MID-TERM EXAMINATION

Name:____________________________Section:__________Date:________________

Test I
In connection with the work planning and scheduling, (we performed last prelim exam),
re-estimate the necessary labor, material and equipment for the column-footing and
footing-tie-beam. Determine the unit costs of RSB work, formwork and concrete-work with
respect to the labor cost, material cost and equipment cost with the following given: labor rate
= 62/HR; material: RSB = 50/kg; form = 800/sqm; concrete = 5000/cum; equipment rental: RSB
= 250/HR; concrete = 800/HR. These unit costs will be the factors to determine the weekly
labor cost material cost and equipment cost requirement in your Weekly Schedule.

A B C D
5.0 F2C2 5.0 F2C2 5.0
F1C1 F1C1

1
FTB-1 FTB-1 FTB-1

4.0
FTB-1 FTB-1 FTB-1

F2C2 2
F2C2
F3C3 F3C3
4.0
FTB-1

3
F1C1
F2C2 F2C2 F1C1

FOOTING FOUNDATION PLAN SHOWING COMPLETED FOOTING BARS

L W t a b h1 CVB c d L1
FOOTING COLUMNS FOOTING TIE-BEAM
F1 1.5 1.5 0.3 C1 0.3 0.3 4.5 #12 FTB-1 0.3 0.5 8.0
F2 1.5 2.0 0.4 C2 0.3 0.4 4.5 #14 FTB-1 0.3 0.5 13.0
F3 2.5 2.5 0.5 C3 0.4 0.4 4.5 #16

(1)
c

4-20mm –Bar 1
d
4-16mm –Bar 3
10mm – STIRRUPS

Bar 4 4-20mm –Bar 2

SECTION OF FTB-1

A B C D
5.0 5.0 5.0
a b c c

d1
d2

FOOTING ELEVATION SHOWING CONCRETED FOOTINGS & INSTALLED RSB FOR FTB

A B C 4-20mm –Bar 1x D
4-20mm –Bar 1x 4-20mm –Bar 1y

4-20mm –Bar 2x 4-16mm –Bar 3x 4-20mm –Bar 2y 4-16mm –Bar 3y 4-20mm –Bar 2x

Concrete covering of RSB, “cc” = 0.05m.

1 2 3
4-20mm –Bar 1
4-16mm –Bar 3 4-20mm –Bar 2

cc concrete covering, cc = 0.05 m. cc


L1

(2)
A B C D
TOP OF FIRST LIFT COLUMN
FINISH GROUND SLAB

0.6

FTB-1

SECTION OF FOOTING TIE-BEAM SHOWING SIDE FORMS

h1 = {(H – t) + (h – depth of beam)} /spacing of hoops = # of hoops


FBB: 16mm @ 0.15 m. ON CENTER BOTHWAYS
TOP OF 2ND FLOOR BEAM

FLOOR BEAM: 0.25 x 0.5 a

COLUMN: CVB- 16mm: C1#12; C2 b W


h
#14; C3#16. 10mm diameter

HOOPS @ 0.15 M. ON CENTER


h1

FINISH GROUND FLOOR

cc L cc
H FTB: - 16mm BOTHWAYS
FTB: 16mm @ 0.20 m. ON CENTER BOTHWAYS
t
PLAN OF FOOTING
FBB: – 16mm BOTHWAYS

FOOTING ELEVATION TYPICAL FOOTING DETAIL

(3)
SOLUTION:
1. Estimate the material quantity (RSB, form, and concrete).
Part of Structure Mark Qties. L W t a b h1 c d L1
<>FOOTING -1 F1 1.5 1.5 0.3 x x x x x x

