Professional Documents
Culture Documents
For
Bhadrak
Final
June- 2017
Consultants:
Feedback Infra Private Limited In Joint Venture with B. E. Consultants
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Note
The Master Plan Area tallies with the constituent Major settlement area.
The English Spelling of the Revenue Villages occurring in the Plans tallies
with the Revenue Records.
The existing and proposed areas as shown in the Master Plan area derived
Acknowledgement
offices and institutions as well as general public for their association and co-
operation in the process of preparation of GIS/RS based Master Plan for Bhadrak
(Final).
PREFACE
Cities demand huge investments for their development. Large resources are spent on the development of
various urban settlements but the conditions of these cities continue to deteriorate because of piecemeal nature
of expenditure and lack of definitive development schemes. Adhoc efforts neither result in better environment
nor strengthen the economic base. In view of this, the Special Planning Authority (SPA), Bhadrak has undertaken
the Preparation of GIS/RS based Master Plan of Bhadrak. The Master Plans are expected to give impetus to the
development and economic growth of the city. The SPA, Bhadrak has given this assignment to M/s Feedback
Infra Private Limited, Gurgaon. The GIS/RS based Master Plan of Bhadrak is prepared for the perspective year
2030.
The studies involved in the preparation of GIS/RS based Master Plan of Bhadrak concerns with the areas crucial
to planning and development of the region. It has been a great privilege M/S Feedback Infra Private Limited,
At this juncture, the main purpose for M/s Feedback Infra Private Limited, Gurgaon and M/s B.E. Consultants,
Jaipur in putting this document is to solicit greater participation, meaningfulness and make the GIS/RS based
Master Plan of Bhadrak acceptable to stakeholders who have a role to play in its development and
implementable for the Local Authority.
BE Consultants, Jaipur
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
LIST OF ABBREVIATIONS
AQM : Ambient Quality Monitoring
ASP : Activated Sludge Process
bgl : Below Ground Level
BOD : Biological Oxygen Demand
BOD : Biological Oxygen Demand
BPA : Bhadrak planning Area
CBD : Central Business District
CC : Community Centre
CMP : Comprehensive Master Plan
COD : Chemical Oxygen Demand
COD : Chemical Oxygen Demand
i
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
MT : Million Tonnes
MVA : Mega Volts
MW : Mega Watt
NAC : Notified Area Council
NESCO : North Eastern Electricity Supply Company of Odisha Limited
i
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Contents
1. Introduction .................................................................................................................................... 9
1.1 Introduction ................................................................................................................................................ 9
1.2 Broad Objective of the Master Plan ............................................................................................................ 9
1.3 The Vision .................................................................................................................................................... 9
1.4 Planning Area ............................................................................................................................................ 10
1.5 Planning Issues of Bhadrak Master Plan ................................................................................................... 10
1.6 The Purpose of Master Plan ...................................................................................................................... 10
1.7 The Planning Process................................................................................................................................. 11
1.8 Structure of the Report ............................................................................................................................. 12
1
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
4.2 Structure and Concept of the Bhadrak Master Plan Area ......................................................................... 29
4.3 Salient features of The Master Plan .......................................................................................................... 31
4.4 Conclusions ............................................................................................................................................... 32
5. Demographic and Economic Perspective ........................................................................................ 33
5.1 Introduction .............................................................................................................................................. 33
5.2 Population Characteristics ........................................................................................................................ 33
5.3 Population Estimation ............................................................................................................................... 35
5.4 Economic Perspective ............................................................................................................................... 36
6. Traffic and Transportation ............................................................................................................. 40
6.1 Introduction .............................................................................................................................................. 40
6.2 Study Area and Traffic Zone ...................................................................................................................... 40
2
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
7.13 Policy for Housing for All in Urban Areas, Odisha-2015 ............................................................................ 93
8. Physical Infrastructure ................................................................................................................... 95
8.1 Water Supply ............................................................................................................................................. 95
8.2 Sewerage System ...................................................................................................................................... 96
8.3 Drainage .................................................................................................................................................... 99
8.4 Solid Waste Management ....................................................................................................................... 101
9. Social Infrastructure .....................................................................................................................111
9.1 Introduction ............................................................................................................................................ 111
9.2 Education ................................................................................................................................................ 111
9.3 Health Care.............................................................................................................................................. 112
9.4 Other Social Infrastructural facilities....................................................................................................... 114
3
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
4
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
List of Tables
Table 2.1: Administrative Setup of Bhadrak District 13
Table 3.1: Distribution of Existing Land Use of Urban Area (Municipal Area) 23
Table 6.2 Volume Count Survey Analysis as per Type of Survey and Location 45
5
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Table 8.7: Land Area Requirement for Solid Waste Dumping Site 110
Table 9.1 Existing Educational facilities and Future Requirement in Bhadrak 111
Table 13.3 Details of Neighborhood Centers (10 Hectares for 10000 to 12,000 population) 143
Table 13.4 Details of Neighborhood Centers Provisions (10 Hectares for 12001 to 15,000 population) 143
Table 14.1 Shows the (a) Uses/Activities Permitted (b) Uses/Activities permissible on application to the
Competent Authority (with conditions / up to 30% area on special consideration) & (c) Activities Prohibited as it
has been already stated according to the Model Zoning regulations. 158
Table 14.2 Spatial Norms and Standards 166
Table 15.1: Sector Wise Investment for Bhadrak Planning area 173
Table 15.2: Summation of Sectoral Investment Plan for Bhadrak Planning Area 176
6
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
List of Figures
Figure 2.1: Location of Bhadrak Town ..................................................................................................................... 14
Figure 2.2: Topographical Map of Bhadrak Region ................................................................................................. 14
Figure 6.2 Volume Count Survey Analysis as per Type of Survey and Location ..................................................... 45
Figure 6.3 Road Inventory on Randhia Road towards Anandapur Stretch ............................................................. 47
Figure 6.4 Road Inventory on Aradi Road Stretch .................................................................................................. 48
7
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Figure 7.4: Existing Slum Pockets in Bhadrak Municipal Council Area .................................................................... 89
Figure 13.2 Bhadrak Proposed Land Use Distribution of Developed area -2030 ................................................. 139
Figure 13.3 Bhadrak Proposed Land Use Distribution of the Planning Area -2030 .............................................. 139
List of Maps
Map 6.1: Proposed Road Network- Bhadrak ........................................................................................................... 71
Map 9.1: Locations of Main Power Stations & Sub-Stations in Bhadrak ............................................................... 116
Map 13.1: Proposed Bhadrak Planning Area Land Use Plan -2030 ....................................................................... 141
8
1
Introduction
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
1. Introduction
1.1 Introduction
M/s Feedback Infra Private Limited, Gurgaon in joint venture with B. E. Consultants, Jaipur has submitted the
long term Master Plan for Bhadrak and provide vision to the anticipated development for the target year 2030 in
July 2015. In the Master Plan / Perspective Plan, broad level strategies and policies on various aspects of urban
development were provided. To translate these broad level strategies into implementable medium term
planning proposals in Master Plan is formulated within the framework detailed out in the Odisha Town Planning
and Improvement Trust Act, 1956.
This vision statement is neither a prediction of what will actually occur, nor simply a wish list of desirable but
unattainable ends. Rather, it is a statement of what is possible for Bhadrak to achieve, through proper
mobilization of all the available resources (human, organizational, technological and financial), generating the
required will and making the necessary effort.
9
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
10
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
and regional coordination. It is also the basis for taking day to day decisions on land use conversion that follow
an optimistic and hopeful long term vision.
According to the Odisha Town Planning and Improvement Trust Act, 1956, Master Plan / Comprehensive
Development Plan:
shall define the various zones into which the land covered by the Comprehensive Development Plan
may be divided for the purpose of development and indicate the manner in which the land in each zone
is proposed to be used (whether by the carrying out thereon of development or otherwise) and the
stages by which any such development shall be carried out;
Serve as a basic pattern of framework within which the Zonal Development Plan of the various zones
may be prepared.
Using the provision of the Act and the rules, these will comprise of:
Demography
Economy
Traffic & Transportation
Housing & Slums
Physical Infrastructure
Social Infrastructure
Culture, Recreation and Tourism
Heritage and Conservation
Environment
Development Management
The preparation of the Plan started with the assessment of the existing conditions and accounting for the
potential resources and constraints for development. Thereafter, development priorities were set up for the
urban area taking into consideration of the socio-economic and other infrastructure needs. The formulation of
11
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
the Plan for the development area started after status analysis and consideration of the prime issues as
indicated in the following six stages as stated below:
Stage-1: The Plan had delineated BPA into 2- planning zones considering mainly, drainage network,
transportation network, ground water prospect, vegetable index, land use land cover, physical boundary and
administrative boundary. These 2 planning zones were then superimposed with the mouza boundaries and plot
boundaries.
Stage-2: The study of existing land use of the planning zones was carried out. After the required land use study
and analysis, the existing central functions in the various zones were identified. This helped in the assessment of
the type and quantum of the various central functions and land uses in the planning zones.
Stage-3: Subsequently identification of vacant land as well as plot wise ownership (Public & Private) of the
planning zones was carried out. Also the potential locations for distribution of land uses/central functions in the
various planning zones were evaluated.
Stage-5: Consisted of the implementation mechanism with respect to legal, administrative & financial aspects.
The aspects necessarily included Fiscal Planning, Implementation Agencies, and Administrative Planning reforms
in the present setup/new administrative set-up for development rules & regulations for future growth and
development.
Stage-6: Prepared the future land use plan and their zone wise distribution and subsequently formulated zoning
regulations as per the Odisha Town Planning and Improvement Trust Act, 1956.
The first chapter has explained the broad objectives, purpose and the process of the Master Plan in light of the
vision for the development of the Bhadrak Planning Area, with an overview of the planning issues in the area.
The second chapter provides an overview of the Bhadrak Planning Area with respect to administrative
jurisdiction, geographical setting, topography, climate, soil, water resource, socio-economic characteristics,
nature of development and landform, chronological growth of settlement, economy, traffic and transportation,
housing, physical infrastructure, social infrastructure, cultural, recreation and tourism and heritage and
conservation. The third chapter explains the existing land use & land ownership in BPA of all the delineated
planning zones. The fourth chapter outlines the Planning Strategy of the proposed plan and integrates the
Functional Structure for the achievement of the same.
The chapters fifth to twelfth give the policies of development and sectoral plans of the various aspects namely
Population & Economic Perspective, Traffic & Transportation, Housing & Slums, Physical Infrastructure, Social
Infrastructure, Culture, Recreation and Tourism, Heritage and Conservation, Environment and Development
Management respectively, because development in a comprehensive sense requires improvement in socio-
cultural, economic, administrative and physical dimensions of a society. The thirteenth chapter outlines the
Future Land Use with the potential locations for distribution of population, land uses and central functions in the
various planning zones through the assessment of the type and quantum of the various central functions and
land uses in the planning zones. While the Fourteenth chapter deliberates with the financial implication of the
plan including suggested guidelines of resource mobilization.
12
2
Bhadrak Master Plan Area-
Overview
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
District Sub District Name of Town Population Share in Total Class of Town
District Urban
1,85,838 100 %
Dhamanagar 22,920
Dhamanagar (NAC) 22,920 12.33 % IV
Bhadrak 1,26,960
Bhadrak
Bhadrak (M+OG) 1,19,070 64.07 % I
Erein (CT) 7,890 4.25 % V
Basudebpur 33,690
Basudebpur 33,690 18.13 % III
Source: Census of India, 2011
13
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
2.4 Topography
Bhadrak town is located on the
coastal plain. The town can be
bifurcated into two physiographic
divisions. The area encompassed by
Chandbali bypass, National Highway –
16, railway lines, MDR-73, High Level
Canal and road leading to Kothar is
generally up land. The contour of this
area is varies from 69’ in North-West
corner of the town to 46’ South-East.
This area constitutes the developed
portion of the town. The river bank of
Salandi is high and slopes down
towards South-East. Intervening
vacant lands are utilized for paddy
cultivation. This area is subject to Figure 2.2: Topographical Map of Bhadrak Region
water logging during high floods.
The area beyond this is follow and agricultural lands with contour declining from 49’ to 34’ in South-East
direction. Area towards North-West is slightly up-land and is suitable for industrial uses. The present Bhadrak
town is nucleated in these areas namely Puruna Bazaar, Charampa and Naya Bazaar.
14
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
2.6 Climate
2.6.1 Temperature
The temperature in summer season at Bhadrak is about 48° C. The summer season starts with April month and
ends with the month of June. Winter starts from end of October and remains till February month. The chilled
climate of this region can be felt easily. The temperature during winter season is generally 17° C. The month of
December is the coldest month of the year.
2.6.2 Rainfall
The monsoon season starts from July and remains as it till October end. The rainfall during July to October
comprises of at least 75% of the total rainfall at Bhadrak region. The relative humidity is generally high from July
to November. The morning RH ranges from 43 to 68 % and afternoon from 88 to 92 %.
2.6.3 Wind
The wind velocity is moderate throughout the year and it becomes stronger during the south-west monsoon.
During the south-west monsoon, the average wind speed is 15 kms per hour and it drops to 5-10 kms per hour in
October. From October to January, the wind direction is from North East to South West and the direction is
reversed during South West monsoon when it is from South West to North East. During November to February,
the prevailing wind direction is from North- North East to South- South West.
2.6.4 Soil
Broadly, the soil of Odisha may be classified as transported and residual soil on the basis of its mode of
formation. The catchment basins of the different drainage systems are dominated by granite and gneissic rocks,
which have resulted in a sandy soil. Clayey soils predominate in middle and lower reach of the drainage
channels. The coastal stretch of state is dominated by Deltaic Alluvial soil followed by Saline & Sandy Saline Alkali
soil and Coastal Alluvial soil. The Bhadrak region has Deltaic Alluvial Soils.
15
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
16
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The common birds, mammals, rodents, reptiles and fishes are also found in the Bhadrak region. No endangered
species of plants and animals has been found in planning area.
17
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
spaces. Majority of the middle and high groups are inhabited on the peripheral newly developed areas. the
urban sprawl has taken place in all directions but more significantly in the northern and southern directions.
During the Murundas period the town developed around the South-West and South-East bank of Salandi. The
physical development was very slow and this continued till 1110 when the Ganges dynasty was followed by
Suryavamsis. During the period of Suryavamsis Bhadrak rose to prominence as a maritime and agrarian trade
centre. With the down fall of the dynasty the area plunged into political chaos. The Afghans took advantage of it
and were in power till 1592. In 1575 a large Muslim population began to settle down at Bhadrak. This marked
Bhadrak was annexed under British rule in 1803. In June 1804 after British occupied the Odisha, Cuttack and
Bhadrak were two administrative divisions. In 1828 Bhadrak was made the separate town with Bhadrak as sub
division. Following the colossal famine of 1868 the administration was compelled to emancipate its approach
and thereafter, stress was put on reconstruction and reorganization of the economy. In 1880 the Odisha coast
canal connecting the Hoogly at Geonkhali with the river Matai at Charbatia, was constructed to serve as a trade
route. The canal was opened for traffic in 1887. In 1891 the High Level Canal was constructed. In 1895-96 work
on the constructed of B.N. Railway line was initiated. It was completed and opened for goods and passengers
traffic in October 1899. The transport routes namely Calcutta Madras National Highway – 16, the Bhadrak-
Chandbali Road (S.H.-9), MDR-73 and communication easier and helped the pace of development.
2.12 Economy
Bhadrak has been primarily an important collection and distribution centre with a vast agro-forest hinter land.
But because of its location in the core of the cyclonic tract originating in the Bay of Bengal and causing natural
hazards in the coastal tract, its growth could not sustain and the town remained static till the turn of the
century. After the construction of railway line from Howrah to Madras the town developed as an important
transport node for the surrounding region. The transport function gained momentum with the construction of
S.H.-9 and a number of major District Roads. These gave rise to the development of trade and commerce.
Gradually administrative and institutional functions developed and the preponderance of services was clearly
perceptible since 1951.
18
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The nearest railway station is Bhadrak which is 62 kms away from Dhamra on Chennai-Howrah line. Dhamra is
connected by road with Bhadrak (82 kms), the nearest major town on the National Highway-16.
19
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
20
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The health facilities in Bhadrak are generally delivered by Government and private sectors. The major health
facilities are under private ownership. The primary health centres (PHCs), Hospitals, nursing homes, dental clinic,
dispensaries, eye hospitals, trauma centre etc are distributed in the planning area.
The Bhadrak is lacking of other facilities i.e. entertainment, recreational, sports, socio-cultural centres, multiplex
etc.
21
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
2332000 .000000
2332000 .000000
Bh
ay
ad
R ailw
rak
To
A ern
na ast
-D
nd E
ap u th
ha
u r So -16
NH
mr
aR
ly.
SH
SH - 9
-53
ack
C utt
To
2328000 .000000
2328000 .000000
Salandi Riv
To
er
Dh
am
ra
SH
To C
-
han
35
dba
li
ck
tta
Cu
To
2324000 .000000
2324000 .000000
To
A
ra
di
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
RANJA NO 131
!!
!
!
! !
!
!
!
!
!
!
!!
!
!
2
! ! ! !
!
!
!
!
Bh
!! ! !
! !! !!
!
ad
!
!
!!
rak
!
2332000 .000000
2332000 .000000
!!
!!
4
- Dh
!
!!
!
!
EREIN NO.141
1
am
!
!!
!
5
!
!
! !
!
!
ra
!!
!
!
ay
R
!!
ailw
ly.
!!
To R
!!
A ern
ast
!!
E
TENTULIGARIA NO. 144
nd
!
ap th
!!
u 6
u So -1
OGALPUR NO. 114
!
r
!
