Professional Documents
Culture Documents
of FPSO Standardisation
Andrew Newport
Schiedam, 13th December 2018
1/29/2019
Scope of presentation
1/29/2019 3
Objectives of standardisation
1/29/2019 13
Generic FPSO Failures
Launch Closure
Project Contractor Status
Date Date
Nexus 1 FPSO built on
speculation, laid up and finally sold
Nexus 1 FPSO Nexus 2006 2009
to OSX and reconverted to OSX1
FPSO. Programme cancelled.
Bankrupt. FPSO abandoned part
Deep Producer FPSOcean 2007 2009
constructed, later sold.
East Fortune Bankrupt. Vessels sold for
Nortechs 2006 2010
FPSO reconversion.
The first generic unit was modified
to include a turret mooring and a
Aker Smart Aker Floating
2006 2010 major topsides upgrade.
FPSO Production
Programme for 4 FPSOs cancelled
after first FPSO.
1/29/2019 © SBM Offshore. All rights reserved. www.sbmoffshore.com 14
Generic FPSO successes
1 FPSO Falcon
2 FPSO Serpentina
3 FPSO Xikomba
4 FPSO Mondo
5 FPSO Saxi Batuque
1/29/2019 © SBM Offshore. All rights reserved. www.sbmoffshore.com 16
Extent of standardization of the series for ExxonMobil
maximum − minimum
System parameter deviation around mean, Devi
2 x mean
∑
1
j
‘Upper Deck Renewal and Topsides Integration, the Example of Cidade de Maricá and Cidade de Saquarema’
Arselin, Jarry, Marchalot, d’Este, DOT 2015
1/29/2019 28
Incorporating lessons learnt
Fast4Ward™ is based
Our ambition is to transform the business by on five key principles
reducing cycle time to energy delivery, de- 1. Client first
risking projects, and improving quality & safety. 2. Standardization
This is what we refer to as
3. Flawless execution
Fast4Ward™ 4. Integrated supply chain
5. Enabling digital solutions
Enabling
Reducing De-risking
lower break-
cycle time projects evens
FEED contract awarded for 2nd FPSO Liza field offshore Guyana
Construction and Installation, Lease and Operate contracts
awarded for a period of up to 2 years, subject to project sanction
Oil production capacity of 220,000 bbls/day
> 4 billion boe
discovered since 2015
source: ExxonMobil
1/29/2019