PROJECT : JAKARTA MRT

CUST : PT. HPSI


STATUS PLAN PROCESS
NO PART NAME QTY
INPROC BEFORE PROC 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 14-Mar 15-Mar
1 FRM/C 1HB02910-B 4 PCS - A+B+C+D+E A B C D E
2 FRM/C 1HB02910-C 1 PCS - A+B+C+D+E A B C D E
3 BASE/C 1HB02928-A 2 PCS A B+C+D+E B C D E
4 BASE/C 1HB04691-A 4 PCS A B+C+D+E B C D E
5 BASE/C 1HB04692-A 2 PCS A+B+C D+E D E
6 BASE/C 1HB04694-A 2 PCS A+B+C D+E D E
7 FRM 2HB04545-C 1 PCS A B+C+D+E B C D E
8 BASE/C 2HB05655-A 1 PCS A+B+C D+E D E
9 BASE/C 2HB05656-A 1 PCS A+B+C D+E D E
10 FRM/C 2HB05787-A 2 PCS A B+C+D+E B C D E
11 FRM/C 2HB05788-A 1 PCS A B+C+D+E B C D E

URUTAN PROSES :
A WELDING
B DRILL & TAP PT. OSAKA ENGINEERING
C FINISHING
D SEAT
E FLATNESS MASONO