NH
KHORDANG NO.140
!
!
!!
KUNTALA NO.143
7 6
!!
!
!
!
!
!!
PALSINGA NO.142
BAUDPUR NO.113
SH
!!
SH -
!!
9
!!
!!
KUNTALA NO.143 SARGARIA NO. 146
-53
!!
KORANT NO.62
!!
!!
16 BHAGABANPUR NO.147
11
To
!!
!
!!
!
!
!
Dh
!
!!
!
!!
!
10 15
! !
!
!!
am
!
8
!! !!
HAMIRBINDHA NO.108
!!
RANDIA NO.63
ack
!
!
!!
!!
utt
ar
17
!!
!
!
!
C
!
a
!
To 9 12
!!
!
!
!!
!! !!
18
!
!!
!
! !!
!
MALIARUA NO.148
22
!! !! !!
!!
24
!!
! !
!
20
! !
!
2328000 .000000
2328000 .000000
!
!
NACHHIPUR NO.149
!
14
!!
19
!
AMARGARIA NO. 58 21 23
!!
! !
!!
!
! !
BRAMHAPUR NO.150
!
13
!!
!!
!
!!
!
SAMARAEPUR NO.86
!!
26
! ! !
!
!
!!
To C
!
! !
GELPUR NO.64
!
25 h
!
andb
!
!
!
ali
!!
!
BIRIPARA NO. 57
!
ELEKHA NO.96
!!
!!
!!
KEDARPUR NO.151
!!
!!
! !
! !
!!
! !
SH
!!
!
!
! !
-
! !
35
!
KADAPATA NO. 65
!
!! !
!
30
!!
!
!!
BHABANIBINDHA NO 152
29
!
!!
BARADADIHI NO.85
!
28
!!
!
!
!
!!
!!
!!
RAJPUR NO. 84
!!
!!
!!
NALANGA NO. 66
!
KORAKORA NO.97
!!
ck
!
BIJEGANGADHARPUR NO. 153
!
!!
!
!
!!
!
ta
!
!
!!
!
SAIDABAD NO.100
ut
!!
!
!!
!
!!
!
! !
C
!!
TIHIRI NO. 82
! !!
!
To
!!
!!
!
!
!
!
!
!
!
2324000 .000000
2324000 .000000
! !
HARIPUR NO. 99
!
!
!!
!!
!
!!
BILABARI NO. 81
!
! !
!
!
!
! !
!
!
To
!
!!
NANGURI NO. 77
!
A
!
!!
ra
!!
di
!!
!
!
BALAJITPARA No. 78
!!
!!
!!
State Highway
Planning Boundary
Municipal Boundary
Administrative Map of
Bhadrak Master Plan Area
Special Planning Authority
Bhadrak
0 375 750 1,500 Meters
Ü
!
! !! !
!
!!
!! !! !
Village Boundary
15th Floor, Tower 9B, DLF Cy bercity, Phase-III
Gurgaon 122 002, Hary ana, INDIA
Phone: +91 124 416 9100
Web: www.feedbackinfra.c om
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
3
Land Use and Land
Ownership
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
22
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Considering the planning area, it is revealed from the Table 2.1 that the agriculture land use (62.78%)
constitutes the major part of the area followed by residential (19.57%) land use.
3.2.2.1 Urban Area (including Municipal Area, Outgrowths & census town)
Developed area
The total Urban area is about 3722.60 hectares consists of developable area 37.11% and remaining 62.89% area
is undevelopable. The gross residential density of developed area is 92 PPH and net residential density is 128
PPH, which indicates congested growth of the town including outgrowth. Bhadrak lacks planned residential
colonies and the organic growth has resulted in urban sprawl and inefficient utilization of land. Physical
thresholds have played dominant role for shaping the urban structure of town. The major commercial activities
are concentrated in the core area of the town. The commercial land use is 2.69% of the developed area and 1%
of the total urban area. The mixed land use is also available in the urban area of Bhadrak comprises of 8.89
hectares of land area occupies 0.64% of the developed area and 0.24% of the total urban area. Under industrial
Un -developable area
The un developable area is comprises of agriculture, forest , water bodies and environmentally sensitive land
uses. The total area under un developable category is 2341 hectares which is 62.89% of the total urban area. The
maximum percentage area of the land use is covered under agriculture land use, followed by water bodies and
environmentally sensitive land uses. The minimum percentage area is under forest i.e 8.50 hectare.
Table 3.1: Distribution of Existing Land Use of Urban Area (Municipal Area)
Developable area
1 Residential 993.24 71.89 26.68
2 Commercial 37.23 2.69 1.00
3 Mixed Use 8.89 0.64 0.24
4 Industrial 86.07 6.23 2.31
5 Pub & Semi Public 77.66 5.62 2.09
6 Public Utilities & Facilities 4.30 0.31 0.12
7 Recreational 5.98 0.43 0.16
8 Transportation 168.21 12.17 4.52
Sub total (Developed land) 1381.59 100.00 37.11
Un - Developable area
9 Agricultural 1965.03 52.79
23
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Residential
Developed Urban area
Figure 3.2: Existing Land Use Distribution (Developed Urban Area & Total Urban Area)
Developable area
The rural area is occupies 4311.51 hectares consists of 777.53 hectares of developable area i.e 18.03% of the
total rural area and remaining 3533.99 hectares of land under un-developed area which is 81.97% of the total
rural area. The gross density of developable area is 33 PPH and net residential density is 44 PPH. The existing
development pattern shows the segregated settlement pattern in the rural area. The percentage of land comes
under residential land use 579.33(74.51%) hectares followed by traffic & transportation land use 118.89(15.29%)
hectares and public & semi public 26.96(3.47%) hectares.
Un -developable area
Un developable area is comprises of agriculture, forest, water bodies and environmentally sensitive land uses.
The total area under un developable category is 3533.99 hectares which is 81.97% of the total rural area. The
maximum percentage area of the land use is covered under agriculture land use, followed by water bodies and
environmentally sensitive land uses. The minimum percentage area is under forest i.e 23.49(0.54%)hectare.
24
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Developable area
1 Residential 579.33 74.51 13.44
2 Commercial 11.95 1.54 0.28
3 Mixed Use 0.69 0.09 0.02
4 Industrial 26.58 3.42 0.62
5 Pub & Semi Public 26.96 3.47 0.63
6 Public Utilities & Facilities 6.43 0.83 0.15
Un - Developable area
9 Agricultural 3079.19 71.42
10 Forest 23.49 0.54
11 Water Bodies 229.28 5.32
12 Environmentally Sensitive 202.02 4.69
Sub total (Un developed Land) 3533.99 81.97
Residential
Developed Rural area Total Rural area Commercial
Residential
0.86% 5.32%
4.69% 0.28% 0.02% Mixed Use
Commercial 0.54% 0.62%
Industrial
0.83% 0.63% 0.15%
13.44%
3.47% 15.29% Mixed Use 0.16%
Pub & Semi Public
Environmentally
Sensitive
Figure 3.3: Existing Land Use Distribution (Developed Rural Area & Total Rural Area)
25
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
EXISTING
S.No Land Use Category Total %age of %age of As per URDPFI
Existing Area Developed Area Planning Guidelines
(in ha) Area
(Developable land)
1 Residential 1572.58 72.83 19.57 45-50
2 Commercial 49.18 2.38 0.61
2-3
3 Mixed Use 9.58 0.44 0.12
4 Industrial 112.65 5.22 1.40 8 - 10
5 Pub & Semi Public 104.63 4.85 1.30 6-8
Figure 3.4: Existing Land Use Distribution (Developed Planning Area & Total Planning Area)
26
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
3.3.7 Recreation
Parks, play fields, historical monuments have been grouped as recreational land use and constitute about 12.68
hectare, which is 0.6 % of the Developed Area and 0.2 % of the total Planning Area. Uniformly distributed and
well-planned parks and playfields are grossly lacking. Old town lacks both in active as well as passive recreational
27
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
spaces. In absence of any developed are for recreational purposes, the open spaces of schools and college and
other unorganized open spaces are uses as playfield, recreational areas by the local inhabitants.
The Government land category includes all those land owned by various Government departments like; revenue,
PWD, Irrigation, Agriculture, Home, etc. The Government Reserved category includes the lands Reserved and
Reserved Unused of whose kissam is mostly Bagayat (1) & (2), Basti yogya, Urban development in future, Patita,
Gochara etc; which excludes the Chhota Jungle and Patra Jungle. The land owned by Forest Department and the
land in the District Level Committee (DLC) report. It is very interesting to observe that there is almost equal
distribution of ownership between public and privately ownership of land. This implies that renewal, re-
development should start as a joint venture in near future to cater to all sort of development.
28
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 448000 452000
.000000 .000000 .000000
re
so
Bala
To
e
or
las
Ba
To
.000000
.000000
2336000
2336000
RANJA NO 131
CHARAMPA NO.137
TALANG NO. 120
RICE MILL
IFFCO GODOWN
Pond
TATA MOTORS
CHARMPA I.T.I
.000000
DUTTA ELECTRONICS
JAGADHA TRI HOTEL RICE MILL
STATION SQUARE
2332000
2332000
AXIS BANK
UNITED CLUB
BUS STOP RCBL HIGH SCHOOL
ELE. SUB STATION 132/25KVSITARAN AUTO LUBRICANTS EREIN NO.141
RAILWAY QUATERS
SANJIB AUTOMOBILES
Bh
HP PETROL PUMP
ad r
SBI ATM
ak-
HOTEL TRINI CONTINENTAL
CHANDA MOTOR WPRKSHOP
Dh
am
GELTUA NO. 116 HOTEL TARANI CONTINANTALOIL MILL
ra
ICICI BANK
TENTULIGARIA NO. 144
Rly
Fro
. Li
m An INDIAN OIL PETROL PUMP
SHANKAR BAJAJ
OGALPUR NO. 114
SANJAY TVS
an
ne
da
NURSING HOME
KHORDANG NO.140
pu
r
- 16
NH CHAPPULIA BRIDGE KUNTALA NO.143
S.P ELECTRONICS
VISHAL MEGA MART
BUS STAND BHADRAK
ASH BRIDU
HOTEL SAMPARK
FIRDODH HOTEL
BY PASS CHHAK PALSINGA NO.142
R.N EYE HOSPITAL
BAUDPUR NO.113
SH H.P GAS GODOWN METROZOLOGICAL DEPARTMENT
SALNDI CANAL DIVISION
-5 3 HOSPITAL
DAKSHINESWAR KALI TEMPLE WATER RESORSE DEPARTMENT
POLICE CANTEEN
DIXIT RESORT
INTERNATIONAL SCHOOL SARIYA SAGAR RESTAURANT
NESCO BHADRAK SUB DIVISION OFFICE
SHIV MANDIR KUNTALA NO.143
SARGARIA NO. 146
HOTEL CHHAK RAJGHAT CHHAK
PATANJALI HOTEL BLUE VINE
MAHADEV THEATRE BAUDPUR RAILWAY BRIDGE RIMEX PLAY SCHOOL
KORANT NO.62 MAHADEV CINEMA HALL POLICE STATION
HARI HARA TEMPLE RAJGHAT BRIDGE
FACOR POWER LIMITED PROJECT DIVISION AGRICULTURE
MAHATMA GANDHI STATUE PARSAAR BHARTI TV STATION & BHADRAK TV TOWER
JASODA TRADERS MANDAP BHAGABANPUR NO.147
RESERVE POLICE STATION SARASWATI VIDYA MANDIR
RANDIA RAILWAY OVER BRIDGE BHADRAK COLLEGE HANUMAN MANDIR COMPLEX TELEPHONE COLONY
BHADRAK GENRAL HOSPITAL
HOSTEL OM SHANTI DIGNOSTIC CENTRE
MAHA PATRA RICE MILL SH
BHADRAK COLLEGE SQUARE - 9
High Level Canal SWASTIK MESS
LITTLE ANGELS SCHOOL
LITTLE ANGELS SCCONDARY SCHOOL BHARAT PETROLIUMBHADRAK JAIL
SIDHARTHA NIWAS BHADRAK HIGH SCHOOL
DR. NAYAK CLINIC
DISTRICT POLICE STATION ARJUN SETU
BHADRAK TOWN POLICE STATION
MADIA SALA
RANDIA NO.63 KHADIMAS STORE TOWN HALL CHAAK HAMIRBINDHA NO.108
MILK MARKETING CENTRE SAMSAAN GHAT
Lok Nath Temple Pond
High Level Canal SPECIAL PLANING AUTHORITY BHADRAKCIVIL SUPPLIES OFFICE NIT NEHRU MARKET COMPLEX PURANA BAZAR POLICE STATION
l
ana
ICSS
INCOME TAX OFFICESALE TAX OFFICE
el C LIC OFFICE PANDHI NURSING HOME
Lev
Lake
SATSANG VIHAR
h
SCHOOL
Hig
BONTH CHHAKDistrict Fishery Pond BHADRAK HIGH SCHOOL
DRDA BHADRAK
TIRUPATI PLAZA
PRAYAG GROUP
OLD BUS STAND
SAMSAAN GHATPUMP HOUSE BANIA NO. 180
NARAYAN NIWAS COMPLEX
BAL GOPAL MANDIR JAMA MASJID
SABZI MANDI
DHATU TRADING AGENCY
STATE BANK SQUARE
APARTI BINDHA SQUARE
ac k
BHADRAK WOMEN COLLEGE
SATYA SAI VIDYA MANDIR
utt
TAXI STAND KABRISTAAN Bidhya Dhar Lake
MALIARUA NO.148
mC
INDIAN OIL PETROL PUMP DAKSHIH KALI TEMPLE
Fro
NEHRU STADIUM
k
u ttac SANTHIA BRIDGE
mC
TAHSIL OFFICE HANUMAN MANDIR
.000000
SAI HOSPITAL
NARAYAN CHANDRA HIGH SCHOOLJAMIA MASJID
2328000
2328000
AMARGARIA NO. 58
PURANA BAZAR CHHAK
KUNDIKALI TEMPLE
Salandi River
HARI CHHAK
N
To
PARIBINDHAMARPUR NO. 173
Dh
am
CONCRETE PRE COSTING UNIT
GELPUR NO.64
ra
CARMEL SCHOOL
To
133KV GELPUR SUB STATION
C ha
nd
BARIK CHHAK ba
BIRIPARA NO. 57 ELEKHA NO.96
li
GELPUR HIGH SCHOOL
KEDARPUR NO.151
KADAPATA NO. 65
RAJPUR NO. 84
NALANGA NO. 66 KORAKORA NO.97
BIJEGANGADHARPUR NO. 153
k
tt ac
Cu SAIDABAD NO.100
om
Fr
TIHIRI NO. 82
HARIPUR NO. 99
.000000
.000000
2324000
2324000
BILABARI NO. 81
To
Ar
ad
i
NANGURI NO. 77
BALAJITPARA No. 78
Title :
Ü
Legend Scale : 1:17,000
National Highway Water Bodies
Base Map of
Bhadrak Master Plan Area
State Highway Planning Boundary
Major Road Village Boundary Special Planning Authority 0 420 840 1,680
Other Road Flow Direction
Bhadrak Meters
Consultants :
Railway Line FEEDBACK INFRA PVT. LTD.
15th Floor, Tower 9B, DLF Cybercity, Phase-III
Gurgaon 122 002, Haryana, INDIA
Phone: +91 124 416 9100
Web: www.feedbackinfra.com
B. E. CONSULTANTS
ARCHITECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 448000 452000
.000000 .000000 .000000
re
so
ala
B
To
e
or
las
Ba
To
.000000
.000000
2336000
2336000
RANJA NO 131
CHARAMPA NO.137
TALANG NO. 120
Pond
.000000
STATION SQUARE
2332000
2332000
EREIN NO.141
Bh
ad r
ak-
Dh
am
GELTUA NO. 116
ra
TENTULIGARIA NO. 144
Rly
Fro
. Li
m An
an
ne
OGALPUR NO. 114
da 6
KHORDANG NO.140
pu -1
r NH
CHAPPULIA BRIDGE KUNTALA NO.143
SH BAUDPUR NO.113
-5 3
KUNTALA NO.143
HOTEL CHHAK RAJGHAT CHHAK
SARGARIA NO. 146
BAUDPUR RAILWAY BRIDGE
KORANT NO.62
RAJGHAT BRIDGE
MAHATMA GANDHI STATUE
BHAGABANPUR NO.147
RANDIA RAILWAY OVER BRIDGE TELEPHONE COLONY SH
- 9
BHADRAK COLLEGE SQUARE
High Level Canal
ARJUN SETU
el C
High Level Canal
ev
hL
Hig SATSANG VIHAR
Lake
BONTH CHHAKDistrict Fishery Pond
BANIA NO. 180
OLD BUS STAND
mC
Fro MAHATAB SQUARE
NACHHIPUR NO.149 BHATTIRA NO. 179
BAGICHA GHAT
.000000
.000000
2328000
2328000
PURANA BAZAR CHHAK
)
AMARGARIA NO. 58
-5
H
(N
Salandi River
6
-1
HARI CHHAK
SAMARAEPUR NO.86
To
PARIBINDHAMARPUR NO. 173
Dh
am
GELPUR NO.64
ra
To
C ha
BARIK CHHAK ndb
BIRIPARA NO. 57 ELEKHA NO.96 ali
KEDARPUR NO.151
KADAPATA NO. 65
BHABANIBINDHA NO 152
BARADADIHI NO.85
TARAGAN NO. 170
SH-
35
RAJPUR NO. 84
NALANGA NO. 66 KORAKORA NO.97
BIJEGANGADHARPUR NO. 153
ck
tta
Cu
SAIDABAD NO.100
om
Fr
TIHIRI NO. 82
HARIPUR NO. 99
.000000
.000000
2324000
2324000
BILABARI NO. 81
To
A
ra
d
i
NANGURI NO. 77
BALAJITPARA No. 78
Title :
Ü
Scale : 1:17,000
Legend
Meters
[ze
e [z[z
e e
Mixed Built-up land !!!!Dail/ Weekly hat/ Market Post Offices/Telegraph Offices/TE/Bank/ATM e
[e[e[e[Race course/ Golf course area Saltpan
Orchard/ Grooves
Bhadrak
Village Settlement Broadcasting Center / TV Centers/ Studio/Trans.Tower TRANSPORTATION Aquatic Vegetation
INDUSTRIAL Dense Forest
n
mmnn
m Farm House Major raod (N.H)
Industrial Estate/ SSI Police Station / Help Center / Outpost / Jail Open Forest Creek
n
mn n
mm
Scattered House Heavy Industry Cremation Ground / Burial Ground Major Raod (SH & ODR)
Forest/Coastal/Strip Plantation Aquaculture Ponds
Built-up Rural - Others Medium Industry n n n Temple Urban Raods(1,2,4 & 6 lane)
Degraded Plantation River / Stream
Reclaimed Land Light Industry n Mosque Metalled/ Earth Road/ concrete/ Village roads
Dense Scrub Canal/ distributiory/ Power Channel/ Mahara
Consultants :
^
n ^
n ^
Plotted Layout Cottage/Manufacture & Processing units
G
^ G
^ G Church
^ Footpath/ Cart Track
Diary / Poultry farm Lakes/ Ponds
Vacant Land within Residential Area
G G G Rail Station/ P.halt/ R. Yard/ Storage
! ! !