<>FOOTING -2 F2 1.5 2.0 0.4 x x x x x x

<>FOOTING -3 F3 2.5 2.5 0.5 x x x x x x

<>COLUMN -1 C1 x x x 0.3 0.3 4.5 x x x

<>COLUMN -2 C2 x x x 0.3 0.4 4.5 x x x

<>COLUMN -3 C3 x x x 0.4 0.4 4.5 x x x

<>FTG. TIE-BEAM-1 FTB-1 x x x x x x 0.3 0.5 8.0


<>FTG. TIE-BEAM-1 FTB-1 x x x x x x 0.3 0.5 13.0
F1-C1 V= V= V=

F2-C2
Concrete Volume =>
F3-C3 M3
FTB-1
F1-C1 A= A= A=

F2-C2
Area of Form =>
F3-C3 M2
FTB-1
RSB => -do- Refer to the Bar Schedule Refer to the Bar Schedule Refer to the Bar Schedule

BAR REQUIREMENT & BAR CUTTING & BENDING SCHEDULE


#Bar No. TOTAL TOTAL TOTAL Get From Commercial Length
FAB. a b c d
Mark Per of LENGTH QTY. WT. N =chosen length/total length
TYPE (mm) (mm) (mm) (mm)
Ftg. Ftg. (M.) (PCS) (KGS) Q1 = Total Qty/N

F1 1.58kg/ Q1=total Qty/N


FBB
FTB
F2
FBB
FBB
FTB
FTB
F3
(4)
FBB
FTB
C1
CVB
Hoops

C2
CVB
Hoops

C3
CVB
Hoops

FTB-1
Bar-1

Bar-2

Bar-3

Stirrup

FTB-1
Bar-1x

Bar-2x

Bar-3x

Bar-1y

Bar-2y

Bar-3y

Stirrup

Total Weight =>


b a d c
a a a b
TYPE - A c TYPE – C TYPE - D
b
TYPE – B
(5)
FORM MATERIALS & FABRICATION DETAILS
STR. SIDE-FORM DETAIL FOOTING DIMENSION

S FRAME-A L W H Form
BOARD
(m) (m) (m) Area/Ftg.

H F1 1.5 1.5 0.3 ____m2


FRAME-B
F2 1.5 2.0 0.4 ____m2
L
(W +
F3 2.5 2.5 0.5 ____m2
0.10)
Bill of Materials - Footing
1. PLYWOOD 2. WOOD FRAME

Total Form Area = ________________________ m2 2.1. Frame-A: Length/ftg. = {L + (W+0.1)} x 2

F1 Area of 1 sheet Plywood = 2.9768 m2 Length = ________________________________m.

Qty = __________________________________ Pcs. 2.2. Frame-B: N = {L + (W+0.1)}/s

Marine Plywood N = ____________________________________pcs.


F
Total Area = ______________________________m2 2.1. Frame-A: Length/ftg. = {L + (W+0.1)} x 2
O
Area of 1 sheet Plywood = 2.9768 m2 Length = ________________________________m.
O F2
Qty =___________________________________Pcs 2.2. Frame-B: N = {L + (W+0.1)}/s
T
Marine Plywood N = ____________________________________pcs.
I
Total Area = _____________________________m2 2.1. Frame-A: Length/ftg. = {L + (W+0.1)} x 2
N
Area of 1 sheet Plywood = 2.9768 m2 Length =________________________________ m.
G F3
Qty = __________________________________Pcs. 2.2. Frame-B: N = {L + (W+0.1)}/s

Marine Plywood N = ____________________________________pcs.

Use: 2”x 3” Lumber


Q =___________________________ pcs.
Total Length =______________________________________m.
_______Pcs. 1/2”x 4’x 8’ Marine Plywood
Total Bdft =_________________________________ Bdft.

COLUMN DETAIL
Structure SIDE-FORM DETAIL COLUMN DIMENSION
FRAME-A a b L Form

b (m) (m) (m) Area/Col.

COLUMN F1 0.3 0.3 4.5 ____m2


a S FRAME-B
L F2 0.3 0.4 4.5 ____m2
F3 0.4 0.4 4.5 ____m2
Bill of Materials - Column
COL C1 1. PLYWOOD 2. WOOD FRAME
Total Form Area = _________________________m2 2.1. Frame-A: Length/Col. = {L} x 2 x 4

Area of 1 sheet Plywood = 2.9768 m2 Length =____________________________ m. = ______ft.

