Professional Documents
Culture Documents
Abstract- The complex nature of modern equipment OEE: Overall Equipment Effectiveness.
and systems often lead to failures and as a RCA: Root cause analysis.
consequence lead to increase in machine downtime0 PM: Preventive Maintenance.
CDF: Cumulative distribution function.
thus affecting production. The failures of machineries
K-S: Kolmogorov-Smirnov.
cause disruptions in production resulting in a loss of
availability of the system .This further increases the I. INTRODUCTION
cost of maintenance. TPM has been proved as a In most cases machine operators fail to detect the
successful tool for increasing the OEE of machineries actual causes behind any problem whenever a failure
by using simple effective techniques. Initially in this occurs. They are often seen treating the symptoms
study Pareto analysis was used to figure out the major rather than eliminating the problem at the grass root
level. This further elevates the problem to a whole
contributors towards downtime losses. RCA using the
new level which would have otherwise not occurred
Why-Why technique was done so as to explain the had it been treated correctly in the first place. An in
reasons behind equipment breakdown. This helped in depth analysis together with experience and training
developing a PM schedule for the machines. only prepares an individual for proper handling of
Reliability is an important parameter for any piece of failed equipments. A thorough practical knowledge of
equipment. In this study Weibull statistics was used to mechanical, electrical as well as electronic parts able
measure the reliability of the system and also explain an operator to run a complex piece of equipment like
the pouch machine smoothly. Mostly operators gather
the CDF governing the rate of failure. The fitness of
the basic knowledge through experience in the field.
the model developed using weibull distribution was But this has a side effect as well, till the time they had
further verified using the KS test which is a “distance become experts in their fields they had already wasted
test”. The value of the shape parameter β helped to a considerable amount of valuable production time.
understand the current state of the machine and justify Analysis of root causes through brainstormingand
the use of the PM schedule developed. training sessions can only give a clear picture to the
operators of equipments they are handling. This study
was done on the pouch machine or the vertical filling
Keywords: Downtime Losses, TPM, OEE, Pareto
and sealing machine in a cosmetic plant. This machine
analysis, PM schedule,Weibull distribution, CDF, has a wide variety of applications from packing
Distance test, K-S test. liquids, semi liquids to powder products as well. Table
Ishows specifications of the machine under study.
Abbreviations:
TABLE I: MACHINE SPECIFICATIONS
the techniques involved in Planned maintenance. parameter) were estimated from the graph itself. The
Preventive maintenance checklists as prepared by M, values of the distribution function were compared with
Manoj., et al (2014) helped increase availability, the original cumulative failure rate to verify the
MTBF and reduce MTTR significantly. Also the correctness of the model using the Kolmogorov-
number of machine breakdowns were reduced after Smirnovcriteria.
implementation in this case. Parameters like
reliability, MTTR and MTBF are also important To measure the reliability of the machine
factors that define Equipment breakdown and help to using the weibull parameters β and ηo, the formula
understand equipments better. To measure the R(t) = exp[-(t/ηo)β]was used. The time period taken
reliability of any equipment, it is of utmost importance was the average loading time for a period of six
to find out the cumulative distribution function (CDF) months.
governing the failure rate. Mirzai, M. et al. (2006)
V. ANALYSIS & DISCUSSION
uses weibull distribution to explain the failure rate of
power transformers in an Iranian electric company. A. Downtime Analysis.
This paper further does a goodness of fit test on the
developed mathematical model by using the KS test. There are a total of fifteen major downtime
Bose, D., et al (2013) evaluates reliability, availability losses which are recorded by the production
and maintainability of a diesel locomotive engine and department. In order to narrow down the study only
uses weibull statistics to explain the failure to the important ones, the individual loss percentage
rate.Wang, Hsaio-Mei., (2009) states that for distance and cumulative loss percentage were calculated.
tests in cumulative distribution function (CDF) the KS Downtime data is provided in details in Table II.
test is a good approach. He further makes a
TABLE II: MACHINE DOWNTIME DATA
comparison between the Chi-square test and the KS
test.
Total Cumal Individu Cumulati
III. OBJECTIVE Downtim loss ative al loss ve loss
e losses (mins. loss percenta percentag
The objectives of this work are to study the ) (mins.) ge e
root causes behind equipment breakdown. Secondly, Equipmen
1675 1675 34 34
to develop a PM schedule based on the findings of the t failure
RCA analysis. Thirdly, to find out the cumulative Minor
1460 3135 30 64
distribution function governing the rate of failure and stoppages
lastly to measure the reliability of the machine based Shift
297 3432 6 70
on the model parameters. change
Change
285 3717 6 76
over
IV. METHODOLOGY Utility
280 3997 6 81
failure
At first, a Pareto analysis of machine
Others 921 4918 19 100
downtime losses showed that equipment breakdown
was the greatest contributor. To understand Equipment
breakdown better, a RCA using the Why-Why Pareto analysis of downtime losses in Fig. 1
technique was done with the help of machine gives a better picture of the situation. The various
operators and maintenance personnel. This was types of downtime losses are plotted along the primary
followed by the development of a PM schedule based horizontal axis. The individual loss in minutes is
on common industrial practices. plotted along the primary vertical axis, while the
cumulative loss percentage is plotted against the
As for determining the cumulative
secondary vertical axis.
