Name:____________________________Section:__________Date:________________
Test I
In connection with the work planning and scheduling, (we performed last prelim exam),
re-estimate the necessary labor, material and equipment for the column-footing and
footing-tie-beam. Determine the unit costs of RSB work, formwork and concrete-work with
respect to the labor cost, material cost and equipment cost with the following given: labor rate
= 62/HR; material: RSB = 50/kg; form = 800/sqm; concrete = 5000/cum; equipment rental: RSB
= 250/HR; concrete = 800/HR. These unit costs will be the factors to determine the weekly
labor cost material cost and equipment cost requirement in your Weekly Schedule.
A B C D
5.0 F2C2 5.0 F2C2 5.0
F1C1 F1C1
1
FTB-1 FTB-1 FTB-1
4.0
FTB-1 FTB-1 FTB-1
F2C2 2
F2C2
F3C3 F3C3
4.0
FTB-1
3
F1C1
F2C2 F2C2 F1C1
L W t a b h1 CVB c d L1
FOOTING COLUMNS FOOTING TIE-BEAM
F1 1.5 1.5 0.3 C1 0.3 0.3 4.5 #12 FTB-1 0.3 0.5 8.0
F2 1.5 2.0 0.4 C2 0.3 0.4 4.5 #14 FTB-1 0.3 0.5 13.0
F3 2.5 2.5 0.5 C3 0.4 0.4 4.5 #16
(1)
c
4-20mm –Bar 1
d
4-16mm –Bar 3
10mm – STIRRUPS
SECTION OF FTB-1
A B C D
5.0 5.0 5.0
a b c c
d1
d2
FOOTING ELEVATION SHOWING CONCRETED FOOTINGS & INSTALLED RSB FOR FTB
A B C 4-20mm –Bar 1x D
4-20mm –Bar 1x 4-20mm –Bar 1y
4-20mm –Bar 2x 4-16mm –Bar 3x 4-20mm –Bar 2y 4-16mm –Bar 3y 4-20mm –Bar 2x
1 2 3
4-20mm –Bar 1
4-16mm –Bar 3 4-20mm –Bar 2
(2)
A B C D
TOP OF FIRST LIFT COLUMN
FINISH GROUND SLAB
0.6
FTB-1
cc L cc
H FTB: - 16mm BOTHWAYS
FTB: 16mm @ 0.20 m. ON CENTER BOTHWAYS
t
PLAN OF FOOTING
FBB: – 16mm BOTHWAYS
(3)
SOLUTION:
1. Estimate the material quantity (RSB, form, and concrete).
Part of Structure Mark Qties. L W t a b h1 c d L1
<>FOOTING -1 F1 1.5 1.5 0.3 x x x x x x
F2-C2
Concrete Volume =>
F3-C3 M3
FTB-1
F1-C1 A= A= A=
F2-C2
Area of Form =>
F3-C3 M2
FTB-1
RSB => -do- Refer to the Bar Schedule Refer to the Bar Schedule Refer to the Bar Schedule
C2
CVB
Hoops
C3
CVB
Hoops
FTB-1
Bar-1
Bar-2
Bar-3
Stirrup
FTB-1
Bar-1x
Bar-2x
Bar-3x
Bar-1y
Bar-2y
Bar-3y
Stirrup
S FRAME-A L W H Form
BOARD
(m) (m) (m) Area/Ftg.
COLUMN DETAIL
Structure SIDE-FORM DETAIL COLUMN DIMENSION
FRAME-A a b L Form
(6)
Qty =_____________________________________ 2.2. Frame-B: N = {L}/s
C1
Marine Plywood N = ____________________________________pcs.
C1F1
Assume Assume
C2F2 1-CM Assume
______ 6 _____ 2 ______
C3F3 & 5 Supplied
Kgs. Rebar- Sqm. Carpen- cum
Footing Tie-beam 1-BM men
man ter
FTB-1
MH = Qty. / WP MH = Qty. / WP MH = Qty. / WP
MH Computation = ___________________ = ____________________ = ____________________
= _______________mhrs. = _______________mhrs. = _______________mhrs.
D = MH/MP(8 hrs/day) D = MH/MP(8 hrs/day) D = MH/MP(8 hrs/day)
Work Duration
= _________________days = _________________days = _________________days
3. Determine the unit costs on labor, material and equipment of Work Items basing from the
labor cost, material cost and equipment cost.
WORK ITEMS QUANTITIES LABOR COST MATERIAL COST EQUIPMENT COST
UNIT COST=>> 4. 5. 6.
