ua

be
ar

ar

pr
nu
em

ua
A

ar

M
M
br

nu
em

A
M
Ja

br
ec

Fe

Ja
ec

Fe
D

D
Fig. 4. Utilization of studied fleets. Fig. 8. Effectiveness measures for crushers.

35%
Shovel Truck Crusher highly with leading weights for crusher and shovels, whereas uti-
30% lization is rated high for trucks. Availability is rated behind utiliza-
tion and performance for each equipment. It seems that
25% performance is criteria favored by experts over utilization and
availability. Considering the weight from Table 1 and average
20% values for all equipment, MPI is calculated using Eq. (5). Replacing
the values for availability, utilization and performance in
15%
Eqs. (15)–(17) will result in MPI for each equipment.
10% MPIShovel ¼ 860:3  780:37  280:33 ¼ 55:05% ð18Þ
y

ry

ch

il

ay
r
be

ar

pr
ua

ar

0:28 0:41 0:3


MPITrucks ¼ 77:4  26:1  86 ¼ 51:19% ð19Þ
nu
em

A
M
br
Ja
ec

Fe
D

MPICrusher ¼ 72:20:24  50:60:36  20:90:4 ¼ 40:26% ð20Þ


Fig. 5. Performance of studied fleets.

100% 5. Discussion
Availability Utilization Performance
90%
80% Although there are various methods for calculating and deter-
70% mining the mining equipment productivity, very few studies focus
60% on considering all equipment together. The methods discussed in
50%
literature review show that for evaluating the productivity of an
40%
equipment or fleet, availability, utilization and performance are
important criteria. Considering Nakijima’s OEE equation, this effect
30%
can be calculated [65]. However, original OEE equation has limita-
20%
tion in terms of application for mining industry. Prompting the
10%
need to modify this equation, OEE for mining considers quality
y

ry

ch

il

ay
r
be

ar

pr
ua

ar

M
nu
em

parameters, which becomes irrelevant in mining context as per


M
br
Ja
ec

Fe
D

its original definition. The effect of each parameter in OEE equation


Fig. 6. Effectiveness measures for shovel fleet. for mining has to be evaluated. Therefore, this study proposes MPI.
Using the MPI it is easy to evaluate not only effective equipment
100% but also the effect of parameters on the effectiveness. As it is seen,
Availability Utilization Performance
90% only depending upon these three criteria independently, bottle-
80% neck is not easy to find.
70% In the case study, application of MPI reveals that, crusher is the
60%
bottleneck. Crusher is thus by far lagging behind the shovel and
50%
trucks in terms of effectiveness for production. With the weights
obtained it can be said that: without increase in availability or uti-
40%
lization from current level, effectiveness of crusher could be
30%
enhanced with an increase in the performance. However, the
20%
weight evaluation suggests that availability must be focused upon
10%
more closely for improvement. Although crushers’ availability is
y

ry

ch

il

ay
r
be

ar

pr
ua

ar

M
nu
em

comparable to that of trucks and its utilization is less than both


M
br
Ja
ec

Fe
D

other equipment, performance is the criteria that must be focused


Fig. 7. Effectiveness measures for dump truck fleet. upon.
With satisfaction of condition actual production being less than
to conclusion that trucks utilization is effective than any other desired production, the data that should be collected from the sys-
equipment. tem includes downtime of equipment, the actual output by equip-
Considering such variability of mine equipment parameters, it ment and capacities, etc. This data can be utilized to calculate
becomes necessary to evaluate the effect of these parameters alto- availability, utilization and performance for each equipment. This
gether. Output by each equipment will not be correct consideration data along with importance of the equipment can be thus utilized
for evaluation of this equipment together. Performance is rated for MPI evaluation and calculation.
A.A. Lanke et al. / International Journal of Mining Science and Technology 26 (2016) 753–760 759