Ashram / Matha
. . .
Warehouse/ Storage/Godowns Mining Areas Reservoir/ Dam
B. E. CONSULTANTS
Vacant Land - Religious/Socio-cultural Use Cooling Pond
4. Conceptual Plan
4.1 Introduction
Bhadrak Master Plan has been prepared in accordance with the existing developments, issues, constraints,
growth potentials and directions. It also takes into account the vision statement to ‘Unleash the industrial
potential of Bhadrak along with administrative centre and achieving development sustainability’.
The prospects and potentials for the Bhadrak Planning Area has been identified through various primary and
secondary sources and their analysis. Issues and weaknesses in terms of physical linkages, economic potentials,
residential developments, commercial centers and growth nodes has been identified in order to address the
issues of haphazard and unplanned growth of Bhadrak.
• Developing Bhadrak
Town as a base of
Industries, wholesale
market and distribution
centre in the region
• Create a balanced city
having important
functions such as to live,
work and recreation
• Maintaining unique
character of town by
preserving rural
characteristics, water
bodies, and orchard.
The master plan identifies the
undergoing transformations to
identify the existing supply and
to determine the gaps and
demand for the future
perspective year 2030 in Bhadrak
for different sectors and Figure 4.1 Existing Developed Area- Bhadrak 2014
activities.
In Bhadrak there is scarcity of developable land due to natural features, developed infrastructure and other
developments. Different features like existing and proposed developments, growth nodes, and transport
linkages have been taken into account for planning compatible uses. For better Planning and development there
is need for identification of best suitable potential developable lands without hampering the environment and
the quality of land. Total projected Population in 2030 for Bhadrak Planning Area is 2, 84,353 with a total
planning area of about 8034 Ha.
29
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The proposed future developments have been planned considering potentials, availability of land, growth nodes,
and confirming uses. Initially missing links has been identified, potential developed lands has been earmarked
and based on the need and demand future development proposals has been planned and formulated.
4-TIER SYSTEM:
Bhadrak Planning Area has been planned into 4 Tier System. The Tier system is as follows:
1. City Level (Planning Area) : Total Population of 2.84 lakhs
2. Planning Unit Level : 1- 1.5 lakhs of population
3. Neighborhood Level : 10 to 15 thousand population
4. Residential Area Level : 5.0 thousand population
30
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
31
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
4.4 Conclusions
To summarize Bhadrak Master Plan has been formulated based on principles. Some of the planning principles
and salient Features of the Bhadrak Master Plan are:
o Balanced growth and improved quality of life,
o To develop it as the major Industrial town of the region.
o
32
5
Demographic and
Economic Perspective
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Population (2011)
Rural Areas 25,576
Bhadrak MC 1,07,463
Out-growths + Census town 19,497
Total master plan area 1,52,536
33
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
34
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
35
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
1.0 Urban
0.0 Rural
1991 2001 2011 2016* 2021* 2026* 2030*
-1.0 Planning area
-2.0
-3.0
-3.2
5.4.1 Contextual
Economy can be defined as the interrelated activities that deal with consumption and production. Different
activities that provide employment opportunities and income constitute the economic base of an area. Local
economy depends of the economic base of an area. The economic base of Bhadrak planning area is mostly
dependent on agriculture and religious tourism, industrial activities. The economic sector needs to be tapped
well and contribute for the growth of the planning area and region. Therefore the region requires strong
economic magnets for future economic development of the Region. Sometimes during religious festivals and
melas, tourist activity and non-availability of employment for unskilled population we can also see some
development in informal sector also which has been an important issue of physical planning in Bhadrak.
Bhadrak is home to FACOR, one of the largest manufacturers of quality ferro chrome in the country. There are
about 552 industrial units registered with Municipal Council and about 91% are Micro Industries and 9% Small
Scale Industries. These industrial units provide employment to approx. 60% unskilled workers and 40% skilled
workers. Other than these industrial units there is significant land under rice, wheat and pulses, which also forms
the agricultural productivity economic base in Bhadrak.
36
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
37
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
38
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
40.00
35.00 32.50 34.50
28.50 30.50
Growth rate 30.00 26.05
24.06
25.00
20.00
15.00
8.10 7.34
10.00
5.00
0.00
1981 1991 2001 2011 2016 2021 2026 2030
Year
39
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
RANJA NO 131
2332000 .000000
3
4
EREIN NO.141
1
5
Bh
ad
ay
ailw
ra
R
k-D
To
ern
GELTUA NO. 116
A
ast
TENTULIGARIA NO. 144
na
ha
nd E
ap uth
OGALPUR NO. 114
6
mr
So H-1
KHORDANG NO.140
u r N
aR
KUNTALA NO.143
7 6
ly.
PALSINGA NO.142
BAUDPUR NO.113
10 15
RANDIA NO.63
SH 8 HAMIRBINDHA NO.108
ack -53
utt
17
C 12
BANIA NO. 180
To
9
18 MALIARUA NO.148
22
24
2328000 .000000
2328000 .000000
20 NACHHIPUR NO.149 BHATTIRA NO. 179
14
To
AMARGARIA NO. 58 19 21 23
Dh
TARAGAN NO. 170
SAMARAEPUR NO.86 27
am
BRAMHAPUR NO.150
ra
13
PARIBINDHAMARPUR NO. 173
GELPUR NO.64 26
25 To
BIRIPARA NO. 57 ELEKHA NO.96 C han
KEDARPUR NO.151
db
ali
KADAPATA NO. 65
30 BHABANIBINDHA NO 152
SH
2324000 .000000
HARIPUR NO. 99
BILABARI NO. 81
To
NANGURI NO. 77
raA
di
BALAJITPARA No. 78
Ü
Legend:
Municipal Ward Density Map
National Highway River / Stream < 50
of Bhadrak Master Plan Area
State Highway Planning Boundary 51 - 100
Special Planning Authority 0 375 750 1,500 Meters
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
RANJA NO 131
2332000 .000000
3
4
EREIN NO.141
1
5
Bh
ad
ay
ailw
ra
R
k-D
To
ern
GELTUA NO. 116
A
ast
TENTULIGARIA NO. 144
na
ha
nd E
ap uth
OGALPUR NO. 114
6
mr
So H-1
KHORDANG NO.140
u r N
aR
KUNTALA NO.143
7 6
ly.
PALSINGA NO.142
BAUDPUR NO.113
To
BHAGABANPUR NO.147
Dh
10 15
am
RANDIA NO.63
SH 8 HAMIRBINDHA NO.108
ack -53
ra
utt
17
C 12
BANIA NO. 180
To
9
18 MALIARUA NO.148
22
24
2328000 .000000
2328000 .000000
20 NACHHIPUR NO.149 BHATTIRA NO. 179
14
AMARGARIA NO. 58 19 21 23
TARAGAN NO. 170
SAMARAEPUR NO.86 27
BRAMHAPUR NO.150
13
PARIBINDHAMARPUR NO. 173
GELPUR NO.64 26
25 To
BIRIPARA NO. 57 ELEKHA NO.96 C ha
KEDARPUR NO.151 nd
ba
li
KADAPATA NO. 65
30 BHABANIBINDHA NO 152
SH
2324000 .000000
HARIPUR NO. 99
BILABARI NO. 81
To
NANGURI NO. 77
A
ra
di
BALAJITPARA No. 78
Ü
Legend:
Village Population Density Map
National Highway River / Stream <5 of Bhadrak Master Plan Area
State Highway Planning Boundary 6 to 10 Special Planning Authority 0 375 750 1,500 Meters
Bhadrak
Railway Line Municipal Ward 11 to 15
Consultants :
> 15 FEEDBACK INFRA PVT. LTD.
15th Floor, Tower 9B, DLF Cy bercity, Phase-III
Gurgaon 122 002, Hary ana, INDIA
Phone: +91 124 416 9100
Web: www.feedbackinfra.c om
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
6
Traffic and Transportation
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
40
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
41
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
42
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The road surface if in poor condition in most of the locations and there are no footpath or medians on the road.
Furthermore, there are no traffic control measures for controlling traffic on the road. Presence of
encroachments and bottlenecks on the roads render difficulty in the movement of larger vehicles. Hence there is
a need for widening of the main roads and planning a bye pass for through traffic passing Bhadrak.
43
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Different traffic volume count survey locations have been analyzed as per the Peak Hour Traffic in terms of PCU
and Level of Service (L.O.S) has been evaluated in terms of V/C Ratio. The map indicates Peak Hour PCU and the
V/C Ratio (Volume/Capacity).
44
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
45
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
46
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Survey Inferences:
47
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Road Inventory survey analysis inferences on Randhia Road towards Anandapur Stretch are average Road width
– ROW- 23.2m; Average Carriageway – 7.1m; Average Encroachment on both side Right Side- 4.9 M & Left Side-
5 M.
Proposed Strategy:
To ensure free flow of traffic movement, considering the existing issues in the road survey inventory analysis the
following strategies has been recommended:
• This stretch needs to be widened to 4 lanes with minimum ROW 30 Mts.
• As per road inventory Road Widening is permissible on both sides.
Encroachment
ROW Carriage (M)
Road Stretch Shoulder Footpath Median Circulation
SN (M) Way (M) Right
Left Side
side
Aradi Road (Aradi
1 20.7 5.6 2.5 12.6 No No No Two Way
Chhak-Nesco Office)
Aradi Road (Nesco
2 7.6 5.6 1.3 0.7 No No No Two Way
Office-Vinayak College)
Aradi Road (Forest
3 10.9 5.5 3.1 2.3 No No No Two Way
Department-Satabaim)
48
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Encroachment
ROW Carriage (M)
Road Stretch Shoulder Footpath Median Circulation
SN (M) Way (M) Right
Left Side
side
Aradi Road (Law
4 11.9 5.5 1.1 3.2 No No No Two Way
College-Forest Dept)
Aradi Road (Vinayak
5 15.3 5.7 2.1 1.3 No No No Two Way
College-Law College)
Source: Consultant’s Survey Analysis
Survey Inferences:
Road Inventory survey analysis inferences on Aradi Road Stretch are Average Road width – ROW- 13.8 m;
Average Carriageway – 5.58 m, Average Encroachment on both side- Right Side- 2.2 m and Left Side- 4.02 m.
Proposed Strategy:
SN Road Stretch ROW Carriage Encroachment (M.) Shoulder Footpath Median Circulation
49
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Survey Inferences:
Road Inventory survey analysis inferences on Collector Road Stretch are Average Road width – ROW- 24.32m;
Average Carriageway – 10.16 m, Average Encroachment on Both Side Right Side- 2-3m & Left Side- 4.7m.
Proposed Strategy:
To ensure free flow of traffic movement, considering the existing issues in the road survey inventory analysis the
following strategies has been recommended:
➢ This stretch needs to be widened to 2 lanes with minimum ROW 15 Mts.
➢ As per road inventory Road Widening is permissible on both sides.
50
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Encroachment
ROW Carriageway (M)
SN Road Stretch Shoulder Footpath Median Circulation
(m) (m) Right Left
Side Side
Rajghat Chhak To
Chapulia Bypass (D I
1 19.2 7 - - No No No Two Way
Office - Chandbali
Junction)
Chandbali To Police
2 18.2 5 - - No No No Two Way
Station
Police Station To
Yunani Hospital (D I
3 16.0 5.1 - - No No No Two Way
Office - Chandbali
Junction)
Puruna Bazar Road
4 (D I Office - Chandbali 18.5 4.2 - - No No No Two Way
Junction)
Yunani Hospital To
5 Carmel School (D I 20.1 7.2 - - No No No Two Way
Office - Chandbali Jn
Carmel School-
6 Icchapur (Chandbali 15.8 7.2 - - No No No Two Way
Road
Source: Consultant’s Survey Analysis
Survey Inferences:
51
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Road Inventory survey analysis inferences on Chandbali Road Stretch are Average Road width – ROW- 17.96m,
Average Carriageway – 5.95m, there is no Median available even though it is Two Way circulation.
Proposed Strategy:
To ensure free flow of traffic movement, considering the existing issues in the road survey inventory analysis the
following strategies has been recommended:
➢ This stretch needs to be widened to 4 lanes with minimum ROW 30 Mts.
➢ As per road inventory Road Widening is permissible on both sides.
Encroachment (M.)
ROW Carriage
SN Road Stretch Shoulder Footpath Median Circulation
(m) way (m) Right
Left Side
Side
Municipality-
1 Bhadrak Womens 9.5 6.3 - - No No No Two Way
College
52
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Encroachment (M.)
ROW Carriage
SN Road Stretch Shoulder Footpath Median Circulation
(m) way (m) Right
Left Side
Side
Hospital to Rajghat
4 22.5 11.5 7.5 7.5 No No No Two Way
road
Survey Inferences:
Road Inventory survey analysis inferences on Purna Bazar Road Stretch are Average Road width – ROW- 14.7 m,
Average Carriageway – 6.05 m, there is no Median even circulation is Two Way, Encroachment on both side on
Hospital to Rajghat road
Proposed Strategy:
To ensure free flow of traffic movement, considering the existing issues in the road survey inventory analysis the
following strategies has been recommended:
53
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Encroachment (M.)
ROW Carriage way
SN Road Stretch Shoulder Footpath Median Circulation
(m) (m)
Right side Left Side
Bhadrak
1 11.6 0.3 - - No No No Two Way
Station Road
Bhadrak
Station
2 33 10.7 - - No No No Two Way
(Charampa
Road)
Source: Consultant’s Survey Analysis
Survey Inferences:
Road Inventory survey analysis inferences on Station / Charampa Road Stretch are Average Road width – ROW-
22.3 m, Bhadrak Station road width is 11.6 M (ROW) but the Carriageway on Bhadrak Station Road near – 0.3 m
only, there is no Median even its Two Way circulation.
Proposed Strategy:
54
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
To ensure free flow of traffic movement, considering the existing issues in the road survey inventory analysis the
following strategies has been recommended:
➢ Bhadrak Station road width is currently- 11.6 M (ROW) and need to be widened at least 2 lanes with
minimum ROW 9 Mts.
➢ Bhadrak Station- Charampa Road stretch needs to be widened to 2 lanes with minimum ROW15 Mts.
➢ As per road inventory Road Widening is permissible due to availability land for widening on both sides.
Encroachment (M.)
Carriage
SN Road Stretch ROW (m) Shoulder Footpath Median Circulation
way (m) Right side Left Side
SP Residency-
1 Railway Crossing 8.2 5.1 - - No No No Two Way
(Gelti Road)
Source: Consultant’s Survey Analysis
Survey Inferences:
55
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Road Inventory survey analysis inferences on Railway Crossing (Gelti Road) are Average Road width – ROW- 8.2
m, Average Carriageway – 5.1 m, Circulation is Two Way but Median is not available.
Proposed Strategy:
To ensure free flow of traffic movement, considering the existing issues in the road survey inventory analysis the
following strategies has been recommended:
➢ This stretch needs to be widened to 2 lanes with minimum ROW 9 Mts.
➢ As per road inventory Road Widening is permissible on both sides.
Some of the other major roads that need to be addressed and widened and improved for better transport
network and traffic movement in Bhadrak Planning Area are indicated in the Map:
56
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
57
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Reasons for creation of bottlenecks are poor planned junctions; encroachments; on street parking;
Encroachments by shops, hawkers and vendors, high traffic movement; poor traffic management. The identified
bottlenecks need to be cleared on the existing roads for enabling better traffic movement in Bhadrak. The
overall objective of such improvements is to enhance the traffic handling capacities of the intersections,
minimize delays, avoid conflict situations, improving safety and facilitate smooth traffic dispersal.
58
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
6.12 Parking
Parking provisions is an integral part of planned traffic and transportation system in an area. In Bhadrak parking
provisions is one of the major issues of concern. Non-availability of parking spaces in the town is causing on
street and unregulated parking. On street parking create hindrances to the traffic movements within the town.
Parking surveys has been conducted at the following locations in Bhadrak.
1. Mahtab Chhak to SBI Chhak
59
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Figure 6.12 Parking Survey Locations in Bhadrak Final Report of Bhadrak Master Plan
Out of the total stretches highest parking has been spotted near Vishal Mega Mart. The total parking survey has
been conducted from 09:00AM to 07:00 PM at various locations on the stretches indicated in the above map.