(6)
Qty =_____________________________________ 2.2. Frame-B: N = {L}/s
C1
Marine Plywood N = ____________________________________pcs.

Total Form Area =_________________________m2 2.1. Frame-A: Length/Col. = {L} x 2 x 4

Area of 1 sheet Plywood = 2.9768 m2 Length = __________________________m. =________ ft.


C C2
Qty = __________________________________ Pcs. 2.2. Frame-B: N = {L}/s
O
Marine Plywood N = ____________________________________pcs.
L
Total Form Area = _________________________m2 2.1. Frame-A: Length/Col. = {L} x 2 x 4
U
Area of 1 sheet Plywood = 2.9768 m2 Total Length = 4.5 x 2 x 4 x 2 = 72 m. = 236 ft.
M C3
Qty =___________________________________Pcs 2.2. Frame-B: N = {L}/s
N
Marine Plywood N = {4.5} / 0.4 = 13 + 1 = 14 pcs. x 4 x 2 = 112 pcs.

Use: 2”x 3” Lumber


Q =____________________________ Pcs.
Total Length =_______________________________________m
______Pcs. 1/2”x 4’x 8’ Marine Plywood
Total Bdft = _________________________________Bdft.

FRAME-A FRAME-B a b L Area/GL

b FTB-1 0.3 0.5 7.0 ____m2

L FTB-1 0.3 0.5 13.6 ____m2

1. PLYWOOD 2. WOOD FRAME

Total Form Area = _________________________m2 2.1. Frame-A: Length/Col. = {L} x 2 x 4

Area of 1 sheet Plywood = 2.9768 m2 Length =___________________________ m. = _______ft.

Qty = __________________________________Pcs. 2.2. Frame-B: N = {L}/s

FTB- 1 Marine Plywood N = ____________________________________pcs.

Total Form Area =_________________________m2 2.1. Frame-A: Length/Col. = {L} x 2 x 4

Area of 1 sheet Plywood = 2.9768 m2 Length =___________________________ m. = _______ft.

Qty = __________________________________Pcs. 2.2. Frame-B: N = {L}/s

Marine Plywood N =____________________________________ pcs.

Use: 2”x 3” Lumber


Q =______________________________ Pcs.
Total Total Length =_________________________________ Ft.
_______Pcs. 1/2”x 4’x 8’ Marine Plywood
Total Bdft = _________________________________Bdft.
(7)
2. Compute the man-hour and time requirement with the given work parameters and
(assumed) number of manpower.
RSB Work Formwork Concrete
Column-Footing Matl. MP EQPT Matl. MP EQPT Matl. MP EQPT

C1F1
Assume Assume
C2F2 1-CM Assume
______ 6 _____ 2 ______
C3F3 & 5 Supplied
Kgs. Rebar- Sqm. Carpen- cum
Footing Tie-beam 1-BM men
man ter
FTB-1
MH = Qty. / WP MH = Qty. / WP MH = Qty. / WP
MH Computation = ___________________ = ____________________ = ____________________
= _______________mhrs. = _______________mhrs. = _______________mhrs.
D = MH/MP(8 hrs/day) D = MH/MP(8 hrs/day) D = MH/MP(8 hrs/day)
Work Duration
= _________________days = _________________days = _________________days

3. Determine the unit costs on labor, material and equipment of Work Items basing from the
labor cost, material cost and equipment cost.
WORK ITEMS QUANTITIES LABOR COST MATERIAL COST EQUIPMENT COST

_______KGS. Labor rate= Ph62/kg. Matl. Cost = Ph50/kg. Eqpt. Rental=250/hour


1. RSB WORK
(_______MH) 1. 2. 3.

UNIT COST=>> 4. 5. 6.