distribution function governing the failure rate the
weibull distribution was adopted as a model. The
loading time was expressed in terms of minutes and
arranged in an ascending order. In order to convert the
weibull equation into a linear one log normal function
was used twice and after plotting these points the
weibull parameters β (shape parameter) and ηo(slope
14000 100
100
2000 100100 12000
10000 73 77 81 80
1500 76 81 80 8000 62 68 60
64 70 52
60 6000 42 40
1000 4000 25
40 2000 20
34
500 20 0 0
0 0
Fig.1: Pareto Analysis of Machine Downtime. Fig. 2: Pareto Analysis of Equipment Breakdown
From the Pareto analysis the factors Thus, from the Downtime analysis, the major
contributing roughly eighty percent towards downtime equipment breakdown causes were found to be
were found to beEquipment breakdown, Minor Vacuum pump failure , Photocell sensor failure, heater
stoppages, Shift change, Change Over, Utility failure, Cutting failure, paper setting problem, batch
failure.Out of these five major losses equipment cutting failure and the occurrence of leakage and
breakdown was further studied. Table III shows wrinkle(fold marks) on the pouches. Vacuum pump,
equipment breakdown in details. heater and photocell are essentially machine
components while cutting failure, paper setting
TABLE III: EQUIPMENT BREAKDOWN DATA.
problem, batch cutting failure, leakage and wrinkle are
undesirable effects caused during machine operation.
Equipment Total Cumulat Individu Cumul
breakdown loss ive loss al loss ative B. Root Cause Analysis.
/ failure (mins. (mins.) percenta loss
statement ) ge percent Root Cause Analysis is a method to
age understand the actual reasons behind any undesirable
Vacuum 11695 11695 25 25
effect, so as to address the problem at the grass root
pump
Photocell 7460 19155 16 42
level. A typical example of RCA using the why-why
sensor technique in case of vacuum pump is shown Fig. 3.
Heater 4910 24065 11 52
Cutting 4660 28725 10 62
Paper 2720 31445 6 68
setting
Batch 2195 33640 5 73
cutting
Leakage 2010 35650 4 77
Wrinkle 1655 37305 4 81
Others 8845 46150 19 100
Inspection of Pull
12 Visual D 30 sec.
DailyPreventive maintenance activities like rollers
cleaning, inspection and tightening prove necessary in Tightening of
13 Spanner W 1 min.
the long run. Activities like cleaning and tightening Clutch/Brake bolt
are normally assigned to be completed within one Tightening of
14 Allen key W 1 min.
minute, while around thirty seconds are available for Thimble
Tightening of
inspection activities. Cleaning is normally done with 15 Transformer wire Spanner W 1 min.
dry cloth since most of the machines have electrical junction
components in them. Compressed air also provide a Tightening of Sealer
16 Spanner W 1 min.
faster way of cleaning. Compressed air for cleaning do aligning bolt
not require any special set up since most of the Tightening of Rotary
17 Spanner W 1 min.
machines in the process industry have pneumatic blade aligning bolt
Table VI below provides details about the preventive Weibull cumulative distribution function is shown
action.TABLE VI: PM & CM ACTION CHECKLIST. below
Sl. Correct
Failure Preventive
N Causes ive
statement action
o. action
Too In which β and ηo must be determined, where
Vacuum Pressure
much Replace β and ηo are the shape parameter and scale parameter
1 pump oil adjustment to
pressure ment respectively. To achieve a linear equation, we use log
pipe burst be done slowly
.
normal function twice. Now, the equation has the form
Allow
Overhea lnln =βln(t)–βln(ηo) whichis also asimple
Photocell photocel Eye mark
t due to
sensor l to cool detection to be linear equation Y = mX – A , Where, Y =
2 lengthy
malfunctio down done within
adjustm lnln ; X = ln(t) and A = βln(ηo). To calculate
ning for some one minute.
ent.
time.
the values of X and Y we use the failure data against
Use of
Installati loading time. Table VII shows loading time, the
PLC on of Avoid number of failures and the values of X and Y.
negative
3 malfunctio new Negative value
value(-)
ning. program as input. TABLE VII: CALCULATED X & Y FROM FAILURE DATA.
as input
s.
12966
55 302 1 0.9424 0.0576 Valueof Probable
0 Possible Cause
Shape Failure Of
Parameter Mechanism Failure
Therefore, Dn= 0.093251 at sample size, n = 182.
Age Accelerated
β >2 Related wear & tear of
This difference, which is a random variable Pattern components
varies with the sample selected, this value is then Time Process error,
compared with the critical value using the design. fault ,
β≈1 independent
Kolmogorov-Smirnov criteria, which measures the pattern maloperation
goodness of fit. Table IX shows various levels of Manufacturing
significance against the sample size. In this case, the β<1 Early failure Failure and
sample size is more than fifty. reconditioning fault
The value of the shape parameter β is of subjected to a time independent failure and its causes
special importance, as it gives us an idea about the are process error, design fault and maloperation.
current state of machines. Table XI summarises
machine condition for different values of β. The present condition of the machine can be
improved if the proposed PM schedules are strictly
TABLE XI: CLASSIFICATION OF SHAPE PARAMETER followed This might help in improving the reliability
of the machines in the future.