For the perspective year 2030 for organized parking based on feasibility studies designated parking spaces have
to be planned.
60
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
61
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
62
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Zone 1 (MC area), 7, 8, 11 and 12 are the main zones with highest trip interactions in terms of attractions and
generations. Therefore there is need to plan for through traffic and not enabling the through traffic to enter the
town core and thereby avoiding traffic congestions in Bhadrak town area
63
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The major trip interacting zones are zone 8 and zone 11 followed by zones 8 & 1 and zones 1 &12 as per the
Origin and Destination Surveys conducted in Bhadrak Planning Area.
64
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
In MC, Villages & Out Growths majority of the trips are for work purpose followed by Education. Least
percentage of trips are for social and shopping purpose
In MC, Villages & Out Growths majority of the trips starts between 08:00 AM-09:00 AM and in Villages and
Outgrowths due to agricultural activities and more distance of work place there is considerable percentage of
trips between 06:00-08:00 AM.
65
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
In MC, Villages & Out Growths majority of the trips are by walk and cycle, reflects the vehicular ownership.
In Villages and Outgrowths the distance of work place is much higher than that of MC area.
Trips as per Travel Time to Destination
66
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Similar to trip generation locations even trip attraction zones has also been mapped.
67
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
6.15 Terminals
Different surveys have been conducted like Types of Goods Vehicles, Goods/ Commodities Types at different
terminals.
Terminal Surveys has been conducted at the following locations
Some of the major issues and problems associated with the terminals are poorly planned intersections and
junctions which needs to be developed; encroachments, hawkers and vendors, on street parking and
bottlenecks.
68
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
69
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The Master Plan Bhadrak -2030 proposes a network of bye pass loop, new sub arterial, local and access roads,
besides improving access linkages within the existing town limits as reflected in the proposed Land Use Plan. The
basic objective behind the proposed Transportation Network is to improve connectivity within the Planning area
by developing missing links across existing development. The Transportation Network Plan has been devised to
improve the efficacy of proposed land use model by way of providing efficient linkages to functional areas, and
establish a balanced and harmonized land Use pattern in Bhadrak planning area.
70
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The existing roads are proposed to be upgraded in terms of ROW, capacity and other geometrics. The new roads
need to be planned and designed for a higher level of service. Within the core area, the roads will lose their
characteristics and are to be developed as all-purpose roads.
71
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
2332000 .000000
2332000 .000000
Bh
ad
ay
ailw
ra
R
k-D
To
A ern
na ast
ha
nd E
ap u th
-16
mr
u r So NH
aR
ly.
SH
- 9
l
k ana SH
-53
ttac ev el C
Cu hL
To Hig
2328000 .000000
2328000 .000000
To
Dh
am
ra
To C
han
dba
li
SH
-35
ck
tta
Cu
To
2324000 .000000
2324000 .000000
To
A
ra
di
Ü
Legend: Transportation Waterbodies
Major raod (N.H)
Aquaculture Ponds
Existing Road Network of
Bhadrak Master Plan Area
Major Raod (SH & ODR) River / Stream
Urban Raods(1,2,4 & 6 lane)
Canal/ distributiory/ Power Channel/ Mahara
"
T"T Jetties/ Port
Planning Boundary
Gurgaon 122 002, Hary ana, INDIA
Phone: +91 124 416 9100
Web: www.feedbackinfra.c om
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Airport/Helipad Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
7
Housing and Slums
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Table 7.1 Urban and Rural Population, HH size and no. of Households in Bhadrak Planning Area
Urban Rural
Year Population HH Size No. of Households Population HH Size No. of
Households
2001 92,515 6.0 15,338 37,580 5.5 6,869
2011 1,26,960 4.9 25,873 25,576 5.3 4,789
2016* 1,50,765 4.8 31,409 27,378 5.0 5,476
2021* 1,79,033 4.8 37,299 29,308 5.0 5,862
2026* 2,14,840 4.5 47,742 32,402 4.8 6,750
2030* 2,49,215 4.5 55,381 35,138 4.8 7,320
Source: Census of India Note: * Projected figures
72
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
73
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Household Survey
Door to door household survey has been conducted in the entire Bhadrak Planning Area. The survey was
conducted for the 4,302 numbers of households including the urban area and rural area.
74
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
0
MC Wards Rural Villages Out Growth Villages
%age of Workers in 4
Survey Population MC
31 21
Rural Villages
69
%age of Non- 75
Workers/ Out Growth Villages
Dependents in
Survey Population
75
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
72 Out Growth
Villages
%age of Workers
%age of Workers
32 36
64 %age of Non-
68 %age of Non- Workers/
Workers/ Dependents
Dependents
%age of Non-
Workers/
71
Dependents
76
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
In Bhadrak out of the total Survey Population Maximum %age of population is engaged in Business activity (44%)
and followed by self-employed (18%) and Service (17%). Less %age of population is engaged in professional
activities (4%) and unskilled labours (15%) due to low educational facilities and also migration.
16 - 20 km.
80 More than 20
km.
77
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
78
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
79
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
80
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
16 - 20 yrs
95
81
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
31-40
21
82
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Community
toilet
1 6 10 Other
83
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Ownership Pattern:
In MC, Rural Villages and Out Growths more than 90% of %age of Total HH as per Tenancy
the total HH are owned and very less %age are of 5
rented. Most of them have their ancestral lands due to
which owned HH are in majority. Owned
Rented
95
84
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Issues in regard to Infrastructure facilities like Power, Hygiene, Parking, Road access are predominant in all areas
of Bhadrak Planning Area. In Out Growths there are issues in regard to all infrastructure facilities. In Municipal
area issues are in regard to: Water Quality, Power, Hygiene, Parking and Roads.
It has been projected the total housing demand in Bhadrak Planning Area for the year 2030 would be 62,701.
The total projected housing demand in Bhadrak Planning Area has been projected in 5 year phases.
Housing Demand
80000 62701
54493
60000 43160
36885
40000
20000
0
2016* 2021* 2026* 2030*
Bhadrak Housing Plots Scheme and Nagar Palika Plots Patta Scheme has been launched in 2014.
85
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Role of Government
Government has to play proactive role of promoting the housing industry by regulatory measures and acting as a
watch-dog rather than fully involving its organs in the provision of shelter to the town inhabitants. The
magnitude of housing shortage is enormous and the State on its own cannot provide the housing stock.
Government will limit its role to development of serviced land and subsequently its release to private developers
and Cooperative Societies on premium equivalent to the cost of land plus marginal profit with only advisory and
regulatory role in the development of housing industry.
86
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Urban Village
The peripheral village settlements, which have been incorporated in the Planning Area of Bhadrak, are going to
be part of its proposed Urban Area Limits during the process of its expansion. The settlements having a
completely different life-style for centuries are now getting merged into urban environment and need a sensitive
approach in the planning and development process. At present these settlements do not conform to any urban
character and need an ‘Action Plan’ for extension of water supply, sewerage and drainage facilities and other
basic urban amenities and efficient linkages with the main city. The settlements should get the modern services
and amenities and should also be catered for their traditional cultural styles.
7.11 Slums
The Census of India, 2001 has proposed to treat the following as ‘Slum’ areas:
• All areas notified as ‘Slum’ by State/Local Government and UT Administration under any Act;
• All areas recognized as ‘Slum’ by State/Local Government ad UT Administration which have not been
formally notified as slum under any Act;
• A compact area of at least 300 populations or about 60-70 households of poorly built congested
tenements, in unhygienic environment usually with inadequate infrastructure and lacking in proper
sanitary and drinking water facilities.
Urban areas have potential to provide employment to a vast multitude, and attract a large number of people.
Many of them stay in slum colonies for the lack of a better alternative.
Slum-dwellers stay in shanty structures in unhygienic environment, not by choice but by compelling
circumstances as they were thrown out of the formal housing sector, the latter being expensive and much
beyond their income levels.
87
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
SI. No. Name of Slum Area Ward No. Population of Slum Area
1 Munda Sahi 1 450
2 Bidanga 1 447
3 Barala Pokhari 2 2235
4 Nuapokhari 3 111
5 Dagarasahi 4 979
88
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
SI. No. Name of Slum Area Ward No. Population of Slum Area
40 Gardapur 29 1549
41 Uttarbahini 30 463
42 Balipatna 30 740
43 Kelasahi 30 755
Total 57823
Source: Bhadrak M.C DPR Report
The Prime objective of the scheme is to strive for holistic slum development with enabling a healthy urban
environment by providing adequate shelter and basic infrastructures to the urban slum dwellers.
89
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
b. Promote referral system: Each Urban Health Centre catering to a specific targeted population in a defined
geographical area. The cases related to institutional delivery, emergency obstetric care, terminal methods of
family planning and other complicated cases referred to second tier health facilities.
c. Community level activities: To develop and maintain a link between the health facility and the community,
the programme envisages engagement Link Volunteers from the community able to spare 3-4 hours a day. The
capacity of Link Volunteers to facilitate promotion of health seeking behaviour in the community, formation of
women groups, Balika mandal to expand the base of health promotion efforts at the community level and to
build sustainable community process.
90
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The above objectives are inter-sectoral and inter-departmental. To facilitate the above, the following is
envisaged in the Bhadrak Master Plan-2030.
• In case of existing slums, which are on Government lands and on their own land that are not needed
for development of any infrastructure or other urban activities, plans for upgrading of slums may be
prepared and implemented;
• Other slum pockets which are not on their own land may be resettled at appropriate areas with due
consideration of the distance from their work places;
• Under the housing/slums up-gradation scheme 100 % of beneficiaries need to be provided with
financial assistance to improve the structure condition of their houses.
1. Housing
From the above chapters it may consider that 57823 house is residing in 43 slums. Out of 238 eligible
BPL, families from Pathan mahal, Nathasahi & Bhuyana Mohala slum are selected to be provided with
RCC roofed houses. But in first phase we consider 3 slums with 238 Nos of beneficiary who are
identified as BPL holders, are consider as beneficiary.
2. Water Supply
It is proposed to supply underground water to all the slums through bore well and overhead tank, to
make all the beneficiaries independent to avail this vital requirement of life.
3. Sanitation
There is provision for toilet facilities in the proposed DUs. For use of other people, Community Toilet is
proposed under this scheme as per the density of population demand.
6. Street Light
Street light are provided in the DPR along the road length with a regular interval for safety
communication of slum peoples.
91
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
8. Community Facility
Community centres have been provided to all the slums as per their slum population for observing their
social necessity with health care units, crèches, working spaces etc.
9. Education
There is no provision of schools in the slums as the primary education facility and other education
facility are available within ½ km to 2 km radius of the slum areas.
10. Electrification
Provision of electrification made to all the dwelling units for better living, As a whole all the provision of
city living are provided to slum dweller to make their living equal as per the town people of the city and
make the town slum free.
92
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
7.13.1.1 Vision
To ensure that all residents of urban areas in Odisha have access to a range of housing options within their
affordability limits by putting in place a system that will deliver results consistently over a period of time.
7.13.1.2 Mission
To work towards a set of strategies to create a steady supply of affordable housing stocks to cater to the growing
demand. Over a period of 7 years, the government intends to completely address housing deficit in urban areas
and \have an operational system, where supply matches demand.
7.13.1.3 Objectives
The specific objectives of this Policy are as follows:.
a. To create a comprehensive, holistic policy framework to address all aspects of housing for the urban
poor including slum rehabilitation and redevelopment as well as new housing and rental housing.
b. To promote inclusive mixed housing development in all new housing projects, both in the public and
private domain.
c. To promote mixed land use in housing estates in future so as to meet requirements of neighbourhood
shopping, retail etc. within walking distance.
d. Tenable proactive market-led efforts to address the low and informal income market segment.
e. To promote public private partnerships for affordable housing and slum rehabilitation projects.
f. To ensure availability of land for such projects in a time bound and regulated manner.
g. To set principles for allotment of AH units, SRRH units and RH units to various beneficiaries in a
transparent and efficient manner.
h. To establish an effective institutional framework ensuring single window approvals for housing projects.
i. To provide a platform for operation and maintenance of AH, SRRH and RH units in a cooperative
manner.
j. To promote inclusive & participatory planning and implementation processes for slum redevelopment
housing.
93
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
k. To integrate various livelihood programmes with housing programmes benefiting beneficiaries of AH,
SRRH and RH and ensuring overall socioeconomic development of the families.
l. To ensure provision of networked municipal services across the city for ensuring better standards of
living for urban poor,
m. To promote and set up a system for formation of Housing Societies by the existing Slum Dwellers and to
promote their participation in Slum Redevelopment programmes.
n. To promote and ensure minimum relocation of the existing slum dwellers so as to maintain sanctity of
existing economic and social linkages developed over a period of time in the informal settlements.
o. To provide a frame work for supply of Affordable Rental Housing for new migrants to prevent
development of new slums.
p. To provide a mechanism to address operational issues that may arise from time to time during
implementation of policy.
94
8
Physical Infrastructure
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
8. Physical Infrastructure
8.1 Water Supply
8.1.2 Proposals
The Bhadrak Master Plan proposes to cover the water supply scheme for planning area based on criteria, norms,
standards mentioned in CPHEEO Manual. The objectives of full coverage of urban communities with easy access
to potable drinking water in quantities recommended to meet the domestic and other essential non-domestic
purposes, the recommended per capita water supply levels for designing water supply scheme is as follows:
• Residential Water Demand: Total water demand for Residents of residential area has been taken as
135 lpcd for Potable use.
• Industrial water demand: Total water demand for Industrial Area has been computed considering 6000
Gallons / acre/day)
• Fire Demand: Fire Demand has been calculated as 1.0% of the total water demand. The Fire water
demand will be stored in the UGT as dead water demand and will be supplied in the network in case of
95
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
fire. Fire hydrants will be provided near the major road intersections so that in case of emergency the
fire tenders can be filled at the Fire Hydrant locations.
• Unaccounted for Water (UFW): 15% towards losses/ ‘Unaccounted for water has been considered for
Potable water for residential population
• Horticulture: The water demand for irrigation of green areas is estimated at 20,000 litres/acre/day of
the area under soft landscape.
Year
Description
2011 2016 2021 2026 2030
Residential Population 152,536 178,143 208,342 247,242 284,353
Action Plan
• Planning, design and implementation of a sustainable water supply scheme mainly based on
surface/sub-surface/intake wells water supply from the river Salandi and ground water
• Covering the entire planning area with a continuous water supply system assuring 24 hr supply with
adequate pressure in the distribution system even at the tail ends
• Controlled use and management of ground water assuring treatment with disinfectants before
distribution
• Public awareness against misuse of water
• Adequate reforms so as to balance the O&M cost with the revenue out of the water supply distribution
96
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
In absence of underground sewerage system, the sanitation systems are soak pit based. Effluents from public
urinals are directly discharged in drains. Most of the households in urban area within the planning area have
individual toilets or have accessibility to public toilets, whereas most of households in slums and rural areas
either uses public toilets or defecate in open areas.
The situation of sanitation is critical in the planning area. Further, more than 50% of the total population lives in
slum like conditions. These areas are marked by open defecation, lack of proper drainage, no sewerage, and no
treatment of waste water, lack of proper and sufficient toilet facilities and lack of awareness among the peoples
about proper sanitation facilities.
8.2.2 Issues
• Absence of sewerage system: there is absolute absence of sewerage system in Bhadrak planning area
resulting in discharge of un-treated waste water in drains and river Salandi
• Mixing of storm water and sewage: In absence of sewerage and improper drainage system, in many
parts of planning area, there is discharge of sewage into storm water drains and other water bodies
97
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
8.2.4.1 Recommendations
The conventional ASP system is a widely used wastewater treatment option in major cities of India. It has
become popular as a reliable technology with good resource recovery (60-75% methane) of biogas. It assures a
removal rate of more than 90-95% of organics from wastewater. UASB reactors are also gaining ground as an
alternative to the conventional treatment techniques with their simplicity and comparable removal efficiency.
However, the UASB renders effluents with relatively high NPK values demanding post treatment by polishing
units. The cost of treatment of wastewater, unit cost, and quality of the effluent varies only marginally among
these two treatment options. The success of the ASP systems elsewhere, with its easy maintenance and
management makes it an appropriate choice.
98
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
8.3.1 Topography
Bhadrak is located along the river Salandi and the general topography of the town is a gentle slope from west to
east. The variations between the altitudes are between 13 m and 22 m. the river part is higher elevation of 19-21
m whereas it elevation reduces to 18-14 m while moving northern and southern side.
99
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
submerged most parts of the developed area. The major water logging areas in Bhadrak are near Salandi River
and in the old town area.
• Choked Drains: Most of the drains are choked with solid waste and causing water logging situation in
many of the residential areas
• Functioning of Drains as Sewer: Storm water drains of Bhadrak planning area have functioned as media
for carrying sewage. Further due to absence of proper sewerage system and lack of awareness sewage
from residential areas is discharging into drains
• Silting of Drainage System: The available drainage system of the Bhadrak is not properly and frequently
cleaned. Majority of drains are cleaned once in a year before the monsoon or on complaints. Heavy
silting of drains resulting into overflow of water and water logging in rainy season.
8.3.4 Proposals
A separate storm water drainage network apart from sewerage system has been proposed in the development
area for the collection and safe disposal of storm water during rainfall. The design criteria to be followed for
design of Storm Water Drainage network are broadly based on the recommendations as laid down in the
CPHEEO Manual of Sewerage and Sewage Treatment, Ministry of Urban Development, Government of India and
as per provisions laid down in the relevant I.S. Codes and Consultants’ past experience in related field.