1.1. BAR FABRICATION _______KGS. 7. x x

UNIT COST=>> 8. x x

1.2. BAR INSTALLATION _______KGS. 9. x x

UNIT COST=>> 10. x x

BID UNIT COST=>> 11. 12. 13. 14.

PLUS: MARK-UP (20%) 15. 16 17.

SUPERVISION (15%) 18. 19. 20.

CONTIGENCY (5%) 21. 22. 23.

TOTAL UNIT COST=>> 24. 25. 26.

PLUS: VAT (12%)=> 27. 28. 29.

TOTAL BID COST=>> 30. 31 32. 33.


(8)
2. FORMWORK _______SQM Labor rate= Ph62/sqm. Matl. Cost = Ph800/sqm. x
(USING WOOD FORM) (_______MH) 34. 35. x

2.1. FABRICATION _______SQM 36. x x

UNIT COST=>> 37. x x

2.2. INSTALLATION _______SQM 38. x x

UNIT COST=>> 39. 40. x

BID UNIT COST=>> 41. 42. 43. x

PLUS: MARK-UP (20%) 44. 45. x

SUPERVISION (15%) 46. 47. x

CONTIGENCY (5%) 48. 49. x

TOTAL UNIT COST=>> 50. 51. x

PLUS: VAT (12%)=> 52. 53. x

TOTAL BID COST=>> 54. 55. 56. x

_______CUM Labor rate= Ph62/cum. Matl. Cost = 5000/cum. Eqpt. Rental=800/hour


3. CONCRETE WORK
(_______MH) 57. 58. 59.

3.1. CONCRETING _______CUM 60. x x

UNIT COST=>> 61. 62. 63.

BID UNIT COST=>> 64. 65. 66. 67.

PLUS: MARK-UP (20%) 68. 69. 70.

SUPERVISION (15%) 71. 72. 73.

CONTIGENCY (5%) 74. 75. 76.

TOTAL UNIT COST=>> 77. 78. 79.

PLUS: VAT (12%)=> 80. 81. 82.

TOTAL BID COST=>> 83. 84. 85. 86.

4. Summarize the unit costs and bid costs.


WORK ITEMS LABOR COST MATERIAL COST EQUIPMENT COST

COLUMN-FOOTING & QUANTITIES Labor rate= Ph62/kg. Matl. Cost = Ph50/kg. Eqpt. Rental=250/hour

FOOTING TIE-BEAM Unit Cost Bid Cost Unit Cost Bid Cost Unit Cost Bid Cost

1. RSB WORK 5306 KGS. 1. 2. 3. 4. 5. 6.

2. FORMWORK 197 SQM. 7. 8. 9. 10. 0 0

3. CONCRETE 36 CUM. 11. 12. 13. 14. 15. 16.


(9)
Test II

Prepare a Weekly Schedule for the Column-footing and Footing-tie-beam basing from the
illustrations in Test I. Indicate the daily and weekly plan accomplishment with the corresponding
manpower, material and equipment cost considering the unit costs computed in Test I as shown
in Table below.
MANPOWER MATERIAL EQUIPMENT

RSB WORK LABOR RATE PH 21.43/KG. UNIT COST PH 78.4/KG UNIT COST PH 13.02/KG.

FORMWORK LABOR RATE PH 80.93/SQM UNIT COST PH 1254/SQM UNIT COST 0

CONCRETE LABOR RATE PH 162/CUM UNIT COST PH 7840/CUM UNIT COST 418.13/CUM

BAR CHART SCHEDULE - (2-STOREY BUILDING)


Days (2 -day count)
PRE ACT. DATE DATE TIME
ACTIVITY DESCRIPTION 1 1 1 1 1 2 2 2 2
ACT. NO. START FINISH (DAY) 2 4 6 8
0 2 4 6 8 0 2 4 6