Improvement solutions and work orders are taken based on [18] Berton A, Jubinville M, Hodouin D, Prévost CG, Navarra P. Ore storage
simulation for planning a concentrator expansion. Miner Eng 2013;40:
detected bottleneck and dominant factor through MPI comparison
56–66.
and evaluation. The decision will help reduce or eliminate the dis- [19] Faraji R. A comparison between linear programming and simulation models
crepancy between actual produced output and the desired output. for a dispatching system in open pit mines; 2013.
[20] Macheret Y, Koehn P, Sparrow D. Improving reliability and operational
availability of military systems. In: Proceedings of aerospace
6. Conclusions conference. IEEE; 2005. p. 3948–57.
[21] Dhillon BS. Mining equipment reliability, maintainability, and safety. Springer
Science & Business Media; 2008.
As discussed in the article, the proposed index, MPI, is an oper- [22] Samanta B, Sarkar B, Mukherjee S. Reliability modelling and performance
ational measure which helps to detect the bottleneck in mine pro- analyses of an LHD system in mining. J S Afr Inst Min Metall 2004;104(1):
1–8.
duction process accurately. It is an extension of OEE concept which [23] Koellner WG, Brown GM, Rodríguez J, Pontt J, Cortés P, Miranda H. Recent
can be to apply it in field more clearly. Assigning different weights advances in mining haul trucks. Ind Electron 2004;51(2):321–9.
for the OEE components helps the engineers to detect the bottle- [24] Barabady J, Kumar U. Reliability analysis of mining equipment: a case study of
a crushing plant at Jajarm Bauxite Mine in Iran. Reliab Eng Syst Saf 2008;93
neck and find out the root cause of it in a proper and reliable way. (4):647–53.
The literature review shows that there is strong correlation [25] Hadi HS, Mohammad A, Reza K, Uday K. Reliability modelling of
between three parameters of OEE and MPI and the bottlenecks hydraulic system of drum shearer machine. J Coal Sci Eng 2011;17(4):
450–6.
performance.
[26] Roy SK, Bhattacharyya MM, Naikan VNA. Maintainability and reliability
In the case study part, validation of MPi was tried by application analysis of a fleet of shovels. Min Technol 2001;10(3):163–71.
in real production process. The analysis in a Swedish open pit mine [27] Lugtigheid D, Banjevic D, Jardine AKS. System repairs: when to perform and
what to do? Reliab Eng Syst Saf 2008;93(4):604–15.
reveals that crusher is the production bottleneck machine from
[28] Vayenas N, Wu X. Maintenance and reliability analysis of a fleet of load-haul-
view point of MPI evaluation. The validity of crusher being bottle- dump vehicles in an underground hard rock mine. Int J Min Reclam Environ
neck for the period of study was confirmed with mine production 2009;23(3):227–38.
department and management. According to weights assigned and [29] Galar D, Naeem HB, Schunesson H, Berges L, Tormos B. Fusion of operations,
event-log and maintenance data: a case study for optimising availability of
MPI value calculated, performance of crusher can be strongly asso- mining shovels. Mine Plan Equip Sel 2014:1173–94.
ciated with reason for it being bottleneck. It seems that crusher [30] Markeset T, Kumar U. Design and development of product support and
performance is associated with its design parameter along with maintenance concepts for industrial systems. J Qual Maint Eng 2003;9
(4):376–92.
scheduling and planning. [31] Ghodrati B, Kumar U. Operating environment-based spare parts forecasting
Exact relationship between type of uncertainties mentioned in and logistics: a case study. Int J Logis: Res Appl 2005;8(2):95–105.
literature review and bottleneck equipment characteristic is part [32] Ghodrati B, Banjevic D, Jardine A. Developing effective spare parts estimations
results in improved system availability. In: Proceedings of reliability and
of further research of this study. For effective decision making, maintainability symposium (RAMS). IEEE; 2010. p. 1–6.
dynamic situation must be considered during the evaluation of [33] Godoy DR, Pascual R, Knights P. Critical spare parts ordering decisions using
the process effectiveness. conditional reliability and stochastic lead time. Reliab Eng Syst Saf
2013;119:199–206.
[34] Sottile Jr J, Holloway LE. An overview of fault monitoring and diagnosis in
References mining equipment. Ind Appl 1994;30(5):1326–32.
[35] Balaba B, Ibrahim MY, Gunawan I. Utilisation of data mining in mining
industry: improvement of the shearer loader productivity in underground
[1] Brown T, Shaw R, Bide T, Petavratzi E, Raycraft E, Walters A. World mineral
mines. In: Proceedings of the 10th IEEE international conference on industrial
production 2007–2011. Brit Geol Surv; 2013. p. 76.
informatics (INDIN). p. 1041–6.
[2] Muchiri P, Pintelon L. Performance measurement using over-all equipment