There are several ongoing and new proposals for augmentation of drainage system in the Master Plan Area
Bhadrak Under different schemes (Refer annexure).
8.3.4.1 Recommendations
• The lack of proper sanitation and solid waste management, combined with indiscriminate dumping of
solid waste in the drains reduces the carrying capacity of these natural drains. The implementation of a
systematic solid waste and wastewater collection and treatment system is a necessary prerequisite for
proper drainage of the area.
• The natural drains have been encroached upon and are almost in dilapidated state. Also, at many
reaches the drain sidewalls are found to be damaged. The section of the drain is also irregular and less
adequate at many locations. Proper gradient is not maintained at several stretches on its reach and the
100
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
hydraulic parameters are also not uniform. Also, no definite drain section is maintained in many
reaches. So, proper maintenance and management of the existing natural drains turns important. This
necessitates a proper evaluation of the existing natural drainage system.
• Over the years the River Salandi has progressively silted up due to which the flood water flows at ever
higher levels than the water levels in this main drain.
• The natural depressions and ponds, which were instrumental in preventing excess storm run-off, are
getting filled up at a rapid rate due to urbanization. This may further aggravate the existing problem of
water logging. It is necessary that ‘natural sinks’ be retained as such as, they are instrumental in
controlling the water logging of the area.
• An organized drainage system is invariably associated with the implementation of a systematic solid
waste and wastewater collection and treatment system.
• Periodic de-silting of the existing storm water drains should be done.
• Perimeter protection of all the major drains should be checked before every rainy season.
• Overall, the preparation and implementation of a master drainage plan appears essential for Bhadrak
101
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
8.4.3.1 Segregation
Presently, no solid waste segregation either at source or at the site is happening in Bhadrak urban
area. Waste is collected from road side and temporary storage bins from where waste is transported
to dump sites. Approximately, 80% of the total workers are presently involved in segregation of waste
in the urban areas.
102
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Lack of Awareness
There is absolute lack of awareness among people w.r.t. handling and management of waste.
Public Participation:
General environmental awareness and information on health risks due to improper solid waste management are
important factors which need to be continuously communicated to all sectors of the population. Building
awareness among public and community about the need for a better solid waste management system is as
essential as management. Public awareness and attitudes to waste can affect the people's willingness to
cooperate and participate in adequate waste management practices. If people keep on throwing waste on the
streets indiscriminately, the local body alone cannot keep the city clean in spite of their best efforts .Thus, it is
very important to make people understand that the treatment and management of solid waste is a collective
responsibility of the local authority and the community. Municipalities or local governments through
participatory programs should convey this message to the people.
103
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
• The local body may collect waste from community bins by using container handcarts or tricycles
whichever may be convenient, for transferring the wastes to the waste storage sites by employing
municipality sweepers.
• The collection service can be provided on a full-cost recovery basis using contractor services on a day-
to-day basis from individual houses.
• The collection service can be provided on a full-cost recovery basis using contractor services on a day-
to-day basis from individual shops also. The service of rag pickers and part-time sweepers can also be
used in agreement with the shop owners.
• Sweeping of all public roads, streets, and lanes, by-lanes where there is habitation or commercial
activities on either side of the street should be done daily. A list of such streets and roads together with
their length and width should be prepared. The local body, keeping in view the norms of work
prescribed should work out a program for their daily cleaning. However, roads and streets where there
is no habitation around and do not require daily cleaning may be put in a separate group.
The Municipal solid waste (Management and Handling) Rules 2000 of the Government of India have prescribed
the compliance criteria for waste storage depots as under:
• Storage facilities shall be created and established by taking into account quantities of waste generation
in a given area and the population densities. A storage facility shall be so placed that it is accessible to
users.
• Storage facilities to be set up by municipal authorities or any other agencies shall be so designed that
waste stored are not exposed to open atmosphere and shall be aesthetically acceptable and user-
friendly.
• Storage facilities or “bins” shall have “easy to operate” design for handling, transfer and transportation
of waste. Bins for storage of biodegradable waste shall be painted green, those of recyclable waste shall
be painted white and those of other wastes shall be painted black.
• Manual handling of waste shall be prohibited. If unavoidable due to constraints, manual handling shall
be carried out under proper precaution with due care for safety of workers. So, the storage and
handling of SW are extremely important, and hence the steps to be taken by the Municipal authorities
for storage of solid wastes are detailed in table below:
S. No. Generation Source Action Proposed
1 Residential • Not to throw any waste in neighborhoods, on streets, open
space, and vacant lands, in drains or water bodies.
• Keep food waste / biodegradable waste in a non corrosive bin
type – D1
• Keep dry/ recyclable waste in bin type – D2
• Keep hazardous waste separately
2 Multistoried buildings, • 1 to 4 as above.
commercial complexes, private • Provide separate bin type – B large enough to hold wastes
societies generated both biodegradable and recyclable.
• Direct member of the association / society to deposits waste in
bins provided. Sanitary inspectors should vigil the area and fine
should be imposed for not following the actions
104
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Segregation:
These compositional characteristics of the solid waste underline the need for proper segregation before
treatment. Proper segregation of waste into different components and their separate collection can definitely
lead to remarkable changes in the entire system.
The segregation of the waste would be a long drawn exercise as it involves attitudinal changes in people and will
have to be done with careful planning, in a phased manner. The general public is to be first sensitized towards
the whole concept and educated about the need and advantages of doing the segregation. Segregation of waste
at the source itself is extremely important as municipal solid waste, which is otherwise environmentally benign
on getting mixed with hazardous waste like paints, dyes, batteries, and human excreta turns hazardous. The
recyclables like paper and plastic etc. become unsuitable for recycling as these get soiled by the organic matter.
Although, it would be more fruitful to sort and place different kinds of recyclables in separate receptacles, the
waste could be segregated into at least two categories of biodegradable and non-biodegradable initially.
The recyclables obtained through segregation could be straightway transported to recycling units which in turn
would pay certain amount to the corporations, thereby adding to their income. This would help in formalizing
the existing informal set up of recycling units, and this formalization in turn could lead to multi-advantages. The
biodegradable matter could be disposed off either by aerobic composting, anaerobic digestion or sanitary land
filling. Depending upon land availability and financial resources, either of these disposal methods could be
adopted. Though simple land filling is the traditionally practiced system of solid waste management in the
planning area, aerobic composting by wind-row method will be an appropriate option. All the non-
biodegradable waste which is non-recyclable, non-reusable shall be dumped into sanitary land fill. Bio-
degradable waste shall be subjected to composting. Area required for composting shall include the area for
storage of unprocessed material, processing facilities for composting operation and storage for green compost.
The area required for windrow composting with 15 days composting period with moisture content between 55-
60% for aerobic composting, the first turning shall be done at the 4th day and thereafter every third day shall be
1.5 acres to 2 acres per 50 MT per day waste.
105
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Treatment options:
The biodegradable portion of the waste is considerably high. So, aerobic composting of SW after proper
segregation will be more appropriate. In selected locations especially in rural areas, Vermi-Composting can also
be recommended. The manure obtained by these methods can be sold to the local public as fertilizer. Though
costly, sanitary land filling can also be practiced at selected urban locations where the recovery from the waste
will be very high, serving minimum ecological damage. It appears that the aerobic composting by Windrow
method may be a desirable option for the management of the solid waste. The possibilities of generating energy
from SW could be looked into on an experimental basis.
106
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
If a small part of these infectious hospital wastes are mixed with other hospital wastes or municipal solid wastes,
the entire waste will have to be treated as infectious. Segregation helps in reducing the total treatment cost,
stops general waste from becoming infectious, reduces the chances of infecting the Health Care Workers, etc. All
these wastes after segregation must be stored in colour coded containers. Infectious waste should be
disinfected before disposal. It has been observed that majority of the hospitals, nursing homes, pathology
laboratories and health care centres located in these areas are not taking adequate measures for safe disposal of
their bio-medical wastes. These hospitals generate waste in substantial quantities, which needs to be managed
by the hospitals themselves. Many large hospitals dispose of their mixed wastes within the hospital premises,
where waste remains unattended in the open for a long time. Some hospitals and nursing homes have set up
low-temperature incineration plants for the disposal of wastes, which quite often remain out of order as they
are not managed and maintained properly. Infectious and non-infectious wastes are generally not segregated at
source and instead the mixed (often wet) waste is taken to the incineration plant in a very unhygienic manner.
The system of collection, transportation and disposal of bio-medical waste is thus not scientifically designed and
practiced in these areas.
107
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
108
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
A decentralized treatment system will be more feasible option for solid waste treatment. In recent times, there
is a trend towards smaller, manually operated composting plants at community level, initiated primarily by
citizens’ initiatives or non-governmental organizations NGOs) supported by many national and international
nodal funding agencies. In combination with primary waste collection, composting improves the precarious
waste situation in the communities, and residents become less dependent on the poor municipal waste
collection service. Decentralized composting can be operated by an appropriate technology and implemented at
reduced investment and operating costs. Manual composting in small, decentralized plants is more easily
integrated in the prevailing level of development in India and the socio-economic background, as it requires
labour-intensive processes. It will create employment opportunities and a source of income to the
underprivileged people in the rural Bhadrak. Decentralized composting allows reuse of organic waste where it is
generated, thereby reducing waste quantities to be transported as well as transport costs. This may drastically
reduce the overall cost of municipal solid waste treatment.
109
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Table 8.7: Land Area Requirement for Solid Waste Dumping Site
It is advisable to have some hazardous/bio-medical facility for the entire Bhadrak Planning Area. The bio-medical
wastes collected from spots can be stored in selective transfer stations and can be transported to this central
110
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
2332000 .000000
2332000 .000000
Bh
ad
ay
ailw
ra
R
k-D
To
A ern
na ast
ha
nd E
ap u th
-16
mr
u r So NH
aR
ly.
SH
- 9
SH
k -53
ttac
Cu
To
2328000 .000000
2328000 .000000
To
Dh
am
ra
To
Ch
an
d ba
li
SH
-35
ck
tta
Cu
To
2324000 .000000
2324000 .000000
To
A
ra
di
Ü
Legend:
National Highway
Drainage Map
Aquaculture Ponds Reservoir/ Dam
of Bhadrak Master Plan Area
River / Stream Tanks/ WHS State Highway
Special Planning Authority 0 375 750 1,500 Meters
Canal/ distributiory/ Power Channel/ Mahara Sea/BoB Other Road
Bhadrak
Lakes/ Ponds Waterlogged area Railway Line
Consultants :
Planning Boundary FEEDBACK INFRA PVT. LTD.
15th Floor, Tower 9B, DLF Cy bercity, Phase-III
Gurgaon 122 002, Hary ana, INDIA
Phone: +91 124 416 9100
Web: www.feedbackinfra.c om
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
"
/
!
.
.
!
2332000 .000000
2332000 .000000
"
/
"
/
Bh
ad
ay
ailw
ra
R
k-D
To
A ern
na ast
ha
nd E
ap u th
-16
mr
u r So NH
aR
ly.
.
! #
0
"
/
SH
!
. - 9
"
/
l
k ana SH
-53
ttac ev el C
Cu hL
To Hig #
0 .
! .
!
2328000 .000000
2328000 .000000
"
/
To
Dh
"
/
am
ra
.
!
/"
/ .
! To
""
/ C han
dba
li
SH
-35
ck
tta
Cu
To
2324000 .000000
2324000 .000000
To
A
ra
di
Public Toilet
Transportation
National Highway
State Highway
Railway Line
Waterbodies
Others
Waterbodies
Planning Boundary
Phyiscal Infrastructure Facilities
of Bhadrak Master Plan Area
Special Planning Authority
Bhadrak
0 380 760 1,520 Meters
Ü
Consultants :
FEEDBACK INFRA PVT. LTD.
15th Floor, Tower 9B, DLF Cy bercity, Phase-III
Gurgaon 122 002, Hary ana, INDIA
Phone: +91 124 416 9100
Web: www.feedbackinfra.c om
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
9
Social Infrastructure
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
9. Social Infrastructure
9.1 Introduction
Social infrastructure plays an important role to provide quality of life to the residents of the city. The
effectiveness of social infrastructure in achieving the objective of city development plan would depend upon its
capacity to contribute to improvement in the quality of life, enhanced self-dependency and city’s sustainability.
The level of social infrastructure shall aim the creation of livable city through reducing the sense of alienation
among the residents with less dependence on other settlements for basic infrastructure.
Social infrastructure refers to the facilities and mechanisms that ensure education, health care, community
development, and social security, recreational and social welfare. The development cannot be looked at in
isolation without considering the basic needs of the people, and a significant level of investment is needed in
9.2 Education
Education is an important factor influencing the quality of life of the people and future development of an area.
It empowers them with skills and knowledge and helps them to better lead their life and to access best of the
employment opportunities available in the market. This in turn will impact the work force participation rate and
economy of the area.
However, the planning area lacks schools for differently-able children and integrated schools with or without
hostel facility as present.
The assessment of future requirements for educational facilities has been done based on the recommended
norms specified by the URDPFI guidelines and given in Table below.
Table 9.1 Existing Educational facilities and Future Requirement in Bhadrak
Requiremen
Requiremen
Requiremen
Particulars
Pop. /unit
Standards
Area (Ha)
Existing
Future
t (Ha)
S. No
Land
t
111
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Requiremen
Requiremen
Requiremen
Particulars
Pop. /unit
Standards
Area (Ha)
Existing
Future
t (Ha)
S. No
Land
t
t
4 Integrated School 1000-1500 Students, 1 3.5 0.90 lakh 3 - 3 11.05
without Hostel (I-XII) for 90000 Pop
5 Integrated School with 1000-1500 Students, 1 3.9 0.90 lakh 3 - 3 12.31
Hostel (I-XII) for 90000 Pop
6 School for Physically 400 Students / 45000 Pop 0.7 0.45 lakh 6 - 6 4.42
challenged
7 College 1000-1500 students /1.25 5 1.25 lakh 2 1 1 6.36
Lac Pop
8 ITI's 400 Students/ 10 Lac Pop 1.6 10 lakh 3 0 3 4.55
9 Polytechnic 500 Students / 3 Lac Pop 2.4 3 lakh 1 0 1 2.27
10 Professional Institute 1 / 10 lakhs 6 10 lakh - 2 - -
In order to provide adequate educational facilities and infrastructure all through the planning area, Master Plan
has proposed setting up these facilities on a hierarchical basis i.e. at City Level (Planning Area), at Planning Unit
Level, at Neighbourhood Level and lastly at Residential Area Level.
For instance higher order facilities like college, integrated schools, school for handicapped are to be provided at
the master plan level while facilities like Nursery and primary schools are to be provided at the Neighborhood
level.
112
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Requiremen
Requiremen
No. of Beds
Population
Standards
Area (HA)
Numbers
Future
Name
t (HA)
Land
t
1 Intermediate Hospital (A) 1 1 / 1 lakh 100000 1 200 3.70 3.70
2 Intermediate Hospital (B) 1 1 / 1 lakh 100000 1 80 1.0 1.0
3 Nursing home, Maternity 1 1/ 45,000 45000 1 30 0.3 0.30
and Child Hospital
4 Family Welfare Centre 1 1 per 50000 pop. 50000 6 - 0.08 0.45
In order to provide adequate educational facilities and infrastructure all through the planning area, Master Plan
has proposed setting up these facilities on a hierarchical basis i.e. at City Level (Planning Area), at Planning Unit
Level, at Neighbourhood Level and lastly at Residential Area Level. For example, higher order facilities as general
hospital, intermediate hospital, etc. are to be provided at the master plan level while facilities like dispensary
should be provided at the Neighborhood level for better access to these.
113
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Requirement
Population
Particulars
Total Area
Area (HA)
Standard
Future
S. No.
(HA)
1 Convenience shopping 1 for 5,000 Pop 5000 0.15 57 8.52
2 Local shopping including service 1 for 5,000 Pop 15000 0.46 19 8.71
centre
3 Community centre with service centre 1 for 1,00,000 Pop 100000 5 3 14.20
4 District centre 1 for 5 Lac Pop 500000 1 1 1.00
Source: Consultant’s estimation
Amongst the various community facilities, there will be a major requirement of Community rooms, libraries,
Aaganwadi, Milk Booths, Police office, Post Office and Graveyard / Burial Grounds in the planning area. The
assessment of future requirements for various types of community facilities has been done based on the
recommended norms specified by the URDPFI guidelines and given in Table below.
requirement
Population
Particulars
Total Area
Area (Ha)
Standard
Existing
Future
S. No.
(Ha)
114
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Requirement
requirement
Population
Particulars
Total Area
Area (Ha)
Standard
Existing
Future
S. No.
(Ha)
10 Police Station 1 for 90,000 Pop 90000 1.5 3 2 1 1.73
11 Police Post 1 for 40,000 Pop 40000 0.16 7 2 5 0.82
12 Fire Station 1 for 2 Lac Pop 200000 1 1 0 1 1.42
13 Sub Fire Station 1 for 1 Lac Pop 100000 0.6 3 1 2 1.10
14 Post Office 1 for 15,000 Pop 15000 0.6 19 1 18 10.76
15 Graveyard / Burial Ground 1 Ha site for 10000 1 28 7 21 21.41
10,000 Pop
Source: Consultant’s estimation
In terms of Recreational facilities, Bhadrak will have a major requirement of cluster level and neighborhood level
Total Area
Standards
Particular
S. No.
(Ha)
unit
1 Cluster Parks 1 / 5000 Pop 5000 57 1.5 85.22
2 Neighborhood Parks 1 / 10,000 Pop 10000 28 3 85.22
3 Sport Complex (near MET College) 1 at City Level 1 9.3 9.30
4 Exhibition Ground 1 at City Level 1 18.72 18.72
5 City Level Sports Centre 1 at City Level 1 21.2 21.20
6 District Park 1 at City Level 1 20.73 20.73
7 Bio Diversity Park / Botanical Garden 1 at City Level 1 38.1 38.10
Source: Consultant’s estimation
Similar to educational and health care, for the equitable distribution of other social infrastructure facilities as
well in the planning area and to cater to the maximum number of residents in Bhadrak, the Master Plan suggests
planning for these on a hierarchical basis i.e. at City Level (Planning Area), at Planning Unit Level, at
neighbourhood Level and lastly at Residential Area Level. Further, recreational zone with many activities is
proposed to be developed as part of river front development along the River Salandi.