I Structural Work Day-1 Day-___

2 3 Column Footing Day-1 Day-___

2 3.1 RSB Work Day-1 Day-___

3.1 3.2 Form Work Day-___ Day-___

3.2 3.3 Concrete Work Day-___ Day-___

No. of Manpower ->>


Days (1 -day count)
PRE ACT. DATE DATE TIME
ACTIVITY DESCRIPTION 2 2 2 2 2 2 2 3 3 3 3 3 3
ACT. NO. START FINISH (DAY)
3 4 5 6 7 8 9 0 1 2 3 4 5

I Structural Work Day-1 Day-___

2 3 Column Footing Day-1 Day-___

3 4 Footing Tie-beam Day-___ Day-___

3.3 4.1 RSB Work Day-___ Day-___

4.1 4.2 Form Work Day-___ Day-___

4.2 4.3 Concrete Work Day-___ Day-___


No. of Manpower ->>
(10)
SOLUTION:
1. Prepare a Weekly Schedule indicating the daily work accomplishment with the
corresponding manpower and budget man-hour basing on the given work parameters. Also,
determine the adjusted daily or weekly target accomplishment basing from the budget
man-hour of the given manpower.

1. COLUMN-FOOTING – (STRUCTURAL WORK SCHEDULE)


PRE ACT. START FINISH DUR. 1 1 1 1 1 2 2 2 2
WORK ITEMS 2 4 6 8
ACT. CODE DATE DATE (DAYS) 0 2 4 6 8 0 2 4 6

2 3 Column Footing Day-1 Day-___

2 3.1 RSB Work Day-1 Day-___

3.1 3.2 Form Work Day-___ Day-___

3.2 3.3 Concrete Work Day-___ Day-___

WEEKLY PLANNED ACCOMPLISHMENT – (COLUMN-FOOTING)


WEEKLY PLANNED ACCOMPLISHMENT: (PERIOD: JAN. 21-27,2019) ACCOMPLISHMENT
STRUCTURE CONTRACT
JAN-21 JAN-22 JAN-23 JAN-24 JAN-25 JAN-26 JAN-27 WEEKLY QTIES.
QUANTITIES
1. COLUMN-FOOTING M 1 T 2 W 3 T 4 F 5 S 6 S 7 QTIES. TO DATE

1. RSB WORK _______KGS.

ADJUSTED QTIES-> _______KGS.

MANPOWER-> ____BARMAN

MAN- PLANNED FAB=______

HOUR = _____ INST=______

PLANNED MHRS->

ADJUSTED M-HOUR->

WEEKLY PLANNED ACCOMPLISHMENT: (PERIOD: JAN. 28-FEB. 3, 2019) ACTUAL ACCOMP.


CONTRACT
1. COLUMN-FOOTING JAN-28 JAN-29 JAN-30 JAN-31 FEB-1 FEB-2 FEB-3 WEEKLY QTIES.
QUANTITIES
M 8 T 9 W 10 T 11 F 12 S 13 S 14 QTIES. TO DATE

1. RSB WORK ______KGS.

ADJUSTED QTIES-> ______KGS.

MANPOWER-> ____BARMAN

MAN- PLANNED FAB=______

HOUR =_______ INST=______


PLANNED MHRS-> =

ADJUSTED M-HOUR-> =

(11)
WEEKLY PLANNED ACCOMPLISHMENT: (PERIOD: FEB. 4 - FEB. 10, 2019) ACTUAL ACCOMP.
CONTRACT
1. COLUMN-FOOTING FEB-4 FEB-5 FEB-6 FEB-7 FEB-8 FEB-9 FEB-10 WEEKLY QTIES.
QUANTITIES
M 15 T 16 W 17 T 18 F 19 S 20 S 21 QTIES. TO DATE

1. RSB WORK _______KGS.

ADJUSTED QTIES-> _______KGS.

MANPOWER-> ____BARMAN

PLANNED M-HOUR-> =

ADJUSTED MHOUR-> =

2. FORMWORK ______SQM.

ADJUSTED QTIES-> ______SQM.