[36] Cui LR, Hayakawa Y, Gustafson A, Schunnesson H, Galar D, Kumar U.
effectiveness (OEE): literature review and practical application discussion. Int J
Production and maintenance performance analysis: manual versus semi-
Prod Res 2008;46(13):3517–35.
automatic LHDS. J Qual Maint Eng 2013;19(1):74–88.
[3] Lanke A, Hoseinie H, Ghodrati B. Mine production index (MPI): new method to
[37] IEC. IEC 60050-191: International electrotechnical vocabulary: dependability
evaluate effectiveness of mining machinery. In: Proceedings of international
and quality of service Technical report. International Electrotechnical
conference on mining and mineral engineering (ICMME).
Commission (IEC); 1990 [chapter 191].
[4] Mutagwaba W, Hudson J. Use of object-orientated simulation model to assess
[38] Suglo RS, Szymanski J, Booth D, Frimpong S. Simulation analysis of mining
operating and equipment options for underground mine transport system.
models. In: Proceedings of IASTED international conference on applied
Trans Inst Min Metall 1993;102:89–94.
simulation and modelling (ASM2003), Marbella.
[5] Hunag Y. The production system analysis of Kiruna iron ore mine Licentiate
[39] Kear R. Strategic and tactical mine planning components. J S Afr Inst Min
thesis. Luleå: Luleå Tekniska H; 1993.
Metall 2006;106(2):93.
[6] Kumar U. Study of problems caused by oversized boulders in a mine
[40] Angelov A, Naidoo K. Plan compliance process for underground coal mines;
production system: a case study. Int J Surf Min Reclam Environ 1997;11
2010.
(2):69–73.
[41] Hustrulid WA, Kuchta M, Martin RK. Open pit mine planning and design, two
[7] Vagenas N, Runciman N, Clement SR. A methodology for maintenance analysis
volume set & CD-ROM pack; 2013.
of mining equipment. Int J Surf Min Reclam Environ 1997;11(1):33–40.
[42] Godoy M, Dimitrakopoulos R. Managing risk and waste mining in long-term
[8] Pauley GS, Ormerod RJ. The evolution of a performance measurement project
production scheduling of open-pit mines. SME Trans 2004;316.
at RTZ. Interfaces 1998;28(4):94–118.
[43] Guoqing L, Nailian H, Xuchun H. Study on the application of supply chain
[9] Nes’E Çelebi. An equipment selection and cost analysis system for open pit coal
management (SCM) for Jiaojia gold mine. In: Applications of computers and
mines. Int J Surf Min Reclam Environ 1998;12(4):181–7.
operations research in the minerals industries. South African Institute of
[10] Charlton G. Simulation for performance enhancement of systems: a case study
Mining & Metallurgy; 2003.
of an open-cut coal mine operation. Int J Syst Sci 1999;30(4):417–26.
[44] Souza MJ, Coelho IM, Ribas S, Santos HG, Merschmann LH. A hybrid heuristic
[11] Paraszczak J. A failure and downtime reporting: a key to improve mine
algorithm for the open-pit-mining operational planning problem. Eur J Oper
equipment performance. CIM Bull 2000;93(1044):73–7.
Res 2010;207(2):1041–51.
[12] Lewis MW, Steinberg L. Maintenance of mobile mine equipment in the
[45] Topal E, Ramazan S. A new MIP model for mine equipment scheduling by
information age. J Qual Maint Eng 2001;7(4):264–74.
minimizing maintenance cost. Eur J Oper Res 2010;207(2):1065–71.
[13] Samantha B, Sarkar B, Mukherjee S. Selection of opencast mining equipment
[46] Hartman H, Britton SG. SME mining engineering handbook, vol. 2. Society for
by a multi-criteria decision-making process. Min Technol 2002;111
Mining, Metallurgy, & Exploration; 1992.
(2):136–42.
[47] Elevli S, Elevli B. Performance measurement of mining equipments by utilizing
[14] Knights PF. Rethinking Pareto analysis: maintenance applications of
OEE. Acta Montanistica Slovaca 2010;15(2):95.
logarithmic scatterplots. J Qual Maint Eng 2001;7(4):252–63.
[48] Edwards DJ, Holt GD. Estivate: a model for calculating excavator productivity
[15] Hall RA, Daneshmend LK. Reliability modelling of surface mining equipment:
and output costs. Eng, Const Archit Manage 2000;7(1):52–62.
data gathering and analysis methodologies. Int J Surf Min Reclam Environ
[49] Widzyk-Capehart E, Lever PJ. Towards rope shovel automation operation
2003;17(3):139–55.
information system. In: Proceedings of CRC mining conference.
[16] Dimitrakopoulos R, Ramazan S. Uncertainty based production scheduling in
[50] Frimpong S, Hu Y, Inyang H. Dynamic modelling of hydraulic shovel excavators
open pit mining. SME; 2004. p. 316.
for geomaterials. Int J Geomech 2009;8(1):20–9.
[17] Simsir F, Ozfirat MK. Determination of the most effective long wall equipment
[51] Segarra P, Sanchidrián JA, López LM, Querol E. On the prediction of mucking
combination in longwall top coal caving (LTCC) method by simulation
rates in metal ore blasting. J Min Sci 2010;46(2):167–76.
modelling. Int J Rock Mech Min Sci 2008;45(6):1015–23.
760 A.A. Lanke et al. / International Journal of Mining Science and Technology 26 (2016) 753–760