9.6 Power
115
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
9.6.3 Recommendations
In order to minimize the current and future power losses in the planning area, following measure are suggested:
• Renovation and modernization of 33/11 KV and 11 KV / 440 V sub- stations
• Installation of new transformers and capacity augmentation of existing transformers
• Metering of all connections;
• Installation of a HVDS (High Voltage Distribution System)
• Installation of LT ABC (Arial Bonded Cable)
116
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
2332000 .000000
2332000 .000000
Bh
ad
ay
ailw
ra
R
k-D
To
A ern
na ast
ha
nd E
ap u th
-16
mr
u r So NH
aR
ly.
SH
- 9
l
k ana SH
-53
ttac ev el C
Cu hL
To Hig
2328000 .000000
2328000 .000000
To
Dh
am
ra
To
C ha
nd
ba
li
SH
-35
ck
tta
Cu
To
2324000 .000000
2324000 .000000
To
A
ra
di
Ü
Legend:
Infrastructure Facilities
Social Infrastructure Waterbodies
Temple Aquaculture Ponds
Market Complex / Commercial Center
Church
River / Stream
Canal/ distributiory/ Power Channel/ Mahara
Govt. / Semi Govt. / Other Offices/ Institutions
^
G
Y
X
. X
! ^
G
Y
.
! Ashram / Matha
Bhadrak
Library Y X
X
.
! Y
.
!
Park/ G arden / Zoos
Sea/BoB
Consultants :
Beach
Fire Station State Highway
Exhibition ground / Maidan
Post Offices/Telegraph Offices/TE/Bank/ATM
Others
FEEDBACK INFRA PVT. LTD.
15th Floor, Tower 9B, DLF Cy bercity, Phase-III
Gurgaon 122 002, Hary ana, INDIA
Phone: +91 124 416 9100
Police Station / Help Center / Outpost / Jail
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
10
Heritage, Culture and
Tourism
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Chandbali
This place is known for its long coastline and pristine beaches. Also it is the
entry point to the Bhitar Kanika wildlife reserve. The place is also is the entry
point to the Bhitar Kanika wildlife
reserve. He place is marked with
series of delta that has been formed by the river Baitrani. The deltaic
regions are marked with an amazing variety of flora and fauna. The
place is home to over 170-different species of migratory birds, the
Olive Ridley Turtles, reptiles like crocodiles, king cobras and pythons
and wild animals like Rhesus Deers, Sambars and spotted deers.
Dhamra Port
Slated to become the second largest port of the slate, the Dhamra Port
which is being developed jointly by L&T and Tata Steel is based on the
coastline of Bay of Bengal.
Maa Bhadrakali
The famous temple of Goddess Bhadrakali is located in the outskirts of the
revenue village Aharapada which is at a distance of 8 kms away from
Bhadrak town in the south-west direction. One has to go via Santhia and
Utarabahini in the south-west direction of Katchery Chhaka of Bhadrak
town to reach the Shrine. The popular belief is that the name of the Town
has been derived from the name of the deity.
Dhamrai
The temple of the Goddess Dhamrai is at Dhamara a small coastal township, where the river Dhamra meets the
Bay of Bengal. The place is about 60 kms from the district headquarters in the eastern direction. It is surrounded
by Chandbali in the West, Basudebpur in the North, Kalibhanjadia in the South and Bay of Bengal in the East.
Festivals in Bhadrak
117
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The peoples of Odisha celebrate with huge enthusiasm are Raja, Kumar Purnima. This festival has culturally
importance for the people. People do lots of preparation for this festival. A number of special cuisines are made
for this festival. People also celebrate Kali puja, Durga puja, Maha Shiv Ratri, Dusherra, Deepawali, Eid Ul Fitar &
Urs (Dhamnagar & Shankar nagar) etc. These festivals bring lots of fun and create unity among the masses. The
positive vibes at the festival remains for all ventures. The tribal festival that people use to celebrate is Bali Yatra
at river site Salandi at Randia.
10.3 Issues
Dilapidated Condition of structures: Most of the tourism buildings are dilapidated condition i.e. washed out
walls, broken structure etc.
Unavailability of Infrastructure and Services: There is absolute lack of proper drainage and sewerage system in
the residential areas around the tourist spots. The facilities like eating joints and organized retail spaces near to
the monuments are also lacking.
Absence of Monitoring: There is no authority /Department responsible for timely monitoring of the heritage
• Indoor facilities consist of libraries, clubs, cinema hall, auditorium, multiplex, art and craft
centre, shopping malls, food courts, cyber cafés, gymnasium etc.
118
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
• Outdoor recreation facilities consist of gardens, parks, play grounds, golf courses, zoo,
botanical garden, race course, stadium, exhibition ground, water sports complex, green ways,
bike ways etc.
• Development of green belts, plantations, parks, Ghats, plazas along the Salandi riverfront abreast the
Urban set up and invite nature in harsh built environment through myriad ways.
• Amusement Parks to be developed along with horticulture, Pisi-culture, herbal parks, etc.
• Development of eco-tourism with provision of water theme parks, lagoon resorts, weekend resorts
and world class recreation centres such as club towns, golf clubs, spa resorts, etc. at Planning Area
level
Tourism is vital for every place, due to the income generated by the consumption of goods and services by
tourists, the taxes levied on businesses in the tourism industry, and the opportunity for employment and
economic advancement by working in the industry. For these reasons government and private agencies
sometimes promote a specific region as a tourist destination, and support the development of a tourism
industry in that area. The contemporary phenomenon of mass tourism may sometimes result in
overdevelopment; however alternative forms of tourism such as ecotourism seek to avoid such outcomes by
pursuing tourism in a sustainable way.
Bhadrak Region offer great potential for tourism development. According to the existing scenario analysis, it has
been observed that the following categories of tourism have immense potentialities for this region:
• Religious Tourism with historically important structures such as temples and other outdoor
worshipping areas in the vicinity
• Cultural and Heritage Tourism with annual / seasonal traditional village fairs and festivals, folk
or tribal socio-cultural events with arts, crafts, music, dance etc.
• Nature based outdoor recreation and Eco-tourism for hills, forest, riverfront / derelict stone
quarries and vast agricultural area/ village settlements with undulating landforms including
picnic spots, sightseeing, camping sites etc. Presence of all these tourism products calls for the
growth of Adventure Tourism.
• Coordinated Marketing to attract more tourists from other states and foreigners.
• Enhancing Product Quality so as to create a brand image for tourist destinations and enhancing
service quality.
• Facilitating Travel for easy access of tourists to major urban centres and tourist destinations.
• Developing Eco-tourism based on Nature and Culture for Sustainable Tourism Development.
119
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
• Enabling Private Sector Participation for accelerated growth of the industry and efficiency in
facilities and services.
10.8 Conclusion
The relevant policy guidelines and management of cultural and natural heritage can rejuvenate and revitalize the
Bhadrak region and support the existing cultural identity. It can also promote tourism, boost local economy and
contribute a great sense of pride amongst the residents and become a touchstone for future development.
120
11
Environment and Disaster
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
121
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
• Target the particulate matter levels especially re-suspension of road dust and soil dust. As far as
possible convert the unpaved roads to paved roads to minimize re-suspension of road SPM and
associated particulate pollution levels.
11.3.2 Proposals
• Available literature suggests that the water quality in River Salandi shows a decreasing trend with lower
quality levels at some points. Since the waste loads from drains ultimately finds its way to these rivers, in
general, care should be taken to see that the river is not polluted much above its carrying capacity.
• Mandatory to construct soak pits of required capacity along with Septic tank to arrest seepage of waste
water into ground water.
• The minimum clearance prescribed should be maintained between wells and septic tanks or soak pits.
The application for building permits should contain all these information and should be made mandatory.
The residents are to be advised against the improper construction and management of septic tanks and
soak pits which will ultimately lead to ground water contamination.
• Open defecation in the rural and semi-urban especially in slums and along nallah and river areas may
contribute to the surface water or well-water pollution. So, necessary steps may be initiated to construct
low cost community latrines in these areas, especially in slums to solve this problem.
11.4.1 Proposals
• Steps should be taken to control the use of loud speakers, especially in residential areas. In no case are
loud speakers to be permitted after 10 p.m.
• Green belt along the roads and near the junctions also helps in reduction of noise pollution due to
vehicles
122
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Planning and subsequently preparing a list of guidelines for the major urban communities so that the local
capacity is strengthened and they are prepared to respond to natural disasters.
123
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
through open drains. Open dump yards are yet another menace to the environment. The lack of solid waste
dump yard affects the sanitation of the town. There are nallahs and HL Canal covered with weeds and the worst
part of it is that there are slums and week housing along canals.
In absence of space availability for parking in the city, incidence of on-road parking is found everywhere, adding
to the woe of traffic.
124
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
11.5.4.1 Cyclone
Some of the proposals for Cyclone Disaster Mitigation are:
• A thick plantation belt of 0.5 km to be created all along the River Salandi
• Adopt strict enforcement on illegal cutting of forests and protection of existing forest reserve
• Building byelaws to be suitably modified as per the guidelines of the National Disaster Management
Authority
• In some special cases, these byelaws may be suitably amended as per the judgment of the architect to
avoid tunneling effect between buildings while designing a cluster of buildings
• Recreating the forest resources within the designated forest areas through the following measures:
▪ Re-densification of forest.
11.5.4.2 Flood
The various measures adopted for flood mitigation may be categorized into two groups:
▪ Structural
▪ Non- structural
The general approach is aimed at preventing floodwaters from reaching the potential damage centers, as a
result of which a large number of embankments should be constructed along the various flood prone rivers. The
main thrust of the flood protection programme to be undertaken in future in the form of structural measures
may be grouped into the following:
▪ Dams and Reservoirs
▪ Embankments
▪ Natural detention basin
▪ Channel improvement
▪ Drainage improvement
▪ Diversion of floodwaters
The non-structural measures, on the other hand, aiming at modifying the susceptibility to flood damages as
included in the plan include:
▪ Modifying the susceptibility to flood damages through:
▪ Flood plain management
▪ Flood proofing including disaster preparedness, and response planning
▪ Flood forecasting and Warning
Some of the suggested broad guidelines for flood mitigation in CDPA region are:
• Rainwater harvesting is to be made mandatory for all new buildings with more than 200 sq. m. roof area
• Storm water harvesting has to be carried out to utilize the excess water through creation of lakes and
water bodies that would facilitate irrigation and put less pressure on the drainage systems in post flood
situations
• Storm water drainage for the city as well as for individual premises must be properly designed
• In flood prone areas, buildings should preferably be designed on stilts leaving ground space free of any
important activities, with no basement
• A regional plan approach is to be followed for evolving the policies in regulating the carrying capacity of
the river /nallahs
125
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
• The vulnerable areas susceptible to annual flooding should be earmarked as the catchment’s detention
areas. During the off flooding period the stagnant water is to be drained off to the nearby water channels
with preliminary treatment
• Mapping of yearly flood pattern to be recorded by Irrigation Department
126
12
Development Management
and Finance
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The sources of funding available to existing major development agencies such as Special Planning Authority
(SPA), Bhadrak Municipal Council (BMC) and the Village Panchayats have been looked into and their
performances evaluated. The new roles of the urban local bodies in the context of urban governance have also
been evaluated.
127
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
23 Bhadrak Planning Area Preparation of DPR for Power Supply State Electricity Board,
System for Bhadrak Planning Area BMC
Sewerage System
24 Bhadrak Planning Area Preparation of DPR for Sewerage System PHE Dept, BMC, SPA
for Bhadrak Planning Area
25 Bhadrak Planning Area Laying of Sewer Network for Planning Area PHE Dept, BMC, SPA
26 Ward 29 Construction of STP (14 MLD) on 3.31 PHE Dept, BMC, SPA
Hectare of Land
27 Ward 28 Construction of STP (15 MLD) on 3.34 PHE Dept, BMC, SPA
Hectare of Land
128
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
129
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
130
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
HUDCO etc, on the basis of equity distribution as may be mutually agreed upon. This could also be a company on
the CIDCO model. In order to expedite development and attract developers, following may be provided:
▪ A bankable risk sharing mechanism
▪ Mortgage leasehold rights
▪ Exempt first sale on transfer from payment of Stamp Duty or Registration fees
▪ Exempt all inputs from sales tax during construction
131
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
• Improve Capacity Building of local bodies by introduction of community participation and delivery of
public services. Interactive participation of Ward Committees, CDS and HHW is made responsible for
infrastructural development at the community level.
• Augment resource base for revenue generation including rationalized fiscal transfer.
• Adopting modern financial tools for development functions.
• Change of mindset and public awareness is essential for implementation of Cost Recovery.
• Enhancement of Tax base and improvement of collection of Property Tax and other taxes.
• Thrust and focus on adopting Transformation in Civic engagement.
• Expanded role in capital budgeting and selecting their priority schemes.
• The integration of urban local bodies with its own decentralized management through ward
committees as well as with the high level District Planning Committees is essential.
132
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
12.6 Legislation
The evolutionary process of development needs have been reflected in the new legislation and amendments of
existing legislation. The following Acts are in operation:
• Odisha Town Planning and Improvement Trust Act, 1956 (Odisha Act 10 of 1957).
• Odisha Development Authority Act, 1982 (Odisha Act 14 of 1982).
• Odisha Development Authority Rules, 1983.
• 73rd & 74 Constitution Amendment Act in 1992.
• Odisha Municipal Corporation Act, 2003
• Panchayat Extension to Schedule Areas Act (PESA), 1996
133
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
We have followed the land use categories as specified by the Special Planning Authority Bhadrak and URDPFI
with minor changes in the classification. Residential Use Zone, Retail Commercial and Business Use Zone,
Wholesale Commercial Use Zone, Industrial Use Zone, Public and Semi-public Use Zone, Utilities and Services
Use Zone, Recreational Use Zone, Transportation Use Zone, Agriculture and Forest Use Zone and Water Bodies
Use Zone have been retained as it is. Special Area Use zone has been re-grouped as:
(i) Environmentally Sensitive Use Zone
(ii) Special Heritage Use Zone
Environmentally sensitive river front areas, forest areas, marshy areas etc. as Environmentally Sensitive Use and
old built up areas, scenic value, archaeological sites, etc as Special Heritage Use.
134
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
appearing hard to come by. In this context, exploring alternative sources of financing capital investment is the
major option left.
It is proposed to create a dedicated Bhadrak Master Plan capital infrastructure fund, which can attract debt and
private finance.
a) Water Supply
▪ Advance registration fees.
▪ Enhancement of water tariff and metering
▪ Connection charges
▪ Water tax
▪ Development Charges
▪ Other sources such as property tax,
▪ Sale of plots etc.
b) Sewerage
▪ Connection charges
▪ Sewerage Tax
▪ Conservancy tax
▪ Sale of sludge
▪ Sale of renewable waste
▪ Fines for untreated effluent disposal
c) Solid Waste Management
▪ Collection charge
▪ Cess
▪ Sale of renewable waste
135
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Steps should be taken for transparent assessment of properties (unit area method), increased coverage by
property mapping using GIS applications and rationalization of self-assessment system. Every property in the city
must be given a Property Tax Index Number (PTIN) whereby the payment, the changes and nature of use of the
property can be done through computer and E–Seva centre.
12.9.4 Non Tax Revenue Generation through Innovative Land Planning and Development Control
Regulation
• Creation of Special Development Districts (SDD) to make major investment in infrastructure and
services and formulate different Development Control Regulations.
• Imposition of Development Impact Fees in the SDD, the designation of district zones with differing built
form parameter is assumed.
• Utilization of Transfer of Development Right (TDR) enabling flexible development control and
permitting trade for their lost FSI.
• Imposition of User Charges i.e., cost recovery through direct charges to beneficiaries.
136
13
Future Land use
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
137
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
138
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
4.87% Commercial
16.27%
Mixed Use
0.33%
Industrial
2.87% 54.93% Pub & Semi Public
Recreational
8.38%
Transportation
Figure 13.2 Bhadrak Proposed Land Use Distribution of Developed area -2030
Figure 13.3 Bhadrak Proposed Land Use Distribution of the Planning Area -2030
139
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Mixed use has been increased to 385.64 hectares for the projected year 2030 from the existing 9.58 hectares
contributing about 8.38 % and 4.80% of the developed area and the total planning area respectively. As the
population increases the demand for mixed use area increases, hence mixed use areas has been planned along
all the higher level roads.
140
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Figure 13.4 Proposed Bhadrak Planning Area Land Use Plan -2030
141
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
▪ City level
o To facilitate higher order planning, city level facilities are provided.
142
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Higher order facilities as general hospital, intermediate hospital, college, integrated schools, and school for
handicapped, socio-cultural and recreational club, fire and police stations are provided at the master plan level.
Table 13.3 Details of Neighborhood Centers (10 Hectares for 10000 to 12,000 population)
Table 13.4 Details of Neighborhood Centers Provisions (10 Hectares for 12001 to 15,000 population)
143
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Table 13.5 Details of Activities allowed in District Centre & Integrated Commercial Centres
144
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
▪ The development rights that cannot be so consumed can be transferred elsewhere in receiving areas.