MANPOWER-> _CARPENTER

PLANNED M-HOUR-> =

ADJUSTED MHOUR-> =

FEB-11 FEB-12 FEB-13 FEB-14 FEB-15 FEB-16 FEB-17 WEEKLY QTIES.

M 22 T 23 W 24 T 25 F 26 S 27 S 28 QTIES. TO DATE

3. CONCRETEWORK ______CUM.

ADJUSTED QTIES-> ______CUM.

MANPOWER-> ____WORKER

PLANNED M-HOUR-> =

ADJUSTED MHOUR-> =

VARIANCE (DAYS)-> OVERALL = ACTUAL - PLANNED =

2. FOOTING TIE-BEAM – (STRUCTURAL WORK SCHEDULE)


PRE ACT. START FINISH DUR. 2 2 2 2 2 2 2 3 3 3 3 3 3
WORK ITEMS
ACT. CODE DATE DATE (DAYS) 3 4 5 6 7 8 9 0 1 2 3 4 5

3 4 Footing Tie-Beam Day-___ Day-___

3 4.1 RSB Work Day-___ Day-___

4.1 4.2 Form Work Day-___ Day-___

4.2 4.3 Concrete Work Day-___ Day-___

WEEKLY PLANNED ACCOMPLISHMENT


(12)
WEEKLY PLANNED ACCOMPLISHMENT – (FOOTING TIE-BEAM)
WEEKLY PLANNED ACCOMPLISHMENT: (PERIOD: FEB. 4- FEB. 10,2019) ACTUAL ACCOMP.
STRUCTURE CONTRACT
FEB-4 FEB-5 FEB-6 FEB-7 FEB-8 FEB-9 FEB-10 WEEKLY QTIES.
QUANTITIES
1. FOOTING-TIE-BEAM M 15 T 16 W 17 T 18 F 19 S 20 S 21 QTIES. TO DATE

1. RSB WORK ______ KGS.

ADJUSTED QTIES-> ______KGS.

MANPOWER-> ___BARMAN

PLANNED M-HOUR-> =

ADJUSTED MHOUR-> =

WEEKLY PLANNED ACCOMPLISHMENT: (PERIOD: FEB 11 - FEB. 17, 2019) ACTUAL ACCOMP.
CONTRACT
2. FOOTING TIE-BEAM FEB-11 FEB-12 FEB-13 FEB-14 FEB-15 FEB-16 FEB-17 WEEKLY QTIES.
QUANTITIES
M 22 T 23 W 24 T 25 F 26 S 27 S 28 QTIES. TO DATE

1. RSB WORK ______ KGS.

ADJUSTED QTIES-> ______KGS.

MANPOWER-> ___BARMAN

PLANNED M-HOUR-> =

ADJUSTED MHOUR-> =

2. FORMWORK ______SQM.

ADJUSTED QTIES-> ______SQM.

MANPOWER-> ___Carpenter

PLANNED M-HOUR-> =

ADJUSTED MHOUR-> =
(13)
WEEKLY PLANNED ACCOMPLISHMENT: (PERIOD: MAR. 4 – MAR. 10, 2019) ACTUAL ACCOMP.
CONTRACT
2. FOOTING TIE-BEAM FEB-18 FEB-19 FEB-20 FEB-21 FEB-22 FEB-23 FEB-24 WEEKLY QTIES.
QUANTITIES
M 29 T 30 W 31 T 32 F 33 S 34 S 35 QTIES. TO DATE

1. RSB WORK ______ KGS.

ADJUSTED QTIES-> ______KGS.

MANPOWER-> ___BARMAN

PLANNED M-HOUR-> =

ADJUSTED MHOUR-> =

2. FORMWORK ______SQM.

ADJUSTED QTIES-> ______SQM.

MANPOWER-> ___Carpenter

PLANNED M-HOUR-> =

ADJUSTED MHOUR-> =

3. CONCRETEWORK ______CUM.

ADJUSTED QTIES-> ______CUM.