[52] Sanchidrián Blanco JA, Segarra Catasús P, López Sánchez LM. On loader [59] Sbarbaro D. Control of crushing circuits with variable speed drives. In: World
productivity, rock strength and explosive energy in metal mining; 2011. congress, 6. p. 1691.
[53] Brown GM, Elbacher B, Koellner WG. Increased productivity with ac drives for [60] Hulthén E. Real-time optimization of cone crushers. Chalmers University of
mining excavators and haul trucks. In: Proceedings of industry applications Technology; 2010.
conference. IEEE; 2000. p. 28–37. [61] Van Laarhoven P, Pedrycz W. A fuzzy extension of Saaty’s priority theory.
[54] Bascetin A. A decision support system using analytical hierarchy process (AHP) Fuzzy Sets Syst 1983;11(1):199–227.
for the optimal environmental reclamation of an open-pit mine. Environ Geol [62] Mikaeil R, Ataei M, Yousefi R. Application of a fuzzy analytical hierarchy
2007;52(4):663–72. process to the prediction of vibration during rock sawing. Min Sci Technol
[55] Burt CN, Caccetta L. Match factor for heterogeneous truck and loader fleets. Int 2011;21(5):611–9.
J Min Reclam Environ 2007;21(4):262–70. [63] Karimnia H, Bagloo H. Optimum mining method selection using fuzzy
[56] Krzyzanowska J. The impact of mixed fleet hauling on mining operations at analytical hierarchy process-Qapiliq salt mine, Iran. Int J Min Sci Technol
Venetia mine. J S Afr Inst Min Metall 2007;107:215–24. 2011;25(2):225–30.
[57] Maerz NH, Palangio TC. Online fragmentation analysis for grinding and [64] Ya CL, Chao SC. A new approach for application of rock mass classification on
crushing control. In: Proceedings of control symposium, SME annual meeting, rock slope stability assessment. Eng Geol 2007;89:129–43.
Salt Lake City, Utah. p. 109–16. [65] Nakajima Seiichi. Introduction to TPM: total productive
[58] Rosario P, Hall R, Maijer D. Liner wear and performance investigation of maintenance. Cambridge (Massachusetts): Productivity Press; 1988. p. 129.
primary gyratory crushers. Miner Eng 2004;17(11):1241–54.

You might also like