If FAR is related to width of the road, resistance to widening may get reduced.
▪ Public purposes on open land or exclusive plots: Lands required for parks and playgrounds or exclusive
uses like secondary school, fire station etc can be obtained by providing TDRs in lieu of compensation.
However, price differentials in originating and receiving zones could be considered as an incentive in
such cases.
▪ Public purposes that require built-up space but not necessarily exclusive plot: Examples of this could
be municipal vegetable market, library etc. In such cases, landowner may be permitted to use the full
potential of development in terms of FAR over the plot provided he offers the built up space required
for the public purpose to the local body.
▪ The executing agency/the government, can acquire your property by compensating you with TDR If
property is in the way of executing a large infrastructure project. What is actually issued to you is a
Development Rights Certificate specifying a built-up area that is 1.5 times what the person have
145
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
originally surrendered. For e.g., if gave up 600 sq. ft. Built-up area to the Authority under the Roads
Widening Scheme, then will receive a certificate for 900 sq. ft. of built-up area. Built-up area is also
known as Floor Space Index (FSI) or Floor Area Ratio (FAR). The DRC is a certificate, and it is not land
itself.
▪ This can either use the DRC to exceed your allowed (i.e. sanctioned) built-up area on another plot of
land/building that may own in some other part of the city. Or, can sell the DRC in the market. Many
big developers and builders are keen to purchase the DRCs because it legally gives them more FAR.
Innovative Techniques
146
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
B. Rehabilitation
Rehabilitation by three specific measures:
Individual oriented programmes: Education, training and providing employment to the villagers to
integrate them with the urbanisation process.
Village oriented programmes: Devising ways to upgrade the village infrastructure to bring it at par with
the newly built city around them, and
Land compensation: Making villagers effective partners in the development of the new city by sharing
the assets created in the new city with them.
147
442000.000000
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
443500.000000 445000.000000 446500.000000 448000.000000 449500.000000 451000.000000 452500.000000 454000.000000 455500.000000
e
S
or
l as
2337500 .000000
2337500 .000000
Ba
To
e
or
S
l as
Ba
To
S
S
2336000 .000000
2336000 .000000
S
IND
ay
ilw
RANJA NO 131
Ra
n
er
st
Ea
h
ut
So
S
S
2334500 .000000
2334500 .000000
S
S
TISALAPUR NO.133
S ASURA NO 132 OS S
S
S
CHARAMPA NO.137 S OS
To Ambroli
S
S
S
S
S
2333000 .000000
2333000 .000000
S
S
S
S
BARALPOKHARI NO.138 S
S
KANTAPAL NO.139
S
NC
S
EREIN NO.141
S
S S
S S
2331500 .000000
2331500 .000000
P S
S S
W&TC TT
S S
S
S
To S
A na
n GABHASAHI NO 112
S
da
S
pu
r S
S NC KHORDANG NO.140
S
NC
S
S
S
MATHASAHI NO.111 S
S
NC S
DC
S
S
PALSINGA NO.142
S
6
-1
BAUDPUR NO.113
NH
S
2330000 .000000
2330000 .000000
IND
S
S DP S
NC S KUNTALA NO.143
S S
KORANT NO.62 S
SH S
IND KUANS NO.110 -9 ICC
BHAGABANPUR NO.147
S
IND IND
Bh
S S S
ad
S
ra
S S
k
ISAFPUR NO.109 NC
S
-D
JAGANNATHPUR NO.88
ha
S
S
IND
m
S S
ar
RANDIA
S NO.63 IND HAMIRBINDHA NO.108
a
S
Ra
ilw
ay
S
S
BAGHURAI NO.87 P S
Li
S S
n
SH -53 BANK NO.90
e
S S
ck NC
tta
Cu
To NARIPUR NO.89
2328500 .000000
2328500 .000000
S S
S
MALIARUA NO.148
BALIARADA NO.94 MIRJAPURSNO.107
S
al SANTHIA NO.92
el Ca n P
P
h Lev
S
NACHHIPUR NO.149
Hig
S
BT SANKARPUR NO.95
NC
S
S
NILAKANTHAPUR NO.93
S
S
ICC
Sa
la
ck
6
S
-1
di
ta
H
t
S
R
S
Cu
N
BAJETOL NO.105
iv
S
To
e r
S
S
BEKA
S NO.106 BT BRAHMAPUR NO.150
APARTTIBINDHA NO.91
S
S
SAMRAEPUR NO.86
To
S
Dh
S S
am
S
NC
NC
ar
GELAPUR NO.64
a
S S
S S
EH
S S
NC
2327000 .000000
2327000 .000000
ITI
S
S
S S
S
ELEKHA NO.96
S
KEDARPUR NO. 151
S S S
S
To
S S S S
S
C ha
DAHANASUNI NO.104 nd
SC ba
S S
S S BG li
S S
S
S S
S
S
S
SS S S
S S
S S
S
BHABANIBINDHA NO 152
S
BARADADIHI NO.85
S S
BHUYANMAHALLA NO.102
S
S S
S
STP
S S S S
S S S S S
S S S S
S
STPBASAHPUR NO.103
S S S S
S S S
S
S
S S
GARADPUR NO.98
S
S
S
S
2325500 .000000
2325500 .000000
S
KORAKORA NO.97
S S
S
S
S
S S S
SAIDABAD NO.100
ck
S
tta
S S
S
Cu
To
S
SH
-35
S S S
To Kothar
S S
S S
S
S S
S
S
S
S
S S S
S
2324000 .000000
2324000 .000000
S S
S S S
S S S
S
S
To
A
ra
S
di
S
S
S
2322500 .000000
2322500 .000000
442000.000000 443500.000000 445000.000000 446500.000000 448000.000000 449500.000000 451000.000000 452500.000000 454000.000000 455500.000000
Legend Public Utilities & Facilities SC Sports Complex Waterbodies Title : Scale : 1:17,000
.
Residential Public Utilities Transportation Waterbodies
Residential Communication T-1 Existing Road
Embankment PROPOSED LAND USE MAP
Affordable Housing STP Sewage Treatment Plant T-2 Existing Road (Widening)
Green Belt
Mixed Use Public & Semi-Public T-3 Proposed Road
Grazing Land
M-1 Kalyan Mandap/Auditorium/Govt./Semi Govt. offices/Health Centres
T-4 Elevated Road
Educational Centers/Puja Mandap/Fire Station/Police Station/Jail
SPECIAL PLANNING AUTHORITY
M-2 Green Buffer along Road/River
Creamation Ground/Temple/Mosque/Gurudwara
T-5 Railway (ROW)
M-3 EH Educational Hub Others 0 425 850 1,700
DC District Centre ITI Industrial Training Institute
BT / TT Bus Terminal / Truck Terminal
Planning Boundary
BHADRAK Meters
Railway Line
NC Neighbourhood Centre Recreational Municipal Boundary Consultants :
Agriculture
Commercial Park/Garden/Zoos/Playground/Stadium
Cultivation Village Boundary
Retail DP District Park
FEEDBACK INFRA PVT. LTD.
15th Floor, Tower 9B, DLF Cybercity, Phase-III
ICC Integrated Commercial Centre Forest S HT Line Gurgaon 122 002, Haryana, INDIA
BG Bio-Diversity Park-cum-Botanical Garden Phone: +91 124 416 9100
Web: www.feedbackinfra.com
W&TC Wholesale & Trade Centre Forest
OS Organized Open Space
Industrial B. E. CONSULTANTS
P Park ARCHITECHTURE, PLANNING, INTERIORS
IND Industrial A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
2332000 .000000
2332000 .000000
Bh
ad
ay
ailw
ra
R
k-D
To
A ern
na ast
ha
nd E
ap u th
-16
mr
u r So NH
aR
ly.
SH
- 9
l
k ana SH
-53
ttac ev el C
Cu hL
To Hig
2328000 .000000
2328000 .000000
To
Dh
am
ra
To
C han
db
ali
SH
-35
ck
tta
Cu
To
2324000 .000000
2324000 .000000
To
Ara
di
Others
Waterbodies
Planning Boundary
Commercial Activities
of Bhadrak Master Plan Area
Special Planning Authority 0 375 750 1,500 Meters
Ü
Street/ Road Side shops/ Vending Zones
Hotel / Lodge
"
!!
/"
/ Petrol Pump
Dail/ Weekly hat/ Market
Sub-Arterial Road
Railway Line Bhadrak
!! Consultants : FEEDBACK INFRA PVT. LTD.
15th Floor, Tower 9B, DLF Cy bercity, Phase-III
Gurgaon 122 002, Hary ana, INDIA
Phone: +91 124 416 9100
Web: www.feedbackinfra.c om
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
2332000 .000000
2332000 .000000
Bh
ad
ay
ailw
ra
R
k-D
To
A ern
na ast
ha
nd E
ap u th
-16
mr
u r So NH
aR
ly.
SH
- 9
l
k ana SH
-53
ttac ev el C
Cu hL
To Hig
2328000 .000000
2328000 .000000
To
Dh
am
ra
To
C ha
nd
ba
li
SH
-35
ck
tta
Cu
To
2324000 .000000
2324000 .000000
To
A ra
di
Ü
Legend:
Industrial Activities Transportation Waterbodies Industrial Activities
of Bhadrak Master Plan Area
Industries National Highway Waterbodies
Industrial Estate/ SSI State Highway Others
B. E. CON SULTANTS
Industrail dumps ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
"
/
!
.
.
!
2332000 .000000
2332000 .000000
"
/
"
/
Bh
ad
ay
ailw
ra
R
k-D
To
A ern
na ast
ha
nd E
ap u th
-16
mr
u r So NH
aR
ly.
.
! #
0
"
/
SH
!
. - 9
"
/
l
k ana SH
-53
ttac ev el C
Cu hL
To Hig #
0 .
! .
!
2328000 .000000
2328000 .000000
"
/
To
Dh
"
/
am
ra
.
!
/"
/ .
! To
""
/ C han
dba
li
SH
-35
ck
tta
Cu
To
2324000 .000000
2324000 .000000
To
A
ra
di
Public Toilet
Transportation
National Highway
State Highway
Railway Line
Waterbodies
Others
Waterbodies
Planning Boundary
Physical Infrastructure Facilities
of Bhadrak Master Plan Area
Special Planning Authority
Bhadrak
0 375 750 1,500 Meters
Ü
Sewage Treatment Plant Consultants :
FEEDBACK INFRA PVT. LTD.
15th Floor, Tower 9B, DLF Cy bercity, Phase-III
Gurgaon 122 002, Hary ana, INDIA
Phone: +91 124 416 9100
Web: www.feedbackinfra.c om
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
GIS/RS BASED MASTER PLAN OF BHADRAK - 2030
444000 .000000 448000 .000000 452000 .000000
re
so
la
re
Ba
so
To
la
Ba
To
2336000 .000000
2336000 .000000
2332000 .000000
2332000 .000000
Bh
ad
ay
ailw
ra
R
k-D
To
A ern
na ast -16
ha
nd E NH
ap u th
mr
u r So
aR
ly.
SH
- 9
l
k ana SH
-53
ttac ev el C
Cu hL
To Hig
2328000 .000000
2328000 .000000
To
Dh
am
ra
To
C han
dba
li
SH
-35
ck
tta
Cu
To
2324000 .000000
2324000 .000000
To
Ara
di
Ü
Legend:
Proposed Social Infrastructure Transportation Waterbodies Infrastructure Facilities
of Bhadrak Master Plan Area
Integrated Commercial Centre Sports Complex National Highway Waterbodies
B. E. CON SULTANTS
ARCHIT ECHTURE, PLANNING, INTERIORS
A-237, Malviya Nagar,
Jaipur, Rajasthan, INDIA
Phone: +91 141 2520296
14
Zoning Regulations
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
148
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
In Residential Use Zone ‘R’ (Primary Residential with densities, Mixed Residential Zone Unplanned/ Informal
Residential Zone) have been marked for general guidance.
I. Uses/Activities Permitted:
Residence plotted (detached, semi-detached and row housing), group housing, work-cum-residential centre,
hostels, boarding and lodging houses, night shelters, dharamshalas, guest houses, educational buildings nursery,
primary, high school), neighborhood level social, cultural and recreational facilities with adequate parking
provisions, marriage and community halls, convenience shopping, local (retail) shopping, community centers,
clubs, auditoriums, exhibition and art galleries, libraries and gymnasiums, health clinics, yoga centers,
dispensaries, nursing homes and health centers (20 beds), yoga Centres, public utilities and buildings except
service and storage yards, electrical distribution depots and water pumping stations, nursery and green houses,
I. Uses/Activities Permitted:
Retail business, mercantile, commercial centers, banks, financial services and stock exchanges, perishable goods
markets, business and professional offices, private institutional offices and semi government offices, shops and
shopping malls, commercial services, restaurants and hotels, hostels, boarding houses, social and welfare
institutions, guest houses, convenience and neighborhood shopping centers, local shopping centers, weekly and
formal markets, bakeries and confectionaries, cinema halls, theaters, banquet halls, auditoriums,
marriage and community halls, night shelters, clinics and nursing homes, petrol pumps and service stations on
roads of 12 meter or more ROW, IT and IT enabled services, commercial institutes, research and training
149
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
institutes, service uses like hair salon, tailoring shops, beauty parlour, laundry and dry cleaning shops etc. bus
stops, Taxi stands, 3 wheeler/auto stands, rickshaw stands and parking spaces.
II. Uses/Activities Permissible on Application to Competent Authority (with conditions/ upto 30% area
on special consideration):
Associated residential uses, wholesale storage yards, junk yards, service garages provided they do not directly
abut the main road, printing presses employing not more than 10 persons, 20 bedded hospitals not treating
contagious diseases and mental patients, weigh bridges, colleges, polytechnics and higher technical institutes,
sports complex and stadiums, transient visitor’s homes, places of entertainment, recreational uses and
museums, convention centers, religious places, public utilities, telephone exchanges, police posts and post
offices, residential plot/group housing, picnic hut, parks, playgrounds, clubs.
I. Uses/Activities Permitted:
Wholesale business, commercial and business offices and work places, wholesale and storage buildings,
godowns, covered storage and warehousing, weigh bridges, bus stops, Taxi stands, 3-wheeler / auto stands,
rickshaw stands, truck terminal, bus depots and parking spaces, restaurants, public utilities.
II. Uses/Activities Permissible on Application to Competent Authority (with conditions/ upto 30% area
on special consideration):
Freight terminal, railway yards and stations, warehousing, storage godowns of perishable, inflammable goods,
coal, wood, timber yards, non- polluting, non- obnoxious light industries, service centers, garages, workshops,
junk-yards, gas installation and gas works, government and semi-government offices, banks, financial services,
associated residential uses, water treatment plants.
150
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
I. Uses/Activities Permitted:
All the uses /activities are permitted which are mentioned in para 14.2 under Mixed use Zone Category
II. Uses/Activities Permissible on Application to Competent Authority (with conditions/ upto 30% area
on special consideration):
All the uses /activities are permitted which are mentioned in para 14.2 under Mixed use Zone Category
I. Uses/Activities Permitted:
All kind of non polluting industries, IT & ITES, SEZs notified by government of India, Loading, unloading spaces,
warehousing, storage and depots of non perishable and non- inflammable commodities, cold storage and ice
factory, gas godowns, banks, financial institutions and other commercial offices, wholesale business
establishments, petrol filling station with garages and service stations, bus terminals and bus depots and
workshops, parking, taxi stands, 3-wheeler/auto stands, rickshaw stands, residential buildings for essential staff
and for watch and ward, public utilities, railway siding, incidental and utility use incidental to the main use.
II. Uses/Activities Permissible on Application to Competent Authority (with conditions/ upto 30% area
on special consideration):
Heavy, extensive and other obnoxious, hazardous industries subject to the approval of the Orissa Pollution
Control Board, Industrial Research Institute, Technical Educational Institutions, junkyards, sports/ stadiums/
playgrounds, sewage disposal works, electric power plants, service stations, govt. semi-govt., private business
offices, agro-based industries, dairy and farming, gas installations and gas works, workshops garages, hotels and
guest houses, museum, helipads, hospitals and medical centers, quarrying of gravel, sand, clay and stone.
The indicative list of industries which could be permitted subject to the condition that it satisfies above norms is
given in Appendix-I. The List naturally cannot be exhaustive. Therefore any such industry which has not been
indicated in the above referred list can be permitted provided it satisfies the above norms and is approved by
the Director of Town Planning, Odisha.
151
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Table 14.1 List of Industries which permissible in residential and commercial use zones
S. No Type of Industries
1 Cosmetic products
2 Agarbati
3 Writing Ink
4 Sealing Wax
5 Wax Candle
6 Acrylic Sheet Button
7 Plastic Covers(Dairy & Files etc.)
8 Plastic Seeds
9 Knitting Plastic Bags
10 Plastic Moulding Goods (Hand operated)
152
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
S. No Type of Industries
42 Thermometers
43 Decorative Glass articles
44 Chalk Sticks
45 Distemper
46 Nalidar Coal
47 Shikakai & Soapnut powder
48 Wire Brush
49 Umbrella Assembly
50 Wooden toys
51 Paper Pins, Gem Clips
52 Hair Pins
153
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
S. No Type of Industries
84 Dyeing & Darning
85 Cotton Cloth Weaving in Handlooms
86 Making of Ropes and Niwar
87 Making of Textile Garments including Rain- Coats & Caps
88 Ivory carving
89 Engraving Embossing , Polishing & Welding of Metal Products
90 Gold & Silver thread, Zari work, Jewellery, Gold Ornaments
91 Silver art ware including silver repouse work on copper
92 Manufacture, repairing & Tunning of Musical Instruments such as Harmonium, Sitar, Bansuri etc.
I. Uses/Activities Permitted:
Government offices, central , state, local and semi-government, public undertaking offices, universities and
specialized educational institutions, colleges, schools, research and development centers, social and welfare
centers, libraries, hospitals, health centers, dispensaries and clinics, social and cultural institutes, religious
buildings, conference halls, community halls, kalyan mandap, museums, art galleries, exhibition halls,
auditoriums, police stations, police lines, jails, local state and central govt. offices uses for defense purpose,
educational and research institutions, social and cultural and religious institutions, local municipal facilities,
hotels, dharamashala, guest houses, monuments, convention center, banking and financial services, commercial
uses center, shopping complex, public utility buildings, uses for defense purpose, defense quarters, educational
and police headquarters, radio transmitters and wireless stations, uses incidental to govt. offices and for their
use, incidental/ancillary residential use.
