: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Reinforcement

Table of Contents
1- Purpose ………………………………………………. 3
2- Scope of Work ………………………………………………. 3
3- References ………………………………………………. 3
4- Resources ……………………………………………..... 3
5- Work Methodology ……………………………………..... 4
6- Responsibility and Supervision ……………………………..... 5
7- Health and Safety ……………………………………..... 6
8- Quality Assurance ……………………………………..... 7

Page 2
Sub-
: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Reinforcement

1- Purpose:

The purpose of this method statement is to cover the requirements and methodology for
Concrete Reinforcement for the buildings, including materials, tools and equipment, health and
safety requirements, quality assurance and all other related works.

2- Scope of Work:

This method statement is applicable to all buildings of Border Stations D14, Sector
Headquarters D15, Border Compounds D15p and Rear Gates.

3- References:

1. Approved Drawing
2. Approved QA/QC Documents
3. Approved Material Submittals

4- RESOURCES

4.1 Materials 4.2 Equipments 4.3 Personnel


- Steel Reinforcements - Crane - Project Engineer
- Tie wires - Lorry - QA/QC Engineer
- Concrete Spacers - Rebar Cutter - Safety Officer
- Bending Machine - Construction Supervisor
- Water Pump or Air Blower - Skilled Worker / Operator
(Suitable for removing dust - Unskilled Worker
and dirt)
- Minor Tools

Page 3
Sub-
: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Reinforcement

5- WORK METHODOLOGY

Preparations

a. Obtain relevant approved drawings.


b. Ensure materials delivered to site are inspected and approved by Consultant.
c. Secure approved cutting and bending schedule from the engineer in charge specifying the
diameter, length, quantity and the purpose of the reinforcements to be cut.

Execution

a. Cut and segregate the steel reinforcement according to the cutting schedule.
b. Bending should be done by cold bending and according to relevant drawing and bending
schedule.
c. Safety should always be bear in mind in operating the cutting and bending machine.
d. Reinforcement, once cut and bent, shall be stored in the lay down area or on off ground supports
and shall only be transported to the work area when required. All bars will be tagged as per the
bending schedule.
e. All scrapped or unused reinforcement shall be stored in a central area before being removed from
site. In general, no loose or scrap reinforcement shall be left in / around the work areas.
f. Place steel reinforcement according to the position and location shown in the drawings. Secure
the intersections and positions of the reinforcement using approved ties.
g. Use appropriate concrete spacers to attain the required concrete protective cover for each
structure. Concrete protective cover for reinforcement shall be as follows, unless otherwise
shown on the drawings:

Location Cover
1. Foundations cast against soil 75mm
2. Foundations cast against blinding 50mm
3. Retaining walls, basement walls, and water retaining structures 50mm
4. Beams and Columns (not exposed to soil and water) 40mm
5. Walls and Slabs (not exposed to soil and water) 30mm

h. Splice steel reinforcement according to position shown on the drawing. Reinforcement splices
shall be taken as required by (ACI 318-08 clauses 12.14 to 12.19) Class B splices unless
otherwise indicated.

Page 4
Sub-
: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Reinforcement

i. Clean the completed area free from dust and dirt using water pump or air blower prior
inspection.
j. Submit Request for Inspection Form for joint inspection with the Consultant using Structural
Work (Reinforcement / Concrete) Inspection Checklist.
k. On completion of joint inspection, request Consultant to sign on the checklist and file as per
Project Filing Index.

6- RESPONSIBILITY AND SUPERVISION

6. 1 Project Engineer

a. Responsible for controlling all civil activities and overall coordination.


b. Ensure that adequate facilities and equipment are provided to the work to avoid injury,
health impairment or damage and to ensure providing quality works within the planned
time frame.
c. Organize the site so that work is carried out in accordance with the specifications with a
minimum risk to men, equipment and materials.

6. 2 QA/QC Engineer

a. Responsible for work entire quality assurance, quality control and inspection programs.
b. Witness the inspections, sampling, and testing of materials.
c. Review and issue the test results the day after test completion.
d. Produce all quality related documents and reports as necessary.
e. Provide written procedures and method statements in coordination with the project
manager describe the job specific work for each stages / activities.
f. Review tests results for all quality control matters.

6. 3 Safety Officer

a. Ensure that all workers have a safe place of work, advice safe system of work and provide
adequate instructions, training and supervision to enable employees to work in safety.
b. Provide instructions to establish safe working methods outline potential hazards at each
stage and indicate precautions to be adopted.
c. Carry out site survey on daily basis to ensure that the HSE methods of working are in
operation and that all regulations are being observed.
d. Report, determine and analyze the cause of any accident or dangerous occurrence and
recommend measures for preventing recurrence.

Page 5
Sub-
: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Reinforcement

6. 4 Construction Supervisors

a. Adheres to the project specific method statements, procedures, inspection programs and
HSE instructions to get the activities performed as required.

6. 5 Surveyors

a. Ensure that setting out points, levels, and plumb relevant to approved drawings and
reference points.

7- HEALTH AND SAFETY

7. 1 Protective and Safety Equipment

a. Safety Shoes
b. Safety Helmets
c. Safety Glasses
d. Hand Gloves (as required)
e. Dust Masks (as required).

7. 2 Information to Personnel

A pre task briefing will be carried out detailing the following information:
a. Tasks assigned to each personnel
b. Traffic Management / Safety
c. What to do in the event of a first aid injury or other incident
d. Heat stress advice / warning.

7. 3 Emergency Procedures

In the event of an accident or incident, the following procedure shall be followed:


a. Immediately send first aider to the scene.
b. Stop all other activities in the vicinity.
c. Remove or isolate any immediate dangers ONLY if safe to do so.
d. Inform the emergency services regarding the location, type and nature of the incident including
casualty details.
e. Cordon the area to prevent the scene being further disturbed (to aid investigation).
f. Give assistance as requested to the emergency services.
g. Photograph the scene.
h. Take statements from witnesses.
i. Carry out incident investigation.

Page 6
Sub-
: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Reinforcement

8- Quality Assurance:

8. 1 Critical Works

a. Ensure that setting out and survey works are done in accordance with the relevant
drawings, utilizing survey instruments having valid calibration certificates.
b. Ensure that concrete protective cover is attained using concrete spacer.
c. Ensure that all electrical, plumbing and mechanical items are completely installed and
inspected according to specifications and relevant drawings before commencement of
concrete pouring.

8. 2 Inspection & Testing

a. Refer to the inspection and test plan.

Page 7