MANPOWER-> ____WORKER

PLANNED M-HOUR-> =

ADJUSTED MHOUR-> =

VARIANCE (DAYS)-> OVERALL = ACTUAL - PLANNED =

2. Determine the weekly labor cost, material cost and equipment cost with the given unit
costs in Test I.
WORK ITEMS LABOR COST MATERIAL COST EQUIPMENT COST

COLUMN-FOOTING & QUANTITIES Labor rate= Ph62/kg. Matl. Cost = Ph50/kg. Eqpt. Rental=250/hour

FOOTING TIE-BEAM Unit Cost Bid Cost Unit Cost Bid Cost Unit Cost Bid Cost

1. RSB WORK 5306 KGS. 12.40/KG. 50.00/KG. 8.30/KG.

2. FORMWORK 197 SQM. 51.62/SQM 800/SQM 0

3. CONCRETE 36 CUM. 103.33/CUM. 5000/CUM. 266.67/CUM.


(14)
3. Determine the weekly labor cost, material cost and equipment cost basing on the weekly
work schedule.

January 21 – February 13
WORK ITEMS DURATION (DAYS) 1st Week 2nd Week 3rd Week
Date Date Dura- 23 25 27 29 31 3 5 7 9 11 13
Column-Footing
Start Finish tion 2 4 6 8 10 13 15 17 19 21 23

1. RSB Work Day-__ Day-__

2. Formwork Day-__ Day-__

3. Concreting Day-__ Day-__

RSB (_____kgs.)-> ___ /___= _____kgs/day 2. 3. 4.

Form (___Sqm)-> ___ /___ = _____sqm/day 0 0 5.

Conc. (17Cum.)-> ___ /___=_____ cum/day 0 0 6.

Material Kgs. _____ _____ _____ 7. 8. 9.

Budget Sqm. 0 0 _____ 0 0 10.

Cost => Cum 0 0 _____ 0 0 11.

Labor Kgs. _____ _____ _____ 12. 13. 14.

Budget Sqm. 0 0 _____ 0 0 15.

Cost => Cum 0 0 _____ 0 0 16.

Equipment kgs. _____ _____ _____ 17. 18. 19.

Budget Sqm. 0 0 _____ 0 0 0

Cost => Cum 0 0 _____ 0 0 20.

Labor Cost => 21. 22. 23.


Total
Material Cost => 24. 25. 26.
Planned Weekly
Equipment cost => 27. 28. 29.
Cost=>
Total Costs => 30. 31. 32.
(15)
February 6 – February 28
WORK ITEMS DURATION (DAYS) 3rd Week 4th Week 5th Week
Date Date Dura- 7 9 11 13 15 18 20 22 24 26 28
Footing Tie-beam
Start Finish tion 17 19 21 23 25 28 30 32 34 36 38

3.1. RSB Work Day-__ Day-__

3.2. Formwork Day-__ Day-__

3.3. Concreting Day-__ Day-__

RSB (_____ kgs.)-> ____ /___= _____kgs/day 1. 2. 3.

Form (____Sqm)-> ____ /___ = ____sqm/day 0 0 4.

Conc. (___Cum.)-> ____ /____= cum/day 0 0 5.

Material Kgs. _____ _____ _____ 6. 7. 8.

Budget Sqm. 0 0 _____ 0 0 9.

Cost => Cum 0 0 _____ 0 0 10.

Labor Kgs. _____ _____ _____ 11. 12. 13.

Budget Sqm. 0 0 _____ 0 0 14.

Cost => Cum 0 0 _____ 0 0 15.

Equipment kgs. _____ _____ _____ 16. 17. 18.

Budget Sqm. 0 0 _____ 0 0 0

Cost => Cum 0 0 _____ 0 0 19.

Labor Cost => 20. 21. 22.


Total
Material Cost => 23. 24. 25.
Planned Weekly
Equipment cost => 26. 27. 28
Cost=>
Total Costs => 29. 30. 31.