UNIT COST=>> 8. x x
COLUMN-FOOTING & QUANTITIES Labor rate= Ph62/kg. Matl. Cost = Ph50/kg. Eqpt. Rental=250/hour
FOOTING TIE-BEAM Unit Cost Bid Cost Unit Cost Bid Cost Unit Cost Bid Cost
Prepare a Weekly Schedule for the Column-footing and Footing-tie-beam basing from the
illustrations in Test I. Indicate the daily and weekly plan accomplishment with the corresponding
manpower, material and equipment cost considering the unit costs computed in Test I as shown
in Table below.
MANPOWER MATERIAL EQUIPMENT
RSB WORK LABOR RATE PH 21.43/KG. UNIT COST PH 78.4/KG UNIT COST PH 13.02/KG.
CONCRETE LABOR RATE PH 162/CUM UNIT COST PH 7840/CUM UNIT COST 418.13/CUM
MANPOWER-> ____BARMAN
PLANNED MHRS->
ADJUSTED M-HOUR->
MANPOWER-> ____BARMAN
ADJUSTED M-HOUR-> =
(11)
WEEKLY PLANNED ACCOMPLISHMENT: (PERIOD: FEB. 4 - FEB. 10, 2019) ACTUAL ACCOMP.
CONTRACT
1. COLUMN-FOOTING FEB-4 FEB-5 FEB-6 FEB-7 FEB-8 FEB-9 FEB-10 WEEKLY QTIES.
QUANTITIES
M 15 T 16 W 17 T 18 F 19 S 20 S 21 QTIES. TO DATE
MANPOWER-> ____BARMAN
PLANNED M-HOUR-> =
ADJUSTED MHOUR-> =
2. FORMWORK ______SQM.
MANPOWER-> _CARPENTER
PLANNED M-HOUR-> =
ADJUSTED MHOUR-> =
M 22 T 23 W 24 T 25 F 26 S 27 S 28 QTIES. TO DATE
3. CONCRETEWORK ______CUM.
MANPOWER-> ____WORKER
PLANNED M-HOUR-> =
ADJUSTED MHOUR-> =
MANPOWER-> ___BARMAN
PLANNED M-HOUR-> =
ADJUSTED MHOUR-> =
WEEKLY PLANNED ACCOMPLISHMENT: (PERIOD: FEB 11 - FEB. 17, 2019) ACTUAL ACCOMP.
CONTRACT
2. FOOTING TIE-BEAM FEB-11 FEB-12 FEB-13 FEB-14 FEB-15 FEB-16 FEB-17 WEEKLY QTIES.
QUANTITIES
M 22 T 23 W 24 T 25 F 26 S 27 S 28 QTIES. TO DATE
MANPOWER-> ___BARMAN
PLANNED M-HOUR-> =
ADJUSTED MHOUR-> =
2. FORMWORK ______SQM.
MANPOWER-> ___Carpenter
PLANNED M-HOUR-> =
ADJUSTED MHOUR-> =
(13)
WEEKLY PLANNED ACCOMPLISHMENT: (PERIOD: MAR. 4 – MAR. 10, 2019) ACTUAL ACCOMP.
CONTRACT
2. FOOTING TIE-BEAM FEB-18 FEB-19 FEB-20 FEB-21 FEB-22 FEB-23 FEB-24 WEEKLY QTIES.
QUANTITIES
M 29 T 30 W 31 T 32 F 33 S 34 S 35 QTIES. TO DATE
MANPOWER-> ___BARMAN
PLANNED M-HOUR-> =
ADJUSTED MHOUR-> =
2. FORMWORK ______SQM.
MANPOWER-> ___Carpenter
PLANNED M-HOUR-> =
ADJUSTED MHOUR-> =
3. CONCRETEWORK ______CUM.
MANPOWER-> ____WORKER
PLANNED M-HOUR-> =
ADJUSTED MHOUR-> =
2. Determine the weekly labor cost, material cost and equipment cost with the given unit
costs in Test I.
WORK ITEMS LABOR COST MATERIAL COST EQUIPMENT COST
COLUMN-FOOTING & QUANTITIES Labor rate= Ph62/kg. Matl. Cost = Ph50/kg. Eqpt. Rental=250/hour
FOOTING TIE-BEAM Unit Cost Bid Cost Unit Cost Bid Cost Unit Cost Bid Cost
January 21 – February 13
WORK ITEMS DURATION (DAYS) 1st Week 2nd Week 3rd Week
Date Date Dura- 23 25 27 29 31 3 5 7 9 11 13
Column-Footing
Start Finish tion 2 4 6 8 10 13 15 17 19 21 23