II. Uses/Activities Permissible on Application to Competent Authority (with conditions/ upto 30% area
on special consideration):
Residential flats, residential plots for group housing and staff housing, IT services, defense quarters, hostels,
transit accommodation, entertainment and recreational complexes, nursery and kindergarten, welfare center,
open air theater, playground, residential club, guest house, bus and truck terminals, helipads, parking areas, taxi
stands, 3- wheeler/auto stands, rickshaw stands, retail shops, shopping complexes, residential and other uses
which is no way causing any nuisance and hazard incidental to main use.
154
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
I. Uses/Activities Permitted:
Post offices, Telegraph offices, public – utilities and buildings, water Treatment Plant, Sewage Treatment Plant,
Solid waste Treatment Plant solid waste dumping grounds, radio transmitter and wireless stations,
II. Uses/Activities Permissible on Application to Competent Authority (with conditions/ upto 30% area
on special consideration):
Service industry, warehouse/storage godowns, health center for public and staff or any other use incidental to
public utilities and services, information/Payment kiosk, incidental/ancillary residential use, truck terminals,
helipads, commercial use center.
I. Uses/Activities Permitted:
Specialized parks/ maidans for multipurpose use, regional parks, district parks, playgrounds, children’s parks,
clubs, stadiums, picnic huts, holiday resorts, shooting range, sports training center, swimming pools, botanical/
zoological garden, bird sanctuary, green belts, bus and railway passenger terminals, public utilities and facilities
such as police post, fire post, post and telegraph office, health center for players and staff, animal racing or
riding stables, library, incidental/ancillary residential use.
II. Uses/Activities Permissible on Application to Competent Authority (with conditions/ upto 30% area
on special consideration):
Building and structure ancillary to use permitted in open spaces and parks such as stands for vehicles on hire,
taxis and scooters, commercial use of transit nature like cinemas, circus and other shows, public assembly halls,
restaurants, parking areas, caravan parks, open air cinemas/ theatre, entertainment and recreational complexes,
community hall, library, open air theater, theme parks, amphitheaters, residential club, guest house, camping
sites, yoga and meditation centres, fire post, police station, post and telegraph office, commercial uses center,
special education areas.
155
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
I. Uses/Activities Permitted:
All types of roads, railway stations and yards, airport, bus stops and bus and truck terminals, taxi stands, auto
stands, rickshaw stands, ferry ghats, parking areas, multi level car parking, filling stations, transport offices,
booking offices, information kiosks, night shelter, boarding houses, banks, restaurants, workshops and garages,
II. Uses/Activities Permissible on Application to Competent Authority (with conditions/ upto 30% area
on special consideration):
Way side shops and restaurants, authorized/Planned Vending areas, incidental/ancillary residential use,
emergency health care centre, tourism related projects, all ancillary (complimentary) uses for above categories
(subject to decision of the Authority).
I. Uses/Activities Permitted:
Agriculture and Horticulture, dairy and poultry farming, milk chilling center, storage, processing and sale of farm
products, dwelling for the people engaged in the farm (rural settlement), farm houses and accessory buildings,
public utility and facility buildings, forest use, afforestation.
II. Uses/Activities Permissible on Application to Competent Authority (with conditions/ upto 30% area
on special consideration):
Houses incidental to this use, parks and other recreational uses, wayside shops and restaurants, educational and
research institutions, agro serving, agro processing, agro business, cottage industries, burial and cremation
grounds, service industries accessory to obnoxious and hazardous industries, ice factory, cold storage, godowns
and ware houses, soil testing lab, normal expansion of land uses only in the existing homestead land, special
outdoor recreations, solid waste management sites, Sewage disposal works, electric sub-station, quarrying of
gravel, sand, clay or stone, building construction over plots covered under town planning scheme and
conforming uses, brick kilns and extractive areas, servicing and repair of farm machineries and the sale of
agricultural supply, small scale fertilizer chemicals, alcohol and distillery industry, petrol and other fuel filling
stations, hospital for infectious and contagious diseases, mental hospital after clearance from the Authority, eco-
tourism, camping sites, eco-parks, eco lodges, special outdoor recreations.
156
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
I. Uses/Activities Permitted:
Rivers, canals, streams, water spring, ponds, lakes, wetland, aqua culture pond, reservoir, water logged/marshy
II. Uses/Activities Permissible on Application to Competent Authority (with conditions/ upto 30% area
on special consideration):
Fisheries, boating, water theme parks, water sports, lagoons, water based resort with special by-laws, any other
use/activity incidental to Water Bodies use is permitted.
157
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Table 14.2 Shows the (a) Uses/Activities Permitted (b) Uses/Activities permissible on application to the Competent
Authority (with conditions / up to 30% area on special consideration) & (c) Activities Prohibited as it has been already
stated according to the Model Zoning regulations.
158
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
159
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
160
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
161
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
162
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
163
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
164
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
truck terminal
motor garage, workshop
repair and repair shop and
facilities such as night shelter,
boarding house,
banks
restuarants
booking offices
transmission centre, wireless station,
radio and television station
observatory and weather office
Each Planning Zone can be put to such use(s) as detailed out in the Master Plan. The proposed Land use Plan
indicates the location of broad uses and major facility areas. The requirements of these facilities are subject to
necessary modifications when the detailed Zonal Development Plans are conceived. Therefore, the purpose of
Zonal/Sub-zonal byelaws and regulations is not to stop the urban development activities in the Planning Area
but to serve as broad policy framework for the promotion of planned development. The Master Plan proposes
building activity within the prescribed Local Area limits should be controlled and guided by following set of
regulations as spelt out.
165
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
The aim of enforcing the regulations is to achieve a desirable development pattern and structure with good
quality of life. In order to ensure complete harmony between land uses, town has been divided into various Use
Zones including Residential, Commercial, Mixed use, industrial, Recreational, Public & Semi-Public, Transport &
Communication, Agriculture, Plantation, Water bodies etc. However, in enforcing master Plan proposals the
regulations have been made efficient to avoid inconvenience to public. Mixed land use concept has also been
adopted and prescribed which shall need approval of Government. The adoption of mixed land use concept is to
enhance functionality of the uses.
166
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
167
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Vision
To guide physical development toward a desired scale and character
that is consistent with the social, economic and aesthetic values of
the City.
Specific Guidelines
a) Natural Features
Preserve and protect natural landforms and features.
Conserve natural environment and create a linked open
space system. Preserve and enhance naturally occurring
features such as wetlands, riverfronts, slopes and forests.
b) Open Space Linkages
• Link neighborhood, public attractions, parks and other
destinations together through trail systems, bikeways,
landscaped boulevards, formalized parks, and natural open
space;
• Preserve and encourage preservation of physical connectivity and access to open space;
• Recognize that sometimes open spaces prevent the continuation of transportation corridors and inhibit
168
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
mobility between communities. Where conflicts exist between mobility and open space goals, site-
specific solutions may be addressed in community plans.
d) Street Frontage
• Create street frontages with architectural and landscape interest to provide visual appeal to the
streetscape and enhance the pedestrian experience.
• Locate buildings on the site so that they reinforce street
frontages.
• Relate buildings to existing and planned adjacent uses.
• Ensure that building entries are prominent, visible, and
well-located.
• Maintain existing setback patterns, except where
community plans call for a change to the existing pattern.
e) Historic Character
• Respect the context of historic streets, landmarks, and areas that give a community a sense of place or
history. A survey may be done to identify "conservation areas" that retain original community character
in sufficient quantity and quality but typically do not meet designation criteria as an individual historical
resource or as a contributor to a historical district;
• Create guidelines in community plans to be used for new development, so that a neighborhood's
historic character is complemented within the conservation areas where appropriate;
• Review the redevelopment of property within conservation areas to maintain important aspects of the
surviving community character that have been identified as characteristics of a neighborhood that
169
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
could be preserved.
f) Public Spaces
• Include public plazas, squares or other gathering spaces in each neighborhood center;
• Locate public spaces in prominent, recognizable, and accessible locations;
• Design outdoor open areas as “outdoor rooms,” developing a hierarchy of usable spaces that create a
sense of enclosure using landscape, paving, walls, lighting, and structures;
• Develop each public space with a unique character, specific to its site and use;
• Design public spaces to accommodate a variety of artistic, social, cultural, and recreational
opportunities including civic gatherings such as festivals, markets, performances, and exhibits;
• Consider artistic, cultural, and social activities unique to the neighborhood and designed for varying age
groups that can be incorporated into the space;
• Use landscape, hardscape, and public art to improve the quality of public spaces;
• Encourage the active management and programming of public spaces;
h) Landscape
• Landscape materials and design should enhance structures,
create and define public and private spaces, and provide shade,
aesthetic and environmental benefits
• Maximize the planting of new trees, street trees and other
plants for their shading, air quality, and livability benefits;
• Use water conservation through the use of drought-tolerant
landscape, porous materials, and reclaimed water where available;
• Use landscape to support storm water management goals for filtration, percolation and erosion control;
• Use landscape to provide unique identities within neighborhoods, villages and other developed areas;
• Landscape materials and design should complement and build upon the existing character of the
neighborhood;
• Design landscape bordering the pedestrian network with new elements, such as a new plant form or
material, at a scale and intervals appropriate to the site. This is not intended to discourage a uniform
street tree or landscape theme, but to add interest to the streetscape and enhance the pedestrian
experience;
• Establish or maintain tree-lined residential and commercial streets. Neighborhoods and commercial
corridors in the town that contain tree-lined streets present a streetscape that creates a distinctive
character;
o Identify and plant trees that complement and expand on the surrounding street tree fabric.
170
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
j) Lighting
• Provide lighting from a variety of sources at appropriate intensities and qualities for safety;
• Provide pedestrian-scaled lighting for pedestrian circulation and visibility;
• Use effective lighting for vehicular traffic while not overwhelming the quality of pedestrian lighting;
• Use lighting to convey a sense of safety while minimizing glare and contrast;
• Use vandal-resistant light fixtures that complement the neighborhood and character.
• Focus lighting to eliminate spill-over so that lighting is directed, intended use is illuminated.
k) Signage
• Design project signage to effectively utilize sign area and complement the character of the structure
and setting
• Architecturally integrate signage into project design;
• Include pedestrian-oriented signs to acquaint users to various aspects of a development. Place signs to
direct vehicular and pedestrian circulation;
• Post signs to provide directions and rules of conduct where appropriate behavior control is necessary;
• Design signs to minimize negative visual impacts;
• Address community-specific signage issues in community plans, where needed.
171
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
l) Utilities
• Minimize the visual and functional impact of utility systems and equipment on streets, sidewalks, and
the public realm;
• Convert overhead utility wires and poles, and overhead structures such as those associated with
supplying electric, communication, community antenna television, or similar service to underground;
• Design and locate public and private utility infrastructure, such as phone, cable and communications
boxes, transformers, meters, fuel ports, back-flow preventers, ventilation grilles, grease interceptors,
irrigation valves, and any similar elements, to be integrated into adjacent development and as
inconspicuous as possible;
• To minimize obstructions, elements in the sidewalk and public right of way should be located in below
grade vaults or building recesses that do not encroach on the right of way (to the maximum extent
permitted by codes). If located in a landscaped setback, they should be as far from the sidewalk as
possible, clustered and integrated into the landscape design, and screened from public view with plant
and/or fencelike elements;
172
15
Investment Plan
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
This is an indicative investment plan, it would be imperative to find out sources of enhanced capital finances to
be able to carry out the required investment. Further, it has been a common phenomenon that many of the
173
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
174
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
175
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Total 1795.77
176
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
possibilities have to be explored to check migration to other major urban centers by providing the entire
infrastructure envisaged in the Master Plan.
177
Annexure
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
16. Annexure
Table 1: Municipal Area Population
Municipal Area Population (2011)
Bhadrak (M) WARD NO.-0001 2474
Bhadrak (M) WARD NO.-0002 2315
Bhadrak (M) WARD NO.-0003 1834
Bhadrak (M) WARD NO.-0004 3907
Bhadrak (M) WARD NO.-0005 2362
Bhadrak (M) WARD NO.-0006 3102
Bhadrak (M) WARD NO.-0007 4390
178
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Table 3: Population of Out growths included in the Master Planning Area, Bhadrak
Name of Out growths Population (2011)
Randia 2993
Baudpur 2139
Samaraipur 4449
1 Construction of Foot bridge across Badajore of Kani nallah near village Ba-diha of Nuagaon G.P.
2 Construction of C. D. Work & approach road of Kunjakalia Bridge
3 Slope Protection & Restoration to O.A.E. on Salandi Left near Habib Nagar Danga Ghata
4 Slope Protection of Salandi Left Enbankment near Barikpur V. R. B.
5 Restoration of Nazar Nalla Sluice with slope protection
6 Slope Protection to Salandi Left Enbanment near Kuans Smasan
7 Improvement to Naliaa Right Enbankment at Langudi Mahadev Sahi
8 Slope protection with dumping on Salandi Right at Januganja
9 Improvement to road on Salandi left from Gopalia Head Regulator to Aharapada
10 Improvement to Afflux Bundh & approach road of Kanchudi Sluice near village Padampur for the
year 2016-17
11 Improvement to Gates of Rajabandha Sluice near village Bramhani Gaon for the year 2016-17
179
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
S. No New Projects
1 Improvement to Service Road from Salandi Right (Nuasahi) to Nalia Left Enbankment (Arnnapal
RD Road)
2 Improvement to Service Road of River Naliaa Left from Boitalumahara sluice to Rajuali Bindha
1 Construction of cause way over Kelasahi Barasar Embankment near Chabruti & Extention of
embankment upto Barasar U. P. Chool
2 Construction of H. P. Culvert over Hengupati Mohalik Sahi Embankment including raising
strengthening and metalling
3 Construction 2 nos. of H. P. Culvert over Kaudia Left TRE near Kaudia Sluice
4 Construction of Foot Bridge across Begunia jore near village Jenapur in Bijayanagar G. P.
180
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Table 9: State Plan Flood Restoration Works for the Year 2016-17
S. No. Name of Work District Block Constituency Nature of Work
1 2 3 4 5 6
1 Scope Protection & Bhadrak Bhadrak Bhadrak Earth work, Stone
Construction of Packing
Embarkement on Salandi
Right at Bankasahi near
Women's college
2 Slope Protection to Baitarani Bhadrak Chandbali Chandbali Stone dumping &
Left from Lunchghat to Packing
Aranya Nivas
3 Bank Protection to Baitarani Bhadrak Chandbali Chandbali Dumping & Packing
Left near village Pokharisahi
4 Bank Protection to Baitarani Bhadrak Chandbali Chandbali Dumping & Packing
Left near village Sanaharipur
Table 10: Additional Work List Under Salandi Canal Division, Bhadrak
S. No. Name of Work
Flood Control
1 Construction & Slope protection to left & Right embankment of river Salandi to RD 53.10 km
2 Slope Protection to River Nalia at D/S of Durgapur Escape
3 Slope Protection to River Nalia at Rajualibindha & Itapal
4 Repair & Restoration with Construction of Protection Wall to the Feeder of Salandi river near
Banka School
5 Construction of Right embankment of river Salandi from Gabasahi bridge to Januganja
6 Construction of Protection wall on Capital Embankment 2A
7 Construction of Protection wall & stone packing on left embankment of River Salandi at
Durgapur
181
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
182
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Table 16: Master Plan of Strom Water Drainage Projects for Mission Period (As per Table 2.1 of AMRUT
guidelines) Master Plan of Storm Water Projects for Mission Period
183
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
184
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Gazettee Notification of Inclusion of Revenue Villages within the Bhadrak Planning Area.
185
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
186
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
187
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
188
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
189
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
190
GIS/RS BASED MASTER PLAN FOR BHADRAK TOWN
Project Phasing
Year 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
S.No.
Project Name Phase-I Phase-II Phase-III Phase-IV
Urban Development
Year 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
S.No.
Project Name Phase-I Phase-II Phase-III Phase-IV
Installation of new transformers and capacity
2 augmentation of existing transformers
1
Development of Solid Waste Engineering Landfill Site on
2 8.99 Hectare of Land
Drainage
Preparation of DPR for Drainage System for Bhadrak
1 Planning Area
Year 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
S.No.
Project Name Phase-I Phase-II Phase-III Phase-IV
Master plan of Strom Water drainage(Sanctioned Under
6 AMRUT)
Flood control
Year 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
S.No.
Project Name Phase-I Phase-II Phase-III Phase-IV
12 Up gradation of Bus Depots (Sanctioned Under AMRUT)
Development of Transport Nagar (Sanctioned Under
13 AMRUT)
Construction of Foot Over Bridges (Sanctioned Under
14 AMRUT)
Year 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
S.No.
Project Name Phase-I Phase-II Phase-III Phase-IV
1 Development of Industrial Estate – I (165.20 Ha)
2 Development of Industrial Estate – II (205.